PR-1834
Work management for pipeline maintenance & corrosion activities
Petroleum Development Oman L.L.C.
RESTRICTED Oct-2009
Document ID: PR-1834 Filing key: Business
Pipeline Maintenance and repairs
Keywords: Work Order, activities, pipeline, maintenance, maintenance, corrosion, and contract
1
PR-1834
Work management for pipeline maintenance & corrosion activities
This page was intentionally left blank
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this document may be disclosed to others or reproduced, reproduced, stored in a retrieval system, or transmitted in any form by any means (electronic, mechanical, mechanical, reprographic recording or otherwise) without prior written consent of the owner.
2
PR-1834
Work management for pipeline maintenance & corrosion activities
Authorised For Issue
Issue d for appr o
Version 2
Dec ‘04
Version 1
Sep ‘03
Version 0
Aug ‘03
Pam Ooms TTO/14X Nasser Behlani UIP/411 Nasser Behlani UEC/14
Issued for approval Issued for approval Draft
3
PR-1834 ser
Work management for pipeline maintenance & corrosion activities
Behlani,
TTO/14Draft T
able
Dec ‘04
Pam Ooms TTO/14x
of
contents Version 23
4 1 Introd uction 4 1.1 Background 4 Purpose 4 Distribution /target audience 4
Work manag ement proces ses 4 Scope 4 2.1Pipeline maintenanc e and repairs (refer to Index III): 4 2.2Ordering Goods and Materials 4 2.4Contract s 4
3
Work manag ement proces s: Routin e Activiti es 4 3.1 Process
4 Contract Support
PR-1834
Work management for pipeline maintenance & corrosion activities
GEN work
For each asset a GEN W.O. will be created for the total value of the routine
order Issued for
activities for a the full year.
Contract Representative
approval The contract support will estimate the routine activities total amounts and split it according to activities carried out in each asset.
11 W.O. are
Purchase
created and release. After the WO’s been released, PRs are automatically generated which shall
Requisition
be released by the CR/CH/CO (as per release strategy).
System
Purchase Order
All 11 PR’s to be released in same time to create 1 PO containing the
Contract
complete value of routine activities for 1 year. This PO will be sent to the
Representative/
contractor.
Holder /
The Contract Representative/ Holder /Owner will release the PR as per the
Owner
Service Entry
manual of authority On a monthly basis an accrual S.E. is generated against each asset to
Contract
(Accruals) Activities Plan
accrue/record amounts /workload (VOWD – value of work done). SNR planning Engineer prepares and release monthly plans of routine
Representative SNR Planning
Supporting
activities in line with SAP maintenance plan. The contractor carry out activities and record actual carried out tasks
Engineer Contract
Document
against plans.
Planner/Site
Confirmations
Confirmations are done for the executed routine activities.
Manager Contract Planner/Site Manager CSRs
TECO work
CSRs approve supporting documents of carried out activities and TECO
orders
W.O.s
Certify
Supporting documents are certified against plans by SNR planning
SNR planning
Supporting
engineer
Engineer
Document Adjust Service
Amount certified is split into the 11 A/C and the accruals S.E.s are adjusted
Contract
to actual S.E.s The contract support will technically release [OT] the SE to reflect VOWD
Representative Contract
at the end of each month. The Contract representative/Holder/Owner financially releases the SE (As
Representative Contract
per manual of authority).
representative/
entry Technical release Service Entry Financial release Service Entry
Holder/Owner
3.2.2
Activity Work Orders –SAP PM
In parallel with 3.2.1 above, SAP PM Maintenance plans automatically generate WO’s that contain object lists describing the scope of work for activities in a particular area. The WO’s are generated by the system on a regular basis, e.g. weekly, monthly or quarterly, depending on the frequency of the activity. These WO’s require release by CSRs, and maintained by respective area contractor’s planners.
5
PR-1834
Activity Maintenance plan
Work management for pipeline maintenance & corrosion activities
Activity description Each routine activity (e.g. W1 routine pigging in Fahud) has its own
Who?
maintenance plan. These maintenance plans automatically generate the
System
WO’s containing the routine scope of work.
Custodian
For an overview of the maintenance plans see Appendix II – Scope of Work order
work. The WO’s generated by SAP PM (at the beginning of each 6 months) have
user status [INIT]. The WO’s need to be released using ZIW38.
