ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
GIS01 – GAS INSULATED I NSULATED SUBSTATIONS
Elaborado por:
Verificado por:
Aprovado por:
EST/EQPSE
Júlio Cézar do Nascimento
José Eduardo Dias Olesko
R00 05/06/2002 1/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 2/85
ÍNDICE 1. OBJECTIVE OBJECTIVE...... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ..........6 ....6 2.
GENERAL GENERAL REQUIREMEN REQUIREMENTS....... TS............. ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ..........7 ....7 1.1 GENERAL GENERAL CONDITIONS....... CONDITIONS............. ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... .......7 .7 1.2
CORRESPONDE CORRESPONDENCE, NCE, LANGUAGES LANGUAGES AND UNITS ........... ................ ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ..........7 ....7
1.3 TECHNICAL TECHNICAL BID DATA DATA...... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... .......7 .7 1.4 SUPPLIER SUPPLIER DRAWING DRAWINGS S AND DOCUME DOCUMENTS......... NTS.............. ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ..........7 ....7 1.4.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ..........7 ....7 1.4.2 Drawing Drawing Standards Standards ........... ................. ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... .......7 .7 1.4.3 Approval......... Approval.............. ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ..........8 ....8 1.4.4 Document Document Schedule Schedule ........... ................. ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ........... .......9 .9 1.4.5 Drawings Drawings and Documents Documents to be Forwarded Forwarded ........... ................. ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ..........9 ....9 1.4.6 Ownership Ownership of the Drawings. Drawings....... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........10 .....10 1.4.7 Record File Copies Copies ........... ................. ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........10 .....10 1.4.8 Copies of the Manuals Manuals ........... ................. ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........10 .....10 1.5 SUPPLY SUPPLY EXECUTION.... EXECUTION.......... ........... ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........11 .....11 1.5.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........11 ..11 1.5.2 Startand Startand Progress Progress of Services........ Services.............. ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........11 .....11 1.6 PLANNING PLANNING AND CONTROL CONTROL OF MANUFACTURI MANUFACTURING NG ............ .................. ............ ............ ............ ........... ........... ........... ........... ........... ........... ........11 ..11 1.6.1 Review of the Planning Planning Presente Presentedd for for The The Qualificatio Qualificationn Phase....... Phase............. ........... ........... ........... ........... ............ ........... ..........11 .....11 1.6.2 Manufacturing Manufacturing and Supply Schedule.......... Schedule................ ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........11 ..11 1.6.3 Manufacturing Manufacturing Execution Execution Plan................ Plan..................... ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........11 ..11 1.6.4 Manufacturing Manufacturing Inspection Inspection Program......... Program.............. ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........11 ..11 1.6.5 Progress Progress and Planning Planning Report..... Report........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........12 .....12 1.7 QUALITY ASSURANC ASSURANCE E ........... ................. ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........12 .....12 1.7.1 Basic Requirements........ Requirements.............. ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........12 ..12 1.7.2 Project Project Checking....... Checking............. ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........12 ..12 1.7.3 Subsuppliers Subsuppliers...... ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........12 .....12 1.7.4 Certified Certified Reports ........... ................ ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........12 .....12 1.7.5 Manufacturing Manufacturing..... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........12 ..12 1.7.6 “Non-Conformin “Non-Conforming” g” Products....... Products............ ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........12 .....12 1.7.7 Quality Quality Records Records ........... ................ ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........13 .....13 1.8 INSPECTION INSPECTION AND OVERSIGHT......... OVERSIGHT............... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........13 .....13 1.8.1 Inspection Inspection at the the Shop................ Shop..................... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........13 ..13 1.8.2 Jobsite Jobsite Oversight................ Oversight...................... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........13 .....13 1.9 PACKI PACKING, NG, SHIPPIN SHIPPING G AND DELIVERY DELIVERY ........... ................. ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........14 ..14 1.9.1 Packing Packing Instructions... Instructions........ ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........14 ..14 1.9.2 Shipping Shipping ........... ................ ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........14 .....14 1.9.3 Delivery Delivery ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........14 ..14 1.10 REQUIREMEN REQUIREMENTS TS OF SUPPLIER PERSONNEL PERSONNEL AT JOBSITE JOBSITE ........... ................. ............ ............ ............ ............ ............ ........... ..........14 .....14 1.11 SUBSU SUBSUPPLIE PPLIES S AND SUBCONTRACT SUBCONTRACTING ING ........... ................ ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........14 ..14 1.12 STANDARDS............................................................... STANDARDS.......................................................................................................................................15 ........................................................................15 1.13 EQUIPMENT, EQUIPMENT, TOOLS TOOLS AND ELECTRIC ELECTRIC POWER POWER AT JOBSITE JOBSITE ........... ................. ........... ........... ............ ............ ............ ........... ..........15 .....15 1.13.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........15 ..15 1.13.2 Equipment Equipment and Tools............. Tools................... ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........15 .....15 1.13.3 Electric Electric Power at Jobsite Jobsite ............ ................. ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........15 ..15 1.14 DISCLOSURE.............................................................. DISCLOSURE......................................................................................................................................16 ........................................................................16 GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão 2
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 3/85
GENERAL GENERAL TECHNICAL TECHNICAL SPECIFICA SPECIFICATIONS TIONS ........... ................. ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........17 ..17 2.1
OBJECTIVE....... OBJECTIVE............. ........... ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........17 .....17
2.2 2.3
TECHNICAL TECHNICAL STANDARDS... STANDARDS......... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........17 ..17 MATERIALS MATERIALS AND COMPONENTS COMPONENTS ........... ................ ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........17 .....17
2.4
TESTS......... TESTS.............. ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........18 ..18
2.5 MANUFACTURIN MANUFACTURING G QUALITY ........... ................. ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........18 .....18 2.5.1 Quality Quality of Management......... Management............... ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........18 ..18 2.5.2 General Requirements... Requirements........ ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........18 .....18 2.5.3 Electric Electric Welding ........... ................ ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........19 .....19 2.5.4 Brazing.......... Brazing................ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........19 ..19 2.5.5 Cast and/or Forged Steel Parts ........... ................ ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........20 .....20 2.5.6 Finishing..... Finishing........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........20 .....20 2.6 PROTECTIVE PROTECTIVE PAINTING, PAINTING, FINISHING FINISHING AND COVERINGS........ COVERINGS.............. ........... ........... ........... ........... ............ ............ ............ ........... ..........20 .....20 2.6.1 General Requirements... Requirements........ ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........20 .....20 2.6.2 Retouching, Retouching, On-Site On-Site Final Finish Painting Painting and On-Site On-Site Painting Painting ........... ................ ........... ........... ........... ............ ........... ..........21 .....21 2.6.3 Responsibili Responsibilities ties for Painting Painting Service/Pain Service/Paintt Supply...... Supply ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........21 ..21 2.6.4 Paint Quality Quality and Inspection Inspection...... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........22 .....22 2.6.5 Surface Surface Treatment Treatment and Preparation Preparation ........... ................. ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........23 ..23 2.6.6 Color ............ .................. ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........23 .....23 2.6.7 Surfaces Surfaces that that will will be Welded Welded On-Site On-Site ............ .................. ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........23 .....23 2.6.8 Technical Technical Assistance Assistance...... ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........23 ..23 2.6.9 Warranty Warranty ............ ................. ........... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........23 .....23 2.7
PIPING PIPING ........... ................. ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........23 ..23
2.8 GROUNDING....... GROUNDING............. ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........24 ..24 2.8.1 General Requirements... Requirements........ ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........24 .....24 2.8.2 Cable Ways........ Ways............. ........... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........24 .....24 2.8.3 Cable Shielding...... Shielding............ ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........25 .....25 2.8.4 Module Shielding Shielding ............ .................. ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........25 ..25 2.8.5 Cubicles, Cubicles, and/or Boards ........... ................ ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........25 .....25 2.8.6 Other Equipment...... Equipment............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........26 .....26 2.9 GENERAL GENERAL ELECTRICAL ELECTRICAL REQUIREME REQUIREMENTS NTS ............ ................. ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........26 .....26 2.9.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........26 ..26 2.9.2 Substation Substation Voltages............ Voltages.................. ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........26 .....26 2.10 ELECTROMAGN ELECTROMAGNETIC ETIC COMPATIBILIT COMPATIBILITY Y ............ .................. ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........27 .....27 2.11 EQUIPMENT EQUIPMENT CONNECTIONS......... CONNECTIONS.............. ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........27 .....27 2.11.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........27 ..27 2.11.2 Cable Routing Routing ........... ................. ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........27 ..27 2.12 AUTOMATIONS AUTOMATIONS AND INTERLOCKS......... INTERLOCKS.............. ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........28 .....28 2.12.1 General Requirements... Requirements........ ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........28 .....28 2.12.2 Automations......... Automations............... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........28 ..28 2.12.3 Electrical Electrical Interlocks......... Interlocks............... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........28 ..28 2.12.4 Mechanical Mechanical Interlocking Interlocking ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........28 .....28 2.12.5 Lockouts...... Lockouts............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........28 .....28 2.13 EQUIPMENT EQUIPMENT ELECTRICAL ELECTRICAL CONTACTS....... CONTACTS............. ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........29 .....29 2.14 ELECTRONIC ELECTRONIC EQUIPMENT EQUIPMENT - ENVIRONME ENVIRONMENTAL NTAL CONDITIONS...... CONDITIONS............ ............ ........... ........... ........... ........... ........... ........... ........29 ..29 2.14.1 Installation Installation and Operating Operating Environments.. Environments........ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........29 .....29 2.14.2 Influence Influence of the Power Supply Source ........... ................. ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........29 .....29 2.14.3 Capability Capability to Withstand Withstand Electro Electromagneti magneticc Phenomena Phenomena ............ .................. ............ ............ ........... ........... ........... ........... ........... ........... ........29 ..29 GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 4/85
2.15 MOLDED CASE CIRCU CIRCUIT IT BREAK BREAKERS ERS ........... ................. ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........31 ..31 2.15.1 Alternating Alternating Current......... Current.............. ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........31 .....31 2.15.2 Direct Current...... Current............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........31 ..31 2.16 TRANSFORMER TRANSFORMERS........ S.............. ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........31 .....31 2.16.1 Voltage Voltage Transformers Transformers ........... ................. ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........31 ..31 2.16.2 Current Transformers Transformers ........... ................. ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........31 ..31 2.16.3 Control Transformers........ Transformers.............. ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........32 .....32 2.17 CONTACTORS CONTACTORS AND OVERLOAD OVERLOAD RELAYS....... RELAYS............. ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........32 .....32 2.18 SOLENOIDS SOLENOIDS..... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........32 .....32 2.19 ELECTRIC ELECTRIC MOTORS ............ .................. ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........32 ..32 2.20 MONITORING MONITORING AND PROTEC PROTECTION TION COMPONENT COMPONENTS S AND DEVICES DEVICES ............ ................. ........... ........... ........... ........... ........... ........33 ..33 2.20.1 General Requirements... Requirements........ ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........33 .....33 2.20.2 Manometers Manometers...... ........... ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........33 .....33 2.20.3 Pressure Pressure Relays Relays ........... ................ ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........34 .....34 3
TECHNICAL TECHNICAL SPECIFICATI SPECIFICATIONS ONS ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........35 .....35 3.1 SCOPE OF SUPPLY SUPPLY ........... ................ ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........35 .....35 3.1.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........35 ..35 3.1.2 Equipment, Equipment, Materials Materials and Services Services Included Included in the Supply Supply ........... ................. ............ ............ ............ ............ ............ ........... ..........35 .....35 3.1.2.1 242kV EQUIPMENTS EQUIPMENTS ........... ................ ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........35 .....35 3.1.2.2 145 and 72.5kV EQUIPMENTS EQUIPMENTS...... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........36 .....36 3.1.3 Other Materials Materials and Service Servicess Included Included in the the Supply..... Supply.......... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........37 .....37 3.1.4 Supplier’s Supplier’s Cooperation Cooperation with Others...... Others ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........38 .....38 3.2 APPLICABLE APPLICABLE STANDAR STANDARDS DS ............ ................. ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........38 ..38 3.2.1 Objective Objective...... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........38 .....38 3.2.2 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........38 ..38 3.2.3 Circuit-Brea Circuit-Breakers kers ........... ................ ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........38 .....38 3.2.4 Disconnectin Disconnectingg and and Groundi Grounding ng Switche Switchess ........... ................ ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........38 ..38 3.2.5 Voltage/Curre Voltage/Current nt Transformers Transformers ........... ................. ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........39 .....39 3.2.6 Bushings Bushings ............ ................. ........... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........39 .....39 3.2.7 Cable Connections Connections ........... ................. ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........39 .....39 3.2.8 Surge Arresters...... Arresters............ ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........39 .....39 3.2. 3.2.99 Sulfu ulfurr H Hex exaf aflu luor orid idee Gas Gas - SF SF6 ......................................................................................................39 3.3 INSTALLATION INSTALLATION CHAR CHARACTERI ACTERISTICS STICS...... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........39 .....39 3.3.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........39 ..39 3.3.2 Service Service Conditions......... Conditions.............. ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........39 .....39 3.4 GIS CONSTRUC CONSTRUCTIVE TIVE CHARAC CHARACTERIS TERISTICS........ TICS.............. ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........41 .....41 3.4.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........41 ..41 3.4.2 Metal-Enclosu Metal-Enclosures res ............ .................. ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........41 ..41 3.4.3 Conductors... Conductors......... ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........44 .....44 3.4.4 Insulators Insulators ............ .................. ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........44 ..44 3.4.5 Gas Compartments........ Compartments............. ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........44 .....44 3.4.6 Gas Monitoring Monitoring System ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........45 .....45 3.4.7 Buses................ Buses..................... ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........46 .....46 3.4.8 Circuit-break Circuit-breakers ers ........... ................ ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........46 .....46 3.4.9 Disconnectin Disconnectingg and and Groundi Grounding ng Switche Switchess ........... ................ ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........49 ..49 3.4.10 Inductive Inductive Voltage Voltage Transformers...... Transformers............ ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........52 .....52 3.4.11 Current Transformers Transformers ........... ................. ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........53 ..53 3.4.12 Surge Arresters Arresters (if necessary)........... necessary)................. ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........53 .....53 3.4.13 SF6 /Air Bushings ........................................................................... ..........................................................................................................................54 ...............................................54 3.4.14 SF6 - Insulated Cable Connection Enclosures (optional – supplier proposal)..............................54 3.4.15 Supporting Supporting Structures Structures..... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........54 ..54
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão 3.4.16 3.4.17
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 5/85
Grounding Grounding System and and Electromagneti Electromagneticc Compatibility Compatibility ........... ................. ............ ............ ........... ........... ........... ........... ........... ........... ........55 ..55 Voltage Voltage Surges ........... ................ ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........57 .....57
3.5 GIS BAY LOCAL LOCAL CABINETS CABINETS - QCL.......... QCL............... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........58 .....58 3.5.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........58 ..58 3.5.2 Extent of Supply............. Supply.................. ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........58 .....58 3.5.3 Construction Construction Requirements Requirements ........... ................. ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........58 .....58 3.5.4 Control and Supervisory Supervisory Functions Functions Available Available at the QCLs ........... ................. ............ ........... ........... ........... ........... ........... ........... ........59 ..59 3.6 3.6 SU SULF LFUR UR HE HEXA XAFL FLUO UORI RIDE DE (SF (SF6) GAS...............................................................................................60 3.6.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........60 ..60 3.6.2 Gas Containers.............. Containers................... ........... ........... ........... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........60 .....60 3.7 INSPECTIONS INSPECTIONS,, TESTS TESTS AND AND TRAINNING TRAINNING..... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........61 .....61 3.7.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........61 ..61 3.7.2 Applicable Applicable Standards Standards ............ .................. ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........61 ..61 3.7.3 Factory Tests and Inspectio Inspections........ ns.............. ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........61 .....61 3.7.4 Site Tests Tests and Inspections... Inspections......... ........... ........... ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........63 .....63 3.7.5 Training Training ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........67 ..67 3.8 SPECIAL SPECIAL EQUIPMEN EQUIPMENT, T, TOOLS AND MATERIA MATERIALS.... LS.......... ........... ........... ............ ............ ............ ........... ........... ........... ........... ........... ........... ........67 ..67 3.8.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........67 ..67 3.8.2 Special Special Equipment, Equipment, Instruments Instruments and Devices Devices ............ .................. ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........67 .....67 3.8.3 Erection Erection Hardware Hardware ........... ................. ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........68 .....68 3.9 SPARE PARTS...... PARTS........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........68 ..68 3.9.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........68 ..68 3.9.2 Recommended Recommended Spare Parts ........... ................. ........... ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........69 .....69 3.10 INSTALLATION INSTALLATION AND ERECTION ERECTION SUPERVISION SUPERVISION ........... ................. ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........69 ..69 3.10.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........69 ..69 3.10.2 Scope of Installati Installation on and Erection Erection Supervision Supervision Services Services ........... ................ ........... ........... ........... ............ ............ ............ ........... ..........69 .....69 4
TECHNICAL TECHNICAL BID FORMS ............ .................. ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........71 ..71 4.1 72.5 kV GAS INSULATED INSULATED SUBSTATION.... SUBSTATION.......... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ..........71 .....71 4.1.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........71 ..71 4.1.2 Characteristic Characteristicss ........... ................ ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........71 ..71 4.2 145kV GAS INSULATED INSULATED SBSTATION SBSTATION ........... ................. ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........76 .....76 4.2.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........76 ..76 4.2.2 Characteristic Characteristicss ........... ................ ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........76 ..76 4.3 242kV GAS INSULATED INSULATED SUBS SUBSTATIO TATIO ........... ................. ........... ........... ............ ........... ........... ........... ........... ........... ........... ........... ........... ............ ........... ..........81 .....81 4.3.1 General ........... ................ ........... ........... ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........81 ..81 4.3.2 Characteristic Characteristicss ........... ................ ........... ............ ........... ........... ........... ........... ........... ........... ............ ............ ............ ............ ............ ........... ........... ........... ........... ........... ........... ........81 ..81
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 6/85
1. OBJECTIVE These Specifications establish the minimum technical requirements for the supply of SF 6 gas insulated substations (GIS) to be installed in three-phase grounded systems with rated voltages of 72.5, 145 and 242 kV.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 7/85
2. GENERAL REQUIREMENTS 1.1
GENERAL CONDITIONS
The design, workmanship, finishing and manufacturing of Gas Insulated Substations covered by these Specifications shall incorporate, as much as possible, the latest technological advancements, even if not specifically mentioned herein. All materials shall be new, of first quality and suitable for the conditions specified. When more than one unit is requested under the same item of the order, all shall be of the same design and basically identical, with all the corresponding parts being interchangeable.
1.2
CORRESPONDENCE, CORRESPONDENCE, LANGUAGES AND UNITS
All the documents and correspondence will be issued by COPEL in Portuguese or English. All the documents and correspondence shall preferably be issued by the SUPPLIER in Portuguese, while English or Spanish are acceptable. Whenever a technical document has been prepared with the text, titles and notes in a language other than Portuguese, English or Spanish, a corresponding legible translation to one of these languages shall be incorporated in the documents. The International System of Units shall be used in all the documents.Any value, which for convenience is shown in some other system of units, shall be expressed in the corresponding unit of the International System of Units. Foreign Suppliers shall provide Portuguese speaking interpreters to deal with COPEL’s representatives at any time at the place of meeting.
1.3
TECHNICAL BID DATA
Bidder shall fill in the bid forms included in Section 5 of these Specifications and shall furnish copies of all requested and/or necessary information, drawings, catalogs, leaflets, etc., in order to completely describe and define the equipment offered.
1.4
SUPPLIER DRAWINGS AND DOCUMENTS
1.4.1 General The drawing included in Section 6 of these Specifications outline the requirements for the Supply. The SUPPLIER shall design and submit for the approval by COPEL detailed drawings and other data, and technical instructions necessary for the manufacture, shop tests, quality control, handling, erection, field tests, operation and maintenance of the various Supply components. The approval by COPEL does not relieve the SUPPLIER from its responsibility to carry out the Supply in a workmanlike manner, conforming to these Specifications. All drawings shall be submitted for approval by COPEL, conforming to the SUPPLIER Document Schedule as defined in item 2.4.4.
1.4.2 Drawing Standards The drawings prepared by the SUPPLIER shall conform to the Associação Brasileira de Normas Técnicas ABNT (the Brazilian Association of Technical Standards) standards. The preferred size of the drawings is A1, except for schematics and lists, for which it is A3. The drawings shall be sufficiently clear to permit them to be microfilmed and/or scanned.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 8/85
The legends of the drawings and documents shall rigorously follow COPEL standard. Particularly, the space reserved for the titles shall contain: - equipment location physical area; - equipment; - drawing content identification; - COPEL number. COPEL will supply a floppy disk for setting up the legend.
