Installation Quality
Introduction Quality check is an activity which needs to be conducted after site installation is completed. Quality Check is done to verify that the installed site meets the installation guidelines or not.
2013 © Samsung Electronics
2
Table Of Contents Installation Quality Check List RF Antenna RRU - Remote Radio Unit GPS Antenna CDU - Cabinet Digital Unit Other Important Quality Checks
2013 © Samsung Electronics
3
1) Antenna Fixing-RF Antenna Check for proper antenna bolt tightening. Tightening of the bolts should be properly done i.e. bolts should not be loose and should not be over tightened. If the bolts are over tightened, threads may get damaged. Correct torque value is (239.7-270.3 kgf.cm.) Antenna should not move when pushed with force. Antenna should withstand strong air turbulence and should not move even when pushed with force. This is to ensure Antennas remain oriented in the desired direction all the time Attaching Base station Antenna on Poles Using Clamps
Ø 40-90 mm
14 mm
* Torque : 239.7 ~ 270.3 kgf.cm (23.5~26.5 Nm)
2013 © Samsung Electronics
4
2) Antenna Position- RF Antenna In case the height of structure is more than 30M from the ground, lightning-protection umbrella angle should be 23 degrees. In case the height of structure is Less than 30M from the ground, lightning-protection umbrella angle should be 45degrees. [Less than 30M ]
[More than 30M ] Lightning Rod
45°
45°
23°
23°
. GPS Antenna
RRU
2013 © Samsung Electronics
GPS Antenna
RF Antenna
RRU
RF Antenna
5
3) Antenna Azimuth / Tilt Ensure according to TSSR data Get the values of the Antenna Azimuth for Alpha, Beta and Gamma Sector and Antenna tilts from the TSSR Document and verify the calculated values with the values mentioned in the TSSR document. The values should match.
Mechanical down tilt (In the case of tilting)
14 mm * Torque : 239.7 ~ 270.3 kgf.cm (23.5~26.5 Nm)
Azimuth Measurement-Compass Tilt Measurement: Tilt Meter 2013 © Samsung Electronics
6
4) Cable Routing Condition (Jumper & RET) 1/2 Min. bending radius should be 125 mm
RF Antenna
RET Cable Assembly
R’
Min. radius of curvature
Straight cable section
RET Connector
RF cable type
Min. Radius
Manufacturer
1/2 ‘’
125 mm
LS
Connect a 1/2 in. Jumper line to the RF antenna. - If excessive force is applied to the connector assembled to the antenna port or cable, it may cause poor contact or damage because the straight cable section is not long enough. 2013 © Samsung Electronics
7
4) Cable Routing Condition (Jumper & RET) 2/2 First cable tie should be used at 600 mm from antenna port then after at every 300 mm
2013 © Samsung Electronics
8
5) Cable Labeling Labeling should be done according to guideline (Alpha-Blue,Beta-Red,Gamma-Green) Alpha Sector
Sector Alpha
Beta
Gamma
2013 © Samsung Electronics
Beta Sector
Gamma Sector
RF Cable
Color Code
Path#0 Path#1 Path#2 Path#3 Path#0 Path#1 Path#2 Path#3 Path#0 Path#1 Path#2 Path#3
Blue / Yellow(One String) Blue / Yellow(Two String) Blue / Yellow(Three String) Blue / Yellow(Four String) Red / Yellow(One String) Red / Yellow(Two String) Red / Yellow(Three String) Red / Yellow(Four String) Green / Yellow(One String) Green / Yellow(Two String) Green / Yellow(Three String) Green / Yellow(Four String) 9
6) Feeder weather proofing Check Point Antenna cables are finished with insulation tape and with 2 ties, no shrinkage tube or tape missing
Check distance between RRU bottom & the lower cable tie with steel ruler. It should
be minimum 80mm
2013 © Samsung Electronics
10
7) AISG(RET) Cable Connection & Daisy Chain port (1/2) AISG cable connector should be tighten to RET male port. RET daisy chain port should be tighten with weather proof cap to avoid water seepage.
Antenna side
RRH side
2013 © Samsung Electronics
11
7) AISG(RET) Cable Connection & Daisy Chain port (2/2)
If found a Gap, turn the cap clockwise tightly with finger and mark up the permanent marker .
