OIL CAVERNS Risk mitigation through awareness and vigilance Thierry YOU OSR2G Nancy Fr 2013
Geotechnical Risk Mitigation for Hydrocarbon Storage Panorama of Hydrocarbon Storage Design Methodology Feedbacks Conclusions
OSR2G Nancy Fr2013
2
Geotechnical Risks
Reference list - Manuel de Mécanique des roches Tome III - EC7 Eurocode 7 - NF94-500 Geotechnical Tasks - ISRM WG Design Methodology, Hudson & Feng - ASCE Geotechnical Baseline Report - AFTES GT1, GT25, GT32
OSR2G Nancy Fr2013
3
Géostock Expertise Different types of hydrocarbon storage: Salt leached caverns
Mined cavern
Aquifer, depleted field
Natural Gas, LPG, liquid hydrocarbons
LPG, Liquid Hydrocarbons
Natural Gas
OSR2G Nancy Fr2013
4
Underground storage Mined caverns technologies MINED CAVERN
OSR2G Nancy Fr2013
DISSUSED MINES
5
Underground storage Mined caverns technologies Lavera LPG Storage Caverns
Lavera Butane Cavern – Construction OSR2G Nancy Fr2013
Operation Shaft Area 6
Construction of mined caverns Geostock Designer or owner’s assistant: UNDERGROUND STORAGE IN MINED CAVERN GEOSTOCK EXPERIENCE 6
25
5
CAVERNS CONSTRUCTION
20
4 15 3 10 2
5 1
OSR2G Nancy Fr2013
2011
2009
2007
2005
2003
2001
1999
1997
1995
1993
1991
1989
1987
1985
1983
1981
1979
1977
1975
1973
1971
1969
0
1967
0
CAVERNS COMPLETED (CUMULATIVE)
SITE UNDER CONSTRUCTION PROJECTS COMPLETED
7
OSR2G Nancy Fr2013
8
OSR2G Nancy Fr2013
9
OSR2G Nancy Fr2013
10
Mined caverns technologies and associated risks Principes
Operability
Stability
Hydraulic Containment
OSR2G Nancy Fr2013
11
UNDERGROUND STORAGE MINED CAVERNS TECHNOLOGIES
Caverns are unlined Tightness only depends on natural convergent flowrates from the rockmass towards the cavern : this is the hydrodynamic containment principle
Containment principle = HYDRODYNAMIC PRINCIPLE OSR2G Nancy Fr2013
12
UNDERGROUND STORAGE MINED CAVERNS TECHNOLOGIES Product containment Criteria
ground level
water table water gallery
water curtain
flow-lines
maj 11/01
unlined caverns
OSR2G Nancy Fr2013
13
OSR2G Nancy Fr2013
14
Operation shafts
OSR2G Nancy Fr2013
15
Various lay-out adapted to geological conditions
OSR2G Nancy Fr2013
16
UNDERGROUND STORAGE MINED CAVERNS TECHNOLOGIES Diesel Oil Storage of May–sur-Orne
Upper Levels – (Morts terrains)
OSR2G Nancy Fr2013
Access Shaft (Fontenay-le-Marmion)
17
Cavern dimensions: large variations Volume : from 8 000 m3 (LPG) to 2 Mm3 (Crude Oil)
Height: from 6 m (chalk) to 32 m (granite / gneiss)
Section : Up to 650 m²
OSR2G Nancy Fr2013
18
UNDERGROUND STORAGE MINED CAVERNS CONSTRUCTION METHODOLOGY Pyongtaek LPG Cavern
U-1 Crude Oil Cavern
30m
18m
17.5m
22m
12.8m
OSR2G Nancy Fr2013
19
UNDERGROUND STORAGE DESIGN METHODOLOGY
A mined storage cavern is neither A mine A civil work
A laboratory
But our design team learns from all and from all projects
OSR2G Nancy Fr2013
20
Methodology & Codes why?
Rockbolting alternatives based on a individual judgement.