1.4.3 Approval The approval procedure for SUPPLIER drawings and documents is the following: Four (4) dull copies of each document shall be submitted for approval by COPEL. After having analyzed each document, COPEL will forward to the SUPPLIER a technical report with the necessary comments and a dull copy of each document. The documents that need approval will be stamped as follows: - APPROVED - It authorizes the SUPPLIER to proceed with the manufacture or acquisition of the equipment covered by the document, but does no relieve the SUPPLIER from its full responsibility for compliance with its contractual obligations. - APPROVED WITH THE INDICATED CORRECTIONS - It authorizes the SUPPLIER to proceed with the manufacture or acquisition of the equipment covered by the document, conditioned to the execution of the required corrections, but does no relieve the SUPPLIER from its full responsibility for compliance with its contractual obligations. - RETURNED FOR CORRECTIONS - It determines that the SUPPLIER effects the indicated corrections and resubmits the document for approval by COPEL. The documents which shall be submitted only for COPEL knowledge and examination will be stamped as follows: - EXAMINED - It informs that the document has been considered as informative of the conception proposed by the SUPPLIER for the full compliance with the contractual obligations. - EXAMINED AND RETURNED FOR CORRECTIONS - Of a nature similar to the previous case, but it determines that the SUPPLIER effects the indicated corrections and resubmits the document for a new analysis by COPEL. COPEL will have 30 (thirty) days to analyze the SUPPLIER documents, provided they have been submitted in a time sequence and order that avoids the analysis of a large number of documents in a relatively short time, a condition that should be observed in the preparation of the Document Schedule. The approval of the SUPPLIER documents does not relieve the SUPPLIER from the obligation to comply with all the requirements of the Contract Documents or the responsibility for the correctness of the documents. All the documents that are returned with corrections shall be resubmitted to COPEL within 20 (twenty) days from the delivery protocol date. COPEL will then have 20 (twenty) days for a new analysis, from the protocol date of delivery at COPEL. This procedure shall be followed until the documents in question are stamped APPROVED or EXAMINED, as is the case. After this final phase, the SUPPLIER shall send to COPEL one (1) reproducible copy of the document that has been stamped APPROVED or EXAMINED.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 9/85
The SUPPLIER shall make, at its expense, whatever modifications in the documents necessary to obtain approval by COPEL. Whatever acquisitions or manufacturing services made before the approval of the respective documents are for the account and risk of the SUPPLIER. In case that any error is found in a SUPPLIER document during Supply erection, the correction, including any changes considered necessary to the Supply, shall be annotated on the document and the document shall be resubmitted for approval as outlined above. The costs relative to carrying out the changes in the Supply or in the structures design, as a direct result of the errors in the SUPPLIER documents, shall be borne by the SUPPLIER.
1.4.4 Document Schedule The SUPPLIER shall, when it submits its first detailed Manufacturing Schedule, prepare and submit for approval by COPEL a list of the main drawings and other documents that it proposes to submit for approval, conforming to item 2.4.5 - Drawings and Documents to be Forwarded, with the dates that it proposes to submit such drawings and documents. Thereafter, for every 3 (three) months, throughout the life of the Contract, the SUPPLIER shall, together with each revision or confirmation of the Erection Schedule, revise this Document Schedule and submit it for approval by COPEL, or confirm that the Schedule previously submitted is still in effect.
1.4.5 Drawings and Documents to be Forwarded The SUPPLIER shall submit for approval by COPEL and/or for its files, drawings and other documents with the technical data applicable to the Supply that, at the discretion of COPEL, are judged necessary, including but not limited to the following: a) Document Schedule - A complete list of all drawings, technical data and design documents, by title and number, that the SUPPLIER will provide, with the respective delivery dates. b) General Arrangement Drawings - Outline Drawings, indicating the list of components, materials and main equipment accessories, including weights and dimensions. c) Detailed Drawings - Drawings Drawings with all the necessary equipment and material details necessary for manufacture and/or erection. These drawings shall indicate cross-references to all the other corresponding outline drawings. d) Civil Construction Design Requirements and Information - All necessary dimensions and details about the concrete structures, including the location, recesses, embedded items, injection needs, as well as the types, sizes of anchor bolts and others. e) Erection Drawings. f)
Manufacturing Drawings.
g) Transport Drawings. h) Electrical Drawings and Diagrams - All the data referring to electrical equipment, including block, single line, elementary, schematics, and internal wiring diagrams, and terminal blocks for external connections. i)
Interconnection Diagrams - All All necessary details for interconnecting the Supply equipment, including cable lists.
j)
Quality Assurance Manual.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 10/85
k) Quality Control Manual - The SUPPLIER shall prepare and submit for approval by COPEL a Quality Control Manual, which shall cover all activities that influence final quality and performance of the Supply, conforming to the guidelines of the ISO 9001 Standard. l)
Erection Manual - The SUPPLIER shall prepare an Erection Manual that contains all necessary information for Jobsite erection and submit it for approval by COPEL. This document is considered as unique and final, valid for the Supply Erection.
m) Maintenance Manual - The SUPPLIER shall prepare and submit for approval by COPEL a Maintenance Manual that fully describes all aspects of preventive and corrective maintenance. n) Operation Manual. o) Commissioning Reports - Such reports shall be prepared and delivered to COPEL within 30 (thirty) days after the release for operation of each one of the Supply parts, and the issue of the Provisional Acceptance Certificates will be conditioned on their receipt. The final form of the Commissioning Reports shall be submitted for approval by COPEL. p) Data Book - Book of occurrences during manufacture, erection and tests for each piece of equipment, with all its details, mainly test reports and data sheets. q) Calculation Sheets.
1.4.6 Ownership of the Drawings The drawings, diagrams and other engineering documents prepared by the SUPPLIER relative to the present Contract and submitted to COPEL, become the property of COPEL, which will not reuse them for other purposes than the Project for which the data were prepared.
1.4.7 Record File Copies Within 30 (thirty) days after completion of Commissioning for each main component, the SUPPLIER shall deliver to COPEL 1 (one) copy, sufficiently clear to permit all approved drawings “as built” that have been altered or not during the erection and commissioning to be microfilmed or scanned. Drawing revisions, with modifications which occurred during the warranty period shall be submitted for approval by COPEL, within 30 (thirty) days after the fact that caused the revision. Final drawings shall also be furnished on magnetic media. Format shall be DGN of Intergraph Microstation software, release 3.4 or higher, or format DXF. The drawings shall be delivered in 3.5” high density disks DOS formatted. All information related to a drawing shall be in the same file, i.e., no reference files shall be accepted. Note: For DXF format, format, necessary necessary paramete parameters rs (such as colors, colors, fonts, fonts, sizes) sizes) to permit permit conversion conversion to DGN DGN format (COPEL standard) shall be established together with COPEL.
1.4.8 Copies of the Manuals The approved revisions for the Erection, Operation and Maintenance Manuals shall be provided to COPEL in 5 (five) complete sets, and the approved revisions for the Quality Control Manual, conforming to item 2.7Quality Assurance, in 2 (two) complete sets. The manuals can be later revised if inadequacies or errors are detected during manufacturing, erection, tests or warranty period. The SUPPLIER shall replace or supplement the corresponding pages within 30 (thirty) days after notification in writing, by COPEL.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 11/85
The final versions of both the manuals and drawings shall also be submitted in in digital form on magnetic or optical disk, after previous approval by COPEL.
1.5
SUPPLY EXECUTION
1.5.1 General The SUPPLIER shall perform and complete the Supply in strict accordance with the Instructions to Bidders, to the satisfaction of COPEL, and strictly obey and adhere to the instructions and directions of COPEL on any matter, mentioned or not in the Instructions to Bidders, relative to the Supply.
1.5.2 Startand Progress of Services The SUPPLIER shall conclude and deliver all parts of the Supply and in its entirety, within the respective deadlines stipulated in the Instructions to Bidders.
1.6
PLANNING AND CONTROL OF MANUFACTURING
1.6.1 Review of the Planning Presented for The Qualification Phase Within 15 (fifteen) days from the signing of the Contract, COPEL and the SUPPLIER, together, shall hold a meeting for reviewing the Supply Planning documents, presented in the Qualification phase. In this meeting, the planning and control systems to be used during the performance of the Supply will be established. Basic requirements are specified in the subsequent items.
1.6.2 Manufacturing and Supply Schedule Within the deadlines established in the Contract, the SUPPLIER shall submit to COPEL a detailed Manufacturing and Supply Schedule. Thereafter, the SUPPLIER shall submit to COPEL, every 3 (three) months, an updated schedule, or certify that the schedule previously submitted continues in effect. The SUPPLIER shall put a list of Purchase Orders for all its Subsuppliers at the disposition of COPEL. COPEL can, whenever it considers necessary, visit the Subsuppliers. They shall be instructed to cooperate with COPEL and facilitate the work by providing all the information asked for.
1.6.3 Manufacturing Execution Plan The Manufacturing Execution Plan shall be controlled and updated by the SUPPLIER, from the beginning to the end of manufacturing. Only those revisions that have been approved by COPEL in this plan will be acceptable. The necessary revisions to the Manufacturing Execution Plan will have only one purpose, to provide the means for COPEL to effectively oversee the progress of the work, and accepting the revisions does not mean, in any way, that COPEL accepts the responsibility for the adopted methods.
1.6.4 Manufacturing Inspection Program The SUPPLIER shall prepare quarterly inspection and testing programs for raw material, soldering and manufacture, in agreement with the contractual marks and status of the Supply. These programs shall be updated monthly and submitted for approval by COPEL.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 12/85
1.6.5 Progress and Planning Report The SUPPLIER shall submit to COPEL, not later than the tenth day of the following month, 2 (two) copies of a progress and planning report, covering its activities during each month. These reports shall be prepared in a manner satisfactory to COPEL.
1.7
QUALITY ASSURANCE
1.7.1 Basic Requirements The SUPPLIER shall show, at the discretion of COPEL, its capacity to meet the requirements of the ISO 9001 standard for all activities that result in final Supply quality and performance. COPEL considers it a requirement for the SUPPLIER to be certified in meeting the ISO 9001 standard. The SUPPLIER shall prepare and submit for approval by COPEL the Quality Manuals and the quality plans that are being implemented.
1.7.2 Project Checking The SUPPLIER shall send to COPEL a check list of the main phases of project development, covering each step indicating who is responsible for the coordination of each step, and the Supply internal interfaces.
1.7.3 Subsuppliers The SUPPLIER shall list all Subsuppliers by item, material or components to be purchased and submit this list to COPEL. The SUPPLIER shall put the purchase orders and specifications, which shall ensure compliance with the Contract Documents, specific for the Supply, at the disposition of the Inspector. The Inspection Plan for the Subsuppliers (IPS) shall be delivered to COPEL in advance, with enough time for COPEL to define those activities in which the Inspector will participate.
1.7.4 Certified Reports The SUPPLIER shall present Certified Reports for the Type Tests provided for in these Specifications or necessary to prove the quality of any equipment or material, conforming to internationally recognized standards. For the acceptance of these certified reports, COPEL may, at its discretion, require that they be issued by an independent laboratory. The Certificates that do not meet the above requirements are not acceptable to COPEL. In this case, the SUPPLIER shall provide for the necessary tests, and their costs will be borne by the SUPPLIER.
1.7.5 Manufacturing All phases of manufacture shall be covered by the SUPPLIER’s internal Quality Control Plan. An inspection plan for the most relevant phases and events of the manufacturing process, from reception to delivery, shall be submitted for approval by COPEL.
1.7.6 “Non-Conforming” Products
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 13/85
The use or repair of "non-conforming” products at any stage of the Supply shall be submitted for the approval by COPEL. The non-conformity record (NCR) with the corresponding product dispositions shall be included in the Supply Data Book.
1.7.7 Quality Records The documents generated from the SUPPLIER's internal control plans, from the Inspection Plans and the non-conformity records (NCR) shall be organized in a way to serve as a history and subsidy for future technical assistance or maintenance, and shall be available from the SUPPLIER for consulting for 5 (five) years.
1.8
INSPECTION AND OVERSIGHT
1.8.1 Inspection at the Shop The SUPPLIER shall inform COPEL, at least 30 days before, the dates in which the equipment will be ready for inspection. All material and components destined to be included in the Supply, as well as manufacturing quality, will be subject to inspection and testing by COPEL, at any time. COPEL has the right, regardless of any previous inspection or their waiver, or acceptance of the certified test reports, to reject defective material, equipment and manufacturing quality, and require its correction, without entitling the SUPPLIER the right to extend the deadline for the conclusion of the Supply or to additional payment. The decision to accept the material, equipment and manufacturing quality is COPEL’s own. Unless COPEL, in writing, specifically waives the right of inspection and tests, no material or equipment shall be shipped from the SUPPLIER’s shop before the necessary tests and inspection are done, and the corresponding certified reports have been accepted by COPEL. At its expense, the SUPPLIER shall readily provide for all reasonable facilities, manpower, assistance, instruments, devices and necessary material for a safe and convenient inspection, examination, measuring and testing at the disposition of COPEL, before any material and/or component is included in the Supply. Any additional inspection costs due to the impossibility of performing the tests on the fixed dates will be borne by the SUPPLIER. The Inspector will have access to all the locations where service or materials are being prepared for the Supply, and have all the facilities needed to perform unrestricted inspections during normal working hours, in any place where such equipment, materials and services are to be found, including access to the Subsuppliers installations, and purchasing, studies and shipping information. All information that the Inspector needs regarding any components and/or material used or destined to be used in the Supply shall be given to COPEL.
1.8.2 Jobsite Oversight COPEL will exercise total and ample oversight of the Supply, by its own means and/or inspectors duly authorized, who are authorized to halt work, without prior notice, whenever they consider it necessary for the successful execution of the Supply. After the conclusion of each partial service stage, the SUPPLIER shall ask COPEL to check the executed work. Only after release of the completed stage by COPEL, will the SUPPLIER ask for authorization to start the next activity. The SUPPLIER shall facilitate, from all points of view, the oversight and control. This includes, but is not limited to inspection and visits to SUPPLIER installations and premises, and the transmittal of explanations and information of any type regarding the progress of services, as well as information on inventories, number of employees, source of materials, etc. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 14/85
The SUPPLIER, at its own cost, and whenever requested, shall provide COPEL with all facilities, manpower, assistance, instruments and material necessary for overseeing, checking, measuring and testing any material, equipment or service. The SUPPLIER shall bear any additional cost as a result of the inspections to be done on the equipment, materials or services that are not in condition to be inspected on the dates set for the inspection. Judgment as to the acceptability of the material, equipment and manpower is COPEL’s own. Oversight or omission thereof do not diminish nor lessen the responsibility of the SUPPLIER as to accurate execution of the contracted services. The SUPPLIER can not extend the deadline for delivering the Supply by the time taken for the above mentioned oversight.
1.9
PACKING, SHIPPING AND DELIVERY
1.9.1 Packing Instructions The Supply shall be packed and protected for transport, conforming to the best established practices. The SUPPLIER shall, independently of COPEL, be the only one responsible for delivering the Supply in good condition. The SUPPLIER shall be responsible to fulfill all requirements of Brazilian law relative to transport, marine insurance and marking the packages for shipment.
1.9.2 Shipping The SUPPLIER shall provide, at the time of shipping and for each shipment, detailed invoices with the contents and equipment prices.
1.9.3 Delivery If, after delivery , it is found that there is any damage or defect, COPEL can, at its discretion, designate Third Parties to carry out the respective repairs. The costs paid to these Third Parties, in the case of damages attributable to the SUPPLIER, shall be deducted from the Contract price. If COPEL judges that some damage cannot be repaired on the Jobsite, or is of such a nature that COPEL believes it is necessary to carry out the repairs in the SUPPLIER’s shop or even replace the item, the SUPPLIER shall carry out the repair or replacement of the damaged item, immediately after such damage has been observed. All expenses for transport and insurance are to be borne by the SUPPLIER. The judgment of the physical condition and acceptability of the Supply items is COPEL’s own.
1.10 REQUIREMENTS OF SUPPLIER PERSONNEL AT JOBSITE Supplier Personnel at Jobsite shall have sufficient knowledge of Portuguese and/or English, to read, write, understand and speak, during daily working activities. The personnel shall rigorously observe the general and disciplinary regulations of COPEL on the Jobsite. The work hours established by COPEL shall be observed carefully.
1.11 SUBSUPPLIES SUBSUPPLIE S AND SUBCONTRACTING SUBCONTRACTI NG
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 15/85
The SUPPLIER shall submit for prior approval by COPEL the names of Subsuppliers and manufacturers for all material, components and equipment that it intends to include in the Supply, together with the information on performance, capacity and other significant information pertinent to these materials, components and equipment, including corresponding material samples when requested. Material, components or equipment installed or employed, without such approval, run the risk of subsequent rejection. No clause contained in the contract with the subcontractor obligates COPEL contractually with the subcontractors. The SUPPLIER is entirely responsible for payment of the services performed by the subcontractors.
1.12 STANDARDS The standards under which the Supply is to be performed or tested are mentioned in item 4.2. The latest revision or edition of said standards at the time of submission of the Bids will apply. If the SUPPLIER desires to deviate from the mentioned standards relative to design, materials, manufacture and/or testing, a statement of the exact nature of the proposed deviation shall be submitted for approval. Applicable equivalent standards will be acceptable provided evidence of equivalency is submitted to COPEL. Deviations from the basic design criteria will not be permitted. The Supply shall be designed and manufactured in all respects to be fit for its intended purpose, and the SUPPLIER will not be relieved from meeting quality and performance requirements because of compliance with technical standards, Contract Drawings and Technical Specifications.
1.13 EQUIPMENT, TOOLS TOOLS AND ELECTRIC POWER POWER AT JOBSITE JOBSITE 1.13.1 General If COPEL requests, the SUPPLIER shall provide complete details about any type of material or equipment used in certain services. Not meeting such requests can lead to rejection of the equipment or material. All expenses for personnel transport will be borne by the SUPPLIER, as well as the supply, transport and maintenance of all construction tools and equipment necessary for Supply execution. The existence of contracts and commitments between Subcontractors and the SUPPLIER does not relieve nor diminish SUPPLIER responsibilities for the fulfillment of the deadlines and other obligations stipulated in the Instructions to Bidders.
1.13.2 Equipment and Tools The SUPPLIER is entirely responsible for the necessary tools and equipment for the Supply execution. All expenses relative to its own tools and equipment are entirely the responsibility of the SUPPLIER, such as handling, transport, special precautions, erection and disassembly, operation and maintenance, combustibles, lubricants, replacement parts, insurance and others. The acceptance of the tools and equipment by COPEL does not give the SUPPLIER any reason for invoking its inadequacy to fulfill execution deadlines and time schedules, if the mentioned tools and equipment are insufficient and without the conditions to execute the Supply.
1.13.3 Electric Power Power at Jobsite Jobsite The voltages available on the Jobsite are 220/127 V, 60 Hz.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 16/85
1.14 DISCLOSURE The SUPPLIER is obliged to obtain the previous consent by COPEL before the publication of any report, advertising, illustration, photograph, picture, videocassette tape or interview, about the whole or detail of the Jobsite.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão 2 2.1
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 17/85
GENERAL TECHNICAL SPECIFICATIONS OBJECTIVE
This part of the document specifies the general requirements applicable to the materials, components and the manufacturing and field erection quality, involved in the design and in the manufacture of those items of the SUPPLY, covered by Section 4 - Technical Specifications and Section 6 - Specification Drawings. Additional special requirements are defined in the text of the Technical Specifications which, in case of conflict, prevail over these General Technical Specifications.
2.2
TECHNICAL STANDARDS
Except if stated otherwise in Section 4 - Technical Specifications, the design, rated values, technical characteristics, manufacturing quality, storage, erection, and tests for all materials and equipment, which are the object of this SUPPLY, shall comply with the latest revisions of the standards of the following Organizations: ABNT Associação Bra Brassileira de de No Norma rmas Té Técnicas (N (NBR St Standards rds); ANSI American Na National St Standards In Institute; ASME American Society of Mechanical Engineers; ASTM American Society for Testing and Materials; AWS American Welding Society; I EC International Electrotechnical Commission; IEEE Institute of of Electrical and Electronics Engineers; ISO International St Standardization Or Organization; MIL Military Standards; NEMA National Electrical Manufa ufacturers Association; NFPA National Fire Protection Association; SI S Sveri eriges St Standardi rdiser serungskom skomm mission/S n/Swedish S Sttand andards rds In Institution.
2.3
MATERIALS AND COMPONENTS
The SUPPLIER shall supply all those materials and equipment necessary that most completely meet these Specifications. All materials and components incorporated in the equipment object of this SUPPLY shall be of the first class commercial quality, as normally used for this type of equipment, mechanically resistant, durable, manufactured using the best engineering practice and for the service to which the equipment will be subjected, free from defects and imperfections, of recent manufacture and unused, and where shown, of the classifications and grades designated herein. If the SUPPLIER, for whatever reason, wishes to deviate or use material not covered by the listed standards, he shall state the exact nature and degree of difference or exception, and submit the complete specifications of the material that he proposes to use, for approval by COPEL. The SUPPLIER shall submit for approval by COPEL a list outlining the main parts incorporated in or elements of the equipment, indicating the type and characteristics of the material to be used in their manufacture in compliance with the ASTM and ABNT standards. This list shall be submitted for approval by COPEL, before ordering the materials. The SUPPLIER shall submit for approval by COPEL the names of the manufacturers, specifications and catalogues for all the equipment, materials and devices that he proposes to use in the SUPPLY. Designs and lists of materials submitted for approval shall indicate the type and the quality of material. Samples of such equipment, materials and devices shall be submitted for approval by COPEL, when requested. Equipment, GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 18/85
materials and devices used or installed without such approval may be rejected by COPEL. The equipment, materials and devices used for similar or identical services shall be of the same type, mark and manufacturer, and shall be interchangeable.
