PROYEK PEMBANGUNAN PABRIK LIMA DOLLAR KUNINGAN Pekerjaan : Lokasi :
REKAPITULASI I. PEK. PERSIAPAN II. PEKERJAAN SIPIL PONDASI GEDUNG PABRIK 35X21 m III. PEKERJAAN KONTRUKSI BAJA DAN BETON (KOMPOSIT IV. PEKERJAAN ATAP V. PEKERJAAN SIPIL VI. PEKERJAAN KONSEN PINTU DAN JENDELA VII. PEKERJAAN CAT VIII. PEKERJAAN MEKANIKAL/ELEKTRIKAL
Terbilang Dua Milyar Dua puluh lima juta rupiah
20,460,600 185,907,676.71 1,343,168,908.20 127,248,000.00 139,460,400.46
Sub Total PPN 10% Jumlah Total Dibulatkan
1,816,245,585.37 208,868,242.32 2,025,113,827.69 2,025,000,000.00
BILLS OF APPROXIMATE QUANTITY PABRIK LIMA DOLAR KUNINGAN KUNINGAN JAWA BARAT Item Pekerjaan
No. A
Unit Price
Qty
(Rp.)
Total Price ( Rp)
Pembersihan lahan Pengukuran dan Bouwplank Peralatan,Air ,listrik kerja Peralatan keselamatan kerja
m2 m1 ls ls
735.00 5,000 3,675,000 262.00 48,800 12,785,600 1.00 1,500,000 1,500,000 1.00 2,500,000 2,500,000 Sub Jumlah Pekerjaan Persiapan Rp.
20,460,600
PEKERJAAN SIPIL PONDASI GEDUNG PABRIK 35X21 m 1 2 3 4 5 6 7 8 9
Galian Pondasi telapak 150*150*150 Galian Sloof Galian pondasi batu kali + saluran Urugan kembali lobang pondasi Urugan Pasir padat tebal 10 cm Sloof beton bertulang 25 * 40 Pondasi batu kali Pasangan bata merah 1/2 bata tinggi 35 cm Plester,aci
m3 m3 m3 m3 m3 m3 m3 m2 m2
81.00 174.00 57.60 88.64 137.70 30.00 35.28 39.00 39.00
51,100 51,100 51,100 25,550 119,100 4,198,196 557,600 92,400 52,500
4,139,100 8,891,400 2,943,360 2,264,624 16,400,070 125,945,894 19,672,128 3,603,600 2,047,500
sub jumlah pek. Sipil Pondasi pendukung utama Rp. C.
Remark
PEKERJAAN PERSIAPAN 1 2 3 4
B
Unit
PEKERJAAN KONTRUKSI BAJA DAN BETON (KOMPOSIT) 1 1 Berat baja Kolom dan Balok 2 Base plate 370x195x12 mm 3 Angkur dia.19 mm 4 Shear Conector dia. 7/8 5 Shear Conector dia. 3/4 6 Plat simpul 630x150x12mm 7 Pengaku L 50.50.5 8 Baud span dia.3/4"
kg kg bh bh bh kg kg bh
81,904.70 50.00 150.00 6,348.00 1,625.00 356.08 450.00 480.00
14,750 1,208,094,325 18,700 935,000 38,000 5,700,000 13,500 85,698,000 15,000 24,375,000 18,200 6,480,583 18,200 8,190,000 7,700 3,696,000 sub jumlah pek. Konstruksi
185,907,677
1,343,168,908 1,343,168,908
Item Pekerjaan
No.
Unit
Qty
Unit Price (Rp.)
Total Price ( Rp)
Remark
Pindahan hal 1. Rp. 1,549,537,185 D
PEKERJAAN ATAP 1 Atap Allumunium 0.4 mm 2 Nok Allumunium 0.4 mm 3 Baud roofing 4 Talang datar Zincalum 0.4 mm 5 Lisplank plat 1.2 mm 6 Talang PVC 4" 7 Corong talang 9 Knee 4"
E
PEKERJAAN SIPIL
a
1 2 3 4
Kolom pengaku dinding 15 * 25 Balok pengaku 15*25 Ring balok 15 * 20 Pasang dinding conblock 19*19*38
m2 m1 bh m1 m1 m1 bh bh
m3 m3 m3 m2
1,132.00 51.00 6,528.00 102.00 64.00 144.00 18.00 72.00
6.75 5.40 6.48 960.00
78,000 88,296,000 118,000 6,018,000 1,250 8,160,000 115,000 11,730,000 84,000 5,376,000 36,000 5,184,000 40,000 720,000 24,500 1,764,000 sub jumlah pekerjaan atap 4,198,196 4,198,196 4,198,196 63,800
127,248,000
28,337,826 22,670,261 27,204,313 61,248,000
sub jumlah pek. Sipil Rp. Sub Jumlah Rp. PPN & PPH 11,5 % Total Rp. Grand total dibulatkan Rp.
139,460,400 1,816,245,585 208,868,242 2,025,113,828 2,025,000,000 2,755,102 per m2