J. Ray Ray McDe McDermo rmott tt – Asia Pacifi Pacific c Engin eeri eering ng
ENGINEERING PROCEDURE LEVEL 2
PROCESS ENGINEERING JRM-AP-ENG-3000
Page S M
J. Ray Ray McDermot McDermot t Asia A sia Pacifi Pacifi c Enginee Engin eering ring
Procedure number
Procedure title
Rev No.
JRM-AP-ENG-3000
Process Engineering
1
3 of 19 Date
31/03/06
REVISION INDEX
AFFECTED SECTION
AUTHORISED BY ENG. MANAGER ENG. DIRECTOR JKT SING
REV NO.
REVISION DATE
0
23/11/01
Initial Issue
S. Kumar
CK Mohan
1
31/03/06
General Revision
V. Chandrasekharan
Handoko
PREPARED BY
QA
A. Pollack S. Kumar
S. Banerjee
M. Wilson
Page S M
J. Ray Ray McDermot McDermot t Asia A sia Pacifi Pacifi c Enginee Engin eering ring
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
Rev No.
1
4 of 19 Date
31/03/06
TABLE OF CONTENTS
REVISION INDEX..................................... INDEX................................................................... ............................................................. ..................................................3 ...................3 1 INTRODUCTION & SCOPE .......................................................... ...................................................................................5 .........................5 2 OBJECTIVES ......................................................... ........................................................................................ ..................................................5 ...................5 3 REFERENCES..........................................................................................................6 4 DEFINITIONS & ABBREVIATIONS................... ABBREVIATIONS.................................................. ..................................................6 ...................6 5 RESPONSIBILITIES................................................................................................7 6 PROCESSES.............................................................................................................8 7 INTERFACES.........................................................................................................12 8 DOCUMENT REVIEW AND APPROVAL..........................................................12 APPROVAL ..........................................................12 9 DOCUMENT ISSUE ............................................................. ........................................................................................... .................................12 ...12 10 DOCUMENT HANDLING AND ARCHIVING ...................................................13 ...................................................13 FLOWCHART 3001 – Work Overview FLOWCHART 3002 – Datasheets FLOWCHART 3003 – Simulations FLOWCHART 3004 – Calculations FLOWCHART 3005 – Bid Support Work Process APPENDIX A – Material Balance Table ATTACHMENT 3000 – Process Engineering Check Lists
Page S M
J. Ray Ray McDermot McDermot t Asia A sia Pacifi Pacifi c Enginee Engin eering ring
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
1
Rev No.
1
5 of 19 Date
31/03/06
INTRODUCTION INTRODUCTION & SCOPE This document is a Level II procedure for J. Ray McDermott Asia Pacific Engineering (JRMAPE), and forms part of the management system as described in the J. Ray McDermott Asia Pacific (JRMAP) Level I Management System Manual. This Level II standard operating procedure outlines the functions of the Process Engineering Group. Group. Detailed work instructions and other relevant relevant Level II procedures are referenced as applicable.
2
OBJECTIVES a)
The objectives of this procedure is to define the responsibilities, activities and functions of the Process Engineering Group to be used by JRMAPE in performance of work on a project or bid.
b)
Ensure that the design and engineering meet the following conditions: •
•
•
•
c)
Accurate and adhere to all applicable governing codes and regulations Be carried out in accordance with the approved basis of design criteria Present a process design that establishes safety as a primary concern Contain adequate information so that the Customer can readily use them for maintenance and future revisions of the facility
Provide guidelines for achieving and maintaining quality and consistency of work.
This procedure will be subject to audit as part of the ongoing review of quality management system. It is not the intent of JRMAPE to vary these processes for projects unless contractual reasons dictate otherwise. In those instances, any contractually agreed changes will be outlined in the Project Execution Plan.
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
3
4
Rev No.
1
6 of 19 Date
31/03/06
REFERENCES a)
17-01-001, Level I Procedure Management System Manual – J. Ray McDermott Asia Pacific
b)
JRM-AP-ENG-0100, Organisation & Responsibilities
c)
JRM-AP-ENG-1700, Document Control
d)
JRM-AP-ENG-1800, Document Review & Verification
e)
JRM-AP-ENG-1900, Document Initiation, Signoff & Retention
f)
JRM-AP-ENG-2300, Interface Control
g)
JRM-AP-ENG-2600, Specifications & Data Sheets
h)
JRM-AP-ENG-2900, Design (Analysis & Calculations)
i)
JRM-AP-ENG-4000, Process & Mechanical Flow Diagrams
j)
Level II Procedures, as applicable
DEFINITIONS & AB BREVIATIONS AFC
Approved for Construction
AFD
Approved For Design
DBD
Design Basis Document
IDC
Inter Discipline Check
JRMAP
J. Ray McDermott Asia Pacific
JRMAPE
J. Ray McDermott Asia Pacific Engineering
MFD
Mechanical Flow Diagram
P&ID
Piping & Instrument Diagram
PFD
Process Flow Diagram
SAFE Chart
Safety Analysis and Function Evaluation Chart
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
5
Rev No.