After CSRs
release they will have system status: REL. As soon as the work order has Maintain Work
been released the work may start. The contractor will maintain the work orders by planning the scheduled start,
Contractor
Order
duration and finish dates to reflect the execution plan.
planners
Confirmation of
When all work on the WO has been completed, it shall have final
work completed
confirmation (CNF).
[CNF]
Contractor Planners
Selecting the “Final Confirmation” box will set the system status to CNF.
/
Site
Confirmation of work completed can be done using Transaction ZIW37 or Managers IW41. TECO Work
Partial Confirmation (PCNF) may be used to indicate work is in progress. After setting the final confirmation and reporting any missed activities the
Order
WO shall be technically completed [TECO] using SAP transaction IW32 or
CSRs
IW38 by the CSR.
6
PR-1834
Work management for pipeline maintenance & corrosion activities
Z6 Notifications [IW21]
Request change scope of work
(Also refer to PR 1528)
Z6 Notification is used to request update SAP-PM Master Data i.e. creation of CSR/CS new SAP Master Data or changing existing SAP Master Data like Equipment Movement from one location to other, change of Maintenance Plan, etc
[User status: INIT & AWAP ]
If SAP Master Data required an update i.e. creating new maintenance plan, changing frequency, adding or removing an object (function location), deleting maintenances activity from the system….etc, then CSR / CS should raise the Z6 notification in SAP using SAP Transaction IW21 to request the updates. There two types of changes;•
Maintenance Plan information i.e. planner group , main work centre, adding or removing object, deleting existing , creating new maintenance plan, then Main Work Center should be used CDFPMMS
•
Pipelines maintenance and repair related issues i.e. pigging frequency ……etc, then Main Work Center should be used CDFPPL.
The status of Z6 should be A WAP (awaiting approval). For more details, please refer to Z6 Procedure: PR-1528 - Z6 Notification Procedure
Approve & update CDFPs should review Z6 Notifications assigned to them that are AwaitingCDFP & SAP Master data
Approval. Upon review, the CDFP may Approve (APPR), Cancel (CNCL).
[User status:
The SAP-PM Master Data Team will review the Approved Z6 Notifications in
APPR & TBCO]
the SAP System and apply the changes.
Support
The SAP-PM Master Data Management Team will review the Approved Z6 Notifications in the SAP System and apply the changes. The SAP Master Data Team will update the Z6 Notification to indicate that the change request is complete and marked as TBCO (To Be Completed) at the header level to indicate that the Notification is ready to be review by the CDFP for closure. I
7
PR-1834
Work management for pipeline maintenance & corrosion activities
4 Work management process: non-routine activities Process flow Work management process – Non-routine activities Maintain WO Work completed
Contractor
Scope
Estimate
Originator Contractor
Notification OriginatorC SR / Contractor
Work order Orde r CS
PR
PO
CR
Contractor
FCP Contractor CS
CS
CNF WO
Work
TECO WO
CSRContract CSR
COC
Approve COC
Contractor
or Work ongoing [end 24th of the month]
CSR
Actual Actual Certify SE COC Contractor Contractor CS
OT SE
Final entry Entry SE
CS
CS
CR/CH
Accrual SE (VOWD) Contractor
Approve FCP CSR
Refer to non routine activities process flow chart.
4.2
Process description
Activity Scope
Activity description Scope of work is identified, tuned and agreed by CSRs. The scope is logged,
giving reference and sent to contractor requesting an estimate Estimate
Based on the scope of work, the contractor shall prepare a cost estimate
Who?
CSR Contractor
detailing the specific resources and services to carry out the task. The cost estimate shall include the planed start and end date of the job. Notification
This cost estimate shall be sent to the originator.. Once the estimate is agreed, A Z1 notification in SAP is raised (IW21) containing the scope of work and the functional location of the asset. The notification shall
Work originator CSR
be raised by the work originator/ contractor. All of the planned non-routine jobs should be in the system early in the year so that the contractor has an overview of the annual work load and can start scheduling the work orders. The Priority in the Notifications is determining the LAFD of the work order , therefore and the notification set according to the Corrective Maintenance
Prioritization tool by filling the 3 CMPT fields in the Z1 notification: » » »
Fin. release Release SE
Consequence Category Consequence Severity Occurrence Likelihood
The Priority is mandatory information for any corrective job request This is required for (FSR system) Facility Status Reporting) SAP will automatically determine the priority based on the CMPT matrix (see Appendix. IV) The Priority and Required Start and End Date will be calculated by SAP.
