Cilacap Resid Fluid Catalytic Crackin g (RFCC) (RFCC) Proj Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 2 / 47
METHOD STATEMENT FOR WORK OF INSUL INSUL ATION REVISION HISTORICAL SHEET Rev.
Page / Paragraph
Item
1
P6 / 7.1.1
7.1.2.2
P7 / 7.1.2
71.2.3 7.1.2.6 7.1.2.7
1
P7
7.1.3
1
P8
8.5
1
P6 / 7.1.2
9.2.6 9.2.12 9.2.14 9.2.15 9.5 9.6 9.7
Descr Descr ipt ion of Change Change Revised phrase as per Doc No. RFCC-C-CS-SP-002. Added phrase Revised Phrase as per Doc No. RFCC-C-CS-SP-002. Revised Phrase as per MOM No. RFCC-M-GC/PC-0108
1
P9 / 9.2
1
P9
1
P10
9.3.3
Added phrase “ho rizontal and vertical equip ment”
1
P10
9.3.8
Added phrase
1
P11
9.3.13
1
P12
9.5 9.6 9.7
1
P14
Revised Phrase as per MOM No. RFCC-M-GC/PC-0108
Added phrase
Revised Phrase as per MOM No. RFCC-M-GC/PC-0108 Added phrase Added JSA for Insulation Work Using Man Basket
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
METHOD STATEMENT FOR WORK OF INSULATION TABLE OF CONTENTS 1.
PURPOSE
2.
SCOPE
3.
REFERENCES
4.
DEFINITIONS
5.
RESPONSIBILITIES
6.
INSULATION CODES, TYPE & THICKNESS
7.
INSULATION MATERIALS
8.
EXTENT OF INSULATION
9.
APPLICATION PROCEDURE FOR INSULATION
10. INSPECTION AND REPORTING PROCEDURE 11. QA/ QC RESPONSIBILITY 12. HSE 13. JOB SAFETY ANAL YSIS FOR INSULATION WORK 14. ATTACHMENTS
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 3 / 47
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 4 / 47
METHOD STATEMENT FOR WORK OF INSULATION 1. PURPOSE
The purpose of this method statement is to ensure the insulation is carried out as per project specification and to facilitate to the execution team that they are using specified materials as it is required places. 2. SCOPE
The scope of this method statement is to define the guidelines/ procedures to carry out supply and application of Thermal Insulation and Cold Insulation works. Thermal Insulation works includes Hot Insulation works, Personnel Protection works, Electric Tracing and Steam Tracing works on various piping and equipment. All the insulation works shall be done in plant under construction or commissioning at Pertamina Resid Fluid Catalytic Cracking (RFCC) Project in Cilacap, Central Java, Indonesia. 3. REFERENCES
This method statement based on the following: 3.1 Project Specification No: RFCC-C-CS-SP-002. 3.2 Inspection and Test Plan No: RFCC-ITP-PA-0001. 4. DEFINITIONS 4.1
Owner The Owner means Indonesia PT. PERTAMINA (Persero), who is the owner of this project.
4.2. Contractor The Contractor is the employer for whom the sub-contractor is working in the case: ADHI-GS E&C CONSORTIUM. 4.3. Sub Contractor The Sub Contractor is the organization who is performing Insulation Works on this project for Contractor, in this case Sub Contractor is PT. KRAZU NUSANTARA.
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 5 / 47
METHOD STATEMENT FOR WORK OF INSULATION 5. RESPONSIBILITIES 5.1 Site Manager He will be responsible for overall control of work according to this approved method statement in line with requirement of Health, Safety and Environment. He will coordinate with client for the scheduling and progress of work. He will assist his site team for completing the scope as per project requirement. 5.2 Constr uct ion Manager He will be responsible for coordinate with the concerned supervisor and inspectors and to carry out the job as per schedule. 5.3 HSE Manager He will responsible for safe implementation of this method statement for completing the scope as per project Health, Safety and Security, environment requirement. 5.4 QA/QC Inspect or He will be responsible for maintaining the quality of work as per project specification, for the implementation of quality plan and the project requirement, and for the management of nonconformance and quality audit. As per Project Doc. No. RFCC-ITP-PA-0001. 5.5 Supervisor He will be responsible for day to day activity as per planning and instruction of Site Manager. Manpower and equipment planning, daily progress of work shall be his main responsibilities.
6. INSULATION CODES, TYPE & THICKNESS Category Hot service insulation
Cold service insulation Other service insulation
Insulation Codes Ih ST TW TO JW SJ ET C JC A P / Is M
Insulation Type Normal heat conservation insulation Steam tracing insulation Hot water tracing insulation Hot medium tracing insulation Hot water jacketing insulation Steam jacketing insulation Electric tracing insulation Normal cold insulation Cold medium jacketing insulation Anti-sweat insulation Personal protection insulation Dual temperature Service
Following insulation codes based on Project Spec. No. RFCC-C-CS-SP-002. Section 2.1.1
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 6 / 47
METHOD STATEMENT FOR WORK OF INSULATION 6.1
Thick ness In Drawing The insulation thickness as given in the isometrics drawing shall be considered as final and with cross reference with table 2 and 3 and based on this thickness, the work will be executed.
7. INSULATION MATERIALS
All the insulation materials following ref. Project Spec. No: RFCC-C-CS-SP-002. Section 3, insulation materials shall be part of material submittal and is to be approved by owner. The insulation materials delivered at site shall be inspected by QA/QC for it is package and damage conditions, batch no., manufactures certificate, storage and expiry, etc. and recorded in ITP for verification of owner. The materials to be used shall be follows: 7.1
HOT AND PERSONNEL PROTECTION INSULATION
7.1.1
1
7.1.2
1
1
Insul ation Material 7.1.1.1 Calcium silicate pipe section having density of 220 kg/m³, shall be used for piping NPS 2” and above refer Project Spec. No: RFCC-C-CS-SP-002 (ASTM C533, Type I). 7.1.1.2 Mineral wool blanket backed one side with galvanized mesh having density of min. 93 kg/m³ and max. 128 kg/m³ (ASTM C592, Type I, II & III) shall be used for equipment insulation with operation temperature up to 370° C and mineral wool blanket backed one side with stainless steel wire mesh shall be used above 370° C operating temperature and on austenitic stainless steel surfaces. 7.1.1.3 Mineral wool pipe section having density of min. 100 kg/m³, shall be used for piping size NPS 1.5” and below and for socket type (ASTM C547, Type II & III). 7.1.1.4 Ceramic fibre blanket having density 128 kg/m³ (ASTM C892, Type III Grade 8) shall be used for pipe and equipment with temperature above 700 °C. 7.1.1.5 Mineral wool blanket loose (ASTM C553 type VII). Jacketi ng Material The sheet metal jacketing shall be aluminum alloy sheet with moisture retarder which consist of polyethylene or polysurlyn. 1060 Al 99.5 with manganese composition limits max. 0.03. Or AA 3003 with manganese composition limits min. 1.0 and max.1.5 (per cent), and as per ASTM B209M and C1729 (refer Project Spec. No: RFCC-C-CS-SP-002, section 3.6). 7.1.2.1 Flat sheet with a minimum thickness of 0.3mm for insulation below NPS 30” (ASTM B209M). 7.1.2.2 Flat sheet with a minimum thickness of 0.4mm for insulation NPS 30” and above, and for equipment insulation with equipment OD below 760mm (ASTM B209M). 7.1.2.3 Flat sheet with a minimum thickness of 0.6mm for horizontal equipment insulation with equipment OD 760mm and above (ASTM B209M). 7.1.2.4 Flat sheet with a minimum thickness 0.8mm for valve and flange boxes NPS 10” and below (ASTM B209M). 7.1.2.5 Flat sheet with a minimum thickness of 1.0mm for valve and flange boxes NPS 12” and above (ASTM B209M). 7.1.2.6 Corrugated sheet with a minimum thickness of 0.6mm for vertical equipment insulation with equipment OD 760mm and above. (ASTM C1729).