1
7 of 19 Date
31/03/06
SDC
Single Discipline Check
Material Balance
A tabulation of the stream properties at various points in the process flow scheme
RESPONSIBILITIES a)
General responsibilities of the Group will include but not limited to the following: •
•
•
Input for the project DBD Perform process simulation to generate Heat and Material Balance Perform process calculations to define equipment and piping sizes
•
Perform special studies as required on the project
•
Prepare PFDs and MFDs (P&IDs)
•
Prepare SAFE charts
•
Provide process input for inter-discipline documents
Flowchart 3001, outlines work overview within the Process Engineering. b)
The individual responsibilities within the Group are defined in Procedure No. JRM-AP-ENG-0100, Organisation & Responsibilities.
c)
The Lead Process Engineer assigned to a project is responsible for coordinating all process design activities on the project and for reviewing and approving all process deliverables prior to release.
d)
Process Engineers are responsible for performing the analyses and designs assigned to them by the project's Lead Process Engineer.
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
e)
Rev No.
1
8 of 19 Date
31/03/06
Bid support.
Flowchart 3002, 3003 and 3004, outline the main process functions undertaken during a project, further define responsibilities and indicate how interfaces with drafting and other disciplines are managed. Flowchart 3005, outline the main process functions undertaken during bid support.
6
PROCESSES This section gives a brief outline of the processes involved in the overall functioning of the Process Engineering Group.
6.1
OVERVIEW The activities involved in the development of Process Engineering Group deliverables are as detailed in Flowcharts 3001, 3002, 3003, 3004 and 3005 and as described below. All engineering design is performed in accordance with the requirements of Procedure No. JRM-AP-ENG-2900, Design (Analysis & Calculations).
6.2
DESIGN BA SIS DOCUMENT a)
The DBD establishes the basis on which the engineering design of the project will be undertaken and it defines the basic functional requirements of the project.
b)
The DBD is prepared on the basis of Customer design philosophy, scope of work, specifications and Local Government Regulations.
c)
The Lead Process Engineer is responsible for collating input from other discipline engineers and issue of a consolidated document.
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
6.3
Rev No.
1
9 of 19 Date
31/03/06
DATASHEETS a)
After Mechanical / Instrument Engineering create the equipment / instrument datasheets, the Process Engineering Group input the process data required. When complete, the datasheets are returned to Mechanical / Instrument Engineering.
b)
The Process Engineering Group provides process data for: • • •
Equipment and packaged systems Instruments Utility system equipment
Flowchart 3002 outlines the process for the production of datasheets.
6.4
6.5
PROCESS SIMULATION a)
The Process Engineer(s) assigned to a project is responsible for carrying out the process simulations assigned by the Lead Process Engineer.
b)
Process simulations are performed before the heat and material balance data can be provided to Piping Drafting for inclusion in the PFDs.
c)
All process simulations are approved by the Lead Process Engineer prior to issue. Flowchart 3003 outlines the simulation process.
MATERIAL BALANCES a)
The Process Engineer(s) is responsible for preparing material balances for inclusion in the PFDs.
b)
Process simulations must be completed before the material balance data can be produced.
c)
When produced, the material balance data is electronically transferred to the Piping Drafting Discipline for inclusion on the PFDs. The Process Engineer works with the appropriate Piping Drafting Squad Leader to determine whether the material balance is placed on the PFD or on a separate sheet.
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
d)
6.6
6.7
Rev No.
1
10 of 19 Date
31/03/06
Appendix A indicates the data which is generally shown in the material balance tables.
PROCESS STUDIES a)
The purpose of a process study is to investigate various design options and to select one option as the optimum design or confirm a selected design.
b)
The Process Engineer is responsible for undertaking the study which generally requires computer simulations to model the various options.
c)
After computer simulations are completed, equipment sizes/duties are calculated, from which equipment costs can then be generated (by others). Assuming that all options considered meet process requirements, the study will consider other factors, such as capital cost, operating cost, and payback.
d)
The Lead Process Engineer is responsible for reviewing and approving the studies before distribution to other disciplines.
e)
The Lead Process Engineer is responsible for obtaining Customer approval for the process studies.