2.4
TESTS
All materials, parts and assemblies thereof, that make up part of the SUPPLY, unless otherwise directed by COPEL, shall be tested following the applicable standards of ASTM or the best available commercial process, which are suitable for this particular type and class of work. All steel sheets, forged and cast parts to be used in structurally and/or functionally important parts, shall be tested using non-destructive tests, approved by COPEL, in compliance with the applicable ASTM standards or those similar and approved. At COPEL’s discretion, non-destructive tests may be requested for other materials as well as those tests proposed by the SUPPLIER. The SUPPLIER shall prepare the specimens and perform the tests and analysis in such a way as to demonstrate that the various materials comply with the applicable standards. If the SUPPLIER intends to use materials in stock, not manufactured especially for this SUPPLY, he shall show that such materials meet the requirements herein specified. In this case, the tests of these materials may be waived. At COPEL’s discretion, reports and certificates of routine tests may be acceptable. Certified copies of the test reports shall be furnished to COPEL within fifteen days of the tests being performed. The results of these tests shall be presented in a manner that permits verification of the conformity to the applicable specifications for the material tested. All tests or trials shall be made in the presence of a duly authorized Inspector representing COPEL, except when formally waived. The SUPPLIER shall keep COPEL informed, in advance, of the phase of the SUPPLY so that COPEL may program its inspection of such. No material shall be dispatched before all tests, analyses and inspections at the shop have been completed, and certified copies of the test reports have been received by COPEL. The procedures described above shall be incorporated in the Manual of Quality Control required in these Specifications. Costs of all tests and trials, except for the expenses related to the COPEL Inspector, shall be borne by the SUPPLIER and shall be included in the equipment price. The acceptance of the materials, parts and assemblies, or the waiving of the tests by COPEL, does not relieve the SUPPLIER from the complete responsibility for supplying equipment that meets the requirements of these Specifications.
2.5
MANUFACTURING MANUFACTURING QUALITY
2.5.1 Quality of Management The quality management and quality assurance standards system shall be governed by the ISO 9000 Standard series, from the qualification phase of the manufacturer to the specification, proposal, design, material acquisition, manufacture, erection and commissioning phases.
2.5.2 General Requirements Manufacturing quality shall comply with the best practices available for the equipment object of these Specifications, in spite of whatever omission in the Technical Specifications or Specification Drawings. All the SUPPLY shall be carried out by personnel qualified for their respective functions. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 19/85
Replaceable parts shall be machined accurately and to the specified dimensions so that replacements according to the design drawings may be readily made. The SUPPLIER shall have and keep in stock, for at least ten (10) years, at his expense, sufficient templates, gages, dies and other records to enable him to make repair and replacement parts. All the special gages and templates, necessary for the field erection on-site, shall remain the property of COPEL. The dies shall remain the property of the SUPPLIER. All bolt and nut threads shall comply with the ISO 68 Standard, and shall be metric whenever possible.
2.5.3 Electric Welding a) Welding Procedures All welding shall be performed by the electric arc method, by a process that excludes the contact of the metal with the air, and where practicable, using automatic machines. The Welding Welding Procedure Procedure Specification (WPS) shall be submitted for approval by COPEL, duly accompanied by the respective Procedure Qualification Report (PQR) and by the welding plans b) Welding Preparation Parts to be welded shall be accurately cut to size, with edges sheared, flame-cut, or machined to suit the required type of welding and to allow for good fusion with base metal. Cut surfaces shall be free of all visible visible defects, such as laminations, surface defects caused by shearing or flame-cutting, or any other harmful defects. Sheets to be welded shall be free of rust, grease and other foreign matter along the surfaces prepared for welding. c) Stress Relief Regarding the structurally important parts, localized stress-relieving will not be permitted on the parts welded at the shop nor on-site. The design shall clearly state when a part or piece shall be submitted to stress relief. The process for stress relief shall be made before final machining. d) Welder and Operator Qualification For the welding of the main structurally and functionally important parts, the qualification procedures for the welders and welding machine operators assigned to this SUPPLY shall meet the requirements of Section IX of the ASME Boiler and Pressure Vessel Code. For the welding of the less important parts, the qualification procedures for the welders and the welding machine operators may meet other equivalent standards, if they are acceptable to COPEL.
2.5.4 Brazing a) Brazing Procedures Brazings shall be carried out preferably by the methods of induction, electric resistance or controlled atmosphere oven, with the added metal evenly distributed on the joint by capillary attraction. The Brazing Procedure Specification (BPS) shall be submitted for approval by COPEL, duly accompanied by the respective Procedure Qualification Report (PQR) and by the brazing plans.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 20/85
b) Brazers and Operators Qualifications The performance qualification of the brazers and machine operators assigned to performing the brazed joints covered by this SUPPLY shall be carried out based on the requirements of Section IX of the ASME Boiler and Pressure Vessel Code.
2.5.5 Cast and/or Forged Steel Parts Parts shall be free of harmful defects and shall be satisfactorily cleaned for their intended use. The surfaces of cast steel parts that are not machined and that remain exposed until final installation, shall be free of foundry irregularities such as projections, hollows, roughness, honeycombing and chip marks, so that they do not need to be smoothed on-site before painting. Existing defects shall be completely removed to the sound metal. The structure of cast steel parts shall be homogeneous and free of excessive non-metallic inclusions. A concentration of impurities or alloys at critical points in a cast steel part will be sufficient for its rejection. All steel cast parts shall be submitted to an adequate heat treatment.
2.5.6 Finishing Surface finishing shall be indicated in the detailed design drawings and comply with the requirements of the ANSI B-46.1 Surface Roughness, Waviness and Lay standard, or other equivalent approved standard. All parts shall be free of burrs, sharp edges, and cutting, machining and welding imperfections. All visible parts shall receive a special finish to ensure an agreeable appearance once machining is finished.
2.6
PROTECTIVE PAINTING, FINISHING AND COVERINGS
2.6.1 General Requirements After manufacture and inspection, but before shipping, equipment and part surfaces involved in this SUPPLY shall receive treatment according to the following recommendations: a) Surfaces Not Requiring Protection Surfaces to be embedded in concrete, corrosion resistant steel surfaces and the non-ferrous surfaces do not require any protection. Stainless steel, non-ferrous material and machined metals that have sliding or rolling contact do not require painting. b) Surfaces Requiring Protection Machined surfaces shall be completely free of foreign matter and covered with a removable anti-corrosion protection. Those surfaces that are finished and make contact, of ferrous metal, or that have bolted joints, shall be washed with a corrosion inhibitor and covered with a suitable anti-corrosive material before shipping. Finished surfaces for the large parts and all other surfaces shall be protected with wood or another appropriate protection. Unassembled pins and bolts shall be lubricated and packaged in waterproof paper or protected by other approved means. c) Non-Painted Surfaces GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 21/85
Surfaces that are not painted shall be covered or protected by other means during the cleaning operation and the painting of contiguous surfaces. d) Non-machined Exposed Surfaces With the exception of those surfaces that are embedded in concrete and when otherwise specified, all nonmachined exposed surfaces, internal and external, including all equipment and accessories, shall receive surface preparation and paint in compliance with the recommendations of the manufacturer of the paint to be used and the applicable requirements of the standards indicated in these specifications and/or ABNT. e) Galvanized Surfaces Galvanized surfaces do not need to be painted, except where specifically necessary for reasons of appearance; in these cases, surface preparation shall be done by solvent cleaning, in compliance with the NBR 7145 Standard, for the later application of a washprimer. f) Panel Components All cubicle and panel mechanical components composed of non-ferrous metal, such as enclosures, structures, doors and fixed panels, dividers, frames, covers, roofs, floor coverings, sills, and other, shall receive a protection treatment as specified or another equivalent protection submitted for approval by COPEL. The hinged and/or movable parts, where the paint may be removed or scraped, shall be manufactured of stainless steel or brass. g) Bolts, Nuts and Washers Bolts, nuts and washers, when not otherwise specified, shall be zinc coated by an electrolytic process, or a similar process approved by COPEL. The minimum thickness admissible is 12 micrometers.
2.6.2 Retouching, On-Site Final Finish Painting and On-Site Painting After on-site erection of the equipment, the painted surfaces that were damaged due to transport or erection, shall be retouched and, after the retouching, the equipment’s external surfaces shall receive a supplementary coat of finishing paint. This supplementary coat will be called on-site final finish painting. This service will be applicable only for equipment that is painted at the shop. Surfaces that are not painted at the shop will be completely painted on-site, thus called on-site painting. Before performing on-site final finish painting, the surfaces shall be cleaned with the solvent recommended by the paint manufacturer and receive a surface preparation application recommended by the paint manufacturer. To perform the retouching, the recommendation of the paint manufacturer shall be followed.
2.6.3 Responsibilities for Painting Service/Paint Supply Machined surfaces in general shall receive protection or painting at the shop of the SUPPLIER, in compliance with the requirements of the Technical Specifications.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 22/85
Retouching, on-site final finish and on-site painting, after the installation of the equipment, will be done under COPEL’s supervision. For retouching and on-site final finish painting, the SUPPLIER shall furnish the products (paint and solvents) needed in the following quantities: Undercoating and intermediary products: •
30% of the forecast quantity (realized) for the painting at the shop, the minimum quantity being based on data from the paint manufacturer and the area to be painted.
Finishing Paint •
100% of the forecast (realized) quantity for painting at the shop, and that which corresponds to one coat, the minimum quantity being based on data from the paint manufacturer and the area to be painted.
Surface Preparation •
30% of the quantity of finishing paint referred to above. The surface preparation coat is composed of oxygenated solvents destined to re-activate the layers of thermally fixed coverings that have surpassed their curing time.
For on-site painting all the paints and solvents shall be provided by the SUPPLIER, with the estimated minimum quantities being based on data furnished by the paint manufacturer and the area to be painted. Losses of 30% should be considered when specifying the quantities of paint. The SUPPLIER shall indicate each area and the corresponding forecast for the quantity of paint for each piece of equipment. If there are variations in the areas to be painted, the SUPPLIER shall furnish enough paint to complete painting of the total area to be painted. The paints supplied for on-site final finishing shall be new and be within the full validity time period indicated by the paint manufacturer, as of the date they are received by COPEL. The on-site delivery of these paints will be after the on-site erection of all equipment. All paints, solvents and surface preparations for painting at the shop, retouching, on-site final finish painting and on-site painting shall be furnished by the SUPPLIER.
2.6.4 Paint Quality and Inspection All the paint used in the SUPPLY shall come from the same manufacturer, and the products shall be approved by COPEL. In case the products are not approved previously, three liters of each type of paint shall be submitted to COPEL, for analysis, accompanied by the respective technical bulletin. During the reception of the paint, preparation of the surface and application, tests and inspections shall be carried out to ensure the required characteristics at COPEL’s discretion and at the expense of the SUPPLIER, using as a basis the recommendations of the paint manufacturer, applicable standards and the Technical Specifications. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 23/85
Before shipping, the painted surfaces shall not present defects or imperfections. Any necessary retouching shall be approved by COPEL.
2.6.5 Surface Treatment and Preparation To treat the surfaces to be painted, the applicable ABNT or SIS standards shall be complied with, and generally all the parts, before receiving treatment, shall pass a rigorous visual inspection, controlling the welding and sanding finish, cutting burrs, and other imperfections. Cleaning of each piece shall be done by jetblasting with angular and semi-sphere grains of steel, the grains in compliance with the rugosity for the type and thickness of paint demanded and submitted for approval by COPEL. The standard for the jet-blasting shall comply with the Technical Specifications and the NBR 7348 Standard. The jet-blasted part shall be handled with gloves that are suitable for the job, void of dust, grease or other substances that could be transferred to the jet-blasted surface. The jet-blasted part shall not be exposed to an atmosphere with a relative humidity higher than 85%, presence of dust, vapors of any kind, nor oils and grease. The treatment process shall not be interrupted for a period of more than three hours after blasting. All surfaces shall be jet-blasted up to the white metal - Grade Sa3, as specified in NBR 7348. In the case of oil pumps, electric motors and related equipment, the manufacturer's standards may be adopted.
2.6.6 Color Color for the finishing paint of SF6 equipment and buses shall be light gray, Munsell N.6.5.
2.6.7 Surfaces that will be Welded On-Site All the edges of the sheets prepared for on-site welding shall receive a layer of anti-corrosive composite. This composite, which shall be applied in compliance with the instructions of the paint manufacturer, shall be removable with an organic solvent.
2.6.8 Technical Assistance In the case of on-site painting, the SUPPLIER shall furnish complete technical assistance, using a supervisor from the paint manufacturer, whenever painting is begun and whenever it is requested by COPEL. The costs for delays caused by stoppages, losses or service that has to be redone, for not meeting the requirement of the technical assistance or problems caused by paint not performing to the specified characteristics, will be borne by the SUPPLIER.
2.6.9 Warranty The applied paints shall have a 2 (two) year warranty after the date of acceptance by COPEL for any defects resulting from not complying with the desired characteristics of the paint and its application at the shop. The same applies for those paints supplied directly on-site, in this case restricted only to the quality of the paint and any defects that occur because of paint quality.
2.7
PIPING
The SUPPLIER shall furnish all the air, oil, water and drain pipes and the respective valves as required in these Specifications. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 24/85
Design and manufacture of the piping systems shall comply with the latest revision of the American National Standard Code for Pressure Piping - ANSI B-31.1, published by ASME, or other equivalent standards for piping previously approved by COPEL. The thickness of the walls, class and material of the pipes and connections, flanges and valves shall be determined by the maximum operating pressure of the system. Security and pressure test factors shall be those stipulated in the ASME code. Fluid velocity shall not exceed 4 m/s. Gate valves on pressurized lines with a nominal diameter of 214 mm (8") or more shall be provided with a bypass system incorporated in the valve for pressure equalization. Threads on the pipes, valves and connections of 73 mm (2½") in diameter or less shall comply with the ANSI Standard B2.1 (NPT). Pipes with a diameter larger than 73 mm (2½") (2½") shall have flanged connections. The details of the flanges and other connections shall comply with ANSI B16.5, Steel Pipe Flanges and Flanged Fittings. All threads for the bolts and nuts shall comply with the recommendation R68 of the International Standardization Organization (ISO) and shall be metric whenever possible. All the piping system shall be pre-fabricated, up to the longest length possible, leaving only those joints and flanged connections necessary for erection and consequently for maintenance dismantling. When possible, large radius pipe curves shall be used in place of pipe junctions. All pipes shall be carefully cleaned before shipping. Oil pipe shall be impregnated with oil to prevent corrosion. All bolts, studs, nuts, washers, gaskets, seals, etc., needed for field erection, shall be furnished by the SUPPLIER with an excess of 10%.
2.8 GROUNDING 2.8.1 General Requirements The SUPPLIER shall use effective grounding techniques to eliminate or diminish the effects of interference voltages on the equipment that could hinder its operation. The instrument manufacturer recommendations shall be carefully observed as to the placement of grounding points. All power supply and signal cables shall be suitably grounded, as well as all the physical means used to lay them, such as cable ducts and cable trays. All cubicles, panels and boards where electronic equipment is to be installed shall be constructed with electromagnetic shielding techniques according to the requirements of item 3.15.3, even when they operate with their doors open. The grounding techniques suggested as follows shall be carefully analyzed by the SUPPLIER in the sense that they be completely used as is or improved, in compliance with his experience in installing electronic systems. All the techniques to be used in the design of equipment grounding shall be clearly described in the Proposal, as well as recommendations for grounding systems that are not part of the SUPPLY but directly related to it.
2.8.2 Cable Ways
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 25/85
Installation of conduits and junction boxes shall form a continuous continuous system. This system system shall be suitably connected to the grounding system of the plant. In order to prevent corrosion and to ensure grounding continuity, metal paint shall be applied to all threads. When cable trays are used, the system of trays shall have electric continuity by the use of junctions, and also by a ground cable that connects all tray terminals, in order to connect them to the grounding system.
2.8.3 Cable Shielding Metallic shields shall be used for the analog signal cables, in a way that reduces the effects of electromagnetic interference. Shield continuity shall be maintained for the whole length of the cable, including passages through the pull or junction boxes. Single shielded cables (complete shielding) shall be grounded at both cable terminals. Cables with double shielding (shielding by pairs and complete shielding) shall be grounded as follows: •
Internal shielding shall be grounded at one unique point, and this point shall correspond to the grounding point of the signal.
•
The external shielding shall be grounded at both cable terminals.
2.8.4 Module Shielding The electronic modules sensitive to electromagnetic interference shall be individually shielded by using grounding plans in the circuit boards and the metallic covering layers in a way that makes them compatible with the field levels to which they are being submitted. As well, the electromagnetic field generating modules and components, such as oscilloscopes, transformers, coils, capacitors and power supply sources shall be suitably shielded, aiming at reducing the level of electromagnetic emissions. All electronic boards shall have a local protection filter against the propagation of noise through the power supply lines due to consumption power surges and the presence of reactive loads. The filters shall be passive, implemented by way of series inductance and shunt capacitance and shall not introduce resistance on the power supply lines that impair the stability of the supply voltage. Low voltage signal amplifier components shall be metal-enclosed and shall always be based on balanced operational amplifiers. The circuit board routes and cables shall be short and symmetrical to minimize any common mode interference. Other solutions can be used, if they are previously approved by COPEL.
2.8.5 Cubicles, and/or Boards All metallic parts that make up the equipment (drawers, sustaining beams, installation plates, doors, sides, etc.) not subject to voltage shall be arranged so as to give an effective electric path to the ground. All metal equipment frames shall be suitably grounded, in a way to eliminate the possibility of electric shock to maintenance personnel.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 26/85
The various internal grounding subsystems of the equipment shall be insulated from one another and connected to the ground bus-bar. Cubicles, and/or boards shall have on their inner part a copper bar, with a minimum cross section of 70 mm², for connection of the ground wiring and of the control cable shielding. This bar shall have two connectors for bare copper cable with 16 to 70 mm² cross section, of the power station grounding system. Inside the cubicle, and near the external cable entrance, there shall be another ground bar to be used as a connection for the signal cable shielding. This bar shall be insulated from the cabinet and connected, at one unique point, directly to the cubicle ground bar.
2.8.6 Other Equipment All metallic parts of the equipment not subject to voltage shall be arranged so as to provide an effective path to ground. Equipment, support and bases shall be furnished with a suitable ground connector for bare copper cable with 16 to 70 mm² cross section, of the power station grounding system.
2.9
GENERAL ELECTRICAL REQUIREMENTS
2.9.1 General The definition of the operating characteristics for all devices and equipment such as circuit breakers, starters, fuses, bus-bars, wiring, etc., as well as the coordination of the supplied protections, is the full responsibility of the SUPPLIER. The calculation sheets for the functional definitions of the equipment and the protection coordination details shall be sent for review by COPEL.
2.9.2 Substation Voltages The following voltages will be available: - AC Power: a wye three-phase system, grounded neutral, four wire, 220/127V, a voltage variation range of +0% to -9%, 60 Hz and a short-circuit level of 10 kA at 220 V - DC Power: a direct current, insulated system, 125 V, a voltage variation range of +10% to -15%, and a short-circuit level of 10 kA. - Control, Signaling and Emergency: a direct current, insulated system, 125 V, a voltage variation range of +10% to -15%, and a short-circuit level of 10 kA. - Telecommunications: direct current, grounded positive system, 48 V, a voltage variation range of +10% to -15%, and a short-circuit level of 5 kA. The SUPPLIER shall furnish all the necessary devices to protect and ensure perfect operation of the electric and electronic equipment against interference and voltage surges that may occur in the power supply of COPEL.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 27/85
2.10 ELECTROMAGNETIC ELECTROMAGNETIC COMPATIBILITY The introduction of electronic equipment to perform the equipment control and protection functions in highvoltage substations means that there is a need for high levels of reliability for such equipment, that may not be obtained solely from the use of redundancy techniques, since in an operating environment characterized by high levels of electromagnetic interference, these interferences may simultaneously affect the redundant equipment. Special attention is required from the SUPPLIER to evaluate the requirements of these General Technical Specifications and determine the additional requirements that are considered necessary to ensure the electromagnetic compatibility of the equipment, concerning mainly: - Equipment design and construction characteristics (shielding) as to the capability to withstand the effects of electromagnetic interference. - Cable type and characteristics for connection to outside instruments. - Physical means for cable laying for internal panel wiring as well as for interconnection with field instruments. - Equipment shielding and grounding characteristics. As well as ensuring that the equipment will function in a satisfactory form in the forecasted environmental conditions at the installation site, the equipment shall be submitted to interference tests whose results will evaluate their compatibility with the operating environment. On the other hand, the presence in the field of environmental conditions more favorable than those contemplated in the standard, will not be acceptable as an argument for relaxing any of the severity levels related to electromagnetic compatibility required for the equipment in these Specifications.
2.11 EQUIPMENT CONNECTIONS 2.11.1 General If not otherwise stated, the SUPPLIER shall furnish all power cables, control and instrument cables, rigid and flexible bus-bars, conduits, pull boxes, junction boxes, conductors, cable ducts and trays necessary for effective linkage between all the equipment included in the SUPPLY, as well as all the necessary accessories. Repaired or spliced conductors must not be used. The connections, where necessary, shall be made within metallic pull or junction boxes. If there is an accumulation of cables, metallic ducts or cable trays shall be used. Electric cable conduits, ducts and trays shall be arranged in such a way that for their removal, it is not necessary to dismantle any equipment.
2.11.2 Cable Routing For the selection of conductor cables and the physical means for interconnection of the instruments or sensors in the field to the equipment included in the SUPPLY, for electric signal transmission, the SUPPLIER GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 28/85
shall employ techniques for the reduction or elimination of electric noise that could be caused by the presence of electric or magnetic fields and any ground voltage differences. The supplier shall send to COPEL, for review, the criteria he intends to use for cable routing, spacing between power cables and signal cables, cable segregation, etc.
2.12 AUTOMATIONS AND INTERLOCKS 2.12.1 General Requirements Automations and interlocks shall be made using high quality logic boards and equipment, as their impairment could directly affect the substation operation. Whenever possible, automations and interlocks shall be made without using contact multiplying relays. If this is not possible, the multiplying relays shall operate in pairs, one with positive logic and the other with negative logic, fed by two independent electric contacts, with one multiplying function normally open (NO) and the other normally closed (NC). The output concordance indicating a defect in the multiplying relay shall sound an alarm and block the automations.
2.12.2 Automations See Protection and Control Panels Especification.
2.12.3 Electrical Interlocks Electrical interlocks for operational safety shall be made between electrically controlled equipment and in which certain relative positions are prohibited. This type of interlocking shall always be made using at least two normal confirmation conditions, usually equipment position and voltage. Electric interlocking shall be in the form of latent positive action that in the case of circuit breakers, if their closing is electrically prohibited, shall prevent their momentary closing, even with the use of manual or mechanical commands. The electric interlocks may never prevent opening.