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 7 / 47
METHOD STATEMENT FOR WORK OF INSULATION 7.1.2.7 1
7.1.3
1
7.2
Weather proofing mastic, for bottom head of small equipment, body of insulated valve 20” and above (Ih type only) and for unfitted metal jacketing portion.
Auxi li ary Materials 7.1.3.1 Galvanized tie wire swg #20 for fastening of insulation material NPS up to 12”, and galvanized tie wire swg #18 for fastening of insulation material NPS 14” up to 18”, with interval max. 300mm, for tacking of circumferential and horizontal of wire mesh blanket, and shall be used for floating ring of insulation. Stainless steel wire shall be used for fastening insulation material to austenitic stainless piping and equipment. 7.1.3.2 Galvanized strapping band 13 X 0.4mm and wing seal for fastening of insulation material for NPS 20” and above, and for cylindrical equipment with OD below 760mm. Galvanized strapping band 19 X 0.5mm and wing seal for fastening of insulation material for cylindrical equipment with OD 760mm and above. 7.1.3.3 S/s strapping band 13 X 0.4mm and wing seal for fastening jacketing material for all piping, and equipment OD below 760mm. S/s strapping band 19 X 0.5mm for fastening jacketing equipment with OD 760mm and above. 7.1.3.4 S/s self tapping screws as per ASTM A167, 4.8 X 13mm and 4.8 X 19mm for fittings area and equipment jacketing securing. 7.1.3.5 C/s flat bar 30 X 3mm for insulation support ring of vertical pipe and equipment. 7.1.3.6 Blind rivets aluminum 2 X 10mm. 7.1.3.7 Silicone sealant for metal jacketing 7.1.3.8 G/i and s/s bolts and nuts M8. 7.1.3.9 Glass cloth (10 X 10 mesh) for application weather proofing mastic. 7.1.3.10 Glass fiber tape/ ceramic rope (for loop of tracer lines and Instrument tubing insulation). 7.1.3.11 Aluminum foil sheet 20µ and aluminum foil tape (Jacketing of instrument tubing insulation). 7.1.3.12 S/s toggle clips shall be used for valve and flange removable boxes according to size. 7.1.3.13 S/s 304 welded wire mesh 25 X 25 X 3mm for wire mesh barrier of personnel protection on austenitic stainless steel surface. 7.1.3.14 S/s 304 flat bar 30 X 3mm for support ring wire mesh barrier of personnel protection on austenitic s/s stainless steel surface. 7.1.3.15 Insulating cement for filling gap of calcium silicate (gap above 3mm shall be filled by insulating cement) COLD INSULATION & ANTI-SWEAT INSULATION
7.2.1
Insul ation Material 7.2.1.1 PIR (Polyisocyanurate) performed pipe section in green & or natural color with density min. 40 kg/m 3. 7.2.1.2 Rigid preformed cellular urethane with density min. 40 kg/m 3. 7.2.1.3 Mineral wool blanket loose (ASTM C553 type VII).
7.2.2
Aux ili ary Material 7.2.2.1 S/s strapping band 13 X 0.4mm and 19 X 0.5mm.
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 8 / 47
METHOD STATEMENT FOR WORK OF INSULATION 7.2.2.2 7.2.2.3 7.2.2.4 7.2.2.5 7.2.2.6 7.2.2.7 7.2.2.8 7.2.2.9
Joint sealant. Vapor stop (mastic, foam seal, bond) Glass cloth (10 X 10 mesh) Multi flex foil 50µ. (vapor barrier) Multi flex tape 50mm wide. Butyl rubber sheet 1mm. Butyl rubber gum tape 1mm. Filament tape wide 25mm
8. EXTENT OF INSULATION
1
Extent of insulation following ref. Project Spec. No: RFCC-C-CS-SP-002. Section 2: 8.1 Name plates and stamping shall be left clear of insulation or shall be fitted on outside of the jacketing. 8.2 Expansions/ construction joints. 8.3 Pumps area. 8.4 Compressors and auxiliary boilers 8.5 Insulation of valves and flanges box cover in insulated piping for steam lines service and steam tracing lines service (ST). For valves of insulated line (Ih) 20” and above, body of valve shall be insulated with mineral wool blanket with galvanized mesh, covered with glass cloth and weather proofing mastic.
9. APPLICATION PROCEDURE FOR INSULATION 9.1 9.1.1 9.1.2 9.1.3 9.1.4 9.1.5 9.1.6 9.1.7 9.1.8
General Appl icati on Procedur e
Check that the surface to be insulated are clean, dry and free from dust, dirt, grease and oil. The surround area is free from obstacles and debris. Verify insulation system is defined on the work release and attached working isometric or drawing and suitable against the referred temperatures and process class. Check the insulation materials are of the correct type and size for application as per project specification. All calcium silicate and mineral wool pipe section shall be visually checked to ensure edges are not damaged. Damaged area shall be cut back neatly prior to use, wherever practical. Where insulation is secured using wire, the cut ends shall be twisted and turned into the insulation. Fabrication of insulation and jacketing materials shall take place under controlled conditions in suitably equipped workshop situated on the project. Without exception, activities in the field shall commence only after the issue of necessary work permit and TBM. Insulation works shall not be started until it has been ascertained that all appropriate testing has been completed and application of the specified protective coating system is completed and that any damaged areas have been properly repaired.