(Drawing from a cartoon in a brochure on rockfalls published by the Department of Mines of Western Australia)
OSR2G Nancy Fr2013
21
Underground storage Mined caverns GEOGAZ - LAVERA Propane and Butane Storage Caverns Layout
GEOGAZ - Propane GEOGAZ - Butane
OSR2G Nancy Fr2013
22
SIMPLIFIED DESIGN CHART FOR ROCK ENGINEERING ( BIENIAWSKY - 1987 ) OSR2G Nancy Fr2013
23
Typical mode of failure, rock falls
J. Fine 1993 OSR2G Nancy Fr2013
24
Flowchart of rock mechanics modeling and rock engineering design approaches (Feung and Hudson, 2004).
OSR2G Nancy Fr2013
25
OSR2G Nancy Fr2013
26
Typical failure modes of large underground cavern group and its related tunnels
OSR2G Nancy Fr2013
27
Specificities of large sections Likelihood of toe/wall failure
OSR2G Nancy Fr2013
28
Conclusions 1 Methodological advance will bring us huge progresses but also brakes to new ideas.
We still have to learn! Feedback loops and validations remain essential. “No theory can be considered satisfactory until it has been adequately checked by actual observations”. Prof. Ralf B. Peck.
Designers and regulatory bodies tend to place increasingly reliance on analytical procedures of growing complexity and to discount judgement as a nonquantitive, undependable contributor to design Prof. Ralf B. Peck.
OSR2G Nancy Fr2013
29
Mined Caverns ULSAN (South Korea) Owner: SK-GAS 310 000 m3 Propane - 240 000 m3 Butane
Main features:
Parallel galleries Andesite and metasedimentary sandstone Depth: 119 m (propane) - 63 m (butane) Propane: length 830 m - Section 308 m2 Butane: length 629 m - Section 342 m2 Beginning of construction: 1984 Commissioning: 1988
Main Geotechnical features:
Fault crossing Careful mapping Rock fall and repair works Scale effect on wedges
OSR2G Nancy Fr2013
30
Mined Caverns SYDNEY (Australia)
Owner: ELGAS 83 000 m3 Propane
Main features:
Parallel galleries - Sandstone Length: 910 m - Section 142 m3 Depth: 124 m Beginning of construction: 1996 Commissioning: 2000
OSR2G Nancy Fr2013
Main Geotechnical features: Highly anisotropic environment High horizontal stresses Roof falls Grouting works Smooth blasting and tolerance control Difficult construction supervision and contractual environment Design ‘model’ difficulties Post construction environment
31
ROCK FALL EXPLANATIONS (20+)
A large number of explanations were put forward by the parties involved, many of them with ulterior motives: unsuitable section, inappropriate and damaging explosive, poor workmanship (drilling, bolting, etc.), untested rock bolts, too differed bolt grouting, poor site organisation, unsuitable numerical and structural models, underdesigned rockbolts, inappropriate bolting patterns, unsuitable excavation sequence, poor and inefficient quality control, lack of design methodology (EC7), lack of monitoring and inspection, unforeseen stress release, random vertical joints, lack of spot bolt decision on visible instabilities, inclined defects in sheet facies, too high water pressure imposed in the fissures, etc.
At that stage, none of the specified monitoring measures that had been prepared for design validation (geological joint mapping, convergence measurement, profile mapping, pull-out test, etc.), that certainly would have helped as new design basic data, had been implemented.