2.12.4 Mechanical Interlocking Mechanical interlocking for operational safety will be used when the equipment is physically closed, enabling their use. The “kirk” type interlocking system principle, used for operational safety, is that the key used may only be taken out if the activated device is in certain positions. The “kirk” locking shall not inhibit the opening of the circuit breakers. All starters and circuit breakers, except those in molded cases where it is impossible, shall be furnished with an adequate means for locking them in an open position, thus providing a safe block for maintenance.
2.12.5 Lockouts For the drawout elements of the switchgear, the following lockouts shall be provided: The element may not be moved from the inserted, extracted or test position if closed. An eventual movement shall cause immediate opening. The element may not be closed while it is not in the test, inserted or extracted position. The element may not be moved from the test position unless a mechanical releasing device is manually activated. The element may not be closed unless its main contacts are completely inserted, or extracted at a safe distance. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 29/85
The element may not be moved from the inserted, test or extracted position, with the power storage mechanism charged. Eventual movement shall result in immediate discharging of the spring, without resetting. The drawout type molded case circuit breakers shall be furnished with a means to prevent circuit breaker extraction or insertion with the main contacts closed.
2.13 EQUIPMENT ELECTRICAL CONTACTS All electrical contacts for control, metering, protection and monitoring equipment (relays, limit switches, pushbuttons, and control and selector switches) shall function at a voltage of 125 volts, direct current, and shall be electrically independent, operate correctly even when submitted to vibration, and shall meet the recommendations of IEC-947 Standard. The contacts shall have the following technical characteristics, as established in IEC-947-5-1 Standard: •
utilization categorie
DC-13
•
cont contac actt rat ratiing desi design gnat atio ionn
P600 P600
•
mechanical durability
1 million no load operating cycles 120 on-load operating cycles per hour
2.14 ELECTRONIC EQUIPMENT - ENVIRONMENTAL ENVIRONMENTAL CONDITIONS 2.14.1 Installation and Operating Environments Environments Electronic equipment shall be designed for indoor installation in ventilated environment.
2.14.2 Influence of the Power Supply Source Source The digital equipment shall be of the following classes, in compliance with the IEC 870-2-1 Standard.
TOLERANCE In Relation to the Voltage Value In Relation to the Frequency Value In relation to the Presence of Harmonics In Relation to the Ripple Voltage In Relation to Source Interrupting
CLASSES A C SOURCE AC3 F3 H4 V I3
2.14.3 Capability to Withstand Electromagnetic Electromagnetic Phenomena Phenomena a) Capability to Withstand Rated Frequency Voltage GIS01 – GAS INSULATED SUBSTATIONS
D C SOURCE DC3 VR3 V I3
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 30/85
As to the capability of the equipment to withstand power frequency common mode overvoltages, the equipment shall meet class VW3 (insulation level of 2.5 kV rms), in compliance with the IEC 870-2-1 Standard. Electronic modules with rated insulating voltage of 60 V or less shall meet VW1 class (voltage test of 500 V rms) of the same standard. Specifically for relay systems, the equipment shall be compatible with IEC 2555 Standard, C series. b) Capability to Withstand Impulse Voltage As to the capability level to withstand short time high overvoltages, the equipment shall meet class VW3 and class VW1 respectively, as per item 3.15.3.a, according to IEC 870-2-1. Specifically for relay systems, the equipment shall be compatible with IEC 255-5 Standard, with an impulse voltage peak of 5 kV. c) Capability to Withstand Repetitive Fast Transients As to the equipment capability level when subjected to repetitive electrical fast transients (such as caused by interruption of inductive loads and relay contact bounce), the equipment shall meet the IEC 1000-4-4 Standard, severity level 4. Specifically for relay systems, the equipment shall be compatible with IEC 25522-4 Standard class IV. d) Capability to Withstand Oscillatory Waves As to the equipment capability level when subjected to damped oscillatory waves (such as induced by lightning or by switching with restriking of the arc at medium and high voltages), the equipment shall be compatible with what is established in IEC Standard 1000-4-12, severity levels 4 and 3 of the referred Standard, respectively for the ring wave and damped oscillatory wave tests. Specifically for relay systems, the equipment shall be compatible with IEC 255-22-1 Standard, class III. e) Capability to Withstand Electrostatic Discharges As to the capability to withstand electrostatic discharges caused by operator contact, the equipment shall be compatible with the class 3 level of severity (8 kV for air discharge and 6 kV for contact discharges, under the conditions specified), in compliance with the IEC 1000-4-2 Standard. Specifically for relay systems, the equipment shall be compatible with IEC 255-22-2 Standard, class III. f) Capability to Withstand Electromagnetic Radiation It determines the performance of the equipment when submitted to the influence of electromagnetic fields irradiated by communication transmitters. The equipment shall be compatible with the class 3 level of severity (field intensity of 10 V/m), in compliance with the IEC 1000-4-3 Standard. Specifically for relay systems, the equipment shall be compatible with IEC 255-22-3 Standard, class III. g) Capability to Withstand Magnetic Fields As to the capability to withstand the effects of magnetic fields, the equipment shall be compatible with severity level 5 (100 A/m for a continuous field and 1000 A/m for short duration), as per IEC 1000-4-8 Standard. h) Capability to Withstand Electric Fields
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 31/85
As to the capability to withstand the effects of electric fields, the equipment shall be able to operate in environments where the level of electric fields may reach up to 5 kV/m.
2.15 MOLDED CASE CIRCUIT BREAKERS 2.15.1 Alternating Current Alternating current molded case circuit breakers shall be of the industrial type, 600 V insulation class, minimum current class (frame) of 100 A, with a charged spring type operating mechanism, with simultaneous operation in all the phases, regardless of the speed of operator action, and with manual command. For the 220 V circuits, a minimum interrupting capacity of 10 kA symmetric rms value at 220 V. The circuit breakers shall comply with the NBR-5283, 5290, 5391 and IEC-947 Standards. The operating handle shall clearly indicate the main contact positions of the circuit breaker ON - TRIPPED OFF and the discharge mechanism shall be of the trip-free type. Circuit breakers shall be interchangeable, when of the same size and same rated characteristics. Circuit breakers shall be of the thermomagnetic type and of inverse time characteristic. The magnetic element, if not adjustable, shall be able to operate approximately at 10 times the rated current. Where applicable, all adjustments shall be possible without the need to dismantle the equipment. In the specific case of the motor power supply, the circuit breakers shall protect the supply only against short-circuits, being provided only with magnetic protection. Circuit breakers shall be equipped with one reversible auxiliary contact for the main contact position and another independent contact for tripping alarm (protective action). The terminals of the two auxiliary contacts shall be available, and, if not used for control or signaling, shall be connected to outside wiring terminal blocks.
2.15.2 Direct Current Molded case circuit breakers for direct current shall have the same characteristics and accessories as molded case circuit breakers for alternating current, except that they shall be two-pole, minimum interrupting capacity of 10 kA at 250 V, direct current (IEC-157.1 - category P2). Three-pole circuit breakers with two poles connected in series, as well as other similar arrangements, will not be acceptable.
2.16 TRANSFORMERS 2.16.1 Voltage Transformers Voltage transformers shall be dry type, molded in synthetic resin, have electrostatic shielding between primary and secondary windings and shall follow the applicable requirements of the NBR-6855 Standard, except if otherwise specified in these Specifications. The rated burden of the voltage transformers shall be clearly indicated. The primary fuses shall be of the current limiting type, able to withstand the maximum exciting current, and to interrupt the circuit in case of a short-circuit in the transformer secondary. Fuses shall be furnished for secondary protection.
2.16.2 Current Transformers Current transformers shall be dry type, molded in synthetic resin and shall follow the applicable requirements of the NBR-6856 Standard. The secondary wiring of the current transformers shall always be attached to GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 32/85
short-circuitable terminal blocks. These shall be located in such a way that they short-circuit the secondary terminals without any access to the primary bus-bar compartment. The rated burden of the current transformers shall be clearly indicated. Window or bushing type current transformers shall have an insulation level of 10 kV when installed, and shall comply with the requirements for the insulation class of the panels where they are installed, and a voltage test applied between the bus-bars and the secondary terminals of the transformers. All current transformers shall be suitable for continuous operation at full voltage and rated current, at 60 Hz. All current transformers shall be designed to withstand, without damage, the thermal and dynamic forces resultant of short-circuit currents where they will be installed. The SUPPLIER shall submit for review by COPEL all the calculation sheets used for the definition of the characteristics of the current transformers.
2.16.3 Control Transformers Control transformers shall be single phase, dry type, protected by fuses on the primary and secondary sides, with the secondary grounded, and shall comply with the requirements of NBR-5356.
2.17 CONTACTORS AND OVERLOAD RELAYS Three-pole contactors shall be 600 V class, 60 Hz, and two-pole contactors shall be 250 V class, direct current. The contactor shall be suitable for operation at rated load, without the necessity of any maintenance other than routine. The contactor shall be equipped with an arc extinction chamber, or any other device suitable for minimizing the damage from an electric arc. Each contactor shall be equipped with a minimum of four (4) auxiliary contacts, easily convertible from NO to NC and vice-versa. Contactors shall operate free of vibration or any other perceptible noise, when energized. The coils shall be suitable for continuous operation at 115 V ac, or 125 V dc, as applicable. All starters shall be equipped with overload relays, provided with phase-failure protection, environmental temperature compensation and manual reset. The overload relay shall be resettable from outside the panels, without the necessity of accessing the inside of the compartment where the relay is installed.
2.18 SOLENOIDS Solenoids shall be molded in epoxy, resistant to oil, fungi, vapors and humidity. They shall operate continuously at 125 V dc, support the specified voltage variations and equipped with voltage surge protection (RC filters or surge suppressors). Resistance insertion in series with the coil will not be acceptable. The coils shall be easily replaceable. The coils shall have diodes installed to discharge the magnetic field energy at the instant of de-energizing, thus avoiding high-voltage in the circuit.
2.19 ELECTRIC MOTORS Motors shall be induction type, squirrel cage rotor, three phase, 220 V, 60 Hz, of the completely closed type with external ventilation, with a hermetically sealed terminal box, for continuous operation, tropicalized, designed for starting at full voltage, characteristics of starting category N, thermal class F, humidity and oil resistant, an IP-44 degree of protection in compliance with NBR-6146, or better. They shall still meet the applicable requirements of the NBR-7094 Standard. Disconnecting switch motors can be for 125 V dc. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 33/85
Motors shall be provided with a ribbon type heating resistor, fed by 220 V ac, to prevent humidity condensation inside when out of operation.
2.20 MONITORING AND AND PROTECTION PROTECTION COMPONENTS COMPONENTS AND DEVICES 2.20.1 General Requirements -
The SUPP SUPPLIE LIER R shall shall suppl supplyy all the moni monitori toring ng and and contro controll compon component entss and devi devices ces,, such such as manometers, pressure relays and others of the same type, necessary to completely fulfill these Specifications.
-
All compo componen nents ts and devi devices ces shal shalll be suitab suitable le for for install installati ation on in a humid humid envi environ ronment ment and and to withst withstand and the temperature and local vibration conditions, and conform to the applicable standards.
-
The SUPPL SUPPLIER IER shal shalll determi determine ne which which are are the appro appropria priate te scale scaless for the the normal normal operat operating ing condi conditio tionn and the normal operating point shall be in the middle third of the scale. The supplier shall submit the scale of each furnished instrument for review by COPEL.
-
All inst instrume ruments nts and and devices devices shall shall be provid provided ed with with wiring wiring conne connecto ctors rs suitabl suitablee for the the connect connecting ing wiring, with cross section not less than 1.5 mm².
-
Electrical contacts for all the monitoring and protection components and devices shall operate at 125 V dc. Its mechanical life shall not be smaller than 1 million operations, with a conduction capacity of 1 A and interrupting capacity of 0.2 A in circuits with L/R < 40 ms. If for some manufacturing reason the device contacts do not conform to the specified interrupting capacity, RC filters shall be furnished, the calculations of which shall be submitted for review by COPEL.
2.20.2 Manometers -
Manomet Manometers ers shal shalll have have a double double scale, scale, graded graded in in kilopas kilopascal cal (kPa) (kPa) and and kilogr kilogram-f am-force orce per per square square centimeter (kgf/cm²). The instruments used for negative pressure (depression) shall have their scales graded in Pascal (Pa) and gram-force per square centimeter (gf/cm²).
-
Manomet Manometers ers shal shalll be suitab suitable le for for functio functionin ningg at the press pressure ure to whic whichh they are are assign assigned, ed, have have an IPIP44 degree of protection, when applicable (NBR-6146 or NEMA 1, grade A in compliance with the ANSI B-40.1 standard Indicating Pressure and Vacuum Gauges), a scale appropriate for 150% of the normal operating pressure, with the sensitive element in a bronze or stainless steel Bourdon tube, with an accuracy of 1.5% or better.
-
Gauge Gauge valves valves shal shalll be suppl supplied ied with with all all the the indica indicatin tingg instrum instruments ents and and at the the points points wher wheree the manometer tubing is connected to the main equipment. Relief valves and drain valves shall be supplied together with the manometer.
Manometers shall be supplied with a pulsation shock-absorber.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 34/85
2.20.3 Pressure Relays -
Pressure Pressure relay relayss shall shall be single single setti setting, ng, provi provided ded with with mercur mercuryy switche switches, s, a settin settingg lock, lock, sensing sensing element in a bronze or stainless steel Bourdon tube, with an IP-44 (NBR-6146) or NEMA degree of protection. The pressure range between opening and closing shall be fixed and shall not exceed 5% of the operating setting. The same accessories as required for the manometers shall be supplied.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão 3
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 35/85
TECHNICAL SPECIFICATIONS
3.1
SCOPE OF SUPPLY
3.1.1 General This item summarizes the materials, equipment and technical services included in the scope of supply and fixes their limits. The quantity of bays, equipment ratings and other requirements shall be in accordance with the single line diagram established in the separated document.
3.1.2 Equipment, Materials and Services Included in the Supply a) General All equipment shall be for indoor use, SF6-gas insulated. Equipment rated 72.5 kV shall be three-phase metal enclosed. Equipment rated 145 kV shall be three-phase metal enclosed. Equipment rated 245 kV shall be single-phase or three-phase metal enclosed. 3.1.2.1
242kV EQUIPMENTS
a) Transmission Line bays, constituted by (each bay): -
Main buses;
-
Powe Powerr circ circui uitt-bre -break aker er;;
-
Bus-sel Bus-selecto ectorr discon disconnec nectin tingg switch switch,, motor-op motor-operat erated; ed;
-
Line Line disc discon onne nect cting ing switc switch, h, moto motorr-ope opera rate ted; d;
-
High High-sp -spee eedd groun groundi ding ng swit switch ch,, motormotor-ope opera rate ted; d;
-
Grou Ground ndin ingg swit switch ch,, moto motorr oper operat ated ed;;
-
Current Current transf transforme ormers, rs, each each one with with seconda secondary ry windin windings gs for protec protectio tionn and meterin metering; g;
-
SF6 - insulated cable connection enclosures;
-
Zn0 surge surge arresters arresters equipped equipped with with operation operation counter counter and indicating indicating instrument instrument for the the continuous continuous current;
-
Inducti Inductive ve poten potencia ciall transf transforme ormerr with with one secon secondary dary for sync syncroni ronism; sm;
-
Supporting Supporting structure structures: s: all all the necessary necessary structur structural al steel steel supporting supporting structures structures for for the bay, including including concrete inserts, ladders, walkways, platforms, hand rails and similar appurtenances, in order to allow visual access to all inspection windows, gas filling connections and drives;
-
Local Local cubic cubicle le for for the the cont control rol and /or protect protection ion of each each bay. bay.
b) Transformer bays, constituted by (each bay): -
Main buses;
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 36/85
-
Power ci circuit br breaker;
-
BusBus-sel selec ecto torr disco disconne nnect ctin ingg switc switche hes, s, motor motor-o -ope perat rated ed;;
-
Grou Ground ndin ingg swit switch ches es,, moto motorr oper operat ated ed;;
-
Current Current transfo transforme rmers, rs, each each one one with with second secondary ary wind winding ingss for prot protecti ection on and and meteri metering; ng;
-
Zn0 surge surge arres arresters ters equi equippe ppedd with operat operation ion count counter er and indic indicati ating ng instru instrumen mentt for the cont continuo inuous us current;
-
Bus Bus duc ductt from from GIS GIS bay bay to the the tran transf sform ormer er buildi building; ng;
-
SF6 - air bushings;
-
Support Supporting ing struct structures ures:: all the neces necessary sary struc structur tural al steel steel supporti supporting ng structur structures es for the bay, bay, includi including ng concrete inserts, ladders, walkways, platforms, hand rails and similar appurtenances, , in order to allow visual access to all inspection windows, gas filling connections and drives; Local cubicle for the control and /or protection of each bay.
-
c) Bus Potential Transformers Inducti Inductive ve bus bus poten potentia tiall transf transforme ormers, rs, each one with with two two (2) second secondary ary wind winding ingss.
3.1.2.2 a)
145 and 72.5kV EQUIPMENTS
Transmission Line bays, constituted by (each bay): -
Main buses;
-
Power circuit uit-bre breaker;
-
Line Line dis disco conn nnec ectiting ng swi switc tch, h, mot motoror-op opera erate ted; d;
-
High High-s -spee peedd grou ground ndin ingg swit switch ch,, moto motor-o r-ope perat rated ed;;
-
Grou Ground ndin ingg swi switc tch, h, moto motorr ope opera rate ted; d;
-
Current Current trans transfor former mers, s, each each one with with seconda secondary ry windin windings gs for prote protecti ction on and meter metering ing;;
-
SF6 – air bushings (other option shall be proposed by the supplier);
-
Inducti Inductive ve potenci potencial al transfo transforme rmerr with second secondary ary for for protecti protection, on, meteri metering ng and syncron syncronism ism;;
-
Supporting structures: all the necessary structural steel supporting structures for the bay, including concrete inserts, ladders, walkways, platforms, hand rails and similar appurtenances;
-
Local Local cub cubic icle le for for the the con contr trol ol and and /or /or prot protec ectition on of of each each bay bay..
b)
Transformer bays, constituted by (each bay): -
Main buses;
-
Trans Transfo forme rmerr disc discon onne nect ctin ingg swi switc tch, h, motor motor-op -oper erat ated; ed;
-
Grou Ground ndin ingg swit switch ch,, moto motorr oper operat ated ed;;
-
Current Current trans transform formers ers,, each each one with with seco seconda ndary ry windi windings ngs for for protec protectio tionn and mete metering ring;;
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 37/85
-
Zn0 surge surge arres arresters ters equi equippe ppedd with operat operation ion count counter er and indic indicati ating ng instru instrumen mentt for the cont continuo inuous us current (other option shall be proposed by the supplier);
-
SF6 - insulated cable connection enclosures (other option shall be proposed by the supplier);
-
SF6 – air bushings ( option);
-
Set of interco interconne nnecti ction on bus bus (option (option)) ((Tra ((Transfo nsforme rmerr suppli supplied ed by third)) third))
-
Support Supporting ing struct structure ures: s: all the the necessar necessaryy structu structural ral steel steel supporti supporting ng structur structures es for the bay, bay, includi including ng concrete inserts, ladders, walkways, platforms, hand rails and similar appurtenances;
-
Local Local cub cubic icle le for for the the con contro troll and and /or /or prot protect ectio ionn of eac eachh bay. bay.
c)
Bus coupler bay. Obs. The bays shall be complete/prepared to easy expansion, maintenance and operation accordance with the single line diagram.
in
-
Main buses;
-
Power ci circuit br breaker;
-
Bus Bus disc discon onne nect ctin ingg swit switch ch,, moto motorr-op oper erat ated ed;;
-
Grou Ground ndin ingg swit switch ch,, moto motorr oper operat ated ed;;
-
Support Supporting ing struct structures ures:: all the neces necessary sary struc structur tural al steel steel supporti supporting ng structur structures es for the bay, bay, includi including ng concrete inserts, ladders, walkways, platforms, hand rails and similar appurtenances;
-
Local Local cub cubic icle le for for the the con contr trol ol and and /or /or prot protec ectition on of of each each bay bay..
3.1.3 Other Materials and Services Included in the the Supply a) All necessary materials to interconnect the several bays and to permit operation as an integrated substation. Whenever necessary, bellows and removable links shall be included; b) All the wiring interconnecting the different components and the different bays of the substation; c) Electrical interlock of the whole substation; d) Eletromechanical blocking of the disconnecting and grounding switches to prevent maloperations during maintenance and revision; e) Bus, equipment, components and GIS supporting structures grounding system; f)
Sufficient quantity of sulphur hexafluoride (SF6) gas for initial filling and for reserve;
g) Set of special equipment and tools, including all materials required for site erection; h) Set of adapters to connect GIS valves and gas handling mobile equipment; i)
Detailed design of all the equipment and materials, including supply of drawings, reports, catalogs, computation sheets, tests, commissioning and any other pertinent data as required by COPEL
j)
Detailed instructions and descriptions to achieve a perfect electromagnetic compatibility and to reduce the electromagnetic interference within the GIS local cubicle and the Control House;
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 38/85
k) Erection, Operation and Maintenance Manuals; l)
Assembly and shop tests of all equipment and components;
m) Site erection and site tests supervision services.