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 9 / 47
METHOD STATEMENT FOR WORK OF INSULATION 9.1.9 The insulation shall only be started from mechanical and piping team. 9.2 Insul ation for Hot Insulat ion and Person nel Protect ion Codes Ih, ST, JW, SJ, ET, P / Is 9.2.1 9.2.2 9.2.3
9.2.4 9.2.5 9.2.6 1
9.2.7 9.2.8
9.2.9 9.2.10 9.2.11 9.2.12 1
9.2.13
9.2.14 1
9.2.15
The insulation code and thickness shall be verified from isometric drawing or from project specification No. RFCC-C-CS-SP-002. For pipe NPS 1.5” and below, insulation shall be used mineral wool pipe section, and NPS 2” and above insulation shall be used calcium silicate pipe section. On vertical pipe length approximately 4000mm shall be fixed with one support ring for insulation material and fabricated with c/s flat bar 30 X 3mm. And expansion joint with mineral lose wool shall be located under support ring. Support rings shall be isolated with direct contact of pipe or equipment by means glass fiber tape to prevent damage on pipe surface. Piping at slope between 45 o and 90o shall be considered as vertical. Mineral wool pipe section for NPS 1.5” and below (socket type) and calcium silicate pipe sectio n for NPS 2” up to 12” shall be secured with galvanized tie wire swg #20. For 14” up to 18” shall be secured with galvanized tie wire swg #18. Galvanized strapping band 13 X 0.4mm for pipe NPS 20” and above. wire and bands shall be located approximately 50 mm from the end of each section and at center interval of max. 300 mm. Bands shall be machine tensioned, tig htened and sealed. Longitudinal and circumferential joints in outer layers of multiple layer installations shall be sta ggered from those in adjacent inner layer. The insulation for calcium silicate shall include contraction joints as per project specification wi th max. 5700mm spacing for horizontal straight pipe or centre between two pipe shoe or as sp ecified by the vendor design on calculation. Construction joint space is 25mm and filling with mineral loose wool. In case of exposed area in tracer pipe it shall be wrapped with 30 X 3mm glass fiber tape or rope and covering with aluminum foil sheet and foil tape. Insulation on steam traced lines shall be oversized preformed calcium silicate pipe sections arranged to enclose both the line and its accompanying tracer. Bolt clearance shall be maintained on both side of flange, and minimum clearance shall be bolt + 50mm at least one side as per site condition. For equipment insulation shall be used by mineral wool blanket with galvanized wired mesh as per ASTM C592 Type I, II & III for temperature up to 370 oC, and mineral wool blanket with s/s wired mesh for equipment temperature above 370 oC and on austenitic stainless steel surfaces. For alternate insulation material is mineral wool board as per ASTM C612 type II and IV (Project Specification No. RFCC-C-CS-SP-002) In case of equipment Four Stage Cyclone Separator (101-V-511) with temperature 709 oC, insulation shall be covered with ceramic fiber blanket with density 128 kg/m³ as per ASTM C892 Type3 Grade 8. Insulation thickness 150mm with 6 layers of 25mm thickness ceramic fiber blanket, for 1 st, 2 nd, 4th, 5 th layer shall be secured with s/s 304 tie wire and for 3 rd and 6th layer shall be secured with s/s strapping band 19 X 0.5mm. Equipment insulation shall be secured with galvanized band 13 X 0.4mm for OD below 760mm, and galvanized band 19 X 0.5mm for OD 760mm and above , machine tensioned and sealed. Band shall be positioned at max. 300mm spacing centre on vertical equipment and horizontal equipment to avoid loosening of blanket. The adjacent joints of blankets shall be tack stitched with galvanized wire swg #18 or #20.
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 10 / 47
METHOD STATEMENT FOR WORK OF INSULATION 9.2.16 Insulation at equipment flanges shall be stopped short of the bolts. The bolt removal clearance left for all flanged equipment connections. The clearance at equipment shall be nut length plus 50mm. 9.2.17 Where the bending radius is too small to be neatly segmented, insulation shall be fitted in Tee piece form to receive metal jacketing. 9.2.18 Equipment insulation work shall start after completion of external mechanical work done. 9.2.19 Installation insulation shall be done before equipment installation if required. 9.2.20 Instrument tube shall be insulated with glass fiber tape or ceramic rope as per thickness requirement and shall be covered with aluminum foil sheet and shall be fastened with aluminum tape. 9.2.21 All insulation activities shall be completed in one day, if this is impossible, the insulation shall be covered temporarily with water proof film/ plastic, to be sealed at the outer ends of water resistance.
9.3 9.3.1
9.3.2
9.3.3 1
9.3.4 9.3.5 9.3.6 9.3.7
9.3.8 1
Jacketing Procedure of Piping & Equipment
The metal jacketing to be used over insulated piping, fittings and equipment shall be aluminum alloy sheet with moisture retarder which consist of polyethylene or polysurlyn 1060 Al 99.5 with manganese composition limits max. 0.03. Or 3003 with manganese composition limits min. 1.0 and max.1.5 (per cent ) and as per ASTM B209 and ASTM C1729. For pipe jacketing with flat sheet with moisture retarder which consist of polyethylene or polysurlyn 1060 Al 99.5 with manganese composition limits max. 0.03. Or 3003 with manganese composition limits min. 1.0 and max.1.5 (per cent ) and minimum thickness 0.3mm for pipe below NPS 30”, and minimum thickness 0.4 for NPS 30” and above. For vertical equipment jacketing with corrugated sheet with moisture retarder which consist of polyethylene or polysurlyn. 1060 Al 99.5 with manganese composition limits max. 0.03. Or AA 3003 with manganese composition limits min. 1.0 and max.1.5 (per cent ) with deep corrugated dimension 1-¼”x ¼” (32mmX6.3mm) and minimum and minimum thickness 0.6mm for OD 760mm and above. And OD below 760mm jacketing material shall be used flat sheet with minimum thickness 0.4mm. Overlaps of minimum 50mm shall be provided on circumferential and longitudinal joints. All jacketing shall be installed in watershed manner. Longitudinal seams of horizontal piping shall be staggered at 3 O’clock and 5 O’clock. Horizontal seams shall be concealed from view from the sides of pipe rack or pipe track. Longitudinal seams on vertical pipe jacketing shall be staggered and placed away from the prevailing wind direction. On piping jacketing circumferential lap joints shall not be screw fastened, piping shall be secured with s/s bands only, with 13 X 0.4mm for all piping, and shall be positioned at each overlap and at max. 300 mm centers interval. S/s self tapping screw shall be applied only for fittings area. S/s strapping band shall be applied on circumferential equipment jacketing with max. 300mm centers interval, on vertical equipment s/s strapping band shall be secured with ”J” clips to prevent loosing on circumferential. S/s 304 self tapping screws shall be used for securing the equipment jacketing at max. 150mm centers for equipment, every longitudinal and circumferential overlap.
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 11 / 47
METHOD STATEMENT FOR WORK OF INSULATION 9.3.9
9.3.10
9.3.11
9.3.12 9.3.13 1
9.3.14
9.3.15 9.3.16
9.3.17 9.3.18 9.3.19 9.3.20 9.3.21
9.4 9.4.1 9.4.2 9.4.3 9.4.4 9.4.5
Fabrication of elbows/ bends shall be swage in swage for OD up to 600mm, and for above OD 600mm with overlap, each segment shall be secured by s/s 304 self tapping screws with minimum two screws per segment along the longitudinal seam. Caps end shall be installed at insulation terminations. These shall be by disc and swage up to OD 200mm over insulation, and lock formed for insulation OD above 200mm. cap ends on vertical pipe shall be lock formed and conical to provide watershed. “S” clips fabricated from s/s 304 13 X 0.4mm or 19 X 0.5mm strapping band shall be introduced between individual length of metal jacketing on vertical pipe and vertical equipment to prevent telescoping. Metal jacketing shall be installed in watershed manner at all times. The cutted side shall be sealed by the application of a metal silicone sealant. Removable Metal box insulation shall be used for valves and flanges for steam lines service and steam tracing lines service. For valve size 20” and above shall be insulated on body valve only with mineral wool blanket with galvanized mesh, covered with glass cloth and weather proofing mastic (Ih code only) Removable Box shall be fabricated with thickness 1.0mm flat aluminum sheet for NPS 12” and above, thickness 0.8mm flat aluminum sheet for NPS 10” and below, box shall be riveted to the inside of the boxes with pop rivets and screws, and shall be incorporated circumferential and longitudinal lock seams. Removable type metal box shall be pre insulated inside with mineral wool blanket secured with pins or clips and the thickness insulation shall be same of pipe or equipment. Boxes shall be fastened by s/s 304 type quick release toggle fasteners. Toggle shall be minimum two numbers on each side of over laps, additional toggles shall be installed where necessary to neatly and firmly close the box with good seal. Personnel protection with steel welded wire mesh barrier shall consist of physical barriers shall extend to a height of 2000mm and 600mm either side of working platform or walking level. Spacing requirements for shields and cages shall be 50mm minimum, but shall not be less than the heat conservation insulation thickness. Gusset plate and steel ring shall be fabricated of cs or s/s 304 size 30 X 3mm and 25 X 25 X 3mm s/s welded wire mesh shall be installed. Gusset plate shall be isolated with direct contact of pipe or equipment by means of glass fiber tape to prevent damage to pipe surface. For jacketing at small bottom head equipment shall be wrapped with weather proofing mastic.
