PROJECT : SM LIGHT RESIDENCES LOCATION : BONI AVE. EDSA MANDALUYONG CITY SUBJECT : PRODUCTIVITY RATE SCOPE OF WORK : INTERIOR PAINTING OF UNITS FINISH : SEMI-GLOSS (2 COATS) PROCEDURE 1. SURFACE PREPARATION - Putty Works - Sanding 2. PRIMER - Application of Flat Latex - Spot putty and reapply Flat Latex 3. FIRST COAT - Application of Semi-Gloss 4. FINAL COAT - Application of Semi-Gloss
PAINTING TO MASONRY WALL FLOOR : 17TH FLOOR UNIT NO. : 18 AREA : 2
46.9 m 2 8.86 m
UNIT CR
55.76 m DATE 6-Nov 7-Nov 7-Nov 7-Nov 8-Nov 8-Nov 8-Nov 8-Nov
ACTIVITY Surface Preparation - Putty Works Surface Preparation - Putty Works Surface Preparation - Sanding Primer - Application of Flat Latex Primer - Application of Flat Latex Primer - Spot Putty & Reapply Flat Latex 1st Coat - Application of Semigloss Final Coat - Application of Semigloss TOTAL PRODUCTIVITY (Man-hr/m2)
Surface Preparation - Putty Works Surface Preparation - Putty Works Surface Preparation - Sanding Primer - Application of Flat Latex Primer - Application of Flat Latex Primer - Spot Putty & Reapply Flat Latex 1st Coat - Application of Semigloss Final Coat - Application of Semigloss
PAINTING TO MASONRY WALL FLOOR : 17TH FLOOR UNIT NO. : 37-38 AREA : 2 93.8 m
UNIT
2 17.72 m 2 111.52 m
CR
DATE 7-Nov 8-Nov 8-Nov 9-Nov
MANPOWER Painter Painter Painter Painter
ACTIVITY Surface Preparation - Putty Works Surface Preparation - Sanding Primer - Application of Flat Latex Primer - Application of Flat Latex
MANHOUR 22 8.5 4 3
Man-Hrs Man-Hrs Man-Hrs Man-Hrs
10-Nov Painter
Primer - Spot Putty & Reapply Flat Latex
5.5 Man-Hrs
10-Nov Painter 13-Nov Painter
1st Coat - Application of Semigloss Final Coat - Application of Semigloss
6 Man-Hrs 12 Man-Hrs
TOTAL PRODUCTIVITY (Man-hr/m2)
61 Man-Hrs 0.5470
PAINTING TO MASONRY WALL FLOOR : 8TH FLOOR UNIT NO. : 21-22 AREA : 2 93.8 m 2 17.72 m
UNIT CR
2 111.52 m
DATE 7-Nov 8-Nov 8-Nov 9-Nov
MANPOWER Painter Painter Painter Painter
10-Nov Painter
ACTIVITY Surface Preparation - Putty Works Surface Preparation - Putty Works Surface Preparation - Sanding Primer - Application of Flat Latex Primer - Spot Putty & Reapply Flat Latex
MANHOUR 14 10 7.5 6
Man-Hrs Man-Hrs Man-Hrs Man-Hrs
13 Man-Hrs
10-Nov Painter Painter
1st Coat - Application of Semigloss Final Coat - Application of Semigloss
6 Man-Hrs 12 Man-Hrs
TOTAL PRODUCTIVITY (Man-hr/m2)
68.5 Man-Hrs 0.6142
AVERAGE PRODUCTIVITY (Man-hr/m2)
0.6288
FINISH : FLAT FINISH PROCEDURE 1. SURFACE PREPARATION - Putty Works - Sanding 2. PRIMER - Application of Flat Latex - Spot putty and reapply Flat Latex 3. FINAL COAT - Final application of flat latex PAINTING TO CONCRETE CEILING FLOOR : 17TH FLOOR UNIT NO. : 18 AREA : 2 12.8 m 2 12.8 m
ACTIVITY Surface Preparation - Putty Works Surface Preparation - Putty Works Surface Preparation - Sanding Primer - Application of Flat Latex Primer - Application of Flat Latex Primer - Spot Putty & Reapply Flat Latex Final Coat - Application of flat latex TOTAL PRODUCTIVITY (Man-hr/m2)