3.1.4 Supplier’s Cooperation with Others The Supplier shall cooperate during the design, the manufacture and site erection with supplier of other equipment and with the civil structures designers in order that the design and erection may reach timely and successful completion. The supplier cooperate in mutual interchange of all drawings, dimensions, templates, gages and all other data requiredd to ensuree complete coordination of the design, arrengement, manufacture and supply of all equipment interfaces. All accommodations to ensure proper fits among different equipment shall be made between the respective suppliers without extra cost to COPEL.
3.2
APPLICABLE STANDARDS
3.2.1 Objective This item specifies the standards that shall be complied with as to ratings, characteristics, design, manufacture and tests at factory of the GIS and its associated equipment. These Specifications were based on the Standards listed below, which are part of this document. Unless otherwise stated, the equipment, components and materials shall be designed, manufactured, tested and supplied in accordance with the applicable requirements of these Standards. It is stipulated that the Standards listed below are the latest editions standing at the bid time and include any pertinent amendments, supplements, modifications and similar. Any characteristics or numerical value specifically specified in these Specifications overrule the corresponding data which may appear in the Standards.
3.2.2 General IEC IEC Stan Standa dard rd 694 694
- Comm Common on Clau Clause sess for for High High-V -Vol olta tage ge Swit Switch chge gear ar and and Cont Contro rollgear gear Standards.
IEC IEC Sta Stand ndar ardd 517 517
- Gas Gas-Ins -Insul ulat ated ed Met Metal al-E -Enc nclo lose sedd Swi Switc tchg hgea earr for for Rat Rated ed Vol Volta tage gess of 72, 72,55 kV and Above.
3.2.3 Circuit-Breakers IEC Standard 56
-
High-Voltage Alternating - Current Circuit Breakers.
IEC IEC Stan Standa dard rd 267 267
-
Guid Guidee to the the Test Testiing of Circ Circui uitt-Br Brea eake kers rs with with Resp Respec ectt to OutOut-of of-P -Pha hase se Switching.
IEC IEC Sta Stand ndar ardd 427 427
-
Repo Report rt on Synth ynthet etiic Tes Testiting ng of High High-V -Vol olta tage ge Alte Altern rnat atin ingg-Cu Curr rreent Circ Circui uittBreakers.
3.2.4 Disconnecting and Grounding Switches GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 39/85
IEC IEC Stan Standa dard rd 129 129
-
Alte Altern rnat atin ingg Curr Curreent Disc Discon onne nect ctor orss (Iso (Isollator ators) s) and and Earth arthin ingg Switc witche hes. s.
IEC IEC Stan Standa dard rd 1128 1128
-
Alte Altern rnat atin ingg Curr Curren entt Dis Disconn connec ecto tors rs Bus Bus-t -tra rans nsfe ferr Curr Curren entt Swit Switcching hing by by Disconnectors
3.2.5 Voltage/Current Transformers ANSI C93.1
-
Requirements for PLC Coupling Capacitors and Coupling Capacitor Voltage Transformers.
ANSI/IEEE C57.13
-
Requirements for Instrument Transformers.
-
Bushings for Alternating Voltages Above 1000 V.
-
Cabl Cablee Con Conne nect ctio ions ns for for Gas Gas-I -Innsula sulatted Meta Metall-Enc -Enclo lose sedd Swi Swittchge chgear ar for for Rated Voltages of 72.5 kV and above.
-
Surg Surgee Arr Arres este ters rs Part art 4: 4: Met Metal al Oxid Oxidee Sur Surge ge Arre Arrest ster erss wit witho hout ut Gaps Gaps for for A.C. Systems.
3.2.6 Bushings IEC Standard 137
3.2.7 Cable Connections IEC IEC Stan Standa dard rd 859 859
3.2.8 Surge Arresters IEC IEC Stan Standa dard rd 99.4 99.4
3.2.9 Sulfur Hexafluoride Gas - SF6 IEC Standard ard 376
3.3
-
Specif cification and Accept eptance of New Sulfur Hexafluorid ride.
INSTALLATION CHARACTERISTICS CHARACTERISTICS
3.3.1 General The GIS will be installed indoor in a building located in a power substation. The basic characteristics are specified in the section 5. The substation will be equipped with a “Digital Control and Supervision System - SDSC”, supplied by COPEL.
3.3.2 Service Conditions The service conditions are normal for indoor equipment in accordance with IEC Standard 517 and IEC Standard 694 and: - Maximum Maximum ambient ambient air temperature temperature 45º C - Minimum Minimum ambient ambient air temperatu temperature re (indoor) (indoor) - 5º C - Minimu nimum m ambient ent air temperat rature (out (outddoor) oor)
GIS01 – GAS INSULATED SUBSTATIONS
- 10º C
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão - Altitude above sea level
< 1000
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
m
- Pollution Pollution level level (IEC (IEC Standard Standard 71.2, 71.2, tab. 1) no significant significant pollution. pollution.
GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002 40/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão 3.4
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 41/85
GIS CONSTRUCTIVE CHARACTERISTICS CHARACTERISTICS
3.4.1 General The GIS equipment and components shall be designed, manufactured, tested and assembled according to the SUPPLIER’s normal practices. The GIS shall be installed in the space allocated by COPEL. Imposed maximum or minimum limits, distances or clearances must be followed. The GIS enclosures shall be externally painted light gray, Munsell notation N-6.5. The GIS shall not present vibration or audible noise during steady state operation for rated current and voltage. Operation of circuit-breakers, disconnecting and grounding switches shall not produce movement in the supporting structures or joined equipment. The piping shall not present any movement during operation and shall not transmit jerking or vibrating pulses to the equipment or supporting structures. The disconnecting and grounding switches shall operate smoothly and quietly. All equivalent components of same function and rating shall have equal characteristics and be fully interchangeable. The arrangement of the GIS shall permit easy expansion, maintenance and servicing operations. The dismantling of any equipment shall not require cutting of enclosures, supporting structures, piping or wiring. The reassembling of parts of the GIS after any maintenance shall be performed, as far as possible, using the same parts of the original equipment such as enclosures, piping, wiring and supporting structures, with no requirements of welding, machining or any other manufacturing at site. The arrangement of the GIS shall permit easy access of a mobile gas handling unit (not included in the Scope of Supply) to any GIS gas compartment. The GIS building will be equipped with a bridge crane to be used in initial erection and later for maintenance of the GIS. This crane capacity ( in kN) is to be defined by the GIS SUPPLIER. The operating personnel on routine inspection shall be able to check pressure gauges, circuit-breakers and disconnecting/grounding switches position indicators from ground level, without opening any doors or covers. For breaker maintenance the operator shall be able to disable any breaker remote control upon direct confirmation that the isolating switches are open, shall tag the isolating and grounding switches in order to ensure a safe working environment. The operator shall be able to perform safely GIS supervision without need of fuse pullers, tools or portable ladders. The SUPPLIER shall furnish pressure x temperature curves of SF6 gas for the site ambient temperature range, to allow correct replenishment of gas in case of service or maintenance. The equipment and connections within each compartment shall be arranged to allow ready removal and replacement of such compartment with minimum disturbance to the adjacent pressurized compartments. The mobile gas handling equipment shall be fit to be connected to GIS for gas replenishment, treatment or replacement without the need of removing any part of GIS from service.
3.4.2 Metal-Enclosures a) General GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 42/85
The GIS enclosures shall be aluminum alloy or steel. Its thickness shall be adequate to minimize the losses due to circulating and eddy currents. The enclosures shall be provided with safety devices to prevent their rupture due to gas overpressure. The enclosures current carrying capacity shall be not lower than that of the main conductor. The enclosures shall be three-phase (72.5 and 145kV) and single or three phase (245 kV), modular, of standard design. The enclosures shall conform to the ASME Pressure Vessel Code. The enclosures shall have the temperature rise of not more than 30o C at points accessible to the operating personnel as per item 4.4.2 of IEC Standard 517. At all positions where it may be required to dismantle the enclosures for maintenance or test purpose, the enclosure joints shall be made by means of bolted flanged connections. Use of any site welded enclosure joints is not acceptable. All joints and connections shall be designed to compensate for expansion and contraction forces without deformation or malfunctioning and without reliance on sustaining devices, supporting structures and similar. The design and manufacturing of flanged connections shall ensure perfect gas tightness and provide the enclosure electric continuity under any operating condition. View ports shall be provided for each pole of the disconnecting and grounding switches to permit visual inspections of the contact position of each pole. External mechanically connected indicators shall also be provided. b) Pressure Requirements The enclosures shall be designed to withstand full vacuum and specified design pressure. The resulting forces shall not exceed eighty percent (80%) of the yield strength or sixty percent (60%) of the tensile strength of the enclosure material, prevailing the lowest. The test pressure shall be the highest of the values described below: -
1.5 times times the desi design gn press pressure, ure, the desi design gn press pressure ure bein beingg define definedd as the the operati operating ng press pressure ure developed at the upper limit of ambient temperature, at maximum GIS temperature rise due to rated current and to enclosures proximity effect, or
-
The press pressure ure devel developed oped in in case of an an internal internal arc arc with with the specif specified ied short short-cir -circui cuitt current current inten intensit sityy during one second with pressure relief device blocked.
c) Seals The enclosure sealing system used by the SUPPLIER shall assure that yearly gas leakage shall not exceed one percent (1%), in weight, of the total weight of gas in GIS. The gaskets (O-rings) shall comply with internationally accepted standard types and dimensions. The SUPPLIER shall inform the types, the materials, the dimensions, the models and the manufacturers of all gaskets and O-rings used throughout the GIS. d) Arcing Withstand Capability All enclosure parts and components shall be designed and manufactured in order to withstand internal GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 43/85
electric arcs of current intensity up to the specified short-circuit current rating with duration equal to the maximum fault clearing time (protection system operation plus circuit-breaker tripping), without burning through. e) Overpressure Relief Devices Each gas compartment shall have a pressure relief device to mechanically protect the enclosure, limiting the overpressure in accordance with the enclosure protection requirements. The pressure relief device shall be designed to operate on overpressures originated by any internal fault, including internal electric arcs of current intensity up to the specified short-circuit current rating, which may occur at any place within the GIS. The operation of the pressure relief device shall prevent the pressure build-up from exceeding the specified test pressure of the enclosure. The pressure relief device shall be suitably protected against external shock or accidental operation and be fit with suitable deflectors to direct the exhaust to a safe region, not causing any risk to operating personnel. f) Enclosure Protection Requirements The enclosure protection shall be designed considering the following parameters: -
the the ele elect ctri ricc prot protect ection ion syst system em opera operatiting ng time time;;
-
the the vol volum umee of of eac eachh gas gas comp compaartme rtment nt;;
-
the the enc enclo losu sure re burn burn-t -thro hroug ughh wit withs hsta tand nd capa capabi bilility ty;;
-
the the enclo enclosu sure re pres pressu sure re with withst stand and capab capabililitity. y.
These parameters shall be coordinated for any gas compartment as follows: -
the press pressure ure relie relieff device device shall shall not oper operate ate if the the last last back-up back-up elect electric ric protec protectio tionn operates operates normal normally; ly;
-
the enclo enclosur suree shall shall resist resist with without out burn burn-thr -through ough up up to the pres pressure sure reli relief ef device device opera operatio tion; n;
-
the enclo enclosure sure burn burn-th -throug roughh time shal shalll be less less than the the time time require requiredd to build build up the inte internal rnal press pressure ure up to test pressure, with the pressure relief device blocked;
-
in the case case of encl enclosur osuree burn-th burn-throug rough, h, the maxi maximum mum attai attained ned inter internal nal pressu pressure re shall shall not exce exceed ed the test pressure.
g) Flexible Connections Flexible or expansion connections shall be adequate to absorb relative thermal expansion and contraction of equipment as well as other externally applied forces such as transformer vibration and civil structures expansion joints accommodation. These connections and adjustable supporting structures shall be designed to compensate for reasonable tolerances in the civil structures construction, the manufacture and erection of the GIS itself and the transformer. Parts connected by means of bellows or other type of flexible connections shall be designed, manufactured and erected with provisions to prevent erratic movements after the alignment is complete. The assembly shall be designed to preserve the original position and mechanical strength of the equipment. h) Internal Enclosure Painting If it is SUPPLIER’s normal practice to paint the enclosure internal surfaces, in whole or partially, the GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 44/85
SUPPLIER shall inform COPEL, during the design stage, all the methods, procedures and materials employed in such painting.
3.4.3 Conductors The GIS main circuit conductors, used within bus sections, circuit-breakers, disconnecting and grounding switches shall be made of high conductivity copper or aluminum alloy with the rated current carrying capacity and short-circuit withstand capability, as specified. The dimensions and shapes of the conductors shall be designed in order to satisfy all electrical, mechanical and thermal requirements. The conductors shall be of homogeneous material, free from voids, flaws, burrs and cracks. After machining and before final finishing, the conductors shall be carefully cleaned to remove all dirt and foreign material remaining after any extrusion, milling and manufacturing proceedings. The maximum overall rugosity of the outer surface of the conductors after final finishing shall be adequate to ensure the required specifications of the installation. Connections between adjacent conductor lengths, conductor angle segments, taps and equipment terminal connections shall be made by means of multiple contact, individual spring back-up, tulip cluster-type fingers, mating with stud connectors. These connections shall be designed, manufactured and tested in order to have high current carrying capacity, withstand capability to thermal and dynamic effects of short-circuit currents, low level of partial discharges and resistance to mechanical impacts. All parts of the connections shall be silver plated. The deposited silver overlay shall be at least 20 µm thick. The connections shall be designed with sliding contacts or similar means to accommodate the thermal expansion and contraction of the conductors. The contacts shall be suitably enclosed so as to prevent ingress into the electric field of GIS of any particles generated by the sliding action.
3.4.4 Insulators The conductors and equipment live parts shall be held in place inside the enclosures by suitable support insulators placed at convenient intervals. These support insulators are to hold the live parts in proper position relative to the enclosure during any fault condition such as short-circuit. Some of these support insulators shall also act as gas barriers forming gas tight compartments. The insulating material shall have a high resistance to SF6 decomposition sub-products due to internal electric arcs, to oil and moisture, and shall not show significant dielectric strength reduction during the GIS life span. The insulators shall be free from voids and surface defects, ensuring absence of partial discharges during power-frequency withstand test and shall present a uniform voltage distribution along their surfaces. The mechanical fastening between the insulators and the enclosures, and particularly between the insulators and conductors shall be specifically designed for low corona levels. The insulators shall be designed and manufactured to withstand the stresses imposed by different operating conditions, such as differential gas pressure, overpressures caused by internal faults, unbalanced short-circuit currents and thermal effects of both normal and fault operating conditions. The insulators shall not significantly modify the GIS internal electric field in their proximity. No insulators within the GIS shall be installed in horizontal position beneath any spot liable of producing metallic particles under normal operating conditions. The insulators that act as gas barriers, forming the gas compartments, shall be suitably and indelibly painted on their outer surface to allow prompt and easy identification and location.
3.4.5 Gas Compartments The GIS shall be divided into several gas-tight compartments sealed from the adjoining ones by gas barriers. The arrangement and sizing of these compartments shall allow easy depressurization, dismantling, removal and replacement of any compartment with a minimum action on or disturbance of the adjacent pressurized GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 45/85
compartments. The maximum gas volume to be dealt with during service or maintenance of any compartment shall not exceed the capacity of mobile gas handling equipment supplied. The SUPPLIER shall inform the exact gas compartmentalization of the GIS and shall supply a detailed gas service and maintenance schedule for each gas compartment. At least the following GIS sections or equipment shall constitute individual gas compartments: - each phase of the circuit-breaker; - each metal enclosed inductive voltage transformer; - each SF6 / air bushing (if necessary); - each SF6 - insulated cable connection enclosure (if necessary); each phase of metal enclosed surge arrester (if necessary).
All the equipments compartments shall be connected to the GIS with removable links, when removal of these devices require disassemble other parts of the installations. Each gas compartment enclosure shall have a flanged valve adequate for connection of a vacuum pump and gas sampling and another suitable valve for gas density measurement. The valves shall be manufacturer Standard, but set of adapters shall be supplied to allow connection of these valves to the gas handling mobile equipment (LIMCO or DILO type). Each gas compartment shall have sufficient filtering and moisture absorbing material for a minimum of ten years maintenance-free operation. The filtering and moisture absorbing material shall not react with moisture and SF6 decomposition products nor shall introduce any kind of contaminants or solid particles in the internal GIS electric field. The filtering and moisture absorbing material containers shall be removable from the compartments for replacement or recycling. The SUPPLIER shall inform the mass of gas, at rated pressure and 20o C, required for filling of each compartment.
3.4.6 Gas Monitoring System On each gas compartment of each phase shall be installed a pressure gauge and a density monitor (temperature compensated pressure switch). It shall be possible to calibrate and adjust the density monitors in place, without removal. Each density monitor shall have two independent and independently adjustable electric contacts. The wiring from these contacts shall be led to the local cabinets. Each and every gas valve shall have an escutcheon clearly indicating its normal operating position. All the gas piping shall be stainless steel or copper, with welded fittings, vacuum resistant. The contacts of density monitors of all compartments, except the ones installed on circuit-breakers, shall have respectively, the following functions: - first stage alarm upon the density falling to the lower limit of normal operating range, indicating requirement of gas replenishment; - second stage alarm upon the density falling further to 90% of the lower limit of normal operating range. For the circuit-breaker density monitors the contact functions are described in item 4.5.8 GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 46/85
3.4.7 Buses a) General The buses shall be insulated internally with SF 6 gas under positive pressure to guarantee all the electric characteristics of these Technical Specifications. All the buses shall be three-phase, three-phase enclosed (72.5 and 145kV) and single or three-phase enclosed (242kV). The main GIS buses arrangement shall provide suitable conditions for their initial erection and for future expansion and maintenance, without undue interference from one on the other. The bus length shall be divided in gas compartments by means of gas barriers (gas tight isolators) easily detectable and identifiable from outside. The design and manufacturing of bus section connections shall ensure perfect gas tightness and provide the enclosure electric continuity under any operating condition. If the bus design considers the return current through the enclosure, the Supply shall include suitable means for interconnecting the end pieces of the buses enclosures in order to provide a continuous electric path. b) Enclosures The bus enclosures shall comply with requirements specified in these Technical Specifications. c) Transformers Conections (if necessary) Interconnecting buses and SF6 – air bushing designed for connection to the transformer high voltage bushing (transformer supplier) shall be supplied with all necessary appurtenances required for their instalation in order not to intefere with the transformer removal.
3.4.8 Circuit-breakers a) General The circuit-breakers shall be three phase, three-phase enclosed (72.5 and 145 kV) and single or three phase enclosed (242 kV), SF6-insulated, single pressure type, suitable for direct connection to GIS. The circuit-breakers shall be designed and constructed to enable easy access for inspection of interrupting chambers and contacts (both fixed and mobile), allow easy assembly and dismantling for maintenance purpose. The circuit-breakers shall be sturdily constructed, not requiring critical adjustments. The enclosure and the connecting flanges shall be designed and constructed to provide the circuitbreakers with suitable mechanical rigidity under any operating condition. The enclosures shall house the interrupting chamber(s), voltage dividers, filters and any gas preserving facilities. The enclosures shall comply with the requirements specified in item 4.4.2 of these Specifications.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 47/85
b) Temperature Rise Limits The circuit-breakers shall be so designed that when operating within their specified rating, the temperature of each part or component shall be limited to values consistent with a long useful life of such part or component and of the circuit-breaker as a whole. c) Switching Conditions The circuit-breakers shall be restrike and reignition-free. d) Operating Time Span The maximum time difference between the first contact of the first pole and the last contact of the last pole to touch or separate, during respectively a closing or an opening operation, shall not exceed 5 ms. The maximum time difference between the first and the last contact of a pole to touch or separate, during respectively a closing or an opening operation, shall not exceed 1 ms. e) Contacts The contacts shall be designed with suitable thermal and mechanical carrying capacity for the specified current, with a long useful life expectancy so that frequent replacement due to excessive burning shall not be required. The design and construction shall provide for rapid dissipation of the heat generated by electric arc. Any devices provided to limit the current, damp oscillations or prevent restriking prior to a complete interruption of the circuit on opening or to limit overvoltages on closing shall have a life expectancy comparable to that of the circuit-breakers as a whole. f) Voltage Dividers Each circuit-breaker shall be fitted with voltage divider devices to equalize the voltage distribution among the multiple breaks of each pole. ] g) Operating System and Mechanism - General The circuit-breakers operating mechanism shall be of the hydraulically or spring, actuated type, with all the necessary appurtenances for satisfactory operation of all three-poles of the circuit-breaker both in single pole and three-pole operations. The operating mechanisms shall be housed in metal sheet cubicles fit with a lockable door and space heaters suitable for maintaining the internal temperature about 5o C above ambient. - Trip-Free and Anti-pumping The operating mechanism shall be electrically and mechanically trip-free and shall be fit with an antipumping device. - Slow Operation If applicable, the operating mechanism shall permit slow closing and opening of the circuit-breaker for GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 48/85
adjustment purposes. h) Operating Energy Supply and Storage System System Each circuit-breaker shall be provided with its own complete operating energy supply and storage system. A manually operated pump shall be provided as a back-up to a motorized normal pump. - Energy Supply System Capability Each energy supply system shall be capable of restoring the pressure of the energy storage system from lock-out pressure to rated operating pressure within 15 minutes maximum time. - Storage System Capacity Each storage system shall be sized to perform the rated operating sequence (O - 0.3 s - CO - CO - 1 min - CO) CO) of the circuit-breaker without requiring the operation of the energy supply system for rebuilding pressure. i) Operating Energy Storage System Supervision Temperature compensated, adjustable, pressure switches shall be supplied. The set points of the pressure switches shall be adjustable at site. In the circuit-breakers fit with individual, per pole, mechanisms and operating energy storage systems, all operations (tripping, closing, opening and reclosing) of the three-poles shall be blocked in case of occurrence of low operating pressure in any pole. j) Gas Monitoring The contacts of density monitors installed on circuit-breakers enclosures shall have, respectively, the following functions: - first stage alarm upon the density falling to the lower limit of normal operating range, indicating requirement of gas replenishment; - second stage alarm and blocking of all operations (tripping, closing, opening and reclosing) of the threepoles upon the density falling further, at a set point below which the short-circuit current breaking capability of the circuit-breaker falls below rated. k) Control Each breaker pole shall be provided with 2 (two) entirely independent tripping circuits, each with its own coils and valves and a closing circuit with its own coil and valve. All the circuits and components shall be designed and constructed to operate on 125 V, dc power supply. The operating mechanism shall be designed and constructed in a way that once initiated an opening or a closing operation, such operation is completed even for a momentary control pulse, though an opening command shall prevail over the closing command. If one or two poles fail to complete an opening or a closing operation (pole discrepancy) an alarm shall be GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 49/85
initiated and the three-poles are to be tripped after an adjustable (1 to 3 s) delay. The circuit-breakers shall be locally or remotely controlled. The selection of the local or remote control shall be made through a key lockable selector switch. The local control from the local control cabinets shall be always electric and three-pole and when selected shall block the remote manual opening and closing commands. It shall be possible to trip the circuit-breaker by directly actuating, by hand, on the tripping valves installed in the operating mechanism cubicles. All control and supervision devices for the circuit-breaker and its ancillary systems shall be supplied including dc power supply supervision for all command circuits and tripping coils supervision through current circulation. Each pole of the circuit-breaker shall be supplied with twelve (12) auxiliary electrically independent contacts, for COPEL’s use, six (6) “a” type and six (6) “b” type, rated 125 V dc, with current carrying capacity of 10 A continuously and capable of interrupting 0.3 A at 125 V dc corresponding to an inductive load with time constant L/R ≤ 40 ms. l) Operation Counter One (1) operation counter shall be supplied for each circuit-breaker. m) Position Indicator Each circuit-breaker shall have a mechanical type position indicating device, connected to the operating mechanism, to positively indicate the “OPEN” or “CLOSED” position. n) Wiring The wiring of motor feeders, control, protection and supervision circuits shall comply with the requirements of these Specifications.
