PROJECT WORK BREAK DOWN SYSTEM – GENERAL 1. General Requirements 1.1. General Items 1.1.1.Notice 1.1.1.Notice to Proceed (NTP) 1.1.2.Kick-off 1.1.2.Kick-off meeting
1.2. Project Milestones 1.2.1.Mobilization 1.2.1.Mobilization 1.2.2.Testing 1.2.2.Testing and Commissioning Completion 1.3. Construction Milestones 1.3.1.Temporary 1.3.1.Temporary Site Facilities 1.3.1.1. Project femporary fence 1.3.1.2. Temporary site offices 1.3.1.3. Warehouse and fabrication shop 1.3.2.Buildings 1.3.2.Buildings 1.3.2.1. 1.3.2.2. 1.3.2.3. 1.3.2.4. 1.3.2.5. 1.3.2.6. 1.3.2.7.
Substructure Completion Superstructure Completion Architectural Completion Mechanical – Plumbing Completion Mechanical – HVAC Completion Electrical – Power Completion Telecommunication Completion
1.3.3.External 1.3.3.External Works 1.3.3.1. Civil Works Completion 1.3.3.2. Drainage and Sewer System Completion 1.3.3.3. Irrigation System Completion 1.3.3.4. Landscaping Completion 2. Engineering
2.1. Shop Drawings Submittals 2.1.1.Civil 2.1.1.Civil 2.1.2.Architectural 2.1.2.Architectural 2.1.3.MEP 2.1.3.MEP 2.1.4.External 2.1.4.External / Site 2.2. Shop Drawings Approvals 2.2.1.Civil 2.2.1.Civil 2.2.2.Architectural 2.2.2.Architectural 2.2.3.MEP 2.2.3.MEP 2.2.4.External 2.2.4.External / Site
3. Procurement 3.1. Material Submittals 3.1.1.Civil 3.1.1.1. Hollow blocks 3.1.1.2. Waterproofing membrane for wet areas and r oof insulation 3.1.1.3. Precast elements
3.1.2.Architectural 3.1.2.1. Floor finishes – ceramic, marble 3.1.2.2. Ceiling and wall finishes – gypsum board, paints, acoustic tile 3.1.2.3. Doors, windows and accessories 3.1.2.4. Handrails – galvanized and stainless steel 3.1.2.5. Signage’s 3.1.3.MEP 3.1.3.1. 3.1.3.2. 3.1.3.3.
Mechanical - HVAC Electrical & Telecommunication Mechanical – Plumbing, HVAC, Firefighting
3.1.4.External / Site 3.1.4.1. Civil 3.1.4.1.1. 3.1.4.1.2. 3.1.4.1.3.
Precast concrete curbstones Asphalt Interlock tiles
3.1.4.2. Architectural 3.1.4.2.1. Landscaping (Hardscape and Softscape) 3.1.4.3.
MEP
3.2. Material Approvals 3.2.1.Civil 3.2.1.1. Hollow blocks 3.2.1.2. Waterproofing membrane for wet areas and r oof insulation 3.2.1.3. Precast elements 3.2.2.Architectural 3.2.2.1. Floor finishes – ceramic, marble 3.2.2.2. Ceiling and wall finishes – gypsum board, paints, acoustic tile 3.2.2.3. Doors, windows and accessories 3.2.2.4. Handrails – galvanized and stainless steel 3.2.2.5. Signage’s 3.2.3.MEP 3.2.3.1. 3.2.3.2. 3.2.3.3.
Mechanical - HVAC Electrical & Telecommunication Mechanical – Plumbing, HVAC, Firefighting
3.2.4.External / Site 3.2.4.1. Civil 3.2.4.1.1. 3.2.4.1.2. 3.2.4.1.3.
Precast concrete curbstones Asphalt Interlock tiles
3.2.4.2. Architectural 3.2.4.2.1. Landscaping (Hardscape and Softscape) 3.2.4.3.
MEP
3.3. Delivery of Materials – Long Lead Items 3.3.1.Civil 3.3.1.1. Waterproofing membrane for wet areas and r oof insulation 3.3.1.2. Precast elements 3.3.2.Architectural 3.3.2.1. Floor finishes – ceramic, marble 3.3.2.2. Ceiling and wall finishes – gypsum board, paints, acoustic tile 3.3.2.3. Doors, windows and accessories 3.3.2.4. Handrails – galvanized and stainless steel 3.3.2.5. Signage’s 3.3.3.MEP 3.3.3.1. 3.3.3.2. 3.3.3.3.
Mechanical - HVAC Electrical & Telecommunication Mechanical – Plumbing, HVAC, Firefighting
3.3.4.External / Site 3.3.4.1. Civil 3.3.4.1.1. 3.3.4.1.2. 3.3.4.1.3.