8
PR-1834
Work management for pipeline maintenance & corrosion activities
The work originator shall release the notification
Work order
CSR shall approve the cost estimate based on its technical content. The Contract Support shall verify the rates used by the contractor and any changes shall be communicated to the contractor and work originator. Queries shall be discussed with the contractor representatives at the coast. The Contract Support will convert the notification into work Order and release it (IW22). The A/C charged (WBS) is automatically picked by system if correct
Contract Representative
functional location is stated. The order shall be unplanned, i.e. have a lump sum plus a 10% or $1,000 contingency, which ever is higher. The scheduled start dates and durations / scheduled finish dates shall be appropriate to allow the contractor to plan and execute the work. The order shall be a 72FC type i.e. corrective with the appropriate Maintenance Purchase
activity type (MActType): CPM or CRB After the work order has been released, a purchase requisition (PR) will
Requisition
automatically be generated by SAP. In order to generate a PO, the PR needs to be released, (ME54) by CR or CH (as per manual of authority). If the PR value is less than a $1,000, the PR will be automatically released by
Maintain work
the system. The contractor shall maintain the work order after it has been raised and
order
released. The contractor will make sure that the scheduled start and finish date reflect when the work is planned to take place. As the work is ongoing it is important that these dates are kept up-to-date.
Purchase
After the PR is released, a PO is automatically generated by SAP and sent to
Order
the contractor. Once the PO is issued, work can be carried out.
Contract representative / Holder
Contractor planner / site manager
PRs released to one contractor in same time will be clamped as one PO with different items.
System
Contractor shall not carryout any task without a PO, unless declared as an emergency. The contractor shall inform contract representative in the event Work
receiving a PO is not from UI/P4. After receiving the PO the work will be planned, scheduled and executed by the
Execution
contractor. The planning and progress of the work will be discussed during the
Day work
daily meetings between the CSR’s and the contractor site managers. Contract site manager should prepare daily day work sheets summarizing all
sheet
resources used to carry out the task, and shall be submitted to CSR within 24
Contractor Planner / site manager Contractor
hours.
9
PR-1834
Work management for pipeline maintenance & corrosion activities
Monitoring
CSRs shall monitor progress and quality of work being carried out by the
work
contractor.
Partial
Partial confirmation to be attached using IW41 to record the time spent to
Confirmation
carryout the task.
[PCNF] F change
If, during work execution, it turn that more resources are required (not stated in
Proposal
the original estimate) an FCP to be prepared by the contractor. It shall describe
(FCP)
the change to the scope of work, the reason for the change and the additional
procedure
costs.
CSR Contractor Planner / site manager Contractor
CSR
The FCP to be approved by CSR’s and sent to the contract representative. Once the FCP is certified, WO to be amended. If the increase in PR value is equal to or in excess of 5% of the original PR
Contract value, the PR needs to be re-released. Automation to be informed (in writing) of Representative the changes to update the Purchase order. CR/CH When the work is completed the FCP needs to be included within the COC.
Final
As soon as the contractor completes the work, final confirmation shall be made
Confirmation
using transaction IW41. Ticking “final confirmation box” or “no remaining work”
[CNF] Closing COC
will record that the WO is completed Once the work is completed, contractor shall prepare COC (certificate of completion) and a summary of all resources used to carry out the job.
All
supporting documents (originals) shall be attached to the COC. TECO Work
For Supporting documents refer to supporting documents appendix V. Once the COC is accepted, the WO can be technically completed [TECO] using
order Accrual
SAP transaction IW32. At the end of each month (every 24th), accrual exercise shall be carried out by
Exercise
the contractor to record VOWD (value of work done). The exercise shall record percentage completion of all ongoing POs.
Contractor planner / site manager Contractor planner / site manager
CSR
Contractor
Service entries shall be made and updated in SAP by the contractor (ML81N) The accrual entry will be updated on a monthly basis as long as the job is ongoing. Certifying
Contract support shall verify the COC and supporting documents against the
COC Actual service
contract terms and conditions. A service entry is attached to the PO recording all verified resources used to
entry
carry out task. IF an earlier accrual service entry is done, then to be updated to actual.
Contract Representative
Contractor
Creating new service entry or updating existing accruals is done using
Technical
transaction (ML81N) After the contractor has made the service entry, the contract support reviews
release [OT]
and release the service entries technically (OT) using SAP transaction ML81N.
Service entry
There shall be no partial payment for any single PO, but all Service entry shall
Contract Representative
10
PR-1834
Work management for pipeline maintenance & corrosion activities be flagged with final flag payment, which will reset PO value to Service entry value (ACV report is taking the PO value).