3.4.9 Disconnecting and Grounding Switches a) General The disconnecting and grounding switches shall be three phase (72.5 and 145kV) and single or three phase (245 kV) enclosed, SF6-insulated, suitable for direct connection to GIS. The disconnecting and grounding switches shall be three-pole gang-operated both electrically and mechanically. The constructive types of the disconnecting and grounding switches shall be defined by the SUPPLIER to fit the GIS arrangement. However the disconnecting and grounding switches to be supplied shall be designed and manufactured to meet all technical and operating conditions specified in these Specifications. The transmission line grounding switches shall be fast acting, powered by a spring charged mechanism. The spring charging shall be motor powered. The bus grounding switches shall be fast acting, powered by a spring charged mechanism. The spring GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 50/85
charging shall be manual and motor operated. All other grounding switches shall be motor operated. b) Contacts The position of the movable contacts ensuring the insulating distance shall be indicated by a reliable position indicating device. The disconnecting and grounding switches shall operate their moving contacts smoothly, without any vibration or erratic movement. They shall not hit the fixed contacts energetically in order not to infringe any damage, even when operated frequently.
-
Disconnecting Switches The main contacts of the disconnecting switches shall be designed and fabricated to carry their rated current without overheating. The maximum temperature rise of the contacts, when carrying their rated current, over ambient temperature, shall be in accordance with table V of IEC Standard 127 complemented by item 4.4.2 of IEC Standard 517.
-
Grounding Switches The grounding switches shall be designed and constructed to effectively ground the main deenergized circuits and release the trapped charges of associated GIS elements to earth. The enclosure shall be effectivelly connected to GIS grounding system. The grounding bar and all connections shall have the same current rating as the main GIS circuit.
c) Operating Mechanisms -
Disconnecting and Transmission Line Grounding Switches The disconnecting and transmission line grounding switches shall be designed and constructed for three-pole gang operation by means of an electric motor or spring operated mechanism, common to the three-poles. The operating mechanisms shall be electric motor driven or shall have an electric motor for spring charging. Facilities shall be provided for manual operation of the switches or for manual spring charging by means of a removable crank. The insertion of this crank shall make inoperative the electric motor. All components of the operating mechanisms, such as motors, springs, auxiliary switches, terminal blocks etc. shall be housed in a metal sheet enclosure fit with a lockable door and space heaters to prevent humidity condensation. The operating mechanism electric motors shall be powered by 220 V, 60 Hz or 125 V dc power supply.
- Maintenance Grounding Switches The maintenance grounding switches shall be three-pole, motor gang operated. Facilities shall be GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 51/85
provided for a manual operation of the switches by means of a removable crank. - Bus Grounding Switches The bus grounding switches shall be three-pole, fast acting, gang operated by a spring charged mechanism. The spring charging shall be manual. d) Disconnecting and Transmission Line Grounding Switches Control The disconnecting and transmission line grounding switches shall be fit for remote electric control for a three-pole gang operation. Mechanical key operated devices shall be provided to block the line grounding switches in open or closed position, simultaneously rendering inoperative both the electric and manual operation of these line grounding switches. All necessary devices to perform the electric interlocking between disconnecting switches and associated circuit-breakers and between the disconnecting and grounding switches shall be supplied. Each disconnecting and transmission line grounding switch shall be supplied with twelve (12) auxiliary electrically independent contacts, for COPEL’s use, four (04) “a” type, four (04) “b” type, two (02) “af” type and two (02) “bf” type, rated 125 V dc, with current carrying capacity of 10 A continuously and capable of interrupting 0.3 A at 125 V dc corresponding to an inductive load with time constant L/R ≤ 40 ms. The Supplier may use auxiliary relays (included in the Scope of Supply) for contact multiplication except for three (3) type “a” and three (3) type “b”. e) Maintenance and Bus Grounding Switches Control The maintenance and bus grounding switches, that shall be motor operated, shall be provided with key operated mechanical devices to block these grounding switches in open or closed position, simultaneously rendering inoperative manual operation of these grounding switches. All necessary devices to perform the electric interlocking of maintenance and bus grounding switches with associated disconnecting switches and circuit-breakers shall be supplied. Each maintenance and bus grounding switch shall be supplied with twelve (12) auxiliary electrically independent contacts, for COPEL’s use, four (04) “a” type, four (04) “b” type, two (02) “af” type and two (02) “bf” type, type , rated 125 V dc, with current curre nt carrying capacity capa city of 10 A continuously and capable of interrupting 0.3 A at 125 V dc corresponding to an inductive load with time constant L/R ≤ 40 ms. The Supplier may use auxiliary relays (included in the Scope of Supply) for contact multiplication except for three (3) type “a” and three (3) type “b”. f) Position Indicators Each pole of every disconnecting and grounding switch shall have a mechanical type position indicating device, connected to the operating mechanism, to positively indicate the “open” or “closed” position of respective disconnecting switch pole and “OPEN” or “GROUNDED” of respective grounding switch pole. These devices shall be highly reliable, accurate, easily visible and legible from large distances. g) Wiring
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 52/85
The wiring of motor feeders, control, protection and supervision circuits shall comply with the requirements of these Specifications.
3.4.10 Inductive Voltage Transformers a) General The metal enclosed SF6-insulated voltage transformers shall be inductive type, with two (2) secondary windings, designed and manufactured to minimize partial discharges and prevent resonance with other equipment. Each voltage transformer shall constitute a gas compartment. b) Interwinding Shielding Each voltage transformer shall be provided with an electrostatic shielding between the primary and secondary windings in order to reduce the magnitude of voltage surges transferred from primary to secondary windings. The SUPPLIER shall guarantee that in no case the switching surges from primary windings will have any harmful effect on secondary windings or circuits. c) Primary Connection The connection shall be designed so that the GIS may be energized when the voltage transformer is removed. d) Secondary Leads The secondary leads shall be 4 mm² or larger wire, designed generally to IEC 227, with conductor in copper (IEC 228 class 5), flame resistance (IEC 332-1). They shall be brought to a readily accessible terminal box arranged on the voltage transformer enclosure. The terminal boxes shall be provided with a protection class IP 54. The secondary leads shall be connected from the terminal boxes to the bay local cubicle via wireways. The terminal boxes and local cubicle terminal block strips shall have sufficient terminal blocks to connect all the secondary leads plus twenty percent (20%) extra terminal blocks. Mini circuit-breakers with alarm contacts shall be provided in the terminal boxes for protection against short-circuit in the secondary circuits, arranged as close as possible to the winding terminations. The terminal blocks, wire connectors, wiring and all identification means shall be subject to COPEL’s approval. The secondary leads shall be grounded only at the local cubicle terminal blocks. e) Polarity The polarity of the voltage transformers shall be subtractive. Each voltage transformer shall have the polarity markings "H1" and "X1" impressed indelibly on it. f) SF6 Gas Pressure The SF6 gas pressure of the voltage transformers shall be design to provide the required insulation level of the installation. The enclosures shall be provided with one pressure relief device. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 53/85
g) Secondary Windings The secondary windings shall be of the uniformly distributed type.
3.4.11 Current Transformers a) General Current transformers shall be designed to attend the electrical requirements of the control and protection sytems and shall be securely held in place to prevent vibration and noise. For current transformers mounted externally to the GIS enclosure, circulating currents (if any) shall be prevented from flowing through the current transformer cores. b) Secondary Leads The secondary leads shall be 4 mm² or larger wire, designed generally to IEC 227, with conductor in copper (IEC 228) flame resistance (iEC 332-1). They shall be brought to a readily accessible terminal box arranged on the current transformer enclosure. The terminal boxes shall be provided with a protection class IP 54. The secondary leads shall be connected from the terminal boxes to the bay local cubicle via wireways. The terminal boxes and local cubicle terminal block strips shall have sufficient terminal blocks to connect all the secondary leads plus twenty percent (20%) extra terminal blocks. The terminal blocks, wire connectors, wiring and all identification means shall be subject to COPEL’s approval. The terminal blocks in the terminal boxes and in the local cubicle shall be of the short-circuiting type. Rotary switches for short-circuiting current transformer secondaries will not be acceptable. Grounding of current transformer secondary leads shall be done only at the local control panel. c) Polarity Each current transformer core shall have a polarity marking, "H1", impressed indelibly on the core side where the primary current enters when the secondary current leaves the winding from terminal "X1". d) SF6 Gas Pressure For current transformers with cores installed internally to the enclosure, the SF6 gas pressure shall be the same as in the switchgear equipment.
3.4.12 Surge Arresters (if necessary). The surge arresters to be installed on the GIS shall be ZnO (zinc oxide) metal enclosed SF6-insulated type. They shall be provided with all necessary devices to attain a uniform voltage distribution among its elements and to minimize internal ionization level. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 54/85
Each surge arrester shall be provided with an operation counter and a milliammeter indicating instrument to indicate the continuous current. Each metal enclosed SF6-insulated surge arresters shall constitute an individual gas compartment. The connection shall be designed and constructed to permit energization of GIS when the metal enclosed SF6-insulated surge arresters are removed from the GIS.
3.4.13 SF6 /Air Bushings a) General The bushings shall connect the GIS to open air conductors. The bushings shall be self-supporting, for vertical mounting, outdoor immersed type, SF6-insulated (depends on the arrangements – Main Contractor). The bushings shall be supplied complete, with all necessary appurtenances such as supporting structures, gas supervision devices, transition compartments, grounding devices, sealing devices etc. The bushings shall be connected to the high-voltage conductors through tulip-type connectors. The SUPPLIER shall provide covers for the GIS openings when the bushings are removed for maintenance, avoiding entrance of moisture and foreign materials. b) Temperature Rise The bushings shall comply with the requirements of Clause 10 of IEC Standard 137. c) Line Terminal Each bushing shall be supplied with a 4-hole NEMA Standard terminal plate and a connector. d) Insulating Envelope The bushing insulating envelope shall be porcelain or silikon rubber, designed for the required insulation level of the installation.
3.4.14 SF6 - Insulated Cable Connection Enclosures (optional – supplier proposal) The SF6 - insulated cable connection enclosures shall be part of the SF6 switchgear. They shall be adequate for insulated cables. The connection enclosures shall be manufactured in accordance with IEC Standard 859.
3.4.15 Supporting Structures All the necessary structural steel supporting structures of a bolted construction type shall be supplied. The Supply shall include all the hardware such as bolts, washers, nuts, insulated installation adapters and devices for compensating installation tolerances. The Supply shall also include all anchor bolts, and required GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 55/85
appurtenances in order to allow visual access to all inspections windows, gas filling conectors and drives, hardware for piping, electric conduit and cabling, cable trays, control cabinets and panels and similar appurtenances. Wherever required, insulated installation adapters shall be used to prevent circulation of GIS enclosure currents through supporting structures, electric conduit, piping and any other metallic parts not specifically designed for this purpose. The Supply shall include all concrete inserts, foundation and base plates, floor sills, anchor bolts and leveling screws. All equipment shall be fit with adjusting bolts for correct position adjustment and alignment. The arrangement, location and details of all concrete inserts shall be clearly and minutely shown on SUPPLIER’s drawings. The structural steel shapes shall be standard industrial type, manufactured of structural steel. All structure components shall be supplied with their final dimensions not requiring any machining or adjustment at site. The supporting structures shall withstand the loads due to equipment weight, any operating or maintenance load and any loads that may appear due to short-circuits. The distribution of the load shall be uniform to prevent any deflection of equipment, particularly on main buses. All support structures members shall be hot dip galvanized. The hot dip galvanizing shall meet appropriate ASTM Standards, or equivalent applied in the country of the manufacturer. The SUPPLIER shall include in the Supply a minimum excess of ten percent (10%) for each type and size of bolts, washers, nuts, insulating devices and similar hardware required for field installation and erection of GIS.
3.4.16 Grounding System and Electromagnetic Electromagnetic Compatibility Compatibility a) General The Supply shall include all materials and appurtenances required for a safe and sound grounding of GIS and its accessories: all buses, all HV and ancillary equipment, all supporting structures, all control cabinets and similar, all piping, electric conduit, wiring etc. The Supply shall also include Supplier collaboration and assistance to Main Contractor in the design of GIS grounding grid and its integration in the power-substation overall grounding system. The final objective, besides personel and equipment safety, is to avoid any problems from EMI (electromagnetic interference) specially with the digital control systems of the GIS itself and of the whole of the substation. b) GIS Equipment (72,5 up to 242kV) The SUPPLIER shall provide one earth-bus collector for the GIS. The earth-bus collector and the tap-offs to the enclosures shall be designed for adequate distribution of circulating currents among different enclosures grounding points and to direct any fault currents, through suitable connections, to the plant grounding grid. All grounding conductors shall be rated: -
Rated Rated shor shortt – time time with withst stan andd curre current nt,, 1 seco second nd (RMS (RMS)) Rated peak withstand current
40kA 40kA 105kA.
The SUPPLIER shall design the grounding of GIS and accessories considering personal, operational and equipment safety and security. All necessary back-up calculations shall be submitted to COPEL for review. The SUPPLIER shall be responsible for the performance of the complete grounding system as far as the GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 56/85
influence of his Supply is concerned. The grounding system design guideline shall consider the following requirements: - the supporting structures and GIS enclosures shall operate at ground voltage; - the enclosures circulating current shall not flow through the supporting structures; - the circulating currents shall not flow through the grounding grids; - the circulating and fault currents shall not produce hazardous step and touch voltages, which shall be limited to values specified in IEEE Standard No 80; - The SUPPLIER or Main Contractor (with Supplier assistance) will design the GIS building area grounding grid and the substation overall grounding system and will furnish all the necessary connectors; - all grounding connections shall withstand safely the electromagnetic forces and overheating due to the maximum anticipated fault current for the specified duration of the fault; - all grounding connections shall be readily accessible for inspection and maintenance; - the final grounding connections temperature during fault conditions shall not exceed 250o C; - the grounding connections shall be designed for low impedance to high frequency current surges, precluding any flashovers between different grounded components; - connections between dissimilar metals shall be made with devices suitable for this purpose. All grounding system details shall be clearly depicted on the SUPPLIER’s drawings. The SUPPLIER shall provide all the temporary grounding devices that may be required during maintenance or service. These temporary grounding devices shall allow for fast, easy and sound temporary grounding, when and where required, prior to any servicing or maintenance. To reduce high frequency voltage spikes, the SUPPLIER shall provide facilities such as fitting surge arresters at electric discontinuity points or reducing the impedance of grounding connections with the use of straps or multiple grounding connections. To attenuate the effects of these spikes on the control, protection and supervision systems, all the control and power cables in the vicinity of GIS shall be shielded and the cable shielding be conveniently grounded. The SUPPLIER shall provide all pertinent data and detailed description of all precautions that shall be employed at GIS installation and advise other equipment suppliers, for equipment installed in GIS vicinity, of any precautions they should take egarding EMC (eletromagnectic compatibility). This should include techniques and means to be used in grounding, coupling / uncoupling and shielding of equipment, buses, terminal boxes, control boards and panels, electronic / digital equipment, wiring etc., in order to provide the most perfect EMC and to reduce to acceptable (standardized) levels the effects of EMI (electromagnetic interference) throughout the substation. c) Local Cabinets All local cabinets shall be connected to the GIS building grounding grid. An accessible copper grounding bus, clearly marked and easily identifiable shall be provided inside each cubicle which shall be electrically connected to the structures on which the equipment or devices are mounted. At all points of grounding bus connection any non-conductive coating, such as paint, shall be removed or pierced to ensure good electrical contact. The grounding bus shall safely withstand the largest fault current that may occur in the respective cabinet. The grounding bus shall extend through entire length of respective cabinet and shall be solidly fastened to it. At both ends the grounding bus shall be fit with ground terminals suitable for accommodating a bare ground cable with 16 to 70 mm2 cross section. All removable devices shall remain GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 57/85
grounded up to a complete removal, deenergization and safe clearance of the extractable part. d) Supporting Structures All the supporting structures assembly shall be soundly grounded. Special care should be taken to ensure effective electric connection over bolt-joined members. e) Calculation Sheets and Design Data The SUPPLIER shall consider in the design, construction, installation and test of the grounding system the recommendations presented in the paper titled: “EARTHING OF GIS - AN APPLICATION GUIDE”, published by CIGRÉ WG 23.10 in publication ÉLECTRA, No 151 of December, 1993.
3.4.17 Voltage Surges The SUPPLIER shall inform COPEL of any voltage surge that might originate at GIS and be transferred to transformer windings (primary and secondary) or tanks.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão 3.5
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 58/85
GIS BAY LOCAL CABINETS - QCL
3.5.1 General This description establishes the minimum requirements to the GIS control system. The complete supply of the Substation Protection and Control system, arranged in the Substation Control Room, shall be defined by GIS Supplier and Main Contractor (Protection and Control supplier). For detailed specification of the Substation functions see Specification PRC 02. The substation will be equipped with a “Digital Control and Supervision System” – SDSC (Supplied by COPEL). COPEL). All the substation control and supervision will be made by way of this system. The GIS will also be controlled and supervised by SDSC SDSC but but will have some hard-wired facilities as a back-up to SDSC SDSC.. The SDSC SDSC shall have data acquisition and control unit per GIS bay, which can be installed in the local cabinets or protection/control panel. GIS local cabinets are included in the Supply
3.5.2 Extent of Supply - Local Cabinets (one for each bay). - Production of all logic, three line and schematic diagrams of the GIS, wiring diagrams of all QCLs and interconnecting wiring between QCLs and GIS. - Front and internal view drawings, depicting all components and devices. - All cabling and wiring within QCLs and between all QCLs and GIS. - All required hardware to fasten the QCLs to their foundations. - All cabinet and devices nameplates to COPEL standards (portuguese language).
3.5.3 Construction Requirements In addition to requirements set forth in these Specifications, the QCL cubicles QCL cubicles shall: - have provisions for cabling and wiring entering the cabinets; - be suitable for being installed next to walls or juxtaposed to other cabinets or cubicles. The access to internal components and devices for service, maintenance and adjustments and terminals for external wiring, shall be made from the front, by way of hinged door. On these doors shall be installed all the control and selector switches, alarm and status indicating lamps. - have possibility for duplicated 125 V dc power supply feeders. The terminations of all control, and supervision systems cables shall be fitted with suitable plugs mating with suitable receptacles specially designed to prevent EMI problems at connection points. The Supply shall include both the fixed receptacles (to be fastened and wired in the QCLs) QCLs) and the plugs (to be connected to incoming and outgoing cables). This requirement applies to the cables to and from the GIS. Metering and protection cables (from CTs and VTs) shall not use these plugs, but shall have an appropriate terminal connection, to prevent EMI. Bearing in mind that the environment produced by high voltage GIS switching is extremely hostile regarding EMI, the SUPPLIER shall inform, during design stage for COPEL’s consideration, what procedures and GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 59/85
precautions shall be adopted in the design and fabrication of QCLs QCLs and protection and control panels to mitigate EMI. The SUPPLIER shall cooperate with Main Contractor (designer) on removal of any problems that might appear due to EMI, providing all data on his equipment and supplying advice on solutions. If required, the SUPPLIER shall carry out correcting actions on his equipment. These procedures shall proceed until all EMI related problems involving any equipment within GIS building, or in its proximity, are solved. If during site tests, commissioning or operation any EMI associated problems appear that might jeopardize the functionality of QCLs and other panels, the SUPPLIER shall be responsible for immediate corrective actions. If such corrective actions demand modifications on any part of the Supply, such modifications shall be performed by the SUPPLIER with no cost to COPEL.
