Engineering Procedure SAEP-1638
11 July 2012
Site Acceptance Test Test Plan Document Responsibility: Process Control Standards Committee Committee
Saudi Aramco DeskTop Standards Table of Contents 1
Scope............................................................
2
2
Conflicts and Deviations......................... Deviations................................ ....... 2
3
Applicable Documents.......................... Documents................................... ......... 2
4
Definitions...................................................... 3
5
Responsibilities.............................................
6
Instructions.................................................... 4
4
APPENDIX 1 – SAT PLAN........................ PLAN.................................. .......... 6
Previous Issue: 14 September 2009 Next Planned Update: 11 July 2017 Revised paragraphs are indicated in the right margin Primary contact: Chawla, Farrukh Nawaz on 966-3-880-1828 Copyright©Saudi Aramco 2012. All rights reserved.
Page 1 of 10
Document Responsibility: Process Control Standards Committee Issue Date: 11 July 2012 Next Planned Update: 11 July 2017
1
SAEP-1638 Site Acceptance Test Plan
Scope The Site Acceptance Test (SAT) Plan covered by this procedure shall be considered as one of the Non-Material Requirements (NMR) in accordance with SAEP-16. with SAEP-16.
2
3
1.1
This Saudi Aramco Engineering Procedure (SAEP) provides instructions for the development and approval of the process automation system project Site Acceptance Test (SAT) Plan. The document is not required to follow the format provided in this SAEP, but shall contain the information specified.
1.2
The SAT Plan is a document which specifies and describes the conditions, requirements, plans, procedures, success criteria, c riteria, and responsibilities for performance of the SAT.
1.3
The SAT Plan will be used by the Contractor to guide and control the performance of the SAT. The SAT Plan will be used by the Company as the basis for monitoring performance of the SAT and for determining determining satisfactory completion of the SAT.
1.4
This document is not applicable to royalty/custody measurement applications.
Conflicts and Deviations 2.1
Any conflicts between this Procedure and other applicable Saudi Aramco Engineering Procedures (SAEPs), Saudi Aramco Engineering Standards (SAESs), Saudi Aramco Materials System Specifications (SAMSSs), Saudi Aramco Standard Drawings (SASDs), or industry standards, codes, and forms shall be resolved in writing by the Compan y or Buyer Representative through the Manager, Process & Control Systems Department of Saudi Aramco, Dhahran.
2.2
Direct all requests to deviate from this Procedure in writing to the Company or Buyer Representative, who shall follow internal company procedure SAEP-302 procedure SAEP-302 and forward such requests to the Manager, Proces s & Control Systems Department of Saudi Aramco, Dhahran.
Applicable Documents All referenced Procedures, Standards, Specifications, Codes, Forms, Drawings, and similar material or equipment supplied shall be considered part of this P rocedure to the extent specified herein and shall be of o f the latest issue (including all revisions, addenda, and supplements) unless stated otherwise.
Page 2 of 10
Document Responsibility: Process Control Standards Committee Issue Date: 11 July 2012 Next Planned Update: 11 July 2017
SAEP-1638 Site Acceptance Test Plan
Saudi Aramco Engineering Procedures
4
SAEP-16
Project Execution Guide for Process Automation Systems
SAEP-302
Instructions for Obtaining a Waiver of a Mandatory Saudi Aramco Engineering Requirement
SAEP-1634
Factory Acceptance Test
SAEP-1636
Installation and Checkout Plan
Definitions The following is a list of definitions of terms whose meanings may not b e obvious from their usage in this document. Terms that have special meanings when capitalized are shown in that form. Company: refers to a Saudi Arabian Oil Company (Saudi A ramco). Contract: refers to a specific contract. Contractor/Vendor: is an organization under contract to Company.
S ystem with all Factory Acceptance Test (FAT): demonstrates compliance of the System requirements, to the extent possible in the Con tractor's factory environment. d escribes the conditions, requirements, FAT Plan: is a document which specifies and describes plans, procedures, success criteria, and responsibilities for performance of the FAT. The FAT Plan shall contain sufficient content and detail such that successful completion of the FAT, according to the FAT Plan, will demonstrate and document that the System satisfies all requirements of the Job Specification. Functional Specification Document (FSD): provides the technical requirements for the System. Job Specification: is the scope of the work to be performed pursuant to a contract; it describes or references the applicable drawings, standards, specifications, as well as the administrative, procedural, and technical requirements that the contractor shall satisfy or adhere to in accomplishing the work. Non-Material Requirements (NMRs): The complete set of documentation required in the electronic form from the vendor and/or the contractor during the design and development phase of the project. There are three categories categories of NMRs: NMRs:
601 NMRs
Preliminary drawings for review and approval
Page 3 of 10
Document Responsibility: Process Control Standards Committee Issue Date: 11 July 2012 Next Planned Update: 11 July 2017
SAEP-1638 Site Acceptance Test Plan
602 NMRs
Certified drawings, literature, photographs, and parts data/requirements
603 NMRs
Operations, maintenance manuals, installation instructions, test certificates, etc.
