Technical Site Survey Report For Collocation Site (V1.05-20101216)
Project: Region
Mobitel Stage-VII ZTE
Ericsson
Site ID: Site Name: ZTE Engineer: Sub Contractor name: Sub Contractor Engineer: Survey Date:
119405572.xlsx.ms_office
Huawei
1. Current Information Site Type
2G 900
2G 1800
3G
1.1 Site Basic Information Survey Item
Survey Contents
Site locatin information
Site address:
Site Owner Information
Owner :
Coordinates
Latitude:
Longitude:
Altitude:
Operator:
Telephone:
Mobile phone:
Name Mobitel regional leader Telephone: Equipment room location
Site environment checking
Equipment installation cabinet:
Roof top Greenfield
Shelter
Building Floor No(Excluding Ground Floor):
Outdoor Cabinet
Building
Other Distance of Manual Transport required, (Flat land, Rocky land, or Hill), if the distance is >50m
Flat land
Rocky land
Hill
Floors No.
Hand Carry to Rooftops
Is there any evidence of flooding near the site? Ie water stained,wall. Any Special Delivery System Required?
Yes
The Distance to the Site from Colombo Access Restriction Yes No
Please specify:
Access on 7 Day
If No,Please specify:
Yes
No
Crane Boomtruck < 50km 50
No
4WD
Twenty-four hours Yes No If No,Please specify: Prior appointment for access ( person to be informed before site access ) No Site access information
Yes
Telephone:
Contact person: Site access key
Mobitel Access KeyNo
Parking space available
Yes
Equipment delivery to its position by
Landlord Key
Other Access Key
No Hand
Lift
Crane
Other(mention in remarks)
Safe access to all equipment parts & antennas (lifeline systems, fall arrest systems, anchors.) Yes
No
If NO, please specify missing items: Some information is unusual,please remark here: Remarks
1.2 Site Existing Information Meter Cubical Meter Cubical installed SPD
Yes
NO YES `
Is Meter To ACPDB length > 20m? AC
DC
Voltage:
V
V
Voltage:
Armod cable length from MC to ACPDB
Spare breaker Qty:
Armod cable dimension
Breaker/Per capacity:
Additional space for ZTE ACPDB:
Rectifier Qty.
Spare Total Breaker Qty: Power supply Spare Total Breaker capacity:
A
Rectifier 1Type out Put Amperage:
Additional breaker Qty:
Rectifier 2 Type out Put Amperage:
Additional Breaker capacity:
Battery Type and capacity:
Spare AC outlet Qty for test equipment:
Battery Type and capacity:
Three phase Single phase If more than 1 BTS present, Are the AC power cable laid in the same path?
Yes
No
If No, please specify the power cable length in path 2:
ECB
Avaible ECB Qty (Outdoor): Spare ECB holesQty(Outdoor):
Available ECB Qty (Indoor):
Required ECB Qty (Outdoor): Gap between available ECBs of the tower:
Required ECB Qty (Indoor):
Tower Type:
Guyed Mast tower (GMT)
Spare ECB holes Qty(Indoor):
Self Support tower (SST)
Pole
Monopole Tower Tower
Tower Leg Qty
3LEGS
Tower Leg type:
4LEGS
Anguar
Tubular
Tower Height: Qty of spare antenna poles : Transmission
MW
Equipment type
Optical transceiver
Remarks
1.3 Existing GSM System information System 1 Type GSM 900
BTS Qty 2207
Ericsson
Ericsson
DCS 1800 2207
2206
2206
3012
Huawei Existing equipment information
3012
Huawei
3012AE
3012AE
3900
3900
3900A
3900A
8900
ZTE
8900
ZTE
8900A
8900A
Rack Qty
Rack Qty
Indoor
Outdoor
Frequency
Single Band 900MHz
Spare port condition Good Antenna
Indoor
900MHz
Ant. Type Spare port Type
BTS Qty
2100MHz
Dual Band
Tri Band
1800MHz Bad
Sector 1
2100MHz
With Dust Cap Sector 2
Outdoor
1800MHz
Without Dust Cap
Sector 3
Azimuth (º) Downtilt (º)
E
M
E
M E
M Can Ajust the tilt Elec
Height (m) Jumper (Ant.) Length (m) Jumper connector type to Ant
Din or N Type
Mech
IF use TMA TMA
Input Yes or No
TMA Qty Type
Feeder
Type
Input 1/2",7/8"or 1 1/4"
connector type
Din or N Type
Length (m) Jumper (BS)
Length (m)
System 2 Type GSM 900
DCS 1800
BTS Qty 2207
Ericsson
Ericsson
2206
2206
3012
Huawei Existing equipment information
Huawei
3012
3012AE
3012AE
3900
3900
3900A
3900A
8900
ZTE
ZTE
8900
8900A
8900A
Rack Qty
Rack Qty
Indoor
Outdoor
Frequency
1800MHz
Single Band
Dual Band
900MHz
Spare port condition Good
1800MHz Bad
Sector 1
Antenna
Indoor
900MHz
Ant. Type Spare port QTY
BTS Qty
2207
Tri Band 2100MHz
With Dust Cap Sector 2
Outdoor 2100MHz
Without Dust Cap
Sector 3
Azimuth (º) E
M
E
M E
M Can Ajust the tilt
Downtilt (º) Elec
Mech
Height (m) Jumper (Ant.) Length (m) Jumper connector type to Ant IF use TMA TMA
Din or N Type Input Yes or No
TMA Qty Type
Feeder
Type
Input 1/2",7/8"or 1 1/4"
connector type
Din or N Type
Length (m) Jumper (BS)
Length (m)
Jumper connector type to BS Remarks
Input DIN S/R or N type.