Financial
Once contract support release the service entry technically, CR/CH verifies the
release SE
COC and release the service entry financially as per manual of authority.
Invoice
Once the COC is approved b y C R/CH (financially releasing the SE), t he contractor shall prepare an invoice based on the approved COC and handed to
Contract representative/ Holder
Contractor
the payroll section. A copy of the invoice shall be handed to the contract support to close the task. Several COCs can be claimed by one invoice.
11
PR-1834
Work management for pipeline maintenance & corrosion activities
Work management process: ordering goods and materials Process flow Request for quotation (RFQ)
For non stock items
Majan (R & D) For non stock items
GEN Work order Pipeline Supervisor s
5.2
Release work orde r
PR
Pipeline Supervisor s
Release PR
TECO W O
Pipelin SNR PipelineCSR eCSR
PO SAP/buyer
goods receive d PDO supply
Report goods received (MIGO ) PDO Supply For stock items
Process description This process is for ordering goods and materials (Coded only) via PDO supply for non-stock items. All pipeline spares must be SAP coded and ordered at site
Pipeline Spares work order Activity Work order
Activity description Who? Pipeline maintenance supervisors raise and release a GEN work order usingCSR
(IW31) in SAP. Correct A/C shall be charged by selecting the correct functional Purchase
location or the Asset’s WBS. After the work order has been released, the system will trigger the purchaseCSR
Requisition
requisition (PR) automatically. PR shall be released by CSR in order to generate a PO for stock items & RFQ SAP for non-stock items .
Request for
The buyer will float inquiry to request quotations form group of vendors based
quotation (RFQ)
on the AVME. This will generate 3 or more quotations from different vendors Buyer this process usually takes 10-15 day. The buyer will forward the quotations to the originator recommending to cheapest vendor.
Purchase order
CSR The originator can reject the recommendation with justification. A) Stock items : The PO is automatically generated by SAP after releasing the PR.
SAP / Buyer
B) Non-stock items : the buyer will generate the PO after finalizing the RFQ. Receive materials The warehouse (@ Ghala) will receive the materials and goods ordered. FromPDO here the materials will be redistributed to the specified location. Report goods
Warehouse
The delivery note will be sent to the work originator. After the CSR has received the delivery notes, the goods received are reportedCSR
received in MIGO. The MIGO shall be released TECO work order After the PR has been released and the PO created, the work order can beCSR technically completed (TECO).
12
PR-1834
Work management for pipeline maintenance & corrosion activities
13
PR-1834
Work management for pipeline maintenance & corrosion activities
14
PR-1834
Work management for pipeline maintenance & corrosion activities
6
SAP Reports
6.1
SAP Reports
Notification IW28 – Change
Outstanding
Select Notification status ‘outstanding’ to get an overview of all notification (Z1,
In process
Z6 or M3) that are awaiting approval and/or are under investigation [NVST]. Select Notification status ‘in process’ to get an overview of all released
Notifications & IW29 – Display
notifications to which (Z1) a work order will be attached or in case of Z6 are
Notifications Completed
being dealt with by SAP support. Notification status ‘Completed’ gives an overview of all notifications that have been closed following setting a TECO on the attached work order.
Work Orders ZIW37 – Change
Outstanding
Selects all work order operations that need a final confirmation [CNF]. Partial
Completed
confirmed operations are also shown as outstanding. Selects all work order operations that have been confirmed [CNF] or have been
operations: Selection
of
technically completed [TECO].
order operations
ZIW38 – Change
Outstanding
Select Order status ‘outstanding’ to get an overview of all work orders that have
In process
been created and are awaiting release. Select Order status ‘in process’ to get an overview of all released work orders.
Completed
To get a list of all Confirmed work orders select ‘Status inclusive: CNF’. Order status ‘Completed’ gives an overview of all orders that have been TECO-
work orders & ZIW39 – Display
work orders
ed and/or Closed. An order gets TECO-ed as soon as the work has been completed. Confirmations IW48 –
Outstanding
Selecting operations ‘outstanding’ will give an overview of all operations (of a
Confirmation
work order) that still need to be confirmed or have been partially confirmed
using operations
[PCNF] (using IW41). It will allow you to select and confirm these operations.
list Completed
Selecting ‘Completed’ gives an overview of all operations (of a work order) that have a Final confirmation [CNF] status or that have been TECO-ed.