Process automation system: A network of computer-based or microprocessor-based modules whose primary purpose is process automation. The functions of a PAS may include process control, safety, data acquisition, advanced control and optimization, historical archiving, and decision decision support. Examples of process automation systems systems are DCS, SCADA, MIS, ESD, PC and PLC-based systems. Project Management Team (PMT): The team of Company individuals who are assigned the responsibility of managing the project. Site Acceptance Test (SAT): The acceptance test, performed on the installed System that demonstrates compliance with all requirements, except availability. System: is the process automation system that is procured under the Contract. System Design Document: A document prepared by the vendor and/or the design contractor that contains the design narratives and the k ey design issues of the system.
5
6
Responsibilities 4.1
The PMT has overall responsibility for the development of the SAT Plan. The SAT Plan is to be delivered with 601 NMRs and 602 NMRs, which require approval by both PMT and the Operating Operating Organization (OO). Process & Control Systems Department may be requested to review the SAT Plan at any time as a consultant to either PMT or the OO.
4.2
Per SAEP-16, PMT SAEP-16, PMT and the OO are responsible to perform the SAT. Typically, PMT includes in the Job Specification that the Contractor will perform the structured testing. The Company has pass/fail pass/fail approval authority. The OO typically performs unstructured testing.
Instructions 5.1
After completion of installation and checkout per SAEP-1636, Installation SAEP-1636, Installation and Checkout Plan, SAT is performed to verify v erify that the System is installed properly, hardware and software are per specification, grounding/earth connections are properly carried out, and the system is powered up properly. The system is checked for damage of any kind during packing, shipment, installation, or power up.
Page 4 of 10
Document Responsibility: Process Control Standards Committee Issue Date: 11 July 2012 Next Planned Update: 11 July 2017
SAEP-1638 Site Acceptance Test Plan
5.2
Tests not conducted during the FAT due to subsystem unavailability or due to any other reason including integration shall be performed during the SAT as PMT considers appropriate. appropriate. FAT plan and FAT test procedures developed as per SAEP-1634 SAEP-1634 during detailed design or at the time of FAT shall be used.
5.3
The SAT Plan shall provide a complete definition of the SAT, including detailed step-by-step procedures. Appendix 1 describes a suggested outline for the SAT Plan. The plan need not follow this outline but shall contain, as a minimum the information specified.
Revision Summary 11 July 2012
Revised the “Next Planned Update .” Reaffirmed the content of the document, and reissued with no other changes.
Page 5 of 10
Document Responsibility: Process Control Standards Committee Issue Date: 11 July 2012 Next Planned Update: 11 July 2017
SAEP-1638 Site Acceptance Test Plan
APPENDIX 1 – SAT PLAN The SAT Plan serves as a checklist che cklist to sign-off each of the tests as the y are completed. After a test has been satisfactorily completed, the person responsible for the test will sign and date the appropriate section section of the document. This signed document will provide the basis for the acceptance of the Site Acceptance Test. “
”
The SAT will consist of the following categories of testing as defined by subsequent sections in this document. Section 4
Visual System Inspection
Section 5
System Hardware Testing
Section 6
FAT Untestable Items
1.
MANAGEMENT AND REPORTING
All test activities will be managed by Vendor's Site Manager or his designated representative, whose primary role is to monitor progress and manage test activities such that all tests are completed within the planned schedule. Contractor will be responsible for maintaining a record of the test in spe cific forms designed for the test. It is expected that Contractor and Saudi Aramco representatives will endorse their signatures on the test reports for documented proof of test activities. If the test is interrupted for any reason that portion of the test may be re-run, in whole or part, subject to agreement by Contractor and Saudi Aramco. 2.
RECORDING AND RESOLVING EXCEPTIONS
A document called Exception Item List contains sheets that allow the recording and resolution of any exceptions encountered during testing. This document is considered part of the SAT records. “
”
Each exception reported is classified as one of the following types of defects:
PJ
- Project issue
PD
- Product issue
DC - Design Change
Page 6 of 10
Document Responsibility: Process Control Standards Committee Issue Date: 11 July 2012 Next Planned Update: 11 July 2017
SAEP-1638 Site Acceptance Test Plan
Each exception reported is further classified into one of the following resolution categories:
3.
Type 1
-
Exception must be corrected before SAT can continue.
Type 2
-
Exception must be corrected before SAT completion.
Type 3
-
Exception will be corrected before Final Acceptance.
Type 4
-
Exception noted for resolution later by CONTRACTOR and Saudi Aramco.
ACCEPTANCE
SAT shall be considered successful and completed when Contractor has demonstrated and Saudi Aramco has accepted ac cepted all functions stated in the test document. At that time there should be no outstanding type 1 or type 2 exceptions. However, a list of outstanding outstanding type 3 or 4 action items may be included on a formal Exception Item List, together with a schedule for their resolution. 4.