System 3 Type GSM 900
BTS Qty 2207
Ericsson
Ericsson
DCS 1800 2207
2206
2206
3012
Huawei Existing equipment information
3012
Huawei
3012AE
3012AE
3900
3900
3900A
3900A
8900
ZTE
8900
ZTE
8900A
8900A
Rack Qty
Rack Qty
Indoor
Outdoor
Frequency
Indoor
900MHz
Ant. Type
Single Band
Spare port QTY
900MHz
Spare port condition Good
Outdoor
1800MHz
2100MHz
Dual Band
Tri Band
1800MHz Bad
2100MHz
With Dust Cap
Sector 1
Antenna
BTS Qty
Sector 2
Without Dust Cap
Sector 3
Azimuth (º) E
M
E
M E
M Can Ajust the tilt
Downtilt (º) Elec
Mech
Height (m) Jumper (Ant.) Length (m) Jumper connector type to Ant
Din or N Type
IF use TMA TMA
Input Yes or No
TMA Qty Type
Feeder
Type
Input 1/2",7/8"or 1 1/4"
connector type
Din or N Type
Length (m) Jumper (BS)
Length (m)
Jumper connector type to BS Remarks
Input DIN S/R or N type.
System 4Type GSM 900
BTS Qty 2207
Ericsson
Ericsson
DCS 1800 2207
2206
2206
3012
Huawei Existing equipment information
3012
Huawei
3012AE
3012AE
3900
3900
3900A
3900A
8900
ZTE
8900
ZTE
8900A
8900A
Rack Qty
Rack Qty
Indoor
Outdoor
Frequency
Single Band 900MHz
Spare port condition Good Sector 1
Antenna Azimuth (º)
Indoor
900MHz
Ant. Type Spare port QTY
BTS Qty
2100MHz
Dual Band
Tri Band
1800MHz Bad
2100MHz
With Dust Cap Sector 2
Outdoor
1800MHz
Sector 3
Without Dust Cap
Antenna E
M
E
M E
M Can Ajust the tilt
Downtilt (º) Elec
Mech
Height (m) Jumper (Ant.) Length (m) Jumper connector type to Ant
Din or N Type
IF use TMA TMA
Input Yes or No
TMA Qty Type
Feeder
Type
Input 1/2",7/8"or 1 1/4"
connector type
Din or N Type
Length (m) Jumper (BS)
Length (m)
Jumper connector type to BS
Input DIN S/R or N type.
Remarks
1.4 Existing UMTS 2100 Antenna, Feeder, TMA and RF information UMTS 2100 Huawei
BTS Qty
DBS 3800 DBS 3900
Existing equipment information
BTS 3900 8900
ZTE
8900
ZTE
8900A
8900A
Rack Qty Indoor
Outdoor
Share with Other System?