2013 © Samsung Electronics
12
Quality Check List for RRU
13
1) RRU Bracket Fixing (1/2) Check tightening status of nuts and bolts Check horizontal and vertical leveling
[
Pole Mount Bracket Assembly (Universal Bracket) [
Unit Mounting Bracket Assembly * M8 Hex. Bolt/Nut Torque : 122 kgf.cm (Tolerance ±10%) * M12 Hex. Bolt/Nut Torque : 390~400 kgf.cm
Use Spirit Level to check the leveling of the RRU
2013 © Samsung Electronics
14
1) RRU Bracket Fixing (2/2) CHECK POINT #1 4Bolts on the right and left of RRU shall be securely fastened up #2 If found loose screws fasten them again. #3 Make sure that all screws shall be securely fastened up and mark all screws with permanent marker
2013 © Samsung Electronics
15
2) Bolt, Nut, Washer, Bushing, Bakelite status Check all fixing assembly item should be in place according to installation guideline without missing or damage
Bakelite(5T) M8×30L Hex. Bolt
Unit Mounting Bracket Upper furrow
Unit Mounting Bracket
Bakelite(5T) M8 Insulation Bushing M8 Plain Washer M8 Spring Washer M8 x 30L Hex. Bolt
2013 © Samsung Electronics
16
3) RRU insulation test Check continuity with Multimeter bet ween Pole and RRH body(Resistance Value <500V/100M Ohm)
[Strong Anchor fixing Hex. Bolt]
[RRU fixing Hex. Bolt]
Bakelite and insulation bushing should be in place Perform this test only after disconnect the Grounding Cable
[Stud Bolt]
[RRU fixing Hex. Bolt]
[U[U-Bolt]
[RRU fixing Hex. Bolt]
2013 © Samsung Electronics
Indication standard : more than 500V/100MΩ
17
4) Cable Status CPRI, Power, RET cable should be terminated on desired port with correct polarity Check all cable for any damage and sharp bend. Check the routing of all the cables is done properly.
Power cable cover should be projected 10mm from floor of window inside
10mm Power Gland Nut
2013 © Samsung Electronics
18
6) RRU Grounding Grounding should be done using F-GV 6.0㎟ x 1C cable, 2Hole Terminal. Check cable for any damage and sharp bend. Check the routing of the cable is done properly. Check whether grounding cable lugs are covered with the green heat shrink tube. SEMS(M6x12L, 2EA)
RRU Ground Cable
Green heat shrink tube
CPRI for Pressure Terminal RRU for Pressure Terminal
Cable Tie CPRI Ground Cable RRU Ground Cable [R[R-03] ~ [R[R-11] Connection of
Ground Cable
* M6 SEMS Torque : 33.28~49.92 kgf.cm 2013 © Samsung Electronics
19
7) RRU Input Power Check Measure the voltage at both the terminals. Recommended voltage should range from -40 to -57 V DC. Voltage drop should not be more than 1 Volt. Check whether the caps are fixed on the power tapping after power connection is done inside RRU Cross check the color coding of Power cable: Black (RTN) & White (-48 VDC) Check the Heat shrink tube color should be RED( RTN) & BLUE ( -48 VDC)
2013 © Samsung Electronics
20
8) RRU Window tightening Status CHECK POINT #1 4screws shall be securely fastened with 12kgf-cm torque #2 Check “site ID” at the bottom of window face and take a picture of it #3 Make sure that all screws shall be securely fastened up & mark all the screw with permanent marker
2013 © Samsung Electronics
21
9) Cable Labeling(CPRI,Power, Grounding ,RET Cable & Jumper Cable) Check all the labeling done as per installation guideline
25 TMC
25 TMC
30 TMC
The new format of labels
2013 © Samsung Electronics
22
10) Cable Gland tightening Status-Optic Cable gland (1/2) CHECK POINT : #1 Filler and CAP must be included in Gland #2 GAP check as shown in figure
2013 © Samsung Electronics
23
10) Cable Gland tightening Status-Power Cable gland (2/2) CHECK POINT : #1 Filler and CAP must be included in Gland #2 Gap check #3 The length of straight power cable and the positions of tied up to Pole as shown in figure
2013 © Samsung Electronics
24
Quality Check List for GPS
25
1) GPS Pole Fixing and GPS Arrestor (1/2) CHECK POINT #1 GPS antenna should be within 23/°45°angle of lightning protection umbrella. [Less than 30M ]
