An Air Cooled Condenser provides a means of condensing steam without using cooling water, when a lack of water prevents use of a traditional water cooled condenser in a steam power plant.An air coo...
sheet musicDescripción completa
meFull description
Explaining how a cooling system operates
Introduction to solar coolingFull description
cooling systems
CE lab experimentFull description
Descripción: Ficha de inglés para niños, wild animals
mesing pendingin
laporan cooling water
undersatnd cooling towersDescripción completa
Deskripsi lengkap
Full description
airconditioning
WILD AIR COOLING The purpose of this methodology is to outline wild air cooling provision to protect the installations/interior Development Project Phase-IV in Zone Zone S09/S10/S11. fixtures/furniture’s etc. at Jabal Omar Development Upon availability of power to the building, the following activities shall be carried out sequentially for wild air cooling. The LV panels shall be pre-commissioned & commissioned in line with the approved procedure. The LV panels feeding the chillers shall be pre-commissioned & commissioned in line with the approved procedure. The MCC feeding the chilled water pumps shall be pre-commissioned & commissioned in line with the approved procedure. All starter panels/VFDs for pumps & AHUs shall be pre-commissioned & commissioned in line with the approved procedure. NOTE: Contractor shall take the handover of
commissioned installations/equipment.
Procedure 1. All the VFDs shall be by-passed during the start-up of the pumps & AHUs and run in star/delta starter mode. 2. The Chilled Water pumps shall be pre-commissioned & temporarily started in line with the approved procedure. 3. The AHUs at the respective floors shall be pre-commissioned & temporarily started in line with the approved procedure. 4. Flushing shall be completed prior to start the AUS, FCU. 5. Upon start-up of AHUs, the chillers shall be pre-commissioned & temporarily started in line with the approved procedure. 6. The AHUs for the remaining floors shall be started after starting of the c hillers. 7. Chiller plant manager, control, VFDs & BMS will be by-passed during wild air. 8. Air Balancing shall be carried out later & shall not constitute a part of wild air cooling. 9. Control valves will be isolated & the chilled water flow shall be adjusted through the by- pass. 10. Temporary filters shall be used in the AHUs during wild air. 11. Plant rooms & office areas shall be cleaned and all doors to rooms and shafts shall be installed. 12. All remaining works of chilled water system (piping & insulation) shall be completed prior to wild air. 13. All condensate drain pipes horizontal & vertical in conditioned & unconditioned area shall be fully insulated. 14. Start-up of equipment & system is temporary only to improve the working condition of the contractor in office floors. Full commissioning shall be done at a later stage when all systems are fully completed & ready for commissioning. 15. Contractor shall be responsible to pro tect & maintain all equipment, systems, networks, accessories, etc., at no extra time or cost impact to company by using trained personnel continuously until full commissioning has been successfully carried out & officially handed over to company / end user. 16. All Guarantees & Warranties shall start from the date of official handing over. 17. Installation, pre-commissioning & commissioning of heat exchangers is the responsibility of client (JODC), hence client/contractor to ensure that heat exchangers with complete piping are installed & commissioned.