Insulation for Cold Insulation and Anti-Sweat Insulation Codes C, JC and A
Piping and equipment shall have all welding completed and shall be hydrostatically or pneumatically tested prior to application of insulation. For cold insulation it is essential that no water or water vapour penetrates in to the insulation. For cold insulation preformed PIR section shall be used according to table 3 of Spec No.RFCC-C-CS-SP-002. For piping and large cylindrical surfaces insulation preformed cylindrical section or segments shall be used. Vapor stop shall be installed at all pipe supports locations and applied between the pipe and insulation termination. Application shall be extended over the roughened pipe surface for
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 12 / 47
METHOD STATEMENT FOR WORK OF INSULATION
9.4.6 9.4.7 9.4.8
9.4.9 9.5 9.5.1 9.5.2
9.6
50mm. All vapor stops shall start from pipe or equipment surface and to step upward to outer surface to insulation with reinforcing membrane with a minimum overall DFT of 2mm. No reinforcement is required on underside of insulation to a depth of 50mm. Insulation shall be installed after vapor stops becomes dry to touch. Adhesive shall be coated on the dried vapor stop coating for the adjacent outer most layer joint of PIR. In multilayer system, in addition to the primary vapor barrier a secondary vapour barrier shall be applied between the outermost layer and the next insulation layer. The insulation system shall include contraction joints as per project specification. All insulation materials applied in one day shall have the vapor barrier applied the same day. If it is found impracticable to apply the vapor barrier, exposed insulation shall be temporarily protected with a black polyethylene sheet. For jacketing on cold insulation shall be done same system with hot insulation jacketing. Insulation Applicatio n for Piping
Piping insulation shall be done before pressure test except the welding joints on safe working condition. Welding joints in insulation application will be done after pressure test with safe working conditions (i.e. scaffolding, man lift, man basket with approval safety) Insulation Applicatio n for All Equipment
1
9.6.1 9.6.2 9.7 9.7.1 9.7.2
Equipment insulation work shall be done after completion of external mechanical work done. Insulation shall be done before equipment installation on ground if required. Rework on Damage or Open Portion for Piping and Equipment
Damaged insulation and open portion will be checked for extent of damage or open portion and shall be re-insulated with the same specification as required for the piping and equipment. Insulation will be done using scaffolding, man lift or man basket with safety approval.
10. INSPECTION AND REPORTING PROCEDURE
The QA/QC operative on site will carry out periodic and stage wise inspection. Once QA/QC operative is satisfied in all respects with the work, he shall offer the area to Contractor/ Owner for inspection. Inspection will be carried out as per the Inspection and Test Plan. The inspection report with all the finding shall be recorded and signed with all parties in the reporting formats in ITP (Project Doc. No. RFCC-ITP-PA-0001). 11. QA/QC RESPONSIBILITIES
All the insulation works on the project will be under QA/QC operative and main contractor inspection department. The QA/QC operative will be responsible for overall quantity of the work according attached ITP (Doc No. RFCC-ITP-PA-0001) and will fill all the relevant inspection forms which shall be signed off by each party. His specific responsibilities will include:
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 13 / 47
METHOD STATEMENT FOR WORK OF INSULATION 11.1 11.2 11.3 11.4 11.5 11.6
Ensure all the materials for the project are strictly in accordance with the specifications & WMS. Ensure correct materials are used for application. Delivery notes & test certificates/ certificate of compliance shall be reviewed during material inspection. inspected materials shall be used for site work. Inspect workmanship of work in progress, ensure all tools and equipments are in good condition. Responsible for recording on inspection findings and maintaining them for each item to obtain final completion certificate. Strictly follow ITP of the work and report management for any shortfall and non conformance report.
12. HSE
Full care and precaution shall be given by the field management for the safety and sanitation of the manpower in the field to prevent accident during the execution of works. Refer to the site safety for general site control. One of the main aspects of this procedure is Safety and Health Control. This is to control the prevention of incidents, personal injuries as well as damage to equipment and properties during the entire construction period. In order to ensure a safe working environment during the entire construction period, the following safety measures shall be implemented as follows: 12.1 12.2 12.3
12.4
12.5 12.6 12.7 12.8 12.9
All personnel involved in the insulation and other related activities should be inducted as per contractor/ owner safety requirement. Administrative control shall be applied for use to reduce the potential summer season. Provision of rest shelters/ recovery area or stand by vehicle for each group. Each worker shall be provided with drinking water during hot weather conditions during working hours. Toilet with urinal and wash area shall be provided. Drinking water station shall be in place with cold water. All workers shall be provided with and wear Personnel Protective Equipment ie. safety helmet, safety glasses (clear & dark), safety shoes/ boots and wear long sleeve shirt/ jacket or coveralls. Additional PPE requirements shall be provided to workers as work scope dictates ie. face shield (welding/ grinding/ fabrication), respiratory protection (dust mask/ respirator), full body harness (FBH) when working at height and as per MSDS requirements. All waste material will be collected on regular basis to be stacked in a designated location at site, this material should be removed periodically from site. Sufficient number of toilet units provided for workers in line with project regulations and units maintained in hygienic condition. All equipment should be inspected and approved by HSE officer of GS E&C. Tool box meeting shall be arranged before work activity and the same should be recorded. The work site should always be maintained clean and tidy.
13. JOB SAFETY ANAL YSIS FOR INSULATION WORK
As per attachment #1
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero)
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 14 / 47
METHOD STATEMENT FOR WORK OF INSULATION
14. ATTACHMENTS No.
1 1
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Descr ipt ion
Job Safety Analysis for Insulation Job Safety Analysis for Insulation Work Using Man Basket Insulation Thickness for Hot Service (Mineral Wool) Insulation Thickness for Hot Service (Calcium Silicate) Insulation Thickness for Hot Service (Ceramic Fiber + Calcium Silicate) Insulation Thickness for Personnel Protection (Mineral Wool) Insulation Thickness for Personnel Protection (Calcium Silicate) Insulation Thickness for Cold and Anti-Sweat Insulation Inspection and Test Plan Inspection Format Forms Typical Details For Piping Insulation Typical Details For Valve Insulation Flange Insulation And Insulation Support Ring Details Insulation Details at Pipe Support Vertical Vessel Insulation (Blanket Insulation) Vertical Vessel Insulation (Block Insulation) Horizontal Vessel Insulation (Blanket Insulation) Horizontal Vessel Insulation (Block Insulation) Heat Exchanger Insulation Insulation Details For Vertical Vessel Head Flashing Details At Nozzle And “S” And “J”-Clip Details Wire Mesh Barrier for Personnel Protection Details Removable Insulation Cover for Pumps (Hot Insulation) Insulation for Body of Valve 20” and Above (“Ih” Insulation only)
CONSORTIUM ADHI – GS E&C
Reference
Attachment #1 Attachment #2 Table 2 (1) Table 2 (2) Table 2 (3) Table 2 (4) Table 2 (5) Table 3 Attachment #3 Attachment #4 Attachment #5 Attachment #6 Attachment #7 Attachment #8 Attachment #9 Attachment #10 Attachment #11 Attachment #12 Attachment #13 Attachment #14 Attachment #15 Attachment #16 Attachment #17 Attachment #18
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 15 / 47
METHOD STATEMENT FOR WORK OF INSULATION Att achm ent #1.