[More than 30M ] Lightning Rod
45°
45°
23°
GPS Antenna
RRU
2013 © Samsung Electronics
23°
GPS Antenna
RF Antenna
RRU
RF Antenna
26
1) GPS Pole Fixing and GPS Arrestor (2/2) CHECK POINT #2 Ground cable shall be securely connected to CDU #3 There shall be no missing part #4 Need to check all the labeling as per guideline * items required: Nut and 6sq.mm pressure terminal ③ tooth washer, [MGB] [D[D-25] GPS
Antenna
[D[D-11] ~ [D19]
Connection of GPS Ground Cable
②
① [D[D-30] RG-316D Cable-1
[D[D-27] GPS
2013 © Samsung Electronics
Cable(CNT-400)
[D[D-28] GPS
Arrestor
27
2) GPS Connectorization CHECK POINT #1 Check both connector should be made as guideline #2 Crimp ring should crimp with hexagonal crimping tool two times
2013 © Samsung Electronics
28
Quality Check List for CDU
29
1) CDU System Fixing- Horizontally installed (1/2) CHECK POINTS: #1 FAN MODULE shall be on the left front #2 The color of Optic cable boots shall be RED and BLUE from the left to right #3 All dust plug shall be kept securely. #4 All screws shall be securely fastened
2013 © Samsung Electronics
30
1) CDU System Fixing- Vertically installed (2/2) CHECK POINTS: #1 FAN MODULE shall be on the top front #2 The color of Optic cable boots shall be RED and BLUE from the top to bottom #3 All dust plugs shall be kept securely. #4 All screws shall be securely fastened
2013 © Samsung Electronics
31
2) CDU (Dummy Panel & Unused Port) Condition CHECK POINT: #1.Check unused port covered with cap #2.Check unused slots covered with dummy panel
Dummy Panels Unused Ports
2013 © Samsung Electronics
32
3) CDU Grounding CHECK POINTS : #1 Ground cable shall be securely fastened on the back of CDU #2 Grounding should be done using F-GV 4.0㎟ x 1C cable, 2Hole Terminal. #3 Check cable for any damage and sharp bend. #4 Check the routing of the cable is done properly. #5Check whether grounding cable lugs are covered with the green heat shrink tube.
2013 © Samsung Electronics
33
4) Cable status Power cable connector and ground cable inspection CHECK POINT #1 Power connector shall be securely connected to receptacle #2 Ground cable shall be securely fastened #3 Check all cable for any damage and sharp bend. #4Check the routing of all the cables is done properly.
2013 © Samsung Electronics
34
5) SFP module Check SFP module Single mode (Color Blue) If Black multi-mode SFP is found, please return it to Samsung contact person after replacing it with Blue single-mode SFP
Connecting to backhaul cable (Optic) Connect the backhaul cable (opticsingle mode) from the switch/router to BH2 and BH3 ports of the CDU UAMA board. General Case : Optic single cable Connect the CDU-side connectors (LC/UPC) of the cable to the BH2 and BH3 ports of the CDU UAMA board.
2013 © Samsung Electronics
35
Other Important Quality Checks
36
1) Roxtec Check all cable entries in roxtec as per guideline Boots should be fixed properly without any gap
2013 © Samsung Electronics
37
2) ODC Rack internal state All cable should be properly laced Ensure the cleanliness inside the ODC
2013 © Samsung Electronics
38
3)MCB Mention the MCB rating Ensure the labeling MCB screw should be tighten on the copper not on insulation cover Cross check the color coding of Power cable: +VE Black & -VE is White
CDU RRU-0
2013 © Samsung Electronics
RRU-1 RRU-2
39
4)Cable Tray Open cable tray cap and check cable routing at key points and cable should not be crossed or twisted
5) Equipment Status Check for any damages(scratches, dents) on all elements.
2013 © Samsung Electronics
40
Quality Checklist SITE CHECK LIST Site ID Site Name
Ite m
Date Solpar Result (OK/NOK )
Area Auditor
Remarks
Weig ht
Description
1. Pane l Ante nna 1.All Antennas bolt should be tightened w ith torque 239.7270.3 kgf .cm. 2.Antenna should not be moving w hen pushing w ith f orce.