Overview ZWR_WOPRPO
Outstanding
Select Order status ‘outstanding’ to get an overview of all work orders that have
In process
been created and are awaiting release. Select Order status ‘in process’ to get an overview of all released work orders.
Cross reference report
To get a list of all Confirmed work orders select ‘Status inclusive: CNF’.
(Services – WO/
ZWR_WOPRPO report will also give you a PR, PO and SE number and the
PR/PO report ) Completed
service entry status of the work order. Order status ‘Completed’ gives an overview of all orders that have been TECOed and/or Closed. An order gets TECO-ed as soon as the work has been completed. ZWR_WOPRPO report will also give you a PR, PO and SE number and the service entry status of the work order.
Contracts ZCR_COST_AC
Released
V - Planned
POs
This report will list summary of all released POs
Costs vs ACV
15
PR-1834
Work management for pipeline maintenance & corrosion activities
Report FBL1N - Vendor
Invoices
List of invoices
6.2
This report list all logged invoices against the vendor (not the agreement) and their status.
Key Performance Indicators (KPI’s) PDO measures SAP KPIs (Key
Performance Indicators) across PM process to
monitor process performance. These KPI’s are used to monitor the scheduling compliance and technical integrity of the SAP PM/CM work orders.
6.2.1 Integrated Activity Planning (IAP):They use the scheduled start and finish dates of activities, they cover PM and CM work: Weekly frozen includes all the Pipeline Maintenance, Monitoring & repairs activities - 14 day plan Monthly frozen includes only all Pipeline Maintenance, Monitoring & repairs activities production impact – 90 day plan. •
•
6.2.2 Technical Integrity Measures PM/CM compliance, these use the LAFD (Latest Allowed Finish Date) date in Work Orders, they reported on monthly basis. All the KPI’s reported in PDO Total Reliability Measures Dashboard (Refer to variants Index).
Work management process routine activities
11 GEN work orders [raised once a year] GEN work order Fahu dekhwa L ir Yiba l arn Q Alam MOL SOG GG L S Marm ul Bahj a Nim r im R a
Purchase Req.
1 11 P.R.s Purchase generated Order And to be
11 P.R.s generated And to be released in Same time To generate One PO For Administrating purposes
released in Same time To generate One PO For PO is generated for the total value of Routine Tasks For the Whole Year
Contract Support
Accruals Exercise Generated every 24th Of the month
Administr ating purposes
Contract Support
Contract Representative
SAP PM Maintenan ce plans
Service Entry
release WO's Coord inator sCSR
Maintain work Order
Work Carried Out
Contractor
Confirmati on [CNF] WO
Supporting Documents Supporting documents is furnished by Contractor and Approved by Coordinators Verified by SNR Planning Engineer
Service Entry
Report actual amounts Adjust Accrual S.E.s To reflect actual Certified amount
Contractor Support
Report missed activities Change [M3] / of Scope [Z6 notification] Contract orCSR
TECO Coord inator sCSR
16
PR-1834
Work management for pipeline maintenance & corrosion activities
17
PR-1834
Work management for pipeline maintenance & corrosion activities
Appendix I – SAP variants
Overview of variants ZIW37 North Variant name /IIM_STPNTH16D /IIM_STPNTH90D /IIM_STPNTH3D /IIM_STPNTHBK South Variant name /IIM_STPSTH16D /IIM_STPSTH90D /IIM_STPSTH3D /IIM_STPSTHBK ZIW38 North Variant name /IIM_STPNTH16D /IIM_STPNTH90D /IIM_STPNTH16ODUE South Variant name /IIM_STPSTH16D /IIM_STPSTH90D /IIM_STPSTHODUED