Precast concrete curbstones Asphalt Interlock tiles
3.3.4.2. Architectural 3.3.4.2.1. Landscaping (Hardscape and Softscape) 3.3.4.3. MEP 3.3.4.3.1. 3.3.4.3.2. 3.3.4.3.3. 3.3.4.3.4. 3.3.4.3.5.
MV/LV cables MV Panel Boards Transformers Street pole lights Traffic light system
4. Construction Phase
4.1. Building 4.1.1.Substructure Works 4.1.1.1. Foundations 4.1.1.2. Grade Beams 4.1.1.3. Column Neck 4.1.1.4. Grade Slab 4.1.2.Superstructure Works 4.1.2.1. Columns (First floor to upper floor level) 4.1.2.2. Floor Slab (First floor slab up to roof slab) 4.1.2.3. Floor beams and Roof beams 4.1.2.4. Cast-in-place concrete stairs 4.1.2.5. Elevator 4.1.2.6. Precast Concrete Walls and Stair 4.1.2.7. Hollow core slabs 4.1.3.Thermal and Moisture Protection 4.1.3.1. Waterproofing Wet Areas – toilets and kitchen area 4.1.3.2. Roof Insulation System 4.1.3.3. Waterproofing for below ground concrete 4.1.4.Architectural Works 4.1.4.1. Masonry Works 4.1.4.2. Metal Works 4.1.4.2.1. Stair Handrail (Galvanized and Stainless Steel) 4.1.4.2.2. Steel Ladder 4.1.4.3. Wood and Plastic 4.1.4.3.1. Base and Wall Hung Kitchen Cabinets 4.1.4.3.2. Toilet Countertops 4.1.4.4. Doors and Windows 4.1.4.4.1. Steel Frame and Doors 4.1.4.4.2. Solid and Hollow Core Wooden Doors 4.1.4.4.3. Door Hardware and Accessories 4.1.4.4.4. Aluminum Doors, Windows and Accessories 4.1.4.4.5. Aluminum Steel Canopy 4.1.4.5. Finishes 4.1.4.5.1. Floor Finishes – Ceramic, Marble, Skirting 4.1.4.5.2. Ceiling Finishes – Gypsum board, Acoustic, Paint, Aluminum tiles 4.1.4.5.3. Wall Finishes – Plastering, Paints, Cladding 4.1.4.6. Specialties 4.1.4.6.1. Directional Signage’s
4.1.4.7.
Furniture and Equipment
4.1.5.Mechanical Works 4.1.5.1. Domestic water system 4.1.5.1.1. Hot & Cold Water piping 4.1.5.1.2. Electrical Water Heater 4.1.5.2. Sanitary Sewer and Roof drain system 4.1.5.2.1. Waste and vent piping 4.1.5.2.2. Storm drain piping 4.1.5.2.3. Floor drain and roof drain installation 4.1.5.2.4. Sanitary fixtures and accessories 4.1.5.3. Fire Protection System 4.1.5.3.1. Fire water piping and fittings installation 4.1.5.3.2. Sprinkler installation 4.1.5.3.3. Portable fire extinguisher 4.1.5.4. HVAC System 4.1.5.4.1. Galvanized steel ductwork installation 4.1.5.4.2. Ductwork insulation 4.1.5.4.3. HVAC equipment – FCU, AHU AC, etc 4.1.5.4.4. Exhaust fans, ceiling diffusers, gr illes installation 4.1.6.Electrical Works 4.1.6.1. Electrical piping installation 4.1.6.2. MV/LV Cabling Works 4.1.6.3. LV Panel Boards Installation 4.1.6.4. Lighting Fixtures installation 4.1.7.Telecommunication Works 4.1.7.1. 4.2. Site / External Works 4.2.1.Road and Walkways 4.2.1.1. Asphalt Works 4.2.1.2. Walkways 4.2.2.Storm Drainage System 4.2.3.Potable and Fire Water Supply System 4.2.4.Sanitary Wastewater Collection System 4.2.5.Irrigation Distribution System 4.2.6.Landscaping Works (Hardscape and Softscape)
4.2.7.MV/LV Power Distribution 4.2.7.1. MV/LV Cables 4.2.7.2. Transformers 4.2.8.Area Lighting & Traffic Control System 4.2.8.1. Street lights installation 4.2.8.2. Traffic light installation 4.2.9.Telecommunication System 4.2.10. Instrumentation System 5. Testing, Inspection and Commissioning 5.1. MEP Equipment and Accessories 5.1.1.Elevators 5.1.2.Electrical Water Heaters 5.1.3.Electrical Pumps 5.1.4.HVAC Equipment 5.1.5.Lighting fixtures 5.1.6.Telephone System 5.1.7.Public Address System 5.1.8.CCTV & IPTV System 5.1.9.Fire piping test inspection 6. Project Handing Over 6.1. As-Built Drawings 6.2. Initial Handing Over 6.3. Demobilization 6.4. Final Handing Over