1) Antenna Fixing
1
2) Antenna Position
1
All antennas should be w ithin 45°angle of lightning protection umbrella
3) Antenna A zimuth / Tilt
1
Ensure according to TSSR data
4) Cable Routing Condition (Jumper & RET)
1
1.Min. bending radius should be 125 mm 2.First cable tie should be used at 600 mm f rom antenna port then af ter at every 300 mm
5) Cable Labeling
2
Labeling should be done according to guideline (Alpha-Blue,Beta-Red,Gamma-Green)
6) Feeder w eather proof ing
7) AISG(RET) cable connection & Daisy chain port
2.5
1.Heat Shrink Tube length 150 mm, diameter 41mm, 2.Heating should shrink the tube properly w ith no air gap at both ends of tube
7.5
1. AISG cable connector should be tighten to RET male port. 2. RET daisy chain port should be tighten w ith w eather proof cap not to be seepage.
2. RRH Part 1) RRH Bracket Fixing 2) Bolt,Nut,Washer,Bushing, Bakelite status
3) RRH isolation test
1
1.Check tightening status of nuts and bolts 2.Check horizontal and vertical leveling
2
Check all f ixing assembly item should be in place according to installation guideline w ithout missing or damage
2
4) Cable Status
1
Check continuity w ith Multimeter betw een Pole and RRH body(Resistance V alue <500V/100M Ohm) *Bakelite and insulation bushing should be in place 1.CPRI,Pow er,RET cable should be terminated on desired port w ith correct polarity 2.Check all cable f orlength any damage and sharp31mm, bend. 1.Heat Shrink Tube 150 mm,diameter
5) RRH Feeder w eather proof ing
2.5
2.Heating should shrink the tube properly w ith no air gap at both ends of tube
6) AISG(RET) cable connection
7.5
1. AISG cable connector should be tighten to RRH RET f emale port. 1.Grounding should be done using F-GV 6.0 x 1C cable, 2Hole Terminal, 2.Check cable f or any damage and sharp bend. 3.Check the routing of the cable is done properly. 4.Check w hether grounding cable lugs are covered w ith the green heat shrink tube.
7) RRH Grounding
8) RRH input Pow er Check
2
___V
1
9) RRH Window tightening Status
25
10) Pow er cap , Heat Shrink Tube
2
11) Cable Labeling(CPRI,Pow er, Grounding ,RET Cable & Jumper Cable) 12) CPRI Cable termination inside the RRH
2
㎟
1. Check DC Voltage, mention the pow er. 1. All the RRH w indow screw should be tightened w ith torque driver T20 w ith 12.0kgf .cm f orce, in the pattern mentioned in Installation guideline. 1. Check w hether the caps are f ixed on the pow er tapping af ter pow er connection done inside RRH. 2. Check w hether pow er cable lugs are covered w ith the Blue(-) & Red(+)heat shrink tube. Check all the labeling done as per installation guideline
2
1.CPRI cable w ith insulation cover inside the RRH Box should be equal to 60 mm 2.CPRI termination polarity w ill be Blue(Tx) & Red(Rx)
5
1. Check w hether the Glands of pow er cable, CPRI cable are tightened using standard torque value 30.0kgf .
1) GPS Pole Fixing
1
GPS antenna should be w ithin 45°angle of lightning protection umbrella.
2) GPS Arrester
2
3) Cable status
1
13) Cable Gland tightening Status 3. GPS Part
4) GPS Labeling(CNT-400,RG- 316 D,Ground cable) 5) GPS Connectorization
2013 © Samsung Electronics
1
5
㎟
1.Install the GPS arrestor on the f rame of 19" rack 2.Grounding should be done using F-GV 6.0 x 1C cable 1.CNT-400,RG- 316 D,Ground cable should be terminated on desired port 2.Check all cable f or any damage and sharp bend. As per Guideline 1.Check both connector should be made as guideline 2.Crimp ring should crimp w ith hexagonal crimping tool tw o time
41
Acceptance Test Procedure ATP 11 A is the acceptance test Procedure for the verification of the Hardware Installation and includes the sections as per the ATP Document. ATP 11B is the acceptance test for the verification of Backhaul Integration
Microsoft Office Word 97 - 2003 Document
2013 © Samsung Electronics
43
Commissioning of eNodeB (Including ATP11_B)
Mode of Commissioning- eNodeB Manual Commissioning Solpar needs to commission the equipment at site. This is for first 6,216 eNodeBs to be deployed at different locations
Plug and Play Commissioning This option is available after deployment of first lot of 6,216 eNodeBs’. No Need to commission the CDU at site. Solpar needs to power on the equipment & site will automatically get integrated through LSM-R. Solpar team should standby at the site till the integration activity is done from LSM-R.