3.5.4 Control and Supervisory Functions Available at the QCLs a) Bay Disconnecting and Grounding Switches Control It shall be possible to control all motor operated disconnecting and grounding switches of each bay from the corresponding QCL, QCL, provided the back-up (local) control mode is selected. When remote mode is selected it shall be possible to control by SDSC. b) Bay Circuit-Breaker Control From the QCL cabinets (local mode selected) the tripping or closing of the bay circuit-breaker shall only be possible if the associated disconnecting switches are open, for test and maintenance purposes. When remote mode is selected (QCL) it shall be possible to control by SDSC SDSC or or by control switch installed at control/protection panel, located in the substation control room. c) Interlocking System System for Switchgear Each QCL shall be furnished with all auxiliary relays and devices required for a complete and reliable interlocking system for all disconnecting and grounding switches of the associated bay. d) Abnormal Condition Indicators (Local Annunciators) All abnormal conditions associated to the GIS shall be supervised by SDSC and as back-up by Abnormal Condition Indicators (installed in the QCLs) QCLs) and an alarm annunciation system installed in other panels. The operating principle of the Abnormal Condition Indicators shall be as follows: −
in the event of an abnormal condition, the field alarm contact input will light up the LED of the associated window and will operate an auxiliary relay (the auxiliary relay will have two independent electrical contacts);
−
the abnormal condition, through the auxiliary contacts above mentioned, shall be retransmitted to a remote alarm annunciator;
−
the LED will remain lit until the field contact is restored to normal condition and receipt of a reset command.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 60/85
All Abnormal Condition Indicators shall run on 125 V dc and the visual indication shall be by LEDs associated with plastic windows, or signaling lights with inscribed caps. Lettering shall be in portuguese language. The Abnormal Condition Indicators shall be semi-flush mounting type. e) Interlocking Conditions Indicators The MMI which incorporates keyboard and graphical control display (mimic bus), shall indicate when the interlocking conditions for operation of the respective disconnecting or grounding switch are satisfied. f) GIS Auxiliary Motor Starters and Control All auxiliary motor starters and control circuits of a GIS bay shall be arranged in the respective QCL. The power feeders for these motors shall proceed from a power distributition panel. g) Voltage and Current Transformers Circuits All voltage and current transformers arranged on the GIS bays and on the outgoing transmission lines shall be wired to the respective QCL. At the QCLs these QCLs these circuits shall have suitable test blocks. The secondary circuits of voltage transformers shall always be protected by fuses at the origin.
3.6
SULFUR HEXAFLUORIDE (SF6) GAS
3.6.1 General The SF6 gas included in the Supply shall be new, not previously used. The quantity supplied shall be sufficient for the initial GIS filling plus a minimum excess of ten percent (10%). The gas chemical and physical characteristics shall conform to requirements of IEC Standard 376.
3.6.2 Gas Containers a) Gas Containers The gas containers shall comply with Section 4 of IEC Standard 376. The gas containers for initial filling of GIS may be SUPPLIER’s standard type, will remain property of the SUPPLIER and will be restituted to the SUPPLIER at site. The gas containers of the 10% reserve gas shall remain COPEL’s property. The containers to stay with COPEL shall be limited to 150 liters capacity each. b) Gas Containers Identification and Marking The containers to stay with COPEL shall be painted and identified in accordance with Brazilian Standard GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 61/85
NB-46 as follows: - gas identification; - gas manufacturer; - mass of gas; - cylinder serial number; - cylinder fabrication date; - cylinder rated pressure; - cylinder test pressure; - date of last pressure test performed on the cylinder; - cylinder internal volume; - cylinder fabrication standard; -
net weight of the cylinder.
c) Gas Container Valves The valves installed on the containers shall be Manufacturer Standard, in that case, set of adapters shall be supplied to allow connection of these valves to COPELs gas handling mobile equipment ( COPEL’s standard is manufactured by DILO).
3.7
INSPECTIONS, TESTS AND TRAINNING
3.7.1 General All equipment and components of the Supply, including spare parts, shall be tested and inspected at factory and at site in accordance with these Technical Specifications. These inspections and testing do not relieve the SUPPLIER in any case of any of his obligations and contractual responsibilities.
3.7.2 Applicable Standards The tests shall comply with pertinent requirements of the standards listed in item 4.2 and of the following standards, as applicable: IEC Standard ard 52 Recomm ommendati ation fo for Vo Voltage Me Measurem rement by by Me Means ans of of Sp Spherere-gaps aps (one sphere earthed); IEC Standard 60 High-voltage Test Techniques; IEC Standard 270 Partial Discharge Me Measurements; IEC Standard ard 506 Switchi ching Impuls ulse Tes Tests on High-voltage Insulators.
3.7.3 Factory Tests and Inspections GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 62/85
a) General All the Supply shall be submitted to factory inspection and tests by the SUPPLIER in presence of COPEL. The SUPPLIER shall provide free access to his works including sub-suppliers facilities, laboratories and any other locations where the Supply is being manufactured, tested, packed or stored. The SUPPLIER shall provide all the equipment, test instruments, materials and qualified personnel to perform the tests and supply relevant information and data. COPEL may test and inspect any component of the Supply covered by these Technical Specifications during manufacturing process, prior to packing and at any time deemed necessary. No component of the Supply shall be released for shipment prior to approval of factory tests reports and final inspection by COPEL. Factory tests of GIS shall be performed on complete bays, on shipping units or individual components, as applicable. Each and every component or shipping unit shall be factory tested and inspected to check complete compliance with these Specifications. During progress of the Contract the SUPPLIER shall submit to COPEL’s approval a test and inspection schedule with the dates when items of Supply shall be ready for testing and inspection. This schedule shall include the nature, location and estimated time required to perform the tests and inspections. At the time of issuing the test and inspection schedule the SUPPLIER shall submit to COPEL’s approval the procedures to be followed and sample forms to be filled out during tests and inspections. The forms shall include all information pertaining to the tests and inspections in order to become a complete document describing the test or inspection that was carried out, stating the specified limits or values, the results and conclusions and the statement of acceptance or rejection of the item tested or inspected. The SUPPLIER shall arrange the item(s) to be tested and the testing facilities, without compromising the scheduled delivery dates, prior to arrival of COPEL’s representative. Any supplemental expenses due to non compliance with this requirement shall be borne by the SUPPLIER. Any delays in testing and inspecting the Supply, imputable to the SUPPLIER, or due to rejection shall be SUPPLIER’s sole responsibility. COPEL shall commence factory tests witnessing and inspections only after receiving and approving all pertaining documents such as drawings, catalogs, bills lists of materials, calculation and data sheets of the item(s) to be tested or inspected. The SUPPLIER shall deliver to COPEL four (4) sets of certified test reports, prepared during the tests, immediately after their completion. b) Acceptance or Rejection Acceptance or rejection criteria shall conform to the Standards and requirements set forth in these Specifications. The acceptance of any item of the Supply by COPEL’s Inspector shall not relieve the SUPPLIER from responsibility to supply the equipment in strict accordance with these Specifications nor invalidate or influence any subsequent claim by COPEL relative to inadequate or defective item supplied. Rejection of any item of Supply during tests or inspections credited to defects or to non-compliance with these Specifications shall not relieve the SUPPLIER of his responsibility to deliver the Supply in the specified condition at the scheduled delivery date and place. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 63/85
c) Type Tests of GIS Equipment Type tests shall be required to prove the soundness of design and the capability of the equipment to meet all ratings set forth in these Specifications and relevant Standards. Certified type test reports may be accepted by COPEL provided they were performed on equipment of the same make and design, without modifications, and that in COPEL’s judgment clearly demonstrate that the equipment then tested meets the specified requirements. If any item of Supply fails to pass any kind of type test, the remaining item of Supply of that class and rating, as well as any repaired or replaced component shall be subjected to the same tests without additional cost to COPEL. If any item of Supply as actually designed and constructed for this Contract includes significant modifications to or departures from the design or construction of equipment on which the certified type test report have been performed and accepted or, in COPEL’s opinion, presents evidence of inadequacy to meet the requirements of these Specifications, COPEL reserves the right to demand the performance of such tests as may be required to demonstrate that this item of Supply meets the requirements of these Specifications, at no additional cost to COPEL. The GIS dielectric tests shall be performed with the SF6 gas at minimal operating density. The type tests to be performed on each component of the Supply are listed in applicable Standards referred to in these Specifications. d) Routine Tests of GIS Equipment The routine tests to be performed on each item (such as individual components or shipping units) of the Supply are listed in applicable Standards referred to in these Specifications. The GIS dielectric tests shall be performed with the SF6 gas at minimal operating pressure.
3.7.4 Site Tests and Inspections a) General The Supply, during and after installation and erection at site and prior to energization, shall be tested by the SUPPLIER under COPEL’s supervision, as stipulated in these Specifications and according to IEC 517 Clause 7.107. Upon the completion of any site test the SUPPLIER and COPEL shall jointly produce a relevant test report comprising all relevant data and results of the test performed. A copy of these test reports shall be furnished to COPEL. The test listing below is just orientative, since COPEL may perform any other tests besides the listed ones if deemed necessary in order to ensure the quality or performance of any item of Supply. All equipment upon installation and erection shall be functionally tested. All characteristics specified in these Specifications and informed by the SUPPLIER in his drawings, data and calculation sheets, catalogs and manuals, shall be checked. It shall be certified that all electrical and mechanical components run within their rating stated in above mentioned documents or in pertinent Standards.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 64/85
Besides the Test Engineer, the Installation and Erection Supervisor shall also attend the Site Tests. b) Test Instruments and Accesories The SUPPLIER will provide all the test instruments and equipment required for the site tests such as meggers, ohm-meters, milliammeters, oscilloscopes, resssonant power frequency equipment, etc. c) Reception Inspection and Tests - General •
Visual inspection.
•
Ohmic resistance measurement of main contacts, through the grounding switches.
•
Leakage inspection of all site installed flanged connections.
•
SF6 gas moisture content.
•
SF6 gas pressure in each gas compartment.
•
Condition of any surface protective coating of all surfaces subject to corrosion or rust.
•
One minute power-frequency withstand voltage tests with partial discharge measurements.
•
Calibration and check of all devices such as pressure gauges, gas density monitors (temperature compensated pressure switches), operation counters and position indicators.
- Inductive voltage transformers •
Visual inspection.
•
Measurement of insulation resistance to earth.
•
Insulation power factor and capacitance measurement.
•
Polarity.
•
Ratios.
•
Windings ohmic resistance measurement.
•
Tightness and SF6 gas moisture content.
•
One minute power-frequency withstand voltage tests with partial discharge measurements.
- Current transformers •
Visual inspection.
•
Measurement of insulation resistance to earth.
•
Polarity.
•
Ratios.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão •
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 65/85
Windings ohmic resistance measurement.
- Surge arresters (if necessary) •
Visual inspection.
•
Measurement of insulation resistance to earth.
•
Continuous current measurement with the insulation power-factor measurement device at 10 kV.
•
Total and resistive continuous current measurement during normal operation duty.
•
Tightness and SF6 gas moisture content.
•
One minute power-frequency withstand voltage tests with partial discharge measurements.
- SF6 /Air Bushings •
Visual inspection.
•
Tightness and SF6 gas moisture content.
•
One minute power-frequency withstand voltage tests with check of audible corona discharge.
•
Partial discharge measurements.
- SF6 /Insulated Cable Connection Enclosures (if necessary) •
Visual inspection.
•
Tightness and SF6 gas moisture content.
•
One minute power-frequency withstand voltage tests with check of audible corona discharge.
•
Partial discharge measurements.
- Circuit-breakers •
Visual inspection.
•
Tightness and SF6 gas moisture content.
•
Wiring and devices check.
•
Measurement of insulation resistance to earth.
•
Functional check of all electric and mechanical devices.
•
Check on settings of Operating Energy Supply and Storage System pressure switches and gas density monitors.
•
Tightness of hydraulic circuits.
•
Functional and interlocking system tests.
•
Ohmic resistance measurement of main contacts.
•
Final calibration and measuring of operating times and contact synchronous operation.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão •
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 66/85
Performance of a minimal number of operation cycles previous to high voltage dielectric tests.
- Disconnecting and Grounding Switches •
Visual inspection.
•
Tightness and SF6 gas moisture content.
•
Wiring and devices check.
•
Measurement of insulation resistance to earth.
•
Functional check of all electric and mechanical devices.
•
Check on settings of gas density monitors.
•
Functional and interlocking system tests.
•
Ohmic resistance measurement of main contacts.
•
Final calibration and measuring of operating times.
•
Performance of a minimal number of operation cycles previous to high voltage dielectric tests.
•
One minute power-frequency withstand voltage tests with check of audible corona discharge.
- Buses •
Visual inspection.
•
Ohmic resistance measurement of all connections.
•
Tightness and SF6 gas moisture content.
•
Wiring and devices check.
•
Functional check of all devices.
•
Check on settings of gas density monitors.
•
One minute power-frequency withstand voltage tests with check of audible corona discharge;
- Local Control Cabinets and GIS Interconnecting Wiring •
Visual inspection.
•
Wiring and Devices Check.
For the power-frequency withstand voltage tests, the power transformers, the voltage transformers and the surge arresters shall be disconnected from GIS. Upon satisfactory completion of all tests the GIS shall be considered ready for operation. The SUPPLIER shall issue a certificate authorizing energization of GIS. After the GIS is connected to the system, tests shall be carried out to determine the characteristics and shapes of the high frequency voltage surges generated by operation of disconnecting switches in all possible configurations and to confront them with the guaranteed values. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 67/85
3.7.5 Training The SUPPLIER shall include in his BID a training program for 2 (two) COPEL's employees, with a minimum duration of 10 (ten) days, during the manufacture of the equipment. At least the following itens shall be included in the program: manufacturing, assembling, adjust, operation and maintenance.
3.8
SPECIAL EQUIPMENT, TOOLS AND MATERIALS
3.8.1 General The SUPPLIER shall furnish and deliver, with the first shipment, all special equipment, instruments and devices, tools and materials required for orderly site assembly, erection operation and maintenance of GIS. The Supply shall include, not being limited to, at least the goods specified in this item.
3.8.2 Special Equipment, Instruments and Devices a) Special Tools and Devices Two (2) sets of special tools, gauges and ancillary devices required for smooth assembly, installation, erection operation and maintenance of GIS shall be included in the Supply. The components of these sets shall be defined by the SUPPLIER based on his experience and particularities of its Supply. b) Special Equipment, Instruments and Software The following shall be included in the Supply: - One (1) special device for adjusting and calibrating the pressure gauges and density monitors (temperature compensated pressure switches) installed on the GIS. This table-top device shall be fit with a standard pressure gauge, 0.5% accuracy of end scale value, with scale compatible with the GIS pressure gauges. All required connections, tubing, couplings, valves and accessories required shall be furnished. It shall be possible to connect this device to the SF6 gas cylinders. - Two (2) special portable SF6 gas detectors powered by a rechargeable battery. These detectors shall be of the leak sniffer type, able to detect small leakages of SF 6 gas to check the tightness of gasketed connections, piping connections and similar. A suitable battery charger shall also be supplied. - If applicable, one (1) hydraulic-pneumatic set for initial nitrogen filling and pressurization of the circuitbreakers operating energy supply and storage system. The set shall be composed of a motor driven pump, motor controls, a hydraulic-pneumatic cylinder, check valves, hoses and fittings. The set shall operate automatically. The motor shall be induction-type, three-phase, 220 V, 60 Hz. - One (1) motorized high pressure pump fit with all accessories suitable for testing the circuit-breakers operating energy supply and storage systems. - If applicable, one (1) circuit-breaker time analyzer furnished in suitable carrying case, with an incorporated printer, positively shielded against electrostatic induction, proper for use in HV substations, with the following characteristics: GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 68/85
•
Power supply automatically selectable in the range 100 to 250 V, 60 Hz, with internal autorechargeable battery good for one hour autonomous operation.
•
Twenty four (24) channels.
•
Ambient temperature operating range: -10o C to +50o C.
•
Scale: 0 - 6.5 seconds.
•
Resolution: 0.1 millisecond.
•
Accuracy: ± 0.01%.
•
Operating sequence : C - O - C - O - C.
•
Internal non volatile memory suitable for storing up to 10 (ten) sets of test measurements for later analysis.
•
Power cables.
•
Shielded metering cables, 15 m long with alligator type prongs on the end to be connected to the circuit-breaker.
•
a printer interface.
•
PC interface.
- Incorporated printer, ink-jet graphic type, with a minimum resolution of 150 dpi suitable for being connected to the circuit-breaker time analyzers. -
One (1) copy of a specialist PC software (to run under MS DOS and / or Windows ) for investigation of circuit-breaker time analyzers test data.
3.8.3 Erection Hardware - All handling accessories such as wire ropes, chains, slings, lifting beams, eye bolts, shackles and similar required for assembly, erection operation and future maintenance shall be supplied. - At least one (1) set of any auxiliary gear to ease assembly, erection and future maintenance, at SUPPLIER's discretion, shall be supplied. - All the hardware required for assembly and erection of the Supply such as bolts, nuts, flat and spring washers, pins, screws, shims, supports and similar shall be supplied. All insulating materials required for assembly and erection of the Supply such as sleeves, washers, shims and similar shall be supplied. The Supply shall include at least ten percent (10%) excess of the above as allowance for loss.
3.9
SPARE PARTS
3.9.1 General The SUPPLIER shall send na itemized list of all spare parts considered necessary or recomended, indicating the respective unit prices and code numbers to facilitate eventual acquisition by COPEL. The total cost of all spare parts shall not be included in the BID. GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 69/85
The SUPPLIER shall furnish and deliver all spare parts, with the first shipment. All the spare parts shall be of the same design, make, material and workmanship as the corresponding original ones. They shall be totally interchangeable and equal to the corresponding original ones. All spare parts shall be suitably protected and packed in crates for long storage periods at the site climatic conditions. The crates shall be externally identified and contain a list of constituent spares with their application codes. Small pieces shall be placed in plastic bags and sorted by their types and application. Materials subject to damage by moisture or fungus shall be placed in sealed plastic bags with desiccant. All inscriptions on the crates and listings shall be in Portuguese. The Maintenance Instruction Manual shall positively inform the exact crate and the application code of specific spares to be used in specific maintenance procedures. The SUPPLIER shall guarantee the supply of any spare part for a period of not less than ten (10) years beginning at the date of final acceptance.
3.9.2 Recommended Spare Parts The SUPPLIER shall be able to supply all parts deemed necessary for normal maintenance for a minimum required period of ten years after delivery and erection of the GIS.
3.10 INSTALLATION AND ERECTION SUPERVISION 3.10.1 General The installation and erection of all electromechanical equipment, including GIS and its associated equipment shall be performed by a specialized firm – Erection Contractor, specifically contracted by Main Contractor or by the SUPPLIER. The SUPPLIER shall designate an Installation and Erection Supervisor that shall stay at site during all installation and erection of GIS and its associated equipment and shall be responsible for all stages of installation and erection of this Supply up to commissioning. The SUPPLIER, by way of his Erection Supervisor, shall take upon himself full responsibility for the quality and correctness of installation and erection of the Supply and workmanship of the personnel allocated by the Erection Contractor. The Installation and Erection Supervisor shall be fully empowered to act in the name of the SUPPLIER in all circumstances of installation and erection of the Supply, solving any problems and conflicts, directing and instructing in cases of doubt and proposing alternate solutions if required. He shall assume total responsibility in the SUPPLIER's name for any modifications introduced in the Supply with his approval. The SUPPLIER shall provide an Installation and Erection Timetable considering the Construction and Delivery Timetable. This Installation and Erection Timetable shall depict the various stages of erection and installation and the required manpower (with personnel qualification) for each stage. Any recommendations or suggestions concerning installation and erection, based on SUPPLIER's experience, shall be appended to this schedule. One hundred (100) days prior to start of erection and installation the SUPPLIER shall submit to COPEL’s review the Installation and Erection Manual.
3.10.2 Scope of Installation and Erection Erection Supervision Services Services GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 70/85
The responsibilities of the SUPPLIER represented by his Erection Supervisor include, but are not limited to, the following activities and work: - Supervision of reception, unloading and storage of all Supply shipments. - Supervision and direction of unpacking and posterior installation and erection of all Supply shipments. - Supervision of site tests. - Supervision of GIS commissioning and early stages of initial operation. The erection supervision services shall be considered terminated only after commissioning of the Supply. The Erection Supervisor shall immediately notify COPEL in case any defect(s) is (are) disclosed during unpacking, erection and site tests. If such defect(s) is (are) due to any design or fabrication flaw it (they) shall be corrected at SUPPLIER's expense. During the site tests the Erection Supervisor shall be responsible for any corrections and adjustments required by the Supply to correct the above mentioned defects, considering the SUPPLIER's obligations and COPEL’s consent. After all defects are corrected, the refurbished items shall be retested to demonstrate its full functionality and conformance to the Technical Specifications.
GIS01 – GAS INSULATED SUBSTATIONS
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão 4
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 71/85
TECHNICAL BID FORMS
4.1
72.5 kV GAS INSULATED SUBSTATION
4.1.1 General The requested data will be used as Bid eligibility parameters. Non presentation of requested data shall unqualify the BID. One (1) asterisk (*), in the column CHARACTERISTICS, indicates that the values to be informed by the BIDDER shall be GUARANTEED VALUES.