PROCESS CALCULATIONS a)
The Process Engineer is responsible for the design of the systems assigned to him by the Lead Process Engineer. After process simulations are complete and the process conditions are fixed, equipment sizing and rating is performed.
b)
Flowchart 3004 outlines the process to be followed for process calculations and their approval. Industry codes and Customer standards are used to size vessels and tanks, calculate heat exchanger and air cooler design duties, and pump and compressor horsepower and line sizes.
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
6.8
6.9
6.10
Rev No.
1
11 of 19 Date
31/03/06
c)
Customer standards may exceed the requirements of Industry standards; however, if Customer standards are less stringent than Industry standards, the Lead Process Engineer will discuss the matter with the Project Engineering Manager before resolving the matter with the Customer. Any deviations will be authorised in writing by the Customer.
d)
The Lead Process Engineer is responsible for approving all calculations before issue for use.
PROCESS & MECHANICAL FLOW DIAGRAMS a)
The Lead Process Engineer is responsible for the technical contents, validity and integrity of the PFDs and MFDs (P&IDs).
b)
PFDs and MFDs (P&IDs) are produced in accordance to JRM-APENG-4000, Process & Mechanical Flow Diagrams.
SAFE CHART a)
The Lead Process Engineer(s) assigned to a project is responsible for technical information contained in the SAFE Chart.
b)
Instrument Drafting is responsible for graphical representations and physical drawings and maintaining records of changes.
c)
The Instrument Discipline are required to coordinate with the Lead Process Engineer to provide necessary inputs in a timely manner.
BID SUPPORT Process Engineering Group is responsible to provide Bid Support for the new bids. The primary bid support activities will include the following: •
• •
•
Review bid documents, bid addendums / clarifications from Customer Prepare and issue request for clarification to Customer as required Mark-up bid PFDs and MFDs (P&IDs) or prepare sketch MFDs (P&IDs) Prepare RFQ for engineering work /study to be subcontracted
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
•
•
•
•
7
Rev No.
1
12 of 19 Date
31/03/06
Assist Mechanical and Instrument Engineering to prepare preliminary / mark-up data sheets Assist Mechanical, Instrument and Electrical Engineering to prepare RFQs and review vendor’s quotations Provide input to Bid Project Engineer for Technical Proposal as required Estimate engineering man-hours for project execution.
INTERFACES All interface control requirements will be issued in accordance with Procedure No. JRM-AP-ENG-2300, Interface Control. The interface with other disciplines, Customers and drafting is primarily handled by the Lead Process Engineer. All design requirements, changes and clarifications are passed on by the Lead Process Engineer to the concerned parties for necessary action. These include IDC drawings and documents, data sheets and vendor data.
8
DOCUMENT REVIEW AND APPROVAL Once a design document is compiled by the assigned Process Engineer, it is passed on to the Lead Process Engineer. The document review within the discipline (SDC) as well as inter discipline (IDC) will be carried out as per the guidelines in Procedure No. JRM-AP-ENG-1800, Document Review & Verification Procedure. Based on the comments from internal review, the document is updated and passed on to Document Control for transmittal to Customer / Third Party for review and approval as per the Project Execution Plan requirements.
9
DOCUMENT ISSUE The document issue will be in accordance with Procedure No. JRM-APENG-1900, Document Initiation, Signoff & Retention. The Lead Process Engineer, in concurrence with the assigned Process Engineer reviews the comments from the Customer on the documents.
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
Rev No.
1
13 of 19 Date
31/03/06
Updates / revisions as required are carried out and the documents are reissued for Review / Approval. All specifications and data sheets are prepared in accordance with the requirements of Procedure No. JRM-AP-ENG-2600, Specifications & Data Sheets.
10
DOCUMENT HANDLING AND ARCHIVING A list of deliverables is identified at the commencement of the Project. The assigned Process Engineers will maintain all internal review “Check Prints” of these documents. The Document Control will maintain the original documents for all revisions of a document during the course of the project. In addition, originals of the Customer commented documents will also be retained by the Document Control and only copies are passed on to the Lead Process Engineer. Document distribution within the discipline is handled by the Lead Process Engineer. The document control will be in accordance with Procedure No. JRM-APENG-1700, Document Control. At the end of the project, final revisions of all original documents are handed over to the Library for archiving for future reference.
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
Rev No.
JRM-AP-ENG-3000
Process Engineering
1
14 of 19 Date
31/03/06
Process Engineering FLOWCHART 3001 Work Overview
Design basis
Process calculations
Process simulation
Process studies
Material balances
Equipment list
Process datasheets
PFDs Control & shutdown philosophy
SAFE Charts
Instrument Eng'g MFD input
Mechanical Eng'g MFD input
MFDs (P&IDs)
Electrical Eng'g MFD input To Mechanical & Instrument Eng'g
Project tagged equipment list for use by all disciplines. Maintained by Mechanical Eng'g
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
Rev No.