2013 © Samsung Electronics
45
Pre-requisites of Commissioning RS232 C Cable or Ethernet Cable (Debug Cable) Laptop with serial or Ethernet Port CLI Login details TeraTerm Application/other Telnet application software installed on Laptop Site Parameter details like IP of LSM-R, IP of eNodeB, IP of CSS- Gateway etc. 4G Dongle for data call test (In case of Backhaul availability)
2013 © Samsung Electronics
46
Login Options 1. Serial Port(RS232) interface 2. Ethernet(RJ45) Interface (Recommended)
2013 © Samsung Electronics
47
Login Option - Using Serial Port Connecting Laptop with the DBG port on UAMA board through Serial Cable (Requires RS232 on Laptop)
2013 © Samsung Electronics
48
Login Option-USB to Serial Convertor If serial port is not available on the laptop, use the USB to serial converter as below
2013 © Samsung Electronics
49
Login- Serial Cable Access the UAMA board using TeraTerm or any other telnet program on Laptop through the serial cable. Steps of Login Set the Baud Rate to 115200 bps. Set the Serial Port Settings to COM1 Login ID: ******* Password: *******
2013 © Samsung Electronics
50
Login Option 1- Serial Cable Access the UAMA board using TeraTerm or any other telnet program on Laptop through the serial cable. Steps of Login Step 1. TeraTerm Settings Open TeraTerm Application Software, and do the following setting in it as shown in figure
Set the Serial Port Settings to COM1 Set the Baud Rate to 115200 bps. Login ID: ******* Password: ******* 2013 © Samsung Electronics
51
Step 1-TeraTerm Settings
2013 © Samsung Electronics
52
Login Option 2-Ethernet Connecting Laptop with the EDBG port on UAMA board through Ethernet Cable
2013 © Samsung Electronics
53
Login Option 2-Ethernet Steps of Login Step 1. IP LAN Settings IP Address:
192.168.32.28
Subnet Mask:
255.255.255.0
Default Gateway:
192.168.32.27
2013 © Samsung Electronics
54
Login Option 2-Ethernet Steps of Login Step 2. Access UAMA board by TeraTerm or any other Telnet program Step 3. Connection IP is 192.168.32.27
Step 4. Click Ok, following window get appears 2013 © Samsung Electronics
55
Login Option 2-Ethernet Steps of Login
Step 5. Enter User name & Password (Contact the person incharge for Username and password) 2013 © Samsung Electronics
56
Steps of Commissioning Steps: 1) Login to UAMA board 2)Setting eNB environment parameters a) Login as Super User mode b) Check the original eNB environment parameters c) Delete/Add eNB environment parameters d) Confirm parameter settings
3) Initiate memory & eNB reboot 4) Verify network connectivity 5) Check System Status ( Hardware Alarms) 2013 © Samsung Electronics
57
Steps of Commissioning- Login to UAMA board Steps: 1) Login to UAMA board If the connection to the UAMA board is successful, following window appears:
2013 © Samsung Electronics
58
Steps of Commissioning- Setting eNB environment parameters Steps: 2) Setting eNB environment parameters a) Login as Super User mode Command Used: su –
Password: ********
(Contact the person incharge for password)
2013 © Samsung Electronics
59
Steps of Commissioning- Setting eNB environment parameters Steps: 2) Setting eNB environment parameters b)Check the original eNB environment parameters Command Used: getenv –a Following window gets appear __BOOTUP_FLAG__=000000020e LEIP2_IP=10.5.46.14 LEIP2_NM=16 LEIP2_GW=10.5.0.1 PORT_0_0_2_IPV4_IP=10.5.46.14 PORT_0_0_2_IPV4_GW=10.5.0.1 PORT_0_0_2_IPV4_NM=16 bootdelay=1 baudrate=115200 pci_console_active=yes pci_console_count=1 pci_console_size=2097152 stdin=pci stdout=pci stderr=pci ethact=octeth0 2013 © Samsung Electronics