JOB SAFETY A NAL YSIS FOR INSULATION
Prepared by:
Afendi Muslim
Approved by:
Cho In Seok
Reviewed by:
Yanam
Date
20 August 2013
Step No. 1
Description of Task Step Insulation Fixing & Removal
Control Measures/ Preventive Measures
Hazard Calcium Silicate, Glass wool. Sharp Objects. Dust. Skin Irritation.
•
•
•
•
•
•
•
•
•
Falling object.
•
•
Flammable gasses
•
•
Inadequate access
• •
•
2
Fabrication Shop
• • • • •
Working at height Pinch point Sharp object Electrical tools Slip, trip and fall Machinery equipment
:
•
• • • • •
Proper PPE as per MSDS. Wear proper hand gloves, proper manual handling. Wear proper dust mask, good housekeeping. Agreed Lay down area for storage, proper PPE as per MSDS. Secure all loose insulation at storage area from high wind, secure all tools during working at height. Gas testing to be done at the start of insulation work on any line containing flammable gasses . Make sure that adequate access is available. If scaffold is used for access it should be inspected by a certified scaffolding inspector & scaff-tag should be installed 100% tied off full body harness. Wear proper hand gloves Proper manual handling, wear proper hand gloves Isolate power cable, secure with Lock Out Tag Out. Proper material arranging and good housekeeping. Equipment certification and Fire Extinguisher
CONSORTIUM ADHI – GS E&C
Responsible Person
• • • •
Worker Worker Worker Worker
Worker
•
•
Authorized gas tester
Worker Scaffolding Inspector
• •
Worker
•
• • • • •
Worker Worker Worker Worker Safety Officer
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 16 / 47
METHOD STATEMENT FOR WORK OF INSULATION Step No. 3
Description of Task Step Using Foam Spray for Insulation
Control Measures/ Preventive Measures
Hazard
• •
• •
Chemical (Polyol + Iso-cyanide, Polyurethane) Pressured Injection gun Foaming machine
• • • • •
•
4
Wasting Insulation Material (Hazardous Substances)
•
Health Impairment
•
•
Fire / Explosion
•
•
•
Environmental Impact
•
•
Proper Gun maintenance Fire Extinguisher Wear proper PPE as per the MSDS (mater Workers should not play around with the tools Only competent workers are allowed to use the pressurized injection gun Operators must read the manufacturers for using the foaming machine Assessment on the hazards and risk to health by potentially harmful substances shall be carried out. Shall detail the control measures that will be taken to reduce risk to health. MSDS and assessment of the risk and necessary control measure shall be in place prior to the work being carried out. Personnel shall be instructed to take appropriate precautions to protect their health from the hazards. Training shall be given in the correct use and maintenance of PPE. Hazardous substances shall be stored in a safe manner. Materials shall be segregated in accordance with good practice, e.g. Keeping oxidizing and reducing agent apart. Contingency arrangements shall be in place to initiate the spillage of any hazardous substances.
CONSORTIUM ADHI – GS E&C
Responsible Person Worker Safety Officer Worker Worker Worker
• • • • •
Worker
•
•
Worker & Safety Officer
•
Worker & Safety Officer
•
Worker & Safety Officer
•
Worker & Safety Officer
•
Worker & Safety Officer
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 17 / 47
METHOD STATEMENT FOR WORK OF INSULATION Step No. 5
Description of Task Step House Keeping
Control Measures/ Preventive Measures
Hazard •
Can occur when particles of dust, debris or grit, etc. Are blown around the workplace or when such particles are dislodged from work areas above. I.e. from scaffolding
•
•
•
Personnel shall ensure that the highest levels of housekeeping are maintained at all times. The company operates a mandatory “Eye Protection” policy on all project locations. Personnel shall adhere to this strict policy at all times. Supervisors shall monitor the standards of housekeeping on a daily basis to ensure that they are acceptable and implement routine “Clean Ups” where necessary.
CONSORTIUM ADHI – GS E&C
Responsible Person Worker
•
Worker
•
Supervisor
•
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 18 / 47
METHOD STATEMENT FOR WORK OF INSULATION 1
Att ach ment #2.
JOB SAFETY A NALYSIS FOR INSULATION WORK USING MAN BASK ET
Prepared by:
Afendi Muslim
Approved by:
Cho In Seok
Reviewed by:
Yanam
Date
11 January 2014
Step No. 1.
Description of Task Step Insulation Fixing & Removal
Control Measures/ Preventive Measures
Hazard Inexperienced or incompetent operator/ riggers
Faulty lifting equipment
:
Crane Operators and Riggers shall be certified by Third Party Inspection and competent enough to perform Lifting Operations. Other personnel may assist in rigging operations (if experienced) however a Rigger shall examine all rigging prior to commencing a lift. Toolbox talks shall be held prior to all major or unusual lifts to ensure that all personnel are aware of the operations.
Responsible Person HSE Officer
•
•
•
•
•
•
Visually inspect all equipment priors to use to ensure it is free from any defects / Leaks and or damage. Color Coding and all test certificates by Third Party Inspection on Man-basket / Equipment shall be checked to ensure they are current. Ensure that the number of Person(s) allowed in Manbasket is stenciled on its side. All equipment shall be of adequate rating to perform operations. Any damaged equipment shall be quarantined and
Crane Operator/ Rigger
HSE Officer
Crane Operator/ Rigger
•
•
•
•
•
•
Crane Operator/ Rigger
•
•
Crane Operator/ Rigger
•
•
Crane Operator/ Rigger
CONSORTIUM ADHI – GS E&C
HSE Officer
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 19 / 47
METHOD STATEMENT FOR WORK OF INSULATION Step No.
Description of Task Step
Control Measures/ Preventive Measures
Hazard
reported to your Supervisor immediately. Outriggers shall be properly extended, set and locked where locking devices are provided. All equipment shall be properly maintained and inspected on a weekly basis.
Personnel injuries
Uncontrolled lifts
Responsible Person
•
•
Crane Operator/ Rigger
•
•
HSE Officer/ Inspector
Leather Hand Gloves shall be worn at all times to protect the hands during lifting operations Workers shall wear Full Body Harness, which is connected to the lifeline that is attached to the Crane hook prior to lift. Loads or Man-basket shall not be moved or swing on top of workers. Workers shall use Grab Bar and keep all parts of their body inside the man-basket during Hoisting, Lowering and Positioning. The Crane Operator shall never leave the crane controls unattended while personnel are still working or the man-basket is suspended.
Worker
•
•
•
•
•
•
•
•
•
•
Single point lifting shall be avoided wherever possible If direct lifting is not possible, use of Taglines shall be utilized to avoid the load from swinging. Lifting/ rigging operations shall be carried out from approve codes of practice. Short cuts causes accidents, do not take risks
Worker
Crane Operator/ Rigger
Worker
Crane Operator/ Rigger
•
•
•
•
Crane Operator/ Rigger Crane Operator/ Rigger
•
•
Crane Operator/ Rigger
•
•
CONSORTIUM ADHI – GS E&C
Worker
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 20 / 47
METHOD STATEMENT FOR WORK OF INSULATION Step No.