VISUAL SYSTEM INSPECTION
The purpose of this section of the test is to ensure that all of the required system components are installed per the documents and are free of defects. This section is intended for an engineering review and that a certified Quality Assurance inspection has been performed. performed. This section may be eliminated or minimized as deemed by the project team. 4.1
MECHANICAL DEFECT INSPECTION Verify that all the DCS system and vendor subsystem components are free of damage or manufacturing defects by b y visually inspecting them.
4.2
HARDWARE INVENTORY Verify that all of the system components are installed b y checking their installation against the Cabinet Internal Arrangement and Wiring Drawings. Checking is to include:
4.3
a)
Subsystem quantity and interconnection.
b)
Enclosure loading and cabling.
MODULE IDENTIFICATION Verify that the module identification of all DCS a nd sub-system modules
Page 7 of 10
Document Responsibility: Process Control Standards Committee Issue Date: 11 July 2012 Next Planned Update: 11 July 2017
SAEP-1638 Site Acceptance Test Plan
and/or devices are correctly installed by checking them against the Cabinet Internal Arrangement Drawings. 4.4
GENERAL LABELING Verify that the proper labels are attached, per the requirements of the Saudi Aramco specification as documented on the enclosure and console drawings, for the following items:
4.5 Cabinet
a)
DCS and Subsystem Enclosures
b)
Workstations
c)
I/O termination blocks
d)
Printers
e)
System Cables
f)
Marshalling Cabinets
VISUAL INSPECTION CHECKOUT SHEETS
Mechanical Defects Inspection
H/W Inventory
Module ID
General Label
Complete Date
Contractor
Saudi Aramco
_________ _________
________ ________
_______ _______
_______ _______
__/__/__ __/__/__
________ ________
_______ _______
Remarks CONSOLES ________ ________
_________ _________ _________ _________
________ ________ ________ ________
_______ _______ _______ _______
_______ _______ _______ _______
_______ _______ _______ _______
________ ________ ________ ________
DCS PROCESSOR & I/O _______ ________ _______ ________ _______ ________ _______ ________
_________ _________ _________
________ ________ ________
_______ _______ _______
_______ _______ _______
_______ _______ _______
________ ________ ________
_______ _______ _______
DCS M/C ________ ________ ________
_________ _________
________ ________
_______ _______
_______ _______
__/__/__ __/__/__
________ ________
_______ _______
VMS ________ ________
_________ _________
________ ________
_______ _______
_______ _______
__/__/__ __/__/__
________ ________
_______ _______
ESD ________ ________
_________ _________
________ ________
_______ _______
_______ _______
__/__/__ __/__/__
________ ________
_______ _______
COMM ________ ________
Page 8 of 10
Document Responsibility: Process Control Standards Committee Issue Date: 11 July 2012 Next Planned Update: 11 July 2017
5.
SAEP-1638 Site Acceptance Test Plan
SYSTEM HARDWARE TESTING
The purpose of this section of the test is to ensure that all of the system hardware components are functioning properly. 5.1
SYSTEM POWER FAILURE Turn power off to all of the enclosures en closures and wait 30 seconds for the power to drain. Turn the power on to all of the enclosures and allow the system to boot. Verify that all of the modules pass their diagnostics and are running.
5.2
SYSTEM REDUNDANCY & FAIL-SAFE 5.2.1
POWER SUPPLIES Turn off the main power supplies and verify that the back-up power supply maintains power to all modules and that an alarm is generated to notify the operator that power has been disrupted. Carry out this test for all the the systems.
5.2.2
NETWORK The system monitor network display is used to monitor the current status of the network and stations. Test for switch over of the network by failing primary network. Ensure that network failure alarm is generated. Verify that communications are operative over the 2nd network by accessing displays and confirming proper data up dating. nd Repeat the test for 2 network.
5.2.3
FIELDBUS Perform the following procedure for each fieldbus isolator: Disconnect the network cable from a fieldbus that is currently transmitting and receiving messages. System alarm messages messages are reported following the the disconnection. Fieldbus modules automatically switch to the alternate network. Verify that the correct data value appears on the graphic as the input is varied.
5.2.4
DCS CONTROL PROCESSOR Perform the test to ensure that fault-tolerant control processor switches to its back up module and functions appropriately. Page 9 of 10
Document Responsibility: Process Control Standards Committee Issue Date: 11 July 2012 Next Planned Update: 11 July 2017
SAEP-1638 Site Acceptance Test Plan
Upon returning back online, the failed processor should become the back up. 5.2.5
PERIPHERAL DEVICES Verify that all peripheral devices function as expected.
5.2.6
FAT UNTESTABLE ITEMS Using FAT test procedures FAT untestable items needs to b e tested as planned by Saudi Aramco.
Page 10 of 10