bootcmd=bootoctbflag AUTH=yes BOOTMODE=static RS_LOGIN=sysuser RS_PASSWD=syslte123 SECU_CONN=yes SECU_PASSWD=yes adminstate=0 RS_IP=100.127.129.84 BOOTPORT=PORT_0_0_0 PORT_0_0_0_IPVER=4 PORT_0_0_0_IPV4_NM=30 PORT_0_0_0_IPV4_IP=100.127.132.1 PORT_0_0_0_IPV4_GW=100.127.132.2 NE_ID=16 IPV6_ENABLE=1 PORT_0_0_0_VLANID=103
60
Steps of Commissioning- Setting eNB environment parameters Steps: 2) Setting eNB environment parameters c) Delete/Add eNB environment parameters Command Used: delenv
-p [Parameter Name]
Ex) root@UAMA:/root> delenv -p NE_ID Ex) root@UAMA:/root> setenv -p NE_ID XX
As shown in next figure
2013 © Samsung Electronics
61
Steps of Commissioning- Setting eNB environment parameters Steps: 2) Setting eNB environment parameters c) Delete/Add eNB environment parameters Command Used: delenv
2013 © Samsung Electronics
-p [Parameter Name]
root@UAMA:/root> root@UAMA:/root> delenv -p NE_ID Name = NE_ID Value = root@UAMA:/root> getenv -a [Env Information] bootdelay=1 baudrate=115200 pci_console_active=yes pci_console_count=1 pci_console_size=2097152 ~~ RS_IP=2405:201:fffb:0:1::52 BOOTPORT=PORT_0_0_2 PORT_0_0_2_IPVER=6 PORT_0_0_2_IPV6_NM=112 PORT_0_0_2_IPV6_GW= 4fa1:f00d:1234:5678:9abc:def1:aaaa:3 PORT_0_0_2_IPV6_IP= 4fa1:f00d:1234:5678:9abc:def1:aaaa:25 IPV6_ENABLE=1 __BOOTUP_FLAG__=000000020e
62
Steps of Commissioning- Setting eNB environment parameters Steps: 2) Setting eNB environment parameters c) Delete/Add eNB environment parameters Command Used: setenv
2013 © Samsung Electronics
-p [Parameter Name]
root@UAMA:/root> setenv -p NE_ID 26405 Name = NE_ID Value = 26405 root@UAMA:/root> getenv -a [Env Information] bootdelay=1 baudrate=115200 pci_console_active=yes pci_console_count=1 pci_console_size=2097152 ~~ RS_IP=2405:201:fffb:0:1::52 BOOTPORT=PORT_0_0_2 PORT_0_0_2_IPVER=6 PORT_0_0_2_IPV6_NM=112 PORT_0_0_2_IPV6_GW= 4fa1:f00d:1234:5678:9abc:def1:aaaa:3 PORT_0_0_2_IPV6_IP=4fa1:f00d:1234:5678:9abc:def1:aaaa:25 IPV6_ENABLE=1 __BOOTUP_FLAG__=000000020e NE_ID=26405
63
Steps of Commissioning- Setting eNB environment parameters Script:
2013 © Samsung Electronics
setenv -p bootdelay 1 setenv -p baudrate 115200 setenv -p pci_console_active yes setenv -p pci_console_count 1 setenv -p pci_console_size 2097152 setenv -p stdin pci setenv -p stdout pci setenv -p stderr pci setenv -p ethact octeth0 setenv -p bootcmd bootoctbflag setenv -p AUTH yes setenv -p BOOTMODE static setenv -p RS_LOGIN sysuser setenv -p RS_PASSWD syslte123 setenv -p SECU_CONN yes setenv -p SECU_PASSWD yes setenv -p adminstate 0 setenv –p RS_IP 2405:201:fffb:0:1::52 setenv –p BOOTPORT PORT_0_0_2 setenv –p PORT_0_0_2_IPVER 6 setenv –p PORT_0_0_2_IPV6_NM 112 setenv –p PORT_0_0_2_IPV6_GW 4fa1:f00d:1234:5678:9abc:def1:aaaa:3 setenv –p PORT_0_0_2_IPV6_IP 4fa1:f00d:1234:5678:9abc:def1:aaaa:25 setenv –p NE_ID 26405 Press enter after this setenv –p IPV6_ENABLE 1 setenv –p PORT_0_0_2_VLANID 103 64
Steps of Commissioning- Setting eNB environment parameters Result:
2013 © Samsung Electronics
