AC UPS Sizing - Open Electrical
http://www.openelectrical.org/wiki/index.php?title=AC_UPS_Sizing
From Open Electrical
Contents 1 Introduction 1.1 Why do the calculation? 1.2 When to do the calculation? 2 Calculation Methodology Methodology 2.1 Step 1: Collect the AC UPS Loads 2.2 Step 2: Load Profile, Design Load and Design Energy 2.3 Step 3: Batte ry Sizing Sizing 2.3.1 Nominal Battery (or DC Link) Voltage 2.3.2 Number of Cells in Series 2.4 Step 4: UPS Sizing 2.4.1 Overall UPS Sizing 2.4.2 Rectifier / Charger Sizing Sizing 2.4.3 Inverter Sizing Sizing 2.4.4 Static Switch Sizing 3 Worked Exa mple 3.1 Step 1 and 2: Collect the AC UPS Loads and Construct Load Profile 3.2 Step 3: Batte ry Sizing Sizing 3.3 Step 4: UPS Sizing 3.3.1 Overall Sizing 3.3.2 Rec tifier Sizing Sizing 3.3.3 Inverter and Static Switch Sizing Sizing 4 Template 5 Computer Software 6 What next?
Introduction This calculation deals with with the sizing of an AC uninterruptible power supply (UPS) (UPS) system (i.e. rectifier, bat tery bank and inverte r). In this calculation, it is assumed that the AC UPS is a double conversion type with a basic system topology as shown in Figure 1. An external maintenance bypass switch and galvanic isolation isolation transformers are other common additions additions to the basic topology, topology, but these have bee n omitted from the system as they are irrelevant for the sizing calculation.
Why do the calculation? An AC UPS system is is used to support critical / sensitive AC loads. It is typically a battery-backed system which will continue continue to opera te for a specified amount of time (called the autonomy) aft er a main power supply interruption. AC UPS systems are also used as sta ble power supplies that provide a reasonably constant voltage and frequenc y output, independent of voltage input. This is particularly useful for sensitive electrical equipment on main power supplies that are prone to voltage / frequenc y fluctuations or instability. The AC UPS sizing sizing calculation determines the ra tings for the main AC UPS system components: 1) rectifier, 2) battery banks and 3) inverter. In some cases, the manufacturer will independently size the system and it is only necessary to construct the AC UPS load schedule and load profile. However the calculation results will also help determine the indicative dimensions dimensions of the equipment (e.g. size of batte ry banks) for preliminary preliminary layout purposes.
When to do the calculation?
Figure 1 - AC UPS basic system topology
The AC UPS sizing calculation can be done when the following prerequisite information is known: UPS loads loads that ne ed to be supported Input / Output AC voltage Autonomy time(s) Battery type
Calculation Methodology The calculation procedure has four main steps: 1) Determine and collect t he prospective AC UPS loads 2) Construct a load profile and deter mine the UPS design load (VA) and design energy (VAh) (VAh) 3) Calculate the size of the stationary battery (number of cells in series and Ah capacity) 4) Determine the size of the inverter, rectifier/ charger and static switch
Step 1: Collect the AC UPS Loads
1 f4
6/10/2011 3 13 PM
AC UPS Sizing - Open Electrical
http://www.openelectrical.org/wiki/index.php?title=AC_UPS_Sizing
The first step is to determine the type and quantity of loads that the AC UPS system will be expected to support. For industrial facilities, this will typically be critical instrumentation and control loads such as the DCS and ESD processor and marshalling hardware, critical workstations and HMI's, te lecommunications equipment and sensitive electronics. The necessary load data should be available from the instrumentation and control engineers. For commercial facilities, UPS loads will mainly be server, da ta / network and t elecommunications hardware.
Step 2: Load Profile, Design Load and Design Energy Refer to the Load Profile Calculation for details on how to construct a load profile, calculate the design load ( method" for c onstructing load profiles is typically used for AC UPS systems.
) and design energy (
). The "Autonomy
The autonomy time is often specified by the Client (i.e. in their sta ndards). Alternatively, IEEE 446, "IEE E Recommended Pract ice for Emergency and Standby Power Systems for Industrial and Commercial Applications" has some guidance (particularly Table 3-2) for autonomy times. Sometimes a single autonomy time is used for the e ntire AC UPS load, which obviously makes the construction of the load profile easier to compute.
Step 3: Battery Sizing Refer t o the Battery Sizing Calculation for de tails on how to size the battery f or the AC UPS system. The following sections provide additional information specific to bat tery sizing for AC UPS applications. Nominal Battery (or DC Link) Voltage The nominal battery / DC link voltage is often selected by the AC UPS manufacturer. However, if required t o be selected, the following factors need to be considered: DC output voltage range of the rectifier – the rectifier must be able t o output the spec ified DC link voltage DC input voltage range of the inverter – the DC link voltage must be within the input voltage tolerances of the inverter. Note that the battery end of discharge voltage should be within these tolerance s. Number of battery cells required in series – this will affect the overa ll dimensions and size of the batter y rack. If physical space is a constraint, then less batteries in series would be preferable. Total DC link current (at full load) – this will affect t he sizing of the DC c ables and inter-cell batter y links. Obviously the smaller the be tter. In general, the DC link voltage is usually selected t o be close to t he nominal output voltage. Number of Cells in Series The number of battery c ells required to be connect ed in series must be between the two following limits: (1)
(2) where N max is the maximum number of bat tery cells N min is the minimum number of battery cells V dc is the nominal battery / DC link voltage (Vdc) V i,max is the inverter maximum input voltage tolerance (%) V i,min is the inverter minimum input voltage tolerance (%) V f is the nominal cell float (or boost) voltage (Vdc) V eod is the cell end of discharge voltage (Vdc)
The limits are ba sed on the input voltage tolerance of the inverter. As a maximum, the ba ttery at float voltage (or boost if applicable) needs to be within the maximum input voltage range of the inverter. Likewise as a minimum, the battery at its e nd of discharge voltage must be within the minimum input voltage range of the inverter. Select the number of c ells in between these two limits (more or less arbitrary, though somewhere in the middle of the min/max values would be appropriate).