Description of Task Step
Control Measures/ Preventive Measures
Hazard
Barricade the area prior to commencing operations. A qualified signal person must be in the basket at all times when transporting personnel Where applicable, Method Statement shall be read to establish specific precautions necessary to the operations
High winds
Responsible Person
•
•
•
•
•
•
Maximum Wind velocity (25 Knots) must be considered during lifting operations. Check approved Anemometer wind velocity reading from the client. Slings and other lifting materials shall be inspected regularly from defects and properly tagged for colorcoded. Lifting operations shall be closely monitored and supervised by trained and competent Riggers
Crane Operator/ Rigger Crane Operator/ Rigger
All parties
•
•
Crane Operator/ Rigger
•
•
Crane Operator/ Rigger
•
•
HSE Officer/ Inspector
•
•
Crane Operator/ Rigger
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 21 / 47
METHOD STATEMENT FOR WORK OF INSULATION Table 2 (1) Insulation Thickness for Hot Service (Mineral Wool) Unit: mm SIZE
1/2
3/4
1
1.1/2
2
2.1/2
3
4
6
8
10
12
14
16
18
20
22
24 PLANE
100
25
25
25
25
25
25
25
25
30
30
30
30
30
40
40
40
40
40
40
150
25
25
25
25
25
30
30
30
40
40
40
40
40
40
40
50
50
50
50
200
25
25
25
30
30
40
40
40
40
50
50
50
50
50
50
50
50
50
65
250
25
30
30
40
40
40
40
50
50
50
50
65
65
65
65
65
65
65
75
300
30
30
40
40
40
50
50
50
65
65
65
65
65
65
75
75
75
75
90
350
30
40
40
50
50
50
50
65
65
65
75
75
75
75
75
75
75
75
90
400
40
40
50
50
50
65
65
65
75
75
75
75
75
90
90
90
90
90
100
450
40
50
50
50
65
65
65
75
75
90
90
90
90
90
100 100 100 100
115
500
so
50
50
65
65
75
75
75
90
90
100 100
90
100 100 100 100 115
125
550
50
50
65
6S
75
75
75
90
100 100 100 100 100 115 115 115 115 115
140
600
50
65
65
75
75
75
90
90
100 100 115 115 100 125 125 125 125 125
150
650
65
65
65
75
75
90
90 100 100 115 115 115 125 125 125 140 140 140
150
TEMP.
Notes : Density : As per ASTM Code. 128kg/m3 Max. - 93kg/m3 Min. (blanket ) ASTM C592 Type III 128kg/m3 Min.(board/slab) ASTM C612 Class II & IV 100kg/m3 Min. (pipe cover) ASTM C547 Class II & III
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 22 / 47
METHOD STATEMENT FOR WORK OF INSULATION Table 2 (2) Insulation Thickness for Hot Service (Calcium Silicate) Unit: mm SIZE
1/2
3/4
1
1.1/2
2
2.1/2
3
4
6
8
10
12
14
16
18
20
22
24 PLANE
100
25
25
25
25
25
25
25
25
30
30
30
30
30
40
40
40
40
40
40
150
25
25
25
25
25
30
30
30
40
40
40
40
40
40
50
50
50
50
50
200
25
25
25
30
30
40
40
40
40
50
50
50
50
50
50
50
50
50
65
250
30
30
30
30
40
40
40
50
50
50
50
50
65
65
65
65
65
65
75
300
30
30
30
40
40
50
50
50
50
65
65
65
65
65
65
65
65
75
75
350
30
30
40
40
50
50
50
50
65
65
65
75
75
75
75
75
75
75
90
400
40
40
40
50
50
50
50
65
65
75
75
75
75
75
75
75
90
90
100
450
40
'40
50
50
50
65
65
65
75
75
75
75
90
90
90
90
90
90
100
500
40
40
50
50
65
65
65
75
75
75
90
90
90
90
90
100 100 100
115
550
50
50
50
65
65
65
65
75
75
90
90
90
100 100 100 100 100 100
125
600
50
50
50
65
65
75
75
75
90
90
100
100 100 100 100 100 115 115
125
650
50
50
65
65
65
75
75
75
90
100 100
100 100 115 115 115 115 115
140
TEMP.
Notes : Density : As per ASTM C533 type I 220 kg/m³ Table 2 (3) Insulation Thickness for Hot Service (Ceramic Fiber + Calcium Silicate) (Temp. maximum 750 °C) PIPE SIZE
1st layer
2nd layer
(inch )
Ceramic Fiber
Calci um Silic ate
1"
25mm
40mm
1.5"
25mm
50mm
3"
25mm
50mm
30"
50mm
50mm
Plane
150mm
-
Remarks
For 4TH Stage Cyclone Separator
(1) Ceramic fiber Use of Density 128 kg/m³ (ASTM C892 Type3 Grade 8). (2) Maximum Thickness of Ceramic Fiber Blanket 25mm. (3) If the thickness required to 50mm, use of Two layer.
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 23 / 47
METHOD STATEMENT FOR WORK OF INSULATION Table 2 (4) Insulation Thickness for Personnel Protection (Mineral Woo l) Unit · mm SIZE
1/2
3/4
1
1.1/2
2
2.1/2
3
4
6
8
10
12
14
16
18
20
22
24
PLANE
100
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
150
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
200
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
250
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
300
25
25
25
25
30
30
30
30
30
30
40
40
40
40
40
40
40
40
40
350
30
30
30
40
40
40
40
40
40
40
40
50
50
50
50
50
50
50
50
400
40
40
40
40
40
50
50
50
50
50
50
65
65
65
65
65
65
65
65
450
40
40
50
50
50
50
65
65
65
65
65
65
65
65
65
65
65
75
75
500
50
50
50
65
65
65
65
65
75
75
75
75
75
90
90
90
90
90
90
550
65
65
65
65
65
75
75
75
90
90
90
90
90
90
100 100 100 100
115
600
65
65
65
75
90
90
90
90
100 100 115 115 115 115 115 115 115 115
140
650
75
75
75
90
90
90
100 100 115 115 115 125 125 125 125 140 140 140
165
TEMP.
Notes : Density : As per ASTM code 128kg/m3 Max. - 93kg/m3 Min. (blanket ) ASTM C592 Type III 128kg/m3 Min.(board) ASTM C612 Class II & IV 100kg/m3 Min. (pipe cover) ASTM C547 Class II & III
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 24 / 47
METHOD STATEMENT FOR WORK OF INSULATION Table 2 (5) Insulation Thickness for Personnel Protection (Calcium Silicate) Unit · mm SIZE
1/2
3/4
1
1.1/2
2
2.1/2
3
4
6
8
10
12
14
16
18
20
22
24
PLANE
100
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
150
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
200
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
250
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
300
25
25
25
25
25
25
30
.30
30
30
30
30
30
30
30
30
30
30
40
350
25
25
30
30
30
40
40
40
40
40
40
40
40
40
40
40
40
40
40
400
30
30
40
40
40
40
40
40
50
50
50
50
50
50
50
50
50
50
50
450
40
40
40
40
40
50
50
50
50
50
65
65
65
65
65
65
65
65
65
500
40
40
50
50
50
50
50
65
65
65
65
65
65
65
65
65
65
65
75
550
50
50
50
50
65
65
65
65
65
65
75
75
75
75
75
75
75
75
90
600
50
50
65
65
65
65
65
65
75
75
75
75
75
90
90
90
90
90
100
650
50
65
65
65
65
75
75
75
90
90
90
90
90
90
90
100 100 100
115
TEMP.