root@UAMA:/root> root@UAMA:/root> setenv -p bootdelay 1 Name = bootdelay Value = 1 root@UAMA:/root> setenv -p baudrate 115200 Name = baudrate Value = 115200 root@UAMA:/root> setenv -p pci_console_active yes Name = pci_console_active Value = yes root@UAMA:/root> setenv -p pci_console_count 1 Name = pci_console_count Value = 1 root@UAMA:/root> setenv -p pci_console_size 2097152 Name = pci_console_size Value = 2097152 root@UAMA:/root> setenv -p stdin pci Name = stdin Value = pci root@UAMA:/root> setenv -p stdout pci Name = stdout Value = pci root@UAMA:/root> setenv -p stderr pci Name = stderr Value = pci root@UAMA:/root> setenv -p ethact octeth0 Name = ethact Value = octeth0 65
Steps of Commissioning- Setting eNB environment parameters Result:
2013 © Samsung Electronics
root@UAMA:/root> setenv -p bootcmd bootoctbflag Name = bootcmd Value = bootoctbflag root@UAMA:/root> setenv -p AUTH yes Name = AUTH Value = yes root@UAMA:/root> setenv -p BOOTMODE static Name = BOOTMODE Value = static root@UAMA:/root> setenv -p RS_LOGIN sysuser Name = RS_LOGIN Value = sysuser root@UAMA:/root> setenv -p RS_PASSWD syslte123 Name = RS_PASSWD Value = syslte123 root@UAMA:/root> setenv -p SECU_CONN yes Name = SECU_CONN Value = yes root@UAMA:/root> setenv -p SECU_PASSWD yes Name = SECU_PASSWD Value = yes root@UAMA:/root> setenv -p adminstate 0 Name = adminstate Value = 0 root@UAMA:/root> setenv -p RS_IP 2405:201:fffb:0:1::52 Name = RS_IP Value = 2405:201:fffb:0:1::52 66
Steps of Commissioning- Setting eNB environment parameters Result:
2013 © Samsung Electronics
root@UAMA:/root> setenv -p BOOTPORT PORT_0_0_2 Name = BOOTPORT Value = PORT_0_0_2 root@UAMA:/root> setenv -p PORT_0_0_2_IPVER 6 D:\Samsung\SolPar Training_4G RFE-I&C\So Name = PORT_0_0_2_IPVER Value = 6 root@UAMA:/root> setenv -p PORT_0_0_2_IPV6_NM 30 Name = PORT_0_0_2_IPV6_NM Value = 112 root@UAMA:/root> setenv -p PORT_0_0_2_IPV6_IP 4fa1:f00d:1234:5678:9abc:def1:aaaa:25 Name = PORT_0_0_2_IPV6_IP Value = 4fa1:f00d:1234:5678:9abc:def1:aaaa:25 root@UAMA:/root> setenv -p PORT_0_0_2_IPV6_GW 4fa1:f00d:1234:5678:9abc:def1:aaaa:3 Name = PORT_0_0_2_IPV6_GW Value = 4fa1:f00d:1234:5678:9abc:def1:aaaa:3 root@UAMA:/root> setenv -p NE_ID 26405 Name = NE_ID Value = 26405 root@UAMA:/root> setenv -p IPV6_ENABLE 1 Name = IPV6_ENABLE Value = 1 root@UAMA:/root> setenv -p PORT_0_0_2_VLANID 103 Name = PORT_0_0_2_VLANID Value = 103
67
Steps of Commissioning- Setting eNB environment parameters Steps: 2) Setting eNB environment parameters c) Delete/Add eNB environment parameters Command Used: setenv
-p [Parameter Name]
For ready reference following parameter can be use setenv –p RS_IP 2405:201:fffb:0:1::52 setenv –p BOOTPORT PORT_0_0_2 setenv –p PORT_0_0_2_IPVER 6 setenv –p PORT_0_0_2_IPV6_NM 112 setenv –p PORT_0_0_2_IPV6_GW 4fa1:f00d:1234:5678:9abc:def1:aaaa:3 setenv –p PORT_0_0_2_IPV6_IP 4fa1:f00d:1234:5678:9abc:def1:aaaa:25 setenv –p NE_ID 26405 setenv –p IPV6_ENABLE 1 setenv –p PORT_0_0_2_VLANID 103
2013 © Samsung Electronics
LSM server IP Booting port Using IP Version OAM IP Net-mask OAM Gateway IP eNB OAM IP eNB ID IPV6 Enable=1, Disable=0 OAM VLAN ID
68
Steps of Commissioning- Setting eNB environment parameters Steps: 2) Setting eNB environment parameters d) Confirm parameter settings Command Used: getenv –a
After set the environment parameter according to the information of eNB, finally check the whole environment parameter especially confirm the orange line.