JRM-AP-ENG-3000
Process Engineering
PROCESS ENGINEERING
Fuel gas Instrument air Diesel distribution Potable water system Washwater system Nitrogen/CO2 system Heat medium system
Prepare process instrument datasheets for: Relief valves Control valves Flow measuring devices
Date
31/03/06
Process Engineering FLOWCHART 3002 Datasheets
Start
Prepare process portion of utility system equipment datasheets, typically:
1
15 of 19
Perform process simulation to obtain flow & physical properties
OTHER DISCIPLINES
Prepare calculations & process data; e.g.: Pump calculations Compressor horsepower Heat exchangers/air coolers duty Vessel sizing Tanks sizing
Material balance to PFD
Instrument &/or Mechanical Eng'g generate master datasheets & pass to Process Eng'g for input of process data
Input process data on datasheets
Output approved by Lead Process Engineer
Pass approved equipment datasheets to Mechanical Eng'g for retention
Datasheets retained by Mechanical Eng'g & used to prepare RFQs for equipment & packaged systems
Pass approved instrument datasheets to Instrument Eng'g for retention
Datasheets retained by Instrument Eng'g & used to purchase instruments
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
16 of 19
Rev No.
Date
1
31/03/06
Process Engineering FLOWCHART 3003 Simulations
Piping Drafting
Process Engineer
L ead Process Engin eer
Select process
Ensure following data is available: Feed specifications Compositions & rates Conditions (pressure & temperature) Product specifications Compositions & rates Conditions (pressure & temperature) In some cases, utility conditions, such as steam & heat medium conditions
Select appropriate computer program, e.g.: HYSYS PROCESS AMSIM T-SWEET & begin simulation (ensuring that stream numbers used in the simulation are consistent with the stream numbers shown on the PFDs)
Check and copy of simulation input and output, initial & date it, and pass i t to the Lead Process Engineer
Resolve problems
Check
Yes
Comments?
No Initial, date, & return to Process Engineer Input data to PFDs
Electronically transfer material balance data to Piping Drafting
Transfer data to other disciplines, as required
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
17 of 19
Rev No.
Date
1
31/03/06
Process Engineering FLOWCHART 3004 Calculations
Mechanical Engineering
Process Engineer Ensure process simulation is complete & process conditions are fixed
Lead Process Engineer Ass ign sys tems to Process Engineer
Use stream data to size equipment, provide duties for heat exchangers, & specify package requirements (use industry standards or customer standards if customer standards are equal to or more stringent than industry standards)
Initial & date process calculations, & submit to Lead Process Engineer
Check calculations
Changes required?
Yes
Incorporate agree changes & resubmit
File original calculation sheets in the Project Process Calculation Book
Use vessel & tank sizes to Prepare data sheet
Pass vessel & tank sizes to Mechanical Engineering
Give verbal instructions and markedup check print to Process Engineer
No
App rov e by initialing & dating original calculation/ design work
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
18 of 19
Rev No.
1
Date
31/03/06
Process Engineering FLOWCHART 3005 Bid Support Work Process PROCESS DRAFTING
PROCESS ENGINEERING
EPCI / EPC / EP BID PACKAGE
EPCI / EPC / EP BID PACKAGE
REVIEW SCOPE OF WORK
REVIEW SCOPE OF WORK
OTHER DISCIPLINES
BATAM YARD
MANHOURS ESTIMATE AND SCOPE FOR BID SUPPORT
MANHOURS ESTIMATE AND SCOPE FOR BID SUPPORT PROPOSAL GROUP
REVIEW PROCESS DESIGN BASIS, PHILOSOPHIES & SPECIFICATIONS
PREPARE AND/OR REVIEW
PRELIMINARY DRAWINGS: 1. PFDs 2. MFDs (P&IDs)
REVIEW PROCESS DESIGN BASIS, PHILOSOPHIES & SPECIFICATIONS 1. MARK-UPS PFDs AND MFDs (P&IDs) 2. PRELIMINARY PROCESS SIMULATION AND CALCULATIONS 3. PRELIMINARY EQUIPMENT AND INSTRUMENT PROCESS DATA SHEETS 4. PREPARE RFQ FOR PROCESS SPECIAL STUDIES
TECHNICAL CLARIFICATION
TECHNICAL CLARIFICATION
BID PROJECT ENGINEER
INPUT TO PROPOSAL
INPUT TO PROPOSAL
1. DELIVERABLE LIST 2. CTR / MANHOURS ESTIMATE 3. INPUT TO SCHEDULE
1. 2