Step 4: UPS Sizing Overall UPS Sizing Most of the time, all you need to provide is the overall UPS kVA rating and the UPS vendor will do the rest. Given the design load ( in VA or kVA) calculated in Step 2, select an overall UPS rating that excee ds the design load. Vendors typically have standard UPS ratings, so it is possible to simply select the first standard rat ing that exceeds the design load. For example, if the de sign load 12kVA, then the next size unit (e.g. 15kVA UPS) would be selected. Rectifier / Charger Sizing The rectifier / c harger should be sized to supply the inverter at full load and also char ge the batte ries (at the maximum charge current). The design DC load current can be calculated by:
where I L,dc is the design DC load current (full load) (A) S is the selected UPS rating (kVA)
2 f4
6/10/2011 3 13 PM
AC UPS Sizing - Open Electrical
http://www.openelectrical.org/wiki/index.php?title=AC_UPS_Sizing
V dc is the nominal battery / DC link voltage (Vdc)
The maximum battery c harging current ca n be computed as follows:
where I c is the maximum DC charge current (A) C is the selected battery capacity (Ah) k l is the battery recharge efficiency / loss factor (typically 1.1) (pu) t c is the minimum battery rec harge time (hours)
The total minimum DC rectifier / c harger current is therefore:
Select the next standard rectifier / charger rating that exceeds the total minimum DC current above. Inverter Sizing The inverter must be rate d to continuously supply the UPS loads. Therefore, the inverter can be sized using the design AC load current (based on the selected UPS kVA rating). For a three-phase UPS:
For a single-phase UPS:
where I L is the design AC load current (full load) (A) S is the selected UPS rating (kVA) V o is the nominal output voltage (line-to-line voltage for a t hree phase UPS) (Vac)
Select the next standard inverter rating that exceeds the design AC load current. Static Switch Sizing Like the inverter, the static switch must be rated to continuously supply the UPS loads. Therefore, the static switch can be sized using the design AC load current (as above for the inverter sizing).
Worked Example Step 1 and 2: Collect the AC UPS Loads and Construct Load Profile For this example, we shall use the same loads and load profile detailed in the E nergy Load Profile Calculation example. The load profile is shown in the figure right and the following quantities were calculated: Design load S d = 768 VA Design energy demand E d = 3,216 VAh
Step 3: Battery Sizing For this example, we shall use the same batt ery sizes calculated in the Bat tery Sizing Calculation worked example. The selected number of c ells in series is 62 cells and the minimum battery capacity is 44.4 Ah. A battery capacity of 50 Ah is selected.
Step 4: UPS Sizing Overall Sizing
Load profile for this example
Given the design load of 768 VA, then a 1 kVA UPS would be appropriate. Rectifier Sizing Given a nominal dc link voltage of 120Vdc, the design DC load current is:
A
3 f4
6/10/2011 3 13 PM
AC UPS Sizing - Open Electrical
http://www.openelectrical.org/wiki/index.php?title=AC_UPS_Sizing
Suppose the minimum battery recharge time is 2 hours and a recharge efficiency fa ctor of 1.1 is used. The maximum battery charging current is:
A Therefore the total minimum DC rectifier / cha rger current is:
A A DC rectifier ra ting of 40A is selected. Inverter and Static Switch Sizing Suppose the nominal output voltage is 240Vac. The design AC load current is:
A An inverter and stat ic switch rating of 5A is selected.
Template A professional, fully customisable Excel spreadsheet template of the AC UPS calculation can be purchased from Lulu (http://www.lulu.com/product/mediadownload/ac-ups-calculation/15694672) . The template is based on the calculation procedure described in this page and includes the following features: Load schedule and a utomatic load profile generation Battery sizing UPS component sizing (e.g. rectifier, inverte r, etc) Screenshots from AC UPS Template
UPS Configuration
Load Profile
Battery Sizing
Computer Software Preliminary sizing is normally done manually. Notwithstanding this, many AC UPS manufacturers provide sizing tools as pa rt of their service package (for example, see the AP C online UPS selector tool (htt p://www.apc.com/tools/ups_selector/index.cfm?) ).
What next? Using the results of the UPS sizing calculation, the approximate dimensions of the batteries and UPS cabinet can be estimated base d on typical vendor information. This will assist in developing the equipment / room layouts. Preliminary budget pricing can also be estimated based on the calculation results. Retrieved from "http://www.openelectrical.org/wiki/index.php?title=AC_UPS_Sizing" Category: Calculations This page was last modified on 16 May 2011, at 06:38.
4 f4
6/10/2011 3 13 PM