2013 © Samsung Electronics
root@UAMA:/root> getenv -a [Env Information] bootdelay=1 baudrate=115200 pci_console_active=yes pci_console_count=1 pci_console_size=2097152 stdin=pci stdout=pci stderr=pci ethact=octeth0 bootcmd=bootoctbflag AUTH=yes BOOTMODE=static RS_LOGIN=sysuser RS_PASSWD=syslte123 SECU_CONN=yes SECU_PASSWD=yes adminstate=0 RS_IP=2405:201:fffb:0:1::52 BOOTPORT=PORT_0_0_2 PORT_0_0_2_IPVER=6 PORT_0_0_2_IPV6_NM=112 PORT_0_0_2_IPV6_GW=4fa1:f00d:1234:5678:9abc:def1:aaaa:3 PORT_0_0_2_IPV6_IP=4fa1:f00d:1234:5678:9abc:def1:aaaa:25 NE_ID=26405 IPV6_ENABLE=1 PORT_0_0_2_VLANID=103 __BOOTUP_FLAG__=000000020e 69
Steps of Commissioning- Initiate memory & eNB reboot Steps: 3) Initiate memory & eNB reboot Commands Used: cd /mnt & rm –rf* lteuser@UAMA:~$ su Password: root@UAMA:/root> cd /mnt root@UAMA:/mnt> rm -rf * rm: cannot remove directory `CPSW': Device or resource busy rm: cannot remove directory `ram': Device or resource busy rm: cannot remove directory `storage': Device or resource busy rm: cannot remove directory `storage_bk': Device or resource busy root@UAMA:/mnt> sync
There are lots of memories in UAMA unit in the progress of factory test; it can be affected for software loading. Therefore, it is recommended to remove all shred memory under “/mnt” directory in UAMA unit.
2013 © Samsung Electronics
70
Steps of Commissioning- Initiate memory & eNB reboot Steps: 3) Initiate memory & eNB reboot Commands Used: reboot
2013 © Samsung Electronics
71
Steps of Commissioning- Verify network connectivity Steps: 4) Verify network connectivity Commands Used: ping6 [IPv6 IP Address] root@UAMA:/root> ping6 2405:201:fffb:0:1::223 PING 2405:201:fffb:0:1::223(2405:201:fffb:0:1::223) 56 data bytes 64 bytes from 2405:201:fffb:0:1::223: icmp_seq=1 ttl=63 time=0.289 ms --- 2405:201:fffb:0:1::223 ping statistics --1 packets transmitted, 1 received, 0% packet loss, time 996ms rtt min/avg/max/mdev = 0.289/0.289/0.289/0.000 ms
After eNB restart, check the connectivity between eNB and LSM by ping command. If there is issue with connectivity, check whether the eNB IP and route, VLAN configuration is correct, else coordinate with LSM-R Engineer.
2013 © Samsung Electronics
72
Steps of Commissioning- Check System Status ( Hardware Alarms)
Steps: 5) Check System Status ( Hardware Alarms)-In normal condition
ACT and GPS LEDs must blinking
TX LED of SFP port should be green
In normal condition 2013 © Samsung Electronics
73
Steps of Commissioning- Check System Status ( Hardware Alarms)
Steps: 5) Check System Status ( Hardware Alarms)-In abnormal condition
ACT and GPS LEDs starts glowing RED
No glow of LED at SFP Port
Action to be taken: •Report the current situation to LSM-R team •Troubleshoot the problem, coordinate with LSM-R Team •Don’t leave the site till alarm clear
2013 © Samsung Electronics
74
ATP11B
Introduction ATP11_B is conducted after site Integration Test Tools & Method of procedure will be provided by RJIL. Tools needed: Laptop UE (User Equipment) Application to perform test (test tool)
2013 © Samsung Electronics
76
ATP11_B- Items
Microsoft Office Word Document
2013 © Samsung Electronics
77
Gamsahapnida Thank You Copyright and Confidentiality Copyright © 2013, SAMSUNG Electronics Co., Ltd. SAMSUNG Electronics reserves the right to make changes to the specifications of the products detailed in this document at any time without notice and obligation to notify any person of such changes. Information in this document is proprietary to SAMSUNG Electronics Co., Ltd. No information contained here may be copied, translated, transcribed or duplicated by any form without the prior written consent of SAMSUNG Electronics.