Outdoor
Yes If yes,Please specify:
Frequency
900MHz
1800MHz
2100MHz
Ant. Type
Single Band
Dual Band
Tri Band
Spare port QTY Antenna
Indoor No
900MHz
Spare port condition Good
1800MHz Bad
Sector 1
2100MHz
With Dust Cap
Without Dust Cap
Sector 2
Sector 3
Azimuth (º) Downtilt (º) Height (m) Jumper (Ant.) Length (m) Jumper connector type to RRU Fiber from RRU to BBU Remarks
Length (m)
E
M
E
M
E
M
Can Ajust the tilt Elec
Mech
1.5 Existing MW Information IDU Qty.
Dimension:(No.of U)
Detail description of each unit: IDU Information
IDU Installed in:
19''Sevice Rack
In NodeB/BTS Rack
DCDB switch for IDU
Yes
No
E1 connecter type at end point:
BNC (L)
BNC (S)
Link type
SDH
PDH
75 Ω
IF cable type Patch Panel Mounting Type MW Antenna
SMB
SMZ
120 Ω If Yes,Qty :
Yes
No
Pole Mounting
Wall Mounting
Tower Mounting
Ant Qty: Does Antenna mounting with ODU?
TX Cabinet
Yes
Remarks
1.6 Other Information not in the above Table Other Information not in the above Table,such as:
Description of discovered CW-defects or other deficiencies (include photos):
No
Other
2. New ZTE equipment information 2G 900
Site Type
2G 1800
3G
2.1 Site information
Space Checking
Equipment Type
Indoor
Outdoor
Enough Space for cabinet?
Yes
No
Need Site acquisition(Just for outdoor sites)?
Yes
No
Enough vertical cable space?
Yes
No
Need Extention Bars for Vertical Ladder
Yes
No
Enough Space for Extention Bars
Yes
No
Extension Bars (Provide The Drawing)
No
Yes Qty:
Enough horizontal cable space for fiber & power
Yes
No
Need extention ladder from tower to cabinet?
Yes
No
Enough Space for Ant?(Include Sectoral & MW)
Yes
No
Need additional Ant-mount?
No
Yes Qty:
Enough space for mount ZTE RRU
Yes
No
No
Yes Qty:
In case of "No" for the above requirement,specify solution: Comments Need aditional ECBs for Tower ECB 2)
ECB interconnected ground cable Lenghth(35mm : CEB supply AC power available?
Yes
No
AC Phase:
3 Phase
1 Phase
MC To ACDB Power Cable Length (4X16mm2):
2.2 GSM Solution GSM System 1 GSM 900 ZTE BS8900
BTS Configuration
Ericsson Huawei
Equipment Base
Qty BC8910 PC8910 RC8910 2207 2206 3012 3012AE 3900 3900A
Need Additional Steel Frame? Can share existing antennas Antenna Band 900MHz
Antenna and TMA
TMA
DCS1800 ZTE BS8900
Ericsson Huawei
No No New Ant. Cell1
1800MHz
Cell2
2100MHz
Cell3
Yes Yes Ant.type
If Yes,Qty: System Type : Ant. Height Azimuth
Need TMA?
No
Yes
If Yes,Qty:
Need NSBT?
No
Yes
If Yes,Qty: Cell1
Jumper Length from Antenna To Feeder/TMA (m) Feeder, Jumper Feeder Length (m) etc. Jumper Length from Feeder/NSBT To BTS (m) If have TMA,Jumper Length from TMA To Feeder (m) ACPDB To BTS Power Cable Length (4X6mm 2): SPD Ground Cable Length (25 mm2): Battety Cabinet Ground Cable Length (25 mm 2):
Cable & Pipe
BTS/BBU Ground Cable Length (25mm 2): SPD Pole Ground Cable Length (35 mm 2): GI Pipe from Meter to BTS PVC Pipe from the BTS to RRU (fiber & Power)
E1 cable Lenghth: Remarks
Qty
BC8910 PC8910 RC8910 2207 2206 3012 3012AE 3900 3900A
Alarm cable Length:
Cell 2
Tilt(°)
Cell 3
GSM System 2 ZTE BS8900
BTS Configuration
Ericsson Huawei
Equipment Base
GSM 900 BC8910 PC8910 RC8910 2207 2206 3012 3012AE 3900 3900A
Need Additional Steel Frame? Can share existing antennas Antenna Band 900MHz
Antenna and TMA
TMA
Qty ZTE BS8900
Ericsson Huawei
No No New Ant. Cell1
1800MHz
Cell2
2100MHz
Cell3
Yes Yes Ant.type
DCS1800 BC8910 PC8910 RC8910 2207 2206 3012 3012AE 3900 3900A
Qty
If Yes,Qty: System Type : Ant. Height Azimuth
Need TMA?
No
Yes
If Yes,Qty:
Need NSBT?