4.1.2 Characteristics ITEM 01
CHARACTERISTICS
SPECIFICATIONS COPEL BIDDER
GENERAL a- Type of installation b- Complete and detailed GIS description comprising, but not limited to, enclosures, insulators, conductors, shieldings, equipments, flexible connections, finishings, supports, gas compartments, gas monitoring, safety devices, connection of GIS buses with transformers and/or SF6-air bushings. c- Supplier procedure for grounding d- Supplier proce roceddure for ele electr ctroma omagneti etic compat patibility e- Applicable standards
f- Heaviest piece of supply to be handled in the GIS building during erection and/or maintenance (Kn) 02
MAXIMUM YE YEARLY LEAKAGE PE PER GA GAS CO COMPARTMENT (*)
03
COMMON ELECTRICAL CHARACTERISTICS (*) a- Rated voltage b- Rated frequency c- Rated lightning impulse withstand voltage d- Rate Ratedd one one minu minute te powe powerr-fr freq eque uenc ncyy with withst stan andd volt voltag agee e- Rated normal current f- Rated short-time withstand current - Main circuits - Grounding circuits g- Rated duration of short-circuit h- Rated peak withstand current - Main circuits - Grounding circuits i- Maximum level of partial discharges under 72.5/ 3 kV, not higher than: j- Rated voltage of auxiliary circuits (lighting, heating and outlets) v
GIS01 – GAS INSULATED SUBSTATIONS
Indoor -
In accordance with the Technical Specifications 1% in mass
72.5 kV 60 Hz 350 kV 140 140 kV 2 0 00 A ≥25 ≥25
kA kA
3s ≥62,5kA ≥62,5kA
10 pC 220V,phase-tophase, 60Hz
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM 04
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS SF6 BUSES a- Enclosures - Type - Material - External diameter (mm) - Internal diameter (mm) b- Conductors - Material - External diameter (mm) - Internal diameter (mm) c- Insulators - Material d- Pressures (kPa gauge) - Rated - Minimum, for first alarm - Minimum , for second alarm e- Description of painting - Internal - External
05
Revisão:
SINGLE PRESSURE GAS CIRCUIT BREAKERS a- Type b- Enclosure - Type - Material c- Applicable standard d- Rated short-circuit breaking current (*) - AC component - DC component e- Rated short-circuit making current (*) f- Rated break time (*) g- Transient Recovery Voltage (TRV) for Terminal Faults (first pole factor = 1,5) (*) h- Transient Recovery Voltage (TRV) for Short Line Faults (*) i- Transient Recovery Voltage (TRV) for Out-of-Phase Breaking (*) j- Rated Operating Sequence (*) k- Rated Overhead Line Charging Breaking Current (*) l- Rated Underground Cable Charging Breaking Current (*) m- Type of Operating Mechanism n- Motor rated voltage o- Rated pressure of operating mechanism (kPa) p- Trip coils (*)
GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002
SPECIFICATIONS COPEL BIDDER three-phase Aluminum alloy or steel copper or aluminum alloy three-phase Aluminum alloy or steel IEC-56 ≥25 kA ≥40 % ≥62,5 kA
50 ms ≥ 124 kV ≥ 83 ≥ 83
kV kV
O - 0.3 sec-CO1 min - CO ≥ 30 A ≥ 125 A Motor-operated spring or hydraulic 220V, 60 Hz or 125VDC -
72/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS - Quantity - Rated voltage - Momentary current (A) q- Closing coil (*) - Quantity - Rated voltage - Momentary current (A) r- Auxiliary contacts - Minimum quantity - Rated current s- Total mass (kg) t- Design test reports u- Catalogs and/or leaflets
06
DISCONNECTING SWITCHES a- Type b- Enclosure - Type - Material c- Applicable standard d-The disconnecting switches shall be capable of making and breaking capacitive current? (*) e- The disconnecting switches, when open, shall be capable of withstanding phase opposition over contact isolating distance?(*) f- Type of operating mechanism g- Motor rated voltage h- Auxiliary contacts - Minimum quantity - Rated current i- Description of electrical interlock during electrical and manual operation j- Description of mechanical interlock during manual operation k- Design test reports l- Catalogs and/or leaflets
07
Revisão:
GROUNDING SWITCHES a- Type b- Applicable standard c- Type of operating mechanism - Line exit
GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002
SPECIFICATIONS COPEL BIDDER 2 1 25 V DC max 140 V min 90 V 1 1 25 V DC max 140 V min 90 V 5 “a” and 5 “b” 10 A three-phase Aluminum alloy or steel IE C – 1 2 9 Yes Yes Motor and manual 1 25 V DC max 140 V min 90 V 4 “a”, 4 “b”, 2 “af” and 2 “bf” 10 A IEC 1 2 9 Motor spring charged
73/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS - Other grounding switches d- Motor rated voltage (when applicable) e- Auxiliary contacts - Minimum quantity - Rated current f- Description of electrical interlock g- Description of mechanical interlock h- Design test reports i- Catalogs and leaflets
08
CURRENT TRANSFORMERS a- Type b- Applicable standard c- Rated secondary current d- Relaying cores (*) - Quantity - Rated ratios - ANSI rated burden and accuracy class e- Metering cores (*) - Quantity - ANSI rated burden and accuracy class f- Design test reports g- Catalogs and/or leaflets
09
INDUCTIVE VOLTAGE TRANSFORMERS a- Type b- Applicable standard c- Number of secondary windings (*) d- Rated ratios (*) - Primary - full secondary - Primary – secondary tap e- Rated burden and accuracy class, for each winding, full and tap (*) f- Design test reports g- Catalogs and/or leaflets
10
Revisão:
METAL ENCLOSED ZnO SURGE ARRESTERS a- Type b- Applicable standard c- Rated voltage (*) d- Continuous operating voltage (*) e- Residual voltage (*) - Steep Current Impulse (10 kA) - Lightning Current Impulse (10 kA)
GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002
SPECIFICATIONS COPEL BIDDER Manual and motor operation 125 V DC max 140 V min 90 V 4 “a”, 4 “b”, 2 “af” and 2 “bf” 10 A ANSI C57-13 5A ANSI C57.13 2
-
IEC 9 9 - 4 6 0 kV ≥ 46,5 kV ≤ 193 kV ≤ 168 kV
74/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS - Switching Current Impulse (1000A) f- Rated Discharge Current (*) g- Energy absortion capability (*) h- Pressure relief rated current (*) i- Details of operation counter j- Details of milliammeter k- Design test report l- Catalogs and/or leaflets
11
12
13
Revisão:
SF6-AIR BUSHINGS a- Type b- Applicable standard c- Rated insulation levels (*) - Lightning impulse withstand voltage - One minute power-frequency test withstand voltage d- Creepage distance (non-enclosed side) (mm) (*) e- Cantilever strength (daN) (*) f- Design test reports g- Catalogs and/or leaflets SF6 – INSULATED CA CABLE C CO ONNECTION EN ENCLOSURES a- Type b- Applicable Standard c- Rated Insulation Levels (*) - Lightning impulse withstand voltage - One minute power-frequency test withstand voltage d- Design test reports e- Catalogs and/or leaflets LOCAL CONTROL CUBICLES SEE CONTROL CUBICLES SPECIFICATION
GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002
SPECIFICATIONS COPEL BIDDER ≤ 139 kV ≥ 10 kA ≥5 kJ / kV ≥ 20 kA I EC 350 kV IEC 350 kV -
75/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão 4.2
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 76/85
145kV GAS INSULATED SBSTATION
4.2.1 General The requested data will be used as Bid eligibility parameters. Non presentation of requested data shall unqualify the BID. One (1) asterisk (*) in the column CHARACTERISTICS, indicates that the values to be informed by the BIDDER shall be GUARANTEED VALUES.
4.2.2 Characteristics ITEM 01
CHARACTERISTICS GENERAL a- Type of installation b- Complete and detailed GIS description comprising, but not limited to, enclosures, insulators, conductors, shieldings, equipments, flexible connections, finishings, supports, gas compartments, gas monitoring, safety devices, connection of GIS busses with transformers and/or SF6-air bushings c- Supplier procedure for grounding d- Supplier proce roceddure for ele electr ctroma omagneti etic compat patibility e- Applicable standards
f- Heaviest piece of supply to be handled in the GIS building during erection and/or maintenance (kN) 02
MAXIMUM YE YEARLY LEAKAGE PE PER GA GAS CO COMPARTMENT (*)
03
COMMON ELECTRICAL CHARACTERISTICS (*) a- Rated voltage b- Rated frequency c- Rated lightning impulse withstand voltage d- Rate Ratedd one one minu minute te powe powerr-fr freq eque uenc ncyy with withst stan andd volt voltag agee e- Rated normal current f- Rated short-time withstand current - Main circuits - Grounding circuits g- Rated duration of short-circuit h- Rated peak withstand current - Main circuits - Grounding circuits i- Maximum level of partial discharges under 145/V3 kV, not higher than: j- Rated voltage of auxiliary circuits (lighting, heating and outlets)
GIS01 – GAS INSULATED SUBSTATIONS
SPECIFICATIONS COPEL BIDDER Indoor _
In accordance with the Technical Specifications 1% in mass
1 45 k V 60 Hz 650 kV 275 275 kV 1 2 50 A ≥ 31.5 ≥ 31.5
kA kA
3s ≥ 80 ≥ 80
kA kA 10 pC 220V,phaseto-phase, 60Hz
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM 04
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS SF6 BUSES a- Enclosures - Type - Material - External diameter (mm) - Internal diameter (mm) b- Conductors - Material
05
Revisão:
- External diameter (mm) - Internal diameter (mm) c- Insulators - Material d- Pressures (kPa gauge) - Rated - Minimum, for first alarm - Minimum , for second alarm e- Description of painting - Internal - External SINGLE PRESSURE GAS CIRCUIT BREAKERS a- Type b- Enclosure - Type - Material c- Applicable standard d- Rated short-circuit breaking current (*) - AC component - DC component e- Rated short-circuit making current (*) f- Rated break time (*) g- Transient Recovery Voltage (TRV) for Terminal Faults (*) (first pole factor = 1,5) h- Transient Recovery Voltage (TRV) for Short Line Faults (*) i- Transient Recovery Voltage (TRV) for Out-of-Phase Breaking(*) j- Rated Operating Sequence (*)
SPECIFICATIONS COPEL BIDDER three-phase Aluminum alloy or steel Copper or aluminum alloy -
three-phase Aluminum alloy or steel IEC-56 ≥ 31.5 kA ≥ 40 % ≥ 80 kA
50 ms ≥249kV ≥166kV ≥167kV
k- Rated Overhead Line Charging Breaking Current (*)
0 - 0.3 secCO - 1 min CO ≥75A
l- Rated Underground Cable Charging Breaking Current (*)
≥160A
m- Type of Operating Mechanism
Motoroperated spring, pneumatic or hydraulic
GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002 77/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS n- Motor rated voltage o- Rated pressure of operating mechanism (kPa) p- Trip coils (*) - Quantity - Rated voltage - Momentary current (A) q- Closing coil (*) - Quantity - Rated voltage - Momentary current (A) r- Auxiliary contacts - Minimum quantity (NO = normally open, NC = normally closed) - Rated current s- Total mass (kg) t- Design test reports u- Catalogs and/or leaflets
06
DISCONNECTING SWITCHES a- Type b- Enclosure - Type - Material
SPECIFICATIONS COPEL BIDDER 220V, 60 Hz or 125 VDC 2 1 25 V DC max 140 V min 90 V 1 1 25 V DC max 140 V min 90 V 6 NO and 6 NC 10 A -
Three-phase Aluminum alloy or steel c- Applicable standard IE C - 1 2 9 d- The disconnecting switches shall be capable of making and Yes breakimg capacity current?(*) e- The disconnecting switches, when open, shall be capable Yes of withstanding phase opposition over contact isolating distance?(*) f- Type of operating mechanism Motor and manual g- Motor rated voltage 1 25 V DC max 140 V min 90 V h- Auxiliary contacts - Minimum quantity 4 “a”, 4 “b”, 2 “af” and 2 “bf” - Rated current 10 A i- Description of electrical interlock during electrical and manual operation j- Description of mechanical interlock during manual operation k- Design test reports l- Catalogs and/or leaflets 07
Revisão:
GROUNDING SWITCHES a- Type
GIS01 – GAS INSULATED SUBSTATIONS
-
R00 05/06/2002 78/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS b- Applicable standard c- Type of operating mechanism - Line exit - Other grounding switches d- Motor rated voltage (when applicable) e- Auxiliary contacts - Minimum quantity - Rated current f- Description of electrical interlock g- Description of mechanical interlock h- Design test reports i- Catalogs and leaflets
08
CURRENT TRANSFORMERS a- Type b- Applicable standard c- Rated secondary current d- Relaying cores (*) - Quantity - Rated ratios - ANSI rated burden and accuracy class e- Metering cores (*) - Quantity - ANSI rated burden and accuracy class f- Design test reports g- Catalogs and/or leaflets
09
INDUCTIVE VOLTAGE TRANSFORMERS a- Type b- Applicable standard c- Number of secondary windings (*) d- Rated ratios (*) - Primary - full secondary - Primary - secondary tap e- Rated burden and accuracy class, for each winding, full and tap (*) f- Design test reports g- Catalogs and/or leaflets
10
Revisão:
METAL ENCLOSED ZnO SURGE ARRESTERS a- Type b- Applicable standard
GIS01 – GAS INSULATED SUBSTATIONS
SPECIFICATIONS COPEL BIDDER IEC 1 2 9
Motor spring charged Manual operation 125 V DC max 140 V min 90 V 4 “a”, 4 “b”, 2 “af” and 2 “bf” 10 A ANSI C57-13 5A ANSI C57.13 2
IEC 9 9 - 4
R00 05/06/2002 79/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS c- Rated voltage (*) d- Residual voltage (*) (PELA COPEL) e- Rated Discharge Current (*) (PELA COPEL) f- Energy absortion capability (*) (PELA COPEL) g- Pressure relief rated current (*) (PELA COPEL) h- Details of operation counter i- Details of milliammeter j- Design test report k- Catalogs and/or leaflets
11
12
Revisão:
SF6-AIR BUSHINGS a- Type b- Applicable standard c- Rated insulation levels (*) - Lightning impulse withstand voltage - One minute power-frequency test withstand voltage d- Creepage distance (non-enclosed side) (mm) (*) e- Cantilver strength (daN) (*) f- Design test reports g- Catalogs and/or leaflets LOCAL CONTROL CABINETS SEE CONTROL CUBICLES SPECIFICATION
GIS01 – GAS INSULATED SUBSTATIONS
SPECIFICATIONS COPEL BIDDER 1 20 k V
IEC 650 kV -
R00 05/06/2002 80/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão 4.3
Revisão:
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
R00 05/06/2002 81/85
242kV GAS INSULATED SUBSTATIO
4.3.1 General The requested data will be used as Bid eligibility parameters. Non presentation of requested data shall unqualify the BID. One (1) asterisk (*) in the column CHARACTERISTICS, indicates that the values to be informed by the BIDDER shall be GUARANTEED VALUES.
4.3.2 Characteristics ITEM
CHARACTERISTICS
SPECIFICATIONS COPEL BIDDER
01
GENERAL a- Type of installation Indoor b- Complete and detailed GIS description comprising, but not limited to, enclosures, insulators, conductors, shieldings, equipments, flexible connections, finishings, supports, gas compartments, gas monitoring, safety devices, connection of GIS buses with transformers and/or SF6-air bushings c- Supplier procedure for grounding d- Supplier proce roceddure for ele electr ctroma omagneti etic compat patibility e- Applicable standards In accordance with the Technical Specifications f- Heaviest piece of supply to be handled in the GIS building during erection and/or maintenance (kN)
02
MAXIMUM YE YEARLY LEAKAGE PE PER GA GAS CO COMPARTMENT (*)
03
COMMON ELECTRICAL CHARACTERISTICS (*) a- Rated voltage b- Rated frequency c- Rated lightning impulse withstand voltage d- Rate Ratedd one one minu minute te powe powerr-fr freq eque uenc ncyy with withst stan andd volt voltag agee e- Rated normal current f- Rated short-time withstand current - Main circuits - Grounding circuits g- Rated duration of short-circuit h- Rated peak withstand current - Main circuits - Grounding circuits i- Maximum level of partial discharges under 245/ 3 kV, not higher than: j- Rated voltage of auxiliary circuits (lighting, heating and outlets) v
04
SF6 BUSES a- Enclosures - Type
GIS01 – GAS INSULATED SUBSTATIONS
1% in mass
2 45 k V 60 Hz 950 kV 395 395 kV 2 0 00 A 4 0 kA 4 0 kA 3s 1 00 k A 1 0 0 kA 10 pC 220V, phaseto-phase, 60Hz Single/threephase
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS - Material - External diameter (mm) - Internal diameter (mm) b- Conductors - Material - External diameter (mm) - Internal diameter (mm) c- Insulators - Material d- Pressures (kPa gauge) - Rated - Minimum, for first alarm - Minimum , for second alarm e- Description of painting - Internal - External
05
Revisão:
SINGLE PRESSURE GAS CIRCUIT BREAKERS a- Type b- Enclosure - Type - Material c- Applicable standard d- Rated short-circuit breaking current (*) - AC component - DC component e- Rated short-circuit making current (*) f- Rated break time (*) g- Transient Recovery Voltage (TRV) for Terminal Faults (first pole factor = 1,5) (*) h- Transient Recovery Voltage (TRV) for Short Line Faults (*) i- Transient Recovery Voltage (TRV) for Out-of-Phase Breaking (*) j- Rated Operating Sequence (*) k- Rated Overhead Line Charging Breaking Current (*) l- Rated Underground Cable Charging Breaking Current (*) m- Type of Operating Mechanism
n- Motor rated voltage o- Rated pressure of operating mechanism (kPa) GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002
SPECIFICATIONS COPEL BIDDER Aluminum alloy or steel Copper or aluminum alloy Single/threephase Aluminum alloy or steel IEC-56 4 0 kA 40 % 100 kA 50 ms ≥ 415 kV ≥ 277 kV ≥ 279 kV
O - 0.3 secCO- 1 min CO ≥ 130 A ≥ 125 A Motoroperated spring or hydraulic 220V, threephase, 60 Hz -
82/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS p- Trip coils (*) - Quantity - Rated voltage - Momentary current (A) q- Closing coil (*) - Quantity - Rated voltage - Momentary current (A) r- Auxiliary contacts - Minimum quantity - Rated current s- Total mass (kg) t- Design test reports u- Catalogs and/or leaflets
06
DISCONNECTING SWITCHES a- Type b- Enclosure - Type - Material c- Applicable standard d- The disconnecting switches shall be capable of making and breaking capacitive current?(*) e- The disconnecting switches, when open, shall be capable of withstanding phase opposition over contact isolating distance?(*) f- Type of operating mechanism g- Motor rated voltage h- Auxiliary contacts - Minimum quantity - Rated current i- Description of electrical interlock during electrical and manual operation j- Description of mechanical interlock during manual operation k- Design test reports l- Catalogs and/or leaflets
07
Revisão:
GROUNDING SWITCHES a- Type
GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002
SPECIFICATIONS COPEL BIDDER 2 1 25 V DC max 140 V min 90 V 1 1 25 V DC max 140 V min 90 V 6 “a” and 6 “b” 10 A -
Single/threephase Aluminum alloy or steel IE C – 1 2 9 Yes Yes
Motor and manual 1 25 V DC max 140 V min 90 V 4 “a”, 4 “b”, 2”af” and 2 “bf” 10 A -
83/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS b- Applicable standard c- Type of operating mechanism - Line exit - Other grounding switches d- Motor rated voltage (when applicable) e- Auxiliary contacts - Minimum quantity - Rated current f- Description of electrical interlock g- Description of mechanical interlock h- Design test reports i- Catalogs and leaflets
08
CURRENT TRANSFORMERS a- Type b- Applicable standard c- Rated secondary current d- Relaying cores (*) - Quantity - Rated ratios - ANSI rated burden and accuracy class e- Metering cores (*) - Quantity - ANSI rated burden and accuracy class f- Design test reports g- Catalogs and/or leaflets
09
INDUCTIVE VOLTAGE TRANSFORMERS a- Type b- Applicable standard c- Number of secondary windings (*) d- Rated ratios (*) - Primary - full secondary - Primary - secondary tap e- Rated burden and accuracy class, for each winding, full and tap (*) f- Design test reports g- Catalogs and/or leaflets
10
Revisão:
METAL ENCLOSED ZnO SURGE ARRESTERS a- Type
GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002
SPECIFICATIONS COPEL BIDDER IEC 1 2 9 motor spring charged manual and motor operation 125 V DC max 140 V min 90 V 4 “a”, 4 “b”, 2”af” and 2 “bf” 10 A ANSI C57-13 5A ANSI C57.13 2
-
84/85
ÁREA DE ENGENHARIA DE SUBESTAÇÕES - ENSE COPEL
Transmissão ITEM
ESPECIFICAÇÃO TÉCNICA
Data:
00000- 20302- 0115 / 03
Folha:
CHARACTERISTICS b- Applicable standard c- Rated voltage (*) d- Continuous operating voltage (*) e- Residual voltage (*) - Steep Current Impulse (10 kA) - Lightning Current Impulse (10 kA) - Switching Current Impulse (1000A) f- Rated Discharge Current (*) g- Energy absortion capability (*) h- Pressure relief rated current (*) i- Details of operation counter j- Details of milliammeter k- Design test report l- Catalogs and/or leaflets
11
12
Revisão:
SF6-AIR BUSHINGS a- Type b- Applicable standard c- Rated insulation levels (*) - Lightning impulse withstand voltage - One minute power-frequency test withstand voltage d- Creepage distance (non-enclosed side) (mm) (*) e- Cantilever strength (daN) (*) f- Design test reports g- Catalogs and/or leaflets LOCAL CONTROL CUBICLES SEE CONTROL CUBICLES SPECIFICATION
GIS01 – GAS INSULATED SUBSTATIONS
R00 05/06/2002
SPECIFICATIONS COPEL BIDDER IEC 9 9 - 4 1 96 k V ≥ 149 kV ≤ 575 kV ≤ 500 kV ≤ 415 kV ≥ 10 kA ≥ 3 kJ / kV ≥ 40 kA
IEC 1050 kV -
85/85