Short Description STIPALG1 WkCtr Nth: Next 16d ops/ac STIPALG1 WkCtr Nth: Next 90d ops/ac STIPALG1 WkCtr Nth: Yday/Tday/Tomor STIPALG1 WkCtr Nth: Backlog
Operation Level in the Workorder Operation Work Center
Short Description All STIPPLN Nth 16D Plan All STIPPLN Nth 90D Plan All STIPPLN Nth Overdue Header Level in the Workorder Main Work Center Short Description All STIPPLN Sth 16D Plan All STIPPLN Sth 90D Plan All STIPPLN Sth Overdue
18
PR-1834
Work management for pipeline maintenance & corrosion activities
Appendix II – Planner Groups Index
19
PR-1834
Work management for pipeline maintenance & corrosion activities
Appendix III – Scope of work
SCOPE OF WORK
Planner group
Order type
NGKSAL Ghalbi
Routine Maintenance & Monitoring Access Fitting Coupon/Probe Installation, Retrievals Cathodic Protection (CP) Monitoring and Minor Maintenance of CP systems Pipeline Right Of Way/Windrow Inspection. Tell Tale Venting on Polyethylene (PE) Lined Pipes. Pipelines pigging operation and pig maintenance Maintenance of Pig Traps Maintenance of Block Valve Stations Maintenance of Company’s Emergency Stock Material Non-Routine Maintenance & Inspection (Planned) CIPS & DCVG Surveys Cathodic Protection Upgrade Intelligent Pigging Verifications [IPV] Routine Automated UT Monitoring Internal / External defect Verifications [Automated UT] Metallic Repairs Epoxy Grout Sleeve [EGS] & Temporary Clamp Non Metallic Repairs Composite Repair Coating Repairs [Epoxy or Stopaq] Manual UT Inspection ROW / Windrow repairing & Sand Removal MOL/ Interfiled pipeline & Block Valve deficiency
*AG
72FP
*AG
72FC
Non-Routine Maintenance & Inspection (Unplanned - Add-hoc) Emergency Repair
NGKS
Non-routine activities Intelligent pigging Marking
I30
72FC
20
PR-1834
Work management for pipeline maintenance & corrosion activities
Appendix IIII – Material buyer selection
21
PR-1834
Work management for pipeline maintenance & corrosion activities
Ref. Ind
Name
Buyer
FPO2 FPO26A F PO 26 B
Mahoney, Brendan MOHAMED RAMIMI A L Ha di, Nas ser Mubarak Abdula AL Aj mi , A li Is sa Ibrahim AL Shahaibi, Salima Hamed Mselem AL Harthy, Salim Mohamed Amour FPO3 Section AL Al Maskri,
TB buyer Inventory Buyer Inventory Buyer
F PO2 6C FPO26D FPO26E FPO3 FPO51
FPO52 FPO53 FPO54 F PO56 FPO6 FPO6A FPO6C FPO6D FPO6E FPO6F F PO 6G FPO6H FPO6J FPO6K FPO6L FPO6N FPO6P FPO6R FPO6S FPR11 FPR13 FPR14 FPR14 FPR15 FPR15 FPR16 FPR17 FPR17 FPR18 FPR19 FPR19 FPR2 FPR22 FPR23 FPR24 FPR25 FPR26 FPR27 FPR28 F PR29 FPS FPW25 FPW 26 FPW27
Mohamed Ahmed Fath AL Musall ami, Zahir Nasser Amour Naavuru, Sudhakar Siyabi, Badriya AL R iyam i, Ayna Ahmed Nasser AL Mahrouqi, Khamis Ali Abdullah AL Baluchi, Ali Soud Abdulla Barwani, Mathla
Invent. Analyst
Material Groups
New variant name
Description
Yes Yes
Purchase Group 1P1,1A6 All All
All 97-99 43-57, 73-85
OM_MM_M_FPO2 OM_MM_M_FPO26A OM_MM_M_FPO26B
TB Buyer (PG: 1P1 & 1A6 ) Inventory Buyer (MG: 97-99 ) Inventory Buyer (MG: 43-57, 73-85 )
Inventory Buyer
Yes
All
58-64
OM_MM_M_FPO26C
Inventory Buyer (MG: 58-64 )
Inventory Buyer
Yes
All
65-70
OM_MM_M_FPO26D
Inventory Buyer (MG: 65-70 )
Inventory Buyer
Yes
All
13-42
OM_MM_M_FPO26E
Inventory Buyer (MG: 13-42 )
TB buyer TB buyer
1C,1C3 1O2
ALL ALL.
OM_MM_M_FPO3 OM_MM_M_FPO51
TB Buyer (PG: 1C & 1C3 ) TB - GAS (PG:1O2)
TB buyer
1O3
ALL.
