Document Responsibility: Process Control Issue Date: 17 November 2007 Next Planned Update: 17 November 2009
1
SABP-Z-002 Functional Specifications for Process Control Systems
Introduction 1.1
Purpose The purpose of this document is to provide recommended guidelines for defining Functional Specifications and Scope of Work for a Process Control System (PCS) project. It is recommended that Project Teams use the appendices of this document as a starting point in the definition of the Process Control Systems required for their project. Items highlighted in “Red” color should be filled in with information specific to the project.
1.2
Scope The scope of this document is the definition of Functional Requirements and Scope of Work for Process Control Systems referenced in the attached appendices.
1.3
Intended Users This document is intended to be used by Saudi Aramco Project Management Teams (SAPMT) whom are working on projects which require Process Control Systems.
1.4
Disclaimer The use of this Best Practice does not relieve the engineer from his responsibility or duty to confirm and verify the acc uracy of any information presented herein. The use of this information or material does not guarantee results that will satisfy any applicable requirements of Saudi Aramco Standards. P&CSD assumes no responsibility or liability whatsoever for the misuse of the information in this document. This Best practice is intended as guidelines and shall not be considered as replacement for the Mandatory Saudi Aramco Engineering Requirements. Saudi Aramco® is a registered trademark of the Saudi Arabian Oil Company. Copyright, Saudi Aramco, 2007.
1.5
Conflicts with Mandatory Standards In the event of a conflict between this Best Practice and other Mandatory Saudi Aramco Engineering Requirement, the Mandatory Saudi Aramco Engineering Requirement shall govern.
Page 2 of 5
Document Responsibility: Process Control Issue Date: 17 November 2007 Next Planned Update: 17 November 2009
2
SABP-Z-002 Functional Specifications for Process Control Systems
References The latest edition of the following applicable codes, standards, specifications, and references in effect on the date of contract offer shall be used, except as otherwise specified. Short titles will be used herein when appropriate. 2.1
Saudi Aramco References Saudi Aramco Engineering Standards SAES-J-601
Emergency Shutdown and Isolation Systems
SAES-K-402
Centrifugal Compressors
SAES-Z-001
Process Control Systems
Saudi Aramco Materials System Specifications
3
23-SAMSS-010
Distributed Control Systems
23-SAMSS-020
Supervisory Control and Data Acquisition Systems
23-SAMSS-030
Remote Terminal Unit
34-SAMSS-623
Programmable Controller Based ESD Systems
34-SAMSS-820
Instrument Control Cabinets – Indoor
34-SAMSS-821
Instrument Control Cabinets – Outdoor
General Project specifications for Process Control Systems (PCS) should be dev eloped in a manor which separates the ‘Functional’ requirements from the a ctual Scope of Work for the project. For a majority of projects, the functional requirements for the process control system will not vary significantly. It is mainly quantities which will differ. By separating general functional / technical requirements from project specific / Scope of Work requirements; functional requirements which are generic and can be reused from project-to-project can be developed. Process & Control Systems Department have developed the generic functional requirements documents. These are contained in the attached appendices. The main responsibility of the project team is to develop the actual Scope of Work for the project. The appendices of this document should be used as a ‘Go-By’ for developing the project specific scope of work. This document along with the relevant generic functional specifications document and Saudi Aramco standards shall serve as the basis for procurement of the PCS.
Page 3 of 5
Document Responsibility: Process Control Issue Date: 17 November 2007 Next Planned Update: 17 November 2009
17 November 2007
SABP-Z-002 Functional Specifications for Process Control Systems
Revision Summary New Saudi Aramco Best Practice.
Page 4 of 5
Document Responsibility: Process Control Issue Date: 17 November 2007 Next Planned Update: 17 November 2009
SABP-Z-002 Functional Specifications for Process Control Systems
APPENDICES Ap pen di x SABP-Z-002A: Project Specif icatio n for PCS Scope of Work Ap pen di x SABP-Z-002B: Functi onal Specific ation for Proc ess Contro l Systems (PCS) and Integration Ap pen di x SABP-Z-002C: Functional Specification for Distribut ed Control Systems (DCS) Ap pen di x SABP-Z-002D: Functional Specification for Emergency Shutdown Systems (ESD) Ap pen di x SABP-Z-002E: Functional Specification for Compressor Control Systems (CCS) Ap pen di x SABP-Z-002F: Functional Specification for Data Acquisition and Historization Systems (DAHS) Ap pen di x SABP-Z-002G: Functional Specification for Alarm Management Systems (ALMS) Ap pen di x SABP-Z-002H: Functi onal Specific ation for System Design Document (SDD) Ap pen di x SABP-Z-002I: Functional Specification fo r Maintenance Training System (MTS) Ap pen di x SABP-Z-002J: Functi onal Specifi cation for Operator Trainin g System (OTS) Ap pen di x SABP-Z-002K: Functional Specification for Supervisory Control and Data Ac qu is it io n Sy st ems (SCADA ) Ap pen di x SABP-Z-002L: Functi onal Specif icatio n for Remote Termin al Unit (RTU)