Method Statement for retubing of Heat Exchanger.Full description
Deep ExcavationFull description
GoodFull description
Method StatementFull description
Method Statement
Full description
Deep Excavation
sika groutingFull description
Method StatementFull description
Method of statement Fire FightingFull description
Full description
MS for PDA testing
Full description
GTC71 / 2005
1.0
Method Statement for Electrical work Related to replacement of MCC in New Salwa pumping station
Osaka J apan Since 1919
Doc. Ref. : MS – NSPS - EL – 03 Date : 31.12.2008 : .Rev
Replacement of MCC
The present status of existing MCC is Transformer 1 & 2 ( NA5 & NA11 ) & bus coupler (NA6) were in on condition and bus coupler (NA10) is in switched off condition. Sr.No
Activity
1
Inst Instal alla lati tion on of new 11 KV KV swi switc tchg hgea earr and and pre pre com commi miss ssio ioni ning ng to be comp comple lete ted d
2
Lay the LV cable to new DB in 11 KV switch gear room from existing MCC and energize the Battery charger for switchgear protection.
3
Lay the new LV cable from new MCC to pump numbers 3, 4,6,7,8 & 9 and terminate the power cable in the MCC side... Refer drawing number
4
Lay and terminate 11 KV cable between 11 KV switchgear and transformer number – 3 and terminate the cable at both the end.
5
Reroute the 2 numbers of 11KV cable ( Ring ) from Existing 11 11 KV switchgear to new switchgear and commission the new switchgear switchgear by ENA approved approved contractor by taking PTW..
6
Arrange for the inspection of MCC panel by Kahramaa customer department and install the new KWH meter.
7
Commission the transformer – 3 after checking the protection interlock and energize the MCC pertaining to TX- 3
8
Shift the VFD connection for pump number 4 from existing MCC ( NA12) to new MCC (Q48) by taking PTW
9
Shift the VFD connection for pump number 8 from existing MCC ( NA17) to new MCC (Q49) by taking PTW
10
Shift the VFD connection for pump number 9 from existing MCC ( NA18) to new MCC (Q50) by taking PTW
11
Switch on the bus coupler between Transformer Transformer 2 & 3 (QB2) and energize the bus bar of Transformer – 2 and ensure that QM2 in switched off condition
-
1-
Day / Time
Trusted by over 1 million members
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
Trusted by over 1 million members
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
GTC71 / 2005
Method Statement for Electrical work Related to replacement of MCC in New Salwa pumping station
Osaka J apan Since 1919
Doc. Ref. : MS – NSPS - EL – 03 Date : 31.12.2008 : .Rev
1.0 Replacement of MCC - Contd. Sr.No
Activity
12
Shift the VFD connection for pump number 7 from existing MCC ( NA13) to new MCC (Q24) by taking PTW
13
Lay and terminate 11 KV cable between 11 KV switchgear and transformer number – 2 and terminate the cable at both the end, by ENA department department approved Contractor by taking PTW. PTW.
14
Comm Commis issi sion on the the tra trans nsfo form rmer er – 2 afte afterr chec checki king ng the the pro prote tect ctio ion n inte interl rloc ock. k. .
15
Switch off existing transformer number – 2 after obtaining approval from ENA department. Arrange Arrange to remove the KWH meter by the Meter Section of customer department by submitting all relevant documents.
16
Arrange for the inspection of part of MCC panel (Transformer – 2) by Kahramaa customer department and install the new KWH meter. meter.
17
Switch off bus coupler (QB2) and energize the bus bar pertaining to TX- 2.by switching on QM2
18
Ensure that Bus coupler ( NA10 ) should be in switched off condition and remove the part of existing MCC ( NA11, NA12, NA13, NA17 & NA18 ) by obtaining PTW.
19
Install last part of new MCC (Q1 to Q4 ) and complete the installation pertaining to transformer – 1 section
20
Shift the VFD connection for pump number 6 from existing MCC ( NA4) to new MCC (Q23) by taking PTW
21
Shift the VFD connection for pump number 7 from existing MCC ( NA13) to new MCC (Q24) by taking PTW
Day / Time
Trusted by over 1 million members
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions! Start Free Trial Cancel Anytime.
GTC71 / 2005
Method Statement for Electrical work Related to replacement of MCC in New Salwa pumping station
Osaka J apan Since 1919
Doc. Ref. : MS – NSPS - EL – 03 Date : 31.12.2008 : .Rev
1.0 Replacement of MCC - Contd. Sr.No
Activity
23
Shift the VFD connection for pump number 1 from existing MCC ( NA16) to new MCC (Q19) by taking PTW
24
Shift the VFD connection for pump number 2 from existing MCC ( NA1) to new MCC (Q20) by taking PTW
25
Shift the VFD connection for pump number 5 from existing MCC ( NA3) to new MCC (Q21) by taking PTW
26
Shift all auxiliary loads from existing MCC to new MCC – Refer method statement MS – NSPS – EL – 04.
27
Lay and terminate 11 KV cable between 11 KV switchgear and transformer number – 1 and terminate the cable at both the end, by ENA department department approved Contractor by taking PTW. PTW.
28
Comm Commis issi sion on the the tra trans nsfo form rmer er – 1 afte afterr chec checki king ng the the pro prote tect ctio ion n inte interl rloc ock. k. .
29
Switch off existing transformer number – 1 after obtaining approval from ENA department. Arrange Arrange to remove the KWH meter by the Meter Section of customer department by submitting all relevant documents.
30
Arrange for the inspection of part of MCC panel (Transformer – 1) by Kahramaa customer department and install the new KWH meter. meter.
31
Switch off bus coupler (QB1) and energize the bus bar pertaining to TX- 1.by switching on QM1
32
Reroute the balance balance 11KV 11KV cables from Existing Existing 11 KV switchgear to new switchgear by ENA approved contractor by taking PTW from ENA department.