No
Yes
If Yes,Qty: Cell1
Cell 2
Tilt(°)
Cell 3
Jumper Length from Antenna To Feeder/TMA (m) Feeder, Jumper Feeder Length (m) etc. Jumper Length from Feeder/NSBT To BTS (m) If have TMA,Jumper Length from TMA To Feeder (m) ACPDB To BTS Power Cable Length: SPD Ground Cable Length: Battety Cabinet Ground Cable Length: Cable & Pipe
BTS/BBU Ground Cable Length: GI Pipe from Meter to BTS PVC Pipe from the BTS to tower (fiber & Power)
E1 cable Lenghth:
Alarm cable Length:
Remarks GSM System 3 ZTE BS8900
BTS Configuration
Ericsson Huawei
GSM 900 BC8910 PC8910 RC8910 2207 2206 3012 3012AE 3900
Qty ZTE BS8900
Ericsson Huawei
DCS1800 BC8910 PC8910 RC8910 2207 2206 3012 3012AE 3900
3900A Equipment Base
Need Additional Steel Frame? Can share existing antennas Antenna Band 900MHz
Antenna and TMA
TMA
3900A
No No New Ant. Cell1
1800MHz
Cell2
2100MHz
Cell3
Yes Yes Ant.type
If Yes,Qty: System Type : Ant. Height Azimuth
Need TMA?
No
Yes
If Yes,Qty:
Need NSBT?
No
Yes
If Yes,Qty: Cell1
Jumper Length from Antenna To Feeder/TMA (m) Feeder, Jumper Feeder Length (m) etc. Jumper Length from Feeder/NSBT To BTS (m) If have TMA,Jumper Length from TMA To Feeder (m) ACPDB To BTS Power Cable Length: SPD Ground Cable Length: Battety Cabinet Ground Cable Length: Cable & Pipe
BTS/BBU Ground Cable Length: GI Pipe from Meter to BTS PVC Pipe from the BTS to tower (fiber & Power)
E1 cable Lenghth: Remarks
Qty
Alarm cable Length:
Cell 2
Tilt(°)
Cell 3
GSM System 4 GSM 900 BC8910 PC8910 RC8910 2207 2206 3012 3012AE 3900
ZTE BS8900
BTS Configuration
Ericsson Huawei
Qty ZTE BS8900
Ericsson Huawei
DCS1800 BC8910 PC8910 RC8910 2207 2206 3012 3012AE 3900
3900A Equipment Base
Need Additional Steel Frame? Can share existing antennas Antenna Band 900MHz
Antenna and TMA
TMA
Qty
3900A
No No New Ant. Cell1
1800MHz
Cell2
2100MHz
Cell3
Yes Yes Ant.type
If Yes,Qty: System Type : Ant. Height Azimuth
Need TMA?
No
Yes
If Yes,Qty:
Need NSBT?
No
Yes
If Yes,Qty: Cell1
Cell 2
Tilt(°)
Cell 3
Jumper Length from Antenna To Feeder/TMA (m) Feeder, Jumper Feeder Length (m) etc. Jumper Length from Feeder/NSBT To BTS (m) If have TMA,Jumper Length from TMA To Feeder (m) ACPDB To BTS Power Cable Length: SPD Ground Cable Length: Battety Cabinet Ground Cable Length: Cable & Pipe
BTS/BBU Ground Cable Length: GI Pipe from Meter to BTS PVC Pipe from the BTS to tower (fiber & Power)
E1 cable Lenghth:
Alarm cable Length:
Remarks
2.3 UMTS Solution UMTS 2100 Node B Configuration
Equipment Base
ZTE BS8700
Qty
BC8910
Qty
DBS 3800
PC8910
DBS 3900
R8880 &OLPB
BTS 3900
Need Additional Steel Frame? Can share existing antennas
No No New Ant.
Antenna Band Share with GSM 2100MHz
Antenna
UMTS 2100
Huawei
Yes Yes Ant.type
If Yes,Qty: System Type : Ant. Height
Azimuth
Tilt(°)
Cell 2
Cell 3
Cell1 Cell2 Cell3
Clearnce GPS
Location of Installation: Cable Length to BTS Cell1 Jumper Length from Antenna To RRU (m)
Jumper, Fiber etc.
RRU Power Cable Length from RRU to outdoor LPB (m) Fiber Length (m) OLPB Power Cable Length from Rectifier To Outdoor LPB (m) ACPDB To NODEB Power Cable Length: SPD Ground Cable Length: Battery Cabinet Ground Cable Length:
Cable & Pipe
BBU Ground Cable Length: GI Pipe from Meter to NODEB PVC Pipe from NODEB to tower (fiber & Power) E1 cable Lenghth: Alarm cable Length:
Remarks
2.4 ZTE MW Solution IDU
Qty:
Dimension (No.ofU):
Need Rectifier for IDU in case of TX Indoor
Yes
No
Enough space for Rectifier in TX Indoor
Yes
No
Enough space for TX Rack Outdoor Enough Space for ZTE MW IDU Mount in the existing Rack (for the Capacity of existing MW is not enough)
Yes
No
Yes
No
Space Checking IF yes mention rack type and Numbere of free U :
/
,
/
Enough space for IF cable of ZTE MW
Yes
No
Enough space for ZTE MW antenna
Yes
No
Need new 19" rack for IDU
Yes
No
Need separate Outdoor TX Rack for IDU
Yes
No
Yes
No
Distance for E1 cable from BTS/NodeB Outdoor To TX Indoor(m) Comments
In case of "No" for the above requirement,specify solution:
DCDB
When ZTE MW IDU,need new DCDB
Cable (for TX Rack inside the cabin)
E1 Cable Length
E1 Cable Qty
Alam Cable Length
Alam Cable Qty
Power Cable Length GI Pipe from TX Inside to BTS/NodeB Outside length Any other information not above and any suspect obstacles for LOS (Line Of Sight) please remark here:
Remarks
TSSR for Swap Site
3. Photos List NO. Necessary photoes must provided: 1
Actual aerial view of sites ( fromTower top)
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 18 19 20 21 22 23 26 27 28 29 30 31
Panoramic Photo(45Deg per)( Should be over lap) Equipment Room/Cabinet Outlook(Can be identify the cabin properly) Location of power source Close view of Existing antennna Ports (all direction ) (all port should be clearly visible) Existing Room/Cabinet inside (can have several photos to cover the place) Existing Equipment detail Inlook (close and inside veiw of the equipment) Existing Equipment detail Outlook (take with proper distance to fit to the hard copy) Existing ACPDB box inside(with labels) Existing Rectifier Rack inside DC Breakers with lable Existing RF antenna (all operator) (need to check the space to installe antennas)l Existing MW IDU Existing Tower Existing vertical cable ladder Existing horizontal cable ladder Evidence of Crane(if need Crane) Location for ZTE Equipment( if can pre-installation)(Proposed Location) IDU Grounding(ECB end) ODU Grounding(ECB or Tower end) All ECB connection ponit (Should be clearly visible) Cable Entry Port Photo(To be taken parralally to horiziontal) Meter Cubical Photo (front & back) CW Defects #1 CW Defects #2 Exisiting TMA (Sector A) Exisiting TMA (Sector B) Exisiting TMA (Sector C)