Notes : Density : As per ASTM C533 type I 220 kg/m³
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 25 / 47
METHOD STATEMENT FOR WORK OF INSULATION Table 3. Insulation Thickness for Cold and Anti-Sweat Insulation Unit· mm 1/2
3/4
1
1. 1/2
2
2. 1/2
3
4
6
8
10
12
14
16
18
20
24
26
30
36
42
48
PLANE
10
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
5
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
30
0
25
25
25
25
25
25
25
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
35
-5
25
25
25
30
30
30
30
30
35
35
35
35
35
35
35
35
35
35
35
35
35
35
40
-10
25
30
30
30
30
35
35
35
35
40
40
40
40
40
40
40
40
40
40
40
40
40
45
-15
30
30
30
35
35
35
40
40
40
40
45
45
45
45
45
45
45
45
45
45
45
45
50
-20
30
35
35
35
40
40
40
40
45
45
45
50
50
50
50
50
50
50
50
50
50
50
55
-25
35
35
35
40
40
45
45
45
50
50
50
50
55
55
55
55
55
55
55
55
55
55
60
-30
35
40
40
40
45
45
45
50
50
55
55
55
55
60
60
60
60
60
60
60
60
60
65
-35
40
40
40
45
45
50
50
55
55
60
60
60
60
65
65
65
65
65
65
65
65
70
-40
40
40
45
50
50
50
55
55
60
60
65
65
65
65
70
70
70
70
70
70
70
70
75
-45
45
45
45
50
55
55
55
60
65
65
70
70
70
70
70
75
75
75
75
75
75
75
80
-50
45
45
50
55
55
60
60
65
65
70
70
75
75
75
75
75
80
80
80
80
80
85
90
-55
45
50
50
55
60
60
65
65
70
75
75
80
80
80
80
80
85
85
85
85
85
90
95
-60
50
50
55
60
60
65
65
70
75
80
80
80
85
85
85
85
90
90
90
90
90
95
100
-65
50
55
55
60
65
65
70
75
80
80
85
85
85
90
90
90
95
95
95
95
95
100
105
-70
55
55
60
65
65
70
70
75
80
85
90
90
90
95
95
95
95
100
100
100
100
105
110
-75
55
60
60
65
70
70
75
80
85
90
90
95
95
95
100
100
100
100
105
105
105
110
115
-80
55
60
65
70
70
75
80
80
90
90
95
100
100
100
100
105
105
105
110
110
110
110
120
-85
60
60
65
70
75
75
80
85
90
95
100
100
105
105
105
110
110
110
110
115
115
115
125
-90
60
65
65
75
75
80
85
85
95
100
100
105
105
110
110
110
115
115
115
120
120
120
130
-95
65
65
70
75
80
80
85
90
95
100
105
110
110
110
115
115
120
120
120
125
125
125
135
-100
65
70
70
75
80
85
90
95
100
105
110
110
115
115
115
120
120
120
125
125
130
130
140
-105
65
70
75
80
85
85
90
95
105
110
110
115
115
120
120
120
125
125
130
130
130
135
145
-110
70
70
75
80
85
90
95
95
105
110
115
120
120
120
125
125
130
130
130
135
135
135
150
SIZE TEMP
60
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 26 / 47
METHOD STATEMENT FOR WORK OF INSULATION -115
70
75
75
85
85
90
95
100
110
115
115
120
120
125
125
130
130
135
135
140
140
140
155
-120
70
75
80
85
90
95
95
100
110
115
120
125
125
130
130
130
135
135
140
140
145
145
160
-125
70
75
80
85
90
95
100
105
110
120
125
125
130
130
135
135
140
140
140
145
145
150
165
-130
75
75
80
90
95
95
100
105
115
120
125
130
130
135
135
140
140
145
145
150
150
150
170
-135
75
80
85
90
95
100
105
110
115
125
130
130
135
135
140
140
145
145
150
150
155
155
175
-140
75
80
85
90
95
100
105
110
120
125
130
135
135
140
140
145
145
150
150
155
155
160
0.2
-145
75
80
85
95
95
100
105
110
120
125
130
135
140
140
145
145
150
150
155
155
160
160
180
-150
80
85
85
95
100
105
110
115
125
130
135
140
140
145
145
150
150
155
155
160
160
165
185
-155
80
85
90
95
100
105
110
115
125
130
135
140
145
145
150
150
155
155
160
165
165
165
190
-160
80
85
90
95
100
105
110
115
125
135
140
145
145
150
150
155
155
160
160
165
170
170
190
-165
80
85
90
100
105
110
110
120
130
135
140
145
145
150
155
155
160
160
165
170
170
175
195
-170
85
85
90
100
105
110
115
120
130
135
140
145
150
150
155
160
160
165
165
170
175
175
200
-175
85
90
95
100
105
110
115
120
130
140
145
150
150
155
155
160
165
165
170
170
175
180
200
-180
85
90
95
100
105
110
115
125
135
140
145
150
155
155
160
160
165
170
170
175
180
180
205
Notes:
1.
Table is based on thickness required to prevent condensation on surfaces with following design conditions:
Ambient temperature Relative humidity
30 °C
:
: 85 percent 2
Surface heat transfer coefficient: 8 W/(m2·K) [6.88 kcal/(m ·h·°C)] 2. Where other design conditions are used, thickness should be adapted to meet job requirements. 3
3. Bulk density : Min. 40kg/m
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 27 / 47
METHOD STATEMENT FOR WORK OF INSULATION Att achm ent #3.
INSPECTION & TEST PLAN FOR INSULATION No.
A 1
Reference ( Co de /S td /S pe c. /P ro c. )
Description of Inspection
2
Rev. No : 3 Date
:
Page
:
Inspection for R ep or t F or m. No .
Remarks Sc
C
Owner
M
W
I
M
W
I
M
W
I
M
I
I
c) Insulation material form & thickness
M
I
I
d) Extend of Insulation
M
I
I
e) Insulation support ring (Vertical Only)
M
W
I
f) Cool down system installation (Fiber optic Cable-by instrument)
M
I
I
INSULATION Material V erification
Project Specification
a) Verify the material/ Size/ Quantity & Physical Properties
P.O.Spec. / Vendor Documents Field Material Control Procedure
b) Check the damage
2 -1
Doc No : RFCC-ITP-PA-0001
Piping Insulation
Applicable drawing & Specification
Manufacturer's Certificate and Field Receiving Report
ITP-IN(CP)-001
P re -I ns ul at io n C he ck
a) Check the completion of welding, hydro testing and assembly b) Surface cleaning and touch up painting
S c : Su b- Co nt ra ct or ;
C : C on tr ac to r;
M : Execution;
W : Witness;
I : Spot Witness
R : Review Inspection
CONSORTIUM ADHI – GS E&C
H : Hold
MIGAS
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 28 / 47
METHOD STATEMENT FOR WORK OF INSULATION INSPECTION & TEST PLAN FOR INSULATION No.
2-2
Reference (Code/Std/Spec./Proc.)
Description of Inspection
Verifying Document
Doc No : RFCC-ITP-PA-0001 Rev. No : 3 Date
:
Page
:
Intervention Sc
C
Owner
M
I
I
M
I
I
M
I
I
M
I
I
M
I
I
f) Expansion/ Construction Joint
M
I
I
g) Primary vapor barrier w/ Glass cloth
M
I
I
M
I
I
Insulation
Appicable drawing & Specification
ITC-IN(CP)-001
a) Anti-abrasive coating b) Joint staggered & fit up c) Insulation Segments (Approx 8" for 2' Long, Approx 12" for 3' Long) d) SUS band interval for outer layer (SUS 304, min. 0.4mm t x 13 mm w, max 225 mm centers) e) Joint Sealant (Outer layer only, wet film thickness App 3.5mm)
(Dry film thickness 3.0mm) h) Vapor stop ( Pipe Suports, Valves & Flanges)
S c : Su b- Co nt ra ct or ;
C : C on tr ac to r;
M : Execution;
W : Witness;
I : Spot Witness
R : Review Inspection
CONSORTIUM ADHI – GS E&C
H : Hold
MIGAS
Remarks
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 29 / 47
METHOD STATEMENT FOR WORK OF INSULATION INSPECTION & TEST PLAN FOR INSULATION No.