OM_MM_M_FPO52
TB - GAS (PG:1O3)
TB buyer TB buyer Direct Charge Buyer TB buyer
1O4 1O1 1O
All All All
OM_MM_M_FPO53 OM_MM_M_FPO54 OM_MM_M_FPO56
TB - GAS (PG:1O4) TB - GAS (PG:1O1) GAS Others(PG:1O)
1A1-1A5, 1C11C2, 1P All
All
OM_MM_M_FPO6
TB Buyer (PG: 1A1-1A5, 1C1-1C2, 1P)
31, 34, 62
OM_MM_M_FPO6A
DC Buyer (MG 31, 34 & 62 )
All
22, 38, 41-42 & 58
OM_MM_M_FPO6C
DC Buyer (MG 22, 38, 41-42 & 58 )
All
73,76
OM_MM_M_FPO6D
DC Buyer (MG: 73, 76)
All
OM_MM_M_FPO6E
DC Buyer (MG 36-37, 39-40, 43-56, 75,82,84)
OM_MM_M_FPO6F
DC Buyer(MG13-16, 18-19, 21, 23-30,32-33, 35)
All
36-37, 39-40, 43-56, 75,82,84 13-16, 18-19, 21, 2330,32-33, 35 77
OM_MM_M_FPO6G
DC Buyer (MG: 77)
All
81,85
OM_MM_M_FPO6H
DC Buyer (MG: 81, 85)
All
65, 68
OM_MM_M_FPO6J
DC Buyer (MG 65 & 68)
All
78-80, 83
OM_MM_M_FPO6K
DC Buyer (MG: 78-80 & 83)
All
60
OM_MM_M_FPO6L
DC Buyer (MG 60)
All
59, 61
OM_MM_M_FPO6N
DC Buyer (MG: 59 & 61)
All
74
OM_MM_M_FPO6P
DC Buyer (MG: 74)
All
17, 20, 57, 63
OM_MM_M_FPO6R
DC Buyer (MG 17, 20, 57, 63)
All
64, 66-67, 69-70
OM_MM_M_FPO6S
DC Buyer (MG 64,66-67,69-70)
1D2
All
OM_MM_M_FPR11
TB Buyer (PG: 1D2)
1D3
All
OM_MM_M_FPR13
TB Buyer (PG: 1D3)
Yes
All All
86-88 86-88
OM_MM_M_FPR14 OM_MM_M_FPR14a
Inventory Buyer ( MG:86-88 ) DC Buyer (MG: 86, 88)
Yes
All
89
OM_MM_M_FPR15
Inventory Buyer ( MG:89 )
All
89-90
OM_MM_M_FPR15a
DC Buyer (MG: 89-90)
Yes Yes
1D1, 1D4 All All
All 90-96 96-99
OM_MM_M_FPR16 OM_MM_M_FPR17 OM_MM_M_FPR17a
TB Buyer (PG: 1D1 & 1D4) Inventory Buyer ( MG:90-96 ) DC Buyer (MG: 96)
Yes
All
71
OM_MM_M_FPR18
DC Buyer (MG: 71)
1T
All
OM_MM_M_FPR19
Low Value Materials (PG:1T)
All
72
OM_MM_M_FPR19a
DC Buyer (MG: 72)
1P3 1S2,1P2 1S3 1S4 1S5,1S7
All All All All All
OM_MM_M_FPR2 OM_MM_M_FPR22 OM_MM_M_FPR23 OM_MM_M_FPR24 OM_MM_M_FPR25
TB Buyer (PG: 1P3) TB Buyer (PG: 1S2 & 1P2) TB Buyer (PG: 1S3) TB Buyer (PG: 1S4) TB Buyer (PG: 1S5 & 1S7)
1S1 1S6 All
All All 91-95
OM_MM_M_FPR26 OM_MM_M_FPR27 OM_MM_M_FPR28
TB Buyer (PG: 1S1) TB Buyer (PG: 1S6) DC Buyer (MG: 91-95)
All
71-72
OM_MM_M_FPR29
Inventory Buyer ( MG:71-72 )
1AU All All
13aaaa-99xxxx 04 01-12
OM_MM_M_AUTO OM_MM_M_FPW25 OM_MM_M_FPW26
DC Auto Buyer (MG 13-99)-1AU Inventory - Drilling (MG:04) DC-Drilling (MG:01-12)
All
01-03, 05-12
OM_MM_M_FPW27
Inventory-Dril(MG:01-03 & 05-12)
Direct Charge Buyer Direct Charge Buyer AL Lamki, Thabit Mohd Direct Charge Suleiman Buyer AL Baloushi, Muna Direct Charge Abdullah Khamis Buyer AL Harassy, Fadhila Direct Charge Shaib Ali Buyer AL Barwani, Ali Direct Charge Masoud Hilal Buyer AL Harthy, Ali Saleh Direct Charge Mohd Buyer Zakwani, Saif Direct Charge Buyer AL Behlani, Ibtisam Ali Direct Charge Hamood Buyer AL Mahrouqi, Rahma Direct Charge Buyer AL Marhuby, Moza Direct Charge Musallem Amour Buyer AL Bimany, Munira Direct Charge Zahir Salim Buyer Ambusaidy, Ali Direct Charge Buyer ESRY, SHAMSA Direct Charge Buyer Sabbagh, AbdulWahab TB buyer Abdul Malek, Atiankartina Ismaily Kauthar Ismaily Kauthar
All
TB buyer
Inventory Buyer Direct Charge Buyer AL Naamani, Sabaha Inventory Buyer Saleh Sultan AL Naamani, Sabaha Direct Charge Saleh Sultan Buyer Harthy, Abdulla TB buyer Hajry, Salim Inventory Buyer Hajry, Salim Direct Charge Buyer Amri, Abdullah Direct Charge Buyer AL Harthi, Hassina TB buyer Said Hamdan AL Harthi, Hassina Direct Charge Said Hamdan Buyer Rawahy, Mohammed TB buyer Zakwani, Badriya TB buyer Utot, Norina TB buyer Busaidy, Sabah TB buyer Rashdy, R ashid TB buyer Abdula Seif Harthi, Zuwaina TB buyer JABRY, ZUBAIDA TB buyer AL Harrasy, Zeyana Direct Charge Suleiman Nassor Buyer AL Alawi, Badar Inventory Buyer Humaid Salim Automation Support Automation Habsy, Sheikha Inventory Buyer Busaidi, Khoula Direct Charge Buyer Saqry, Mohammed Inventory Buyer
