The presentation: Monsanto coming to Europe is a failed mission. Not only that most GMOs are not allowed in Europe, most of the farmers don't even grow the one that are. An analysis of misu…Full description
heal
FYP presentationFull description
Wireless energy transfer is a very exciting technology which promises to radically change the way we perform any activity. In this report I like to explore the concept of transmitting power …Full description
FiCA presentation in MS Power PointFull description
oliverDescripción completa
Clarisse The Label Thesis Presentation by Clarisse Provido
OTIS GEN 2 COMFORT
Full description
Full description
DESIGN AND CONSTRUCTION OF THE RION ANTIRION BRIDGE FOUNDATIONS
Alain PECKER
Technische Universität Hamburg-Harburg, January 29, 2008
•Finance •Design
Continental Greece
•Build •Own Peloponese
•Operate •Transfer
KEY DATES • • • • •
Launch of tender : 1992 Contract award : December 1997 Start of construction : 1999 Opening to traffic : August 2004 Total cost : 770 Mi Euros (630 construction)
OUTLINE OF PRESENTATION • • • • •
Overview of project Geotechnical and environmental conditions Description of foundation system Design strategy Construction methods
ANTIRION Gulf of Corinth
RION
RION ANTIRION
286
560
560 2252
560
286
230 m
m 0 9
65 m
GEOTECHNICAL CONDITIONS
WEAK ALLUVIUMS : SAND AND GRAVEL CLAY SILT
RION
ANTIRION
65 m.
SOIL CHARACTERISTICS Depth below ground surface
0
20
40
60
80
100 0
100
200
300
400
500 0
Undrained shear strength (kN/m2)
100
200
300
400
500
Shear wave velocity (m/s)
600
ENVIRONMENTAL CONDITIONS
Earthquake design level
Earthquake performance level Life safe
Fully Operational operational
Near collapse
Frequent Occasional Rare Very Rare
Es sen
Sa fet y
tia l/H az a
Cr itic al
Ba
sic
rdo u
ob jec tiv e
so
Unacceptable performance
ob j ec tiv e bje
cti ve
DESIGN SPECTRUM Sea bed level 1.5
S pectral acceleration (g )
Damping 5 %
M = 7.0 Return period 2000 y
1.0
0.5
0.0 0.0
1.0
2.0
3.0
Period (s)
4.0
5.0
TECTONIC MOVEMENTS
PIER BASE ELEVATION :
PLAN :
VERTICAL SLIP : 2 m
HORIZONTAL OPENING : 2 m
SHIP IMPACT :
16 knots RION
ANTIRION
180 000 t
CONTROLLING FACTORS • • •
No rock formation at less than 500 m Large water depth : 65 m Performance objectives (2000 year return period): Damages acceptable but bridge repairable, and re-usable • horizontal sliding acceptable ; tilt prohibited (<0.1 %) • Significant duration for design Possibility for development of innovative concepts
FOUNDATIONS ? PILES EMBEDDED CAISSONS SOIL SUBSTITUTION SHALLOW FOUNDATION
Soil reinforcement with stiff inclusions
SOIL REINFORCEMENT • Driven steel pipes Diameter 2 m, Thickness 20 mm Length 25 m to 30 m Spacing 7 m x 7 m • Gravel layer : 3m thick
200 INCLUSIONS UNDER EACH FOUNDATION
FOUNDATION LAYOUT
ROLE OF INCLUSIONS + GRAVEL LAYER
P
P
n
n n 1 N Brittle links
Ductile link
Ductile chain
CAPACITY DESIGN PHILOSOPHY Plastic hinge = Gravel bed
Bounds for forces in the superstructure Control of failure mode (horizontal sliding)
DESIGN STRATEGY • Facing a new design situation Keep things as simple as possible • Three steps process Conceptual design : New tools (Yield Design Theory) Amenable to parametric studies
Validation : Physical modeling (centrifuge) Final design : non linear finite element models dynamic macro element Structural analyses
SEISMIC CAPACITY
M
Q
N T
BEARING CAPACITY under
COMBINED LOADS B
Fx
M
T
O
Yield design theory M T N
M / CB 2 T / CB N / CB
N
BOUNDING SURFACE
N = 860 MN - L = 25 m - S = 7 m
Overturning moment (MN m)
WITHOUT inclusions 35000 30000
WITH Gravel layer WITH inclusions
WITHOUT Gravel layer
25000 20000 15000 10000 5000 0
0 200 400 600 800 Horizontal shear force at foundation level (MN)
• material (elasto-plastic soil behaviour) : Plasticity model
M
Wave propagation : • dissipation of radiation energy
FAR FIELD
Dynamic elastic impedances K
C
RHEOLOGICAL MODEL
FAR FIELD C
NEAR FIELD FOUNDATION
Horizontal shear force (MN)
SOIL STRUCTURE INTERACTION 500
250
0
-250
Simplified model Finite element model
-500 0
10
20
30
40
Time (s)
50
PIER OFFSET DURING EARTHQUAKE 0.15
0.10
Uy [m]
0.05
0.00 -0.40
-0.35
-0.30
-0.25
-0.20
-0.15
-0.10
-0.05
0.05
-0.05
-0.10
-0.15
Ux [m]
0.10
TECTONIC MOVEMENTS
CONSTRUCTION METHODS
Off-Shore Foundations
Cable stayed bridge
Inclusions
Steel Pipe Driving & Gravel Bed Installation
AUGUST 8th, 2004
END OF AN EXCEPTIONAL TECHNICAL CHALLENGE AND HUMAN ADVENTURE
CONCLUSIONS Key factors to the success •
• •
Correct assessment of foundation performance criterion Time allowed for design Close collaboration and confidence between all parties: Owner, Contractor, Design team, Checker
ACKNOWLEDGMENTS • GEFYRA SA (Concessionaire) Jean Paul Teyssandier • GEFYRA KINOPRAXIA (Contractor) Gilles de Maublanc , Pierre Morand • DESIGN JV Jean Marc Tourtois • DESIGN CHECKER Peter Taylor Ralph Peck, Ricardo Dobry