2-3
Reference (Code/Std/Spec./Proc.)
Description of Inspection
Doc No : RFCC-ITP-PA-0001 Rev. No : 3 Date
:
Page
:
Inspection for Report Form. No.
Sc
C
Owner
M
I
I
M
I
I
M
I
I
d) Flange & Valve Box Installation
M
I
I
Final Inspection
M
W
W
M
I
I
M
I
R
c) Insulation material form & thickness
M
I
I
d) Extend of Insulation
M
I
R
M
I
R
Jacketing
Applicable drawing & Specification
MIGAS
ITP-IN(CP)-001
a) Jacketing installation (Longitudinal overlaps min. 50mm & 90 ° or 150 ° positions) (Circumferential overlaps min. 50mm) b) Jacket band interval ( 0,4mm t x 13mm w for NPS
≤ 24",
max. 300mm centers)
( 0,5mm t x 19mm w for NPS
> 24",
max. 300mm centers)
c) Metal Sealant (white color/ min. 4mm dry thickness)
2-4
3 3 -1
Equipment Insulation
Applicable drawing & Specification
ITP-IN (CE)-002
P re -i ns ul at io n c he ck a) Surface cleaning and touch up painting b) Check the completion of installation, Assembly and final inspection
e) Insulation support ring S c : Su b- Co nt ra ct or ;
C : C on tr ac to r;
M : Execution;
W : Witness;
I : Spot Witness
R : Review Inspection
CONSORTIUM ADHI – GS E&C
H : Hold
Remarks
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 30 / 47
METHOD STATEMENT FOR WORK OF INSULATION INSPECTION & TEST PLAN FOR INSULATION No.
Reference ( Co de /S td /S pe c. /P ro c. )
Description of Inspection
Doc No : RFCC-ITP-PA-0001 Rev. No : 3 Date
:
Page
:
Inspection for R ep or t Fo rm. N o.
Sc
C
Owner
M
I
R
a) Anti-Abrasive coating
M
I
I
b) Joint staggered & fit up
M
I
I
M
I
I
M
I
I
M
I
I
f) Expansion/ Construction Joint
M
I
I
g) Primary vapor barrier w/ Glass cloth
M
I
I
M
I
I
f) Cool down system installation (Fiber optic cable-by instrument)
3-2
Insulation
Applicable drawing & Specification
ITP-IN(CE)-002
c) Insulation Segments (Approx8" for 2' Long, Approx,12" for 3' Long) d) SUS band interval for outer layer (SUS 304, 0.5mm t x 19mm w, max. 300mm centers) e) Joint sealant (Outer layer only, wet film thickness App 3.5mm)
(Dry film thickness 3.0mm) h) Vapor stop (Supports, Valves & Flanges)
S c : Su b- Co nt ra ct or ;
C : C on tr ac to r;
M : Execution;
W : Witness;
I : Spot Witness
R : Review Inspection
CONSORTIUM ADHI – GS E&C
H : Hold
MIGAS
Remarks
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Project
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 31 / 47
METHOD STATEMENT FOR WORK OF INSULATION INSPECTION & TEST PLAN FOR INSULATION No.
3-3
Reference ( Co de /S td /S pe c. /P ro c. )
Description of Inspection
Doc No : RFCC-ITP-PA-0001 Rev. No : 3 Date
:
Page
:
Inspection for R ep or t Fo rm. N o.
Sc
C
Owner
M
I
I
M
I
I
M
I
I
d) Manhole box installation
M
I
I
Final Inspection
M
W
W
ITP-IN(CE)-002
Applicable drawing & Specification
Jacketing
a) Jacketing Installation (Laps-min. 50mm for flat jacketing) b) Jacket band interval (max. 300mm centers) (0.5mm t x 19mm w ) c) Metal Sealant (white color/ min. 4mm dry thickness)
3-4
S c : Su b- Co nt ra ct or ;
C : C on tr ac to r;
M : Execution;
W : Witness;
I : Spot Witness
R : Review Inspection
H : Hold
CONSORTIUM ADHI – GS E&C
MIGAS
Remarks
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
METHOD STATEMENT FOR WORK OF INSULATION Attac hm ent #4.
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 32 / 47
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
METHOD STATEMENT FOR WORK OF INSULATION
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 33 / 47
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #5.
Typic al Det ails Fo r Pi ping Ins ul ati on
COATED WITH MOISTURE BARRIER
Note : All Dimensions are in mm.
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 34 / 47
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 35 / 47
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #6.
Typi cal Details For Valve Ins ul ati on
COATED WITH MOISTURE BARRIER
FLANGED VALVES
COATED WITH MOISTURE BARRIER
VALVE OTHER THAN FLANGED
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 36 / 47
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #7.
Flang e Ins ul ati on And In su lat io n Supp or t Ri ng Details
COATED WITH MOISTURE BARRIER
FLANGE INSULATION
INSULATION SUPPORT RING FOR PIPING
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #8.
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 37 / 47
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 38 / 47
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #9.
COATED WITH MOISTURE BARRIER
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 39 / 47
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #10.
COATED WITH MOISTURE BARRIER
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #11.
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 40 / 47
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #12.
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 41 / 47
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #13.
Heat Exch anger In su lat io n
COATED WITH MOISTURE BARRIER
TYPICAL DETAIL AT PIPING HANGER
COATED WITH MOISTURE BARRIER
DOUBLE PIPE HEAT EXCHANGER
CONSORTIUM ADHI – GS E&C
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 42 / 47
Doc. No. : RFCC-G-CS-PR-010
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect
Rev. No. : 1
PT. PERTAMINA (Persero )
Page No. : 43 / 47
METHOD STATEMENT FOR WORK OF INSULATION Attachment #14.
Insulation Details For Vertical Vessel Head
max interval 150 mm COATED WITH MOISTURE BARRIER
COATED WITH MOISTURE BARRIER
WATERSHED MANNER OVERLAP
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 44 / 47
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #15.
Flashi ng Details At Nozzle And “ S” And “ J” -Cli p Detail s
COATED WITH MOISTURE BARRIER
FLASHING DETAIL AT NOZZLE
COATED WITH MOISTURE BARRIER
COATED WITH MOISTURE BARRIER
“ S” AND :J” CLIP DETAILS
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 45 / 47
METHOD STATEMENT FOR WORK OF INSULATION At tac hm ent #16.
Wir e Mesh Bar ri er f or Pers onnel Protec ti on Details
steel welded wire mesh
* use s/s components on s/s pipe
CONSORTIUM ADHI – GS E&C
Cilacap Resid Fluid Catalytic Cracking (RFCC) Proj ect PT. PERTAMINA (Persero )
Doc. No. : RFCC-G-CS-PR-010 Rev. No. : 1 Page No. : 46 / 47
METHOD STATEMENT FOR WORK OF INSULATION
Attachmen t #17.
Removable In su lat io n Cover fo r Pumps (Hot Ins ul ati on )
Filling with mineral wool
50mm
CONSORTIUM ADHI – GS E&C