Yes
Yes
22
PR-1834
Work management for pipeline maintenance & corrosion activities
Appendix V – Supporting documents Supporting documents required to verify COCs Monthly Routine Monthly Routine activities claim shall include: Activities invoice A) Summary of all Routine activities Summary shows agreed monthly values and any addition or deletions
B) CP data Monthly / Quarterly PACER update COC COC states that PACER is updated with CP station data and CP test post data
C) Monthly Pigging data PACER update COC COC states that PACER is updated with the monthly pigging data
D) Tell Tale Venting data PACER update COC COC states that PACER is updated with tell tale venting data
E) Access fitting installation / retrieval Summary of COSASCO coupon retrieval data sheet
F) CP Monitoring and maintenance Summary of actual routine CP activities Vs planed
G) Tell Tale Venting monitoring Summary of actual tell tale venting activities Vs planed
H) Pipeline Right of way/ windrow inspection and reporting Summary of ROW / windrow inspection
I) Pipeline pigging operation and pig maintenance Summary of actual pigging activities Vs planed
J) Maintenance of pig launchers, receivers & ESD valves Summary of actual pig launchers & receivers activities Vs planed
K) Maintenance of block valve stations Summary of actual block valves activities Vs planed
L) FSM IT Monitoring Summary of FSM monitoring
M) Maintenance of emergency stock materials Summary of actual maintained materials Vs plan
Maintenance/pigging Support crews
Auto UT
CIPS/DCVG
Integrity check
Civil claims
Crews claim shall include: A) COC B) Summary of resources used C) Day work sheets D) Delivery notes in case of materials supply E) Copy of latest approved estimate Auto UT claim shall include: A) COC B) Summary of resources used C) PACER update sheet D) Summary sheet of scanned area by 3 rd party contractor E) Copy of latest approved estimate CIPS/DCVG claim shall include: A) COC B) Summary of resources used C) Transmittal of receive and accept CIPS/DCVG report D) Copy of latest approved estimate Integrity check claims shall include: A) COC B) Summary of resources used C) Day work sheets D) Transmittal of receive and accept integrity check report E) Copy of latest approved estimate Civil claims shall include: A) COC B) Calculation Sheet C) Day work sheets D) Transmittal of receive and accept integrity check report E) Copy of latest approved estimate
23
PR-1834
Work management for pipeline maintenance & corrosion activities
Appendix VI – Corrective Maintenance Prioritisation Tool
How is the Priority is Set Priority
Description
The LAFD is calculated in Work Order
Priority 1
Emergency
Notification Creation date + 30
Priority 2
Schedule Breaker
Notification Creation date + 30
Priority 3
Response 2 Weeks
Notification Creation date + 30
Priority 4
Response 4 Weeks
Notification Creation date + 30
Priority 5
Response 8 Weeks
Notification Creation date + 180
Priority 6
Response 6 Months
Notification Creation date + 180
Priority 7
Response 12 Months
Notification Creation date + 360
24