Maintaining roof integrity was crucial for stability, as was established latter (You et al. Johannesburg ISRM2003)
OSR2G Nancy Fr2013
32
Mined Caverns VISAKHPATNAM (India) Owner: SALPG 127 600 m3 Propane - Butane mixture
Main features:
Parallel galleries + 1 central access tunnel Depth: 162m/msl Length: 342 m Section: 338 m2 2 operation shafts Construction: 2004-2007
Design adaptation High horizontal stress consideration Joint opening model
900 elliptic - crown
800
Sv = 48 bar
ovaloid - crown
haunch
rectangle - haunch
700
crown
3.5 Sv
elliptic - sidewall
Tangential stress (bar)
sidewall
H
600
Main Geotechnical features:
ovaloid - sidewall rectangle - sidewall
500
W
400 300 200 100 0 -100 -200 0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
Slenderness W/H
OSR2G Nancy Fr2013
33
OSR2G Nancy Fr2013
34
OSR2G Nancy Fr2013
35
Feedbacks DURING SITE INVESTIGATION : Supervision by design team during drilling and testing ==> RQD on fresh cores ==> representative sample selection ==> site adaptation of water test
DURING CONSTRUCTION : GEO SURVEY sometime after each blast ==> cartography geo-geo-hydro+ geometry ==> rock quality «i.e. Q factor » ==> adaptative support ==> water monitoring
OSR2G Nancy Fr2013
36
Specificity of large caverns(2) Need of a fine tuned structural investigation in order to adapt bolt support: MUW-10
MUW-6
MUA2 W
MUB1 W
MUB2 W
V.6.287
V.10.215
MUA1 W
MUW-8
Section V9 Ch.242.6
OSR2G Nancy Fr2013
37
GEOTECHNICAL RISKS Geological Mapping: … collection and interpretations
OSR2G Nancy Fr2013
38
Mined Caverns GARGENVILLE (near Paris - France)
Main features:
Chalk Galleries EW and NS Length: 1400 m (EW) - 1300 m (NS) Section: 49 m2 Depth: 132 m Beginning of construction: 1972 Commissioning: 1977 Abandonment: 2008+
Owner: GEOVEXIN 130 000 m3 Propane
Main Geotechnical features: Post peak behavior Construction tolerances Importance of construction record and operation monitoring Adaptative design Closure design for abandonment procedure
OSR2G Nancy Fr2013
39
LPG underground storage Operation shaft dewatering vent
LPG outlet LPG inlet
gas LPG liquid LPG water clay concrete fail safe valve CAVERN
Maj 08/98
instrumentation
OSR2G Nancy Fr2013
LPG pumps
water pumps
40
STEPS OF GEOTECHNICAL RISK MANAGEMENT ( From AFTES GT 32+..) 1) Risk identification: Each project is a prototype, no universal approach available
2) Hierarchize, assess and evaluate the risk: Danger of subjectivity, explain to share
3) Risk treatment ( risk matrix, risk register, event tree) Share between parties, role of insurance ( GBR, GDR)
4) Monitor and control Check actions, vigilance
5) Memorize and capitalise lessons learned ( feedbacks) Difficult but needed.
OSR2G Nancy Fr2013
41
Project studies and phasing Project Development
OSR2G Nancy Fr2013
42
Risk Tree
prepared for one known mined cavern storage 1/2 Weathering
1 of rock walls 2
Ageing of supports
3
Seismic shaking
A Collapse of Cavern or Accesses
Possible exclusion under certain conditions (INERIS DRS-09-103911-09771A) Local or general collapse
Increase of interstitial 4 pressure and gradients Zone poorly supplied with natural water
11 Local increase of permeability on walls
D Local drop of hydraulic gradient and confinement.
C Cavern pressure exceeding critical pressure for leak
OSR2G Nancy Fr2013
Loss of hydrodynamic containment of the cavern 43
Séquence 2 : Risk assessment (2/2)
J. PIRAUD – Incertitudes et risques géotechniques - 29/01/13
Vraisemblance
Matrice des risques Possible
4
8
12
16
Peu Probable
3
6
9
12
Très peu Probable
2
4
6
8
Improbable
1
2
3
4
Faibles
Moyennes
Fortes
Très fortes
Conséquences
Exemple of risk matrix
Colours represent the resulting level of risk for each event (green : acceptable without further action ; red unacceptable risk).
The level of risk related to an event may be deemed more or les acceptable depending of targets and priority of Owner. Decision to take action against a risk is therefore a task devoted to Owners and Engineers.
OSR2G Nancy Fr2013
44
Conclusions 2 Discover the truth through practice and again through practice verify and develop the truth- Mao Tse Toung Nature to be commanded must be obeyed- Francis Bacon
Complexity of geotechnical risks encourage us toward the virtue of humility and listening. We need to carry out a vast amount of observational work, but what we do should be done for a purpose and done well- R.B.Peck Awareness and vigilance naturally lead to design validation and monitoring. Feedbacks and Design Validation Loops remain essential. ”If something is discovered that does not agree with the hypothesis, rejoice! You can then really learn something new. You are on your way to an understanding of the problem”. Ralf B. Peck.