<本文中的所有信息均为中兴通讯股份有限公司内部信息,未经允许,不得外传>
If taken
共 27 页 , 第 10 页
TSSR for Swap Site
4. Site Sketch(The drawing should be clear) 4.1 Site Location Map
5
TSSR for Swap Site
4.2 Outside existing layout diagram (outside of cabin) : Include all operators
5
TSSR for Swap Site
4.3 ZTE proposed Outside layout sketch
5
TSSR for Swap Site
4.4 Inside site layout diagram (inside cabin): Include all operators
5
TSSR for Swap Site
4.5 ZTE proposed Equipment location Inside Cabin layout sketch
5
TSSR for Swap Site
4.6 Cable ladder diagram for inside cabin separately.
5
TSSR for Swap Site
4.7 Elevation of Tower for Existing Antenna ( All antenna mounted points should clearly visible)
5
TSSR for Swap Site
4.8 Elevation of Tower for proposed ZTE Antenna ( All antenna mounted points should clearly visible)
5
TSSR for Swap Site
4.9 Vertical cable ladder diagram ( for additional cable and additional ladder or Extension Bars)
5
TSSR for Swap Site
4.10 Horizontal cable ladder diagram( plan View) ( for additional cable and additional ladder)
5
TSSR for Swap Site
4.10 Horizontal cable ladder diagram( Elevation View) ( for additional cable and additional ladder)
5
TSSR for Swap Site
4.11 RF Connection Scheme(include the feeder,fiber and power cables) (from antenna to BTS/Nodeb in all detail).
5
No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 46 47 48
GSM Material list Detail Description ZXDU 68 w201 Rack with CSU Battery Temp Sensros
★QTY
★UNIT
1
Box
BBU with all cards(With ALL CARDS CC / UBPG/ FS,etc…) ZXDU 68 W201 Accesseries |+ZXD2400(V4.0) 30A Rectifier| -3+ Battery Cable
1 1
Box
12V135Ah Gel VRLA Battery
16
Box
Battery Racks(For 2 BB) RC 8910 Rack assembly(1800)
1
RSU 80W 900M
3
Box
RSU to FS Fiber RRU 1800M
3
Box
Installation Accessories
1
Box
1
Feeder Cable Fiber Cable
m 1800
m
Feeder Clamp Fiber Clamp Power clamp Feeder earth kit Fiber earth Kit ECBs
1
Box
ANT Jumper Cable(RF-08700-029) L ANT Jumper Cable (RF-96514-016) S RF Feeder Connector SFP ports
6
Pcs
FCE monitor combine cable (between 2 BC8910 FCE)
1
Pcs
blue outdoor cable 25mm
16
M
black outdoor cable 25mm
16
M
Ground cab cable 25mm
10
M
Digital Distribution Moudle |FMPX529-DDF75//SM19JA
1
Pcs
DC Cable (16mm) Black
15
M
DC Cable(16mm) Blue
15
M
Inter RSU Cables (TX/RX)
6
Pcs
TMA
3
Pcs
Bias t
3
Pcs
Bais t cabes Antenna -900
3 0
Pcs Pcs
Antenna - 1800
3
Pcs
Clamps - 738546 for 1800 KATHREIN Antenna
3
Pcs
Bracket - 732317 for 1800 KATHREIN Antenna
6
Pcs
Antenna - Dual band
0
Pcs
Antenna - Triple-band 4×6mm2 power cord
0
Pcs
10
M
4×16mm2 power cord
0
M
Metal tube with PVC surface
25
M
Green outdoor cable 35mm
49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67
yellow/green Grunding cable 16mm2
20
M
ACDB for outdoor site SPD1 V25-B+C/3 320V,C25-B+C/NPE-255V
1
set
1
set
SRF SF340A-NE-SG
1
set
3
Each
40A4P MCB 3900 Convertion Plates
Pcs
39012 Convertion Plates
Each
APM 200 Convertion Plates
Each
ZTE Pinth GF
Pcs
ZTE Pinth RT
Pcs
Cabe Tray GF
Pcs
Cabe Tray RT
Pcs
Extension Bar Nut & Bolt for Plinth
Pcs 12
Pcs
Antenna Bracket (Antenna Mounting Poles )
0 3
Pcs Set
SPD ACBD POLE Without Base Plate GF with End Cap
1
Each
SPD ACBD POLE With Base Plate RT with End Cap
1
Each
GI pipe for power cable with connection joints (units in Bars, 1 Bar=5.8 m)
Meter Cubical
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
UMTS Material list Detail Description ZXDU 68 w201 Rack with CSU Battery Temp Sensros BBU with all cards(With ALL CARDS CC / UBPG/ FS,etc…)
★QTY
★UNIT
1
Box
1
ZXDU 68 W201 Accesseries |+ZXD2400(V4.0) 30A Rectifier| -3+ Battery Cable
1
Box
12V135Ah Gel VRLA Battery
16
Box
Battery Raks(For 2 BB)
1
RC 8910 Rack assembly(1800)
1
RRU
3
Box
Installation Accessories
1
Box
ECBs
1
Box
Digital Distribution Moudle |FMPX529-DDF75//SM19JA
1
Pcs
Antenna - Dual band Directional Antenna | 5755.00//742266//CNPX308M-4P-E1//DBXLH-6565C-VTM
0
Pcs
Antenna - Triple-band 65degree dual porlarization (6ports) RET Antenna
3
Pcs
RF-08700-029 | 626970000100 V1.5
6
Pcs
Metal tube with PVC surface
20
M
Earth Cable 25mm
20
M
Fiber Cable Fiber Clamp Power clamp Fiber earth Kit
Earth Cable 35mm
M
DC Cable (16mm) Black
15
DC Cable(16mm) Blue
15
M
3900 Conversion Plate
1
Pcs
3012 Converstion Plate
0
Pcs
3012 Battery Converstion Plate
0
Pcs
APM200 Converstion Plate
0
Pcs
ACDB for outdoor site SPD1 V25-B+C/3 320V,C25-B+C/NPE-255V
0
set
0
set
SRF SF340A-NE-SG
0
set
4×6mm2 power cord
10
M
4×16mm2 power cord
0
M
GI pipe for power cable with connection joints (units in Bars, 1 Bar=5.8 m)
1
Pcs
Nut & Bolts for Plinth
4
Pcs
Meter Cubical
M