LOCAL BANK FUNDED PROJECT (LBFP) Rehabilitation & Upgrading of Naula-Elahara-Laggala-Pallegama-Hettipola (B-312) & Hasalaka-Handungamuwa (B-484) Roads Employer:
Engineer:
Contractor:
Road Development Authority
Central Engineering Consultancy Bureau
Hovael Construction (Private) Limited
Contract No : RDA/DW/CP/GOSL/2012/233
SITE INSTRUCTION TO CONTRACTOR TO :
08
Ref No
Project Managers (Section-1, 2 & 3 ) You are hereby instructed to carry out the works as described hereunder. Such work shall be executed in accordance with the Contract and all relevant specifications.
SPEC. GROUP ICTAD Publication SCA/5 (Standard Specification for Construction & Maintenance of Roads & Bridges)
SPEC. CLAUSE(s)
SUBJECT Traffic Safety & Control
PAY ITEM(s)
103
103(1)
CHAINAGE Work / Item Description :
It was observed that no any safety equipments (safety Jackets, Helmets, etc) provided to staff working in Culvert reconstruction at 57+010 from 01-122013. Hence arrange safety equipments for all staff work in Construction immediately. Also you are advised to follow "Safety Inspection Form" in Site instruction No. 02. Also you are required to follow weightings for monitoring safety arrangement as per the Contract Document (Ref. Page 069).
Supplementary Information (ie sketch) Attached: YES/ NO Measurement :
No of Pages…………..
Payment : Information only General contract requirement Measure and value at contract rates
√ √
Dayworks Provisional Sum
-
For items to be measured under DAYWORKS - records shall be kept, agreed and signed at the end of each days work (Q A Plan Proforma 3.1.1) and submitted for payment with a copy of this instruction.
Issued on behalf of the Engineer : Signed:
Signed :
Name: Indika Kumara Designation: RE Time
Received on behalf of the Contractor :
Name: Designation:
Date
Time
Date
LOCAL BANK FUNDED PROJECT (LBFP) Rehabilitation & Upgrading of Naula-Elahara-Laggala-Pallegama-Hettipola (B-312) & Hasalaka-Handungamuwa (B-484) Roads Employer:
Engineer:
Contractor:
Road Development Authority
Central Engineering Consultancy Bureau
Hovael Construction (Private) Limited
Contract No : RDA/DW/CP/GOSL/2012/233
SITE INSTRUCTION TO CONTRACTOR TO :
09
Ref No
Project Managers (Section-1, 2 & 3 ) You are hereby instructed to carry out the works as described hereunder. Such work shall be executed in accordance with the Contract and all relevant specifications.
SPEC. GROUP ICTAD Publication SCA/5 (Standard Specification for Construction & Maintenance of Roads & Bridges) SUBJECT
SPEC. CLAUSE(s) 202, 1001, 1002
Culvert Reconstructions
PAY ITEM(s)
Bill No. 06
CHAINAGE 57+000 to 59+000 Work / Item Description :
58/1 - 57+006.8, 58/2 - 57+049, 58/3 - 57+281.8, 58/4 - 57+402.5, 58/5 57+529.3, 58/6 - 57+543.2, 58/7 - 57+625.1, 58/8 - 57+846.4, 58/9 57+965.3, 59/1 - 58+019.25, 59/2 - 58+919
Supplementary Information (ie sketch) Attached: YES/ NO Measurement :
No of Pages…………..
Payment : Information only General contract requirement Measure and value at contract rates
√ √
Dayworks Provisional Sum
-
For items to be measured under DAYWORKS - records shall be kept, agreed and signed at the end of each days work (Q A Plan Proforma 3.1.1) and submitted for payment with a copy of this instruction.
Issued on behalf of the Engineer : Signed:
Signed :
Name: Indika Kumara Designation: RE Time
Received on behalf of the Contractor :
Name: Designation:
Date
Time
Date
LOCAL BANK FUNDED PROJECT (LBFP) Rehabilitation & Upgrading of Naula-Elahara-Laggala-Pallegama-Hettipola (B-312) & Hasalaka-Handungamuwa (B-484) Roads Employer:
Engineer:
Contractor:
Road Development Authority
Central Engineering Consultancy Bureau
Hovael Construction (Private) Limited
Contract No : RDA/DW/CP/GOSL/2012/233
SITE INSTRUCTION TO CONTRACTOR TO :
10
Ref No
Project Manager (Section-1 ) You are hereby instructed to carry out the works as described hereunder. Such work shall be executed in accordance with the Contract and all relevant specifications.
SPEC. GROUP ICTAD Publication SCA/5 (Standard Specification for Construction & Maintenance of Roads & Bridges) SUBJECT
SPEC. CLAUSE(s) 1001, 1002, 1008,
Other Structures
PAY ITEM(s)
Bill No. 06
CHAINAGE 57+000 to 59+000 Work / Item Description :
With reference to above pay items, you are informed to construct Retaining wall on B-312 road from 59+660 to 59+900 at the LHS. Follow RDA Typical Drawings, 'Typical Section of Mass Concrete Retaining Walls and Head Walls' M.C.R-2, M.C.R-3 & M.C.R-4 that submitted on 26 th December 2013. Details are attached.
Supplementary Information (ie sketch) Attached: YES/ NO Measurement :
No of Pages…01
Payment : Information only General contract requirement Measure and value at contract rates
√
Dayworks Provisional Sum
-
For items to be measured under DAYWORKS - records shall be kept, agreed and signed at the end of each days work (Q A Plan Proforma 3.1.1) and submitted for payment with a copy of this instruction.
Issued on behalf of the Engineer : Signed:
Signed :
Name: K.M.I.D. Kumara Designation: SE (S1) Time
Received on behalf of the Contractor :
9:30 Date 1/14/2014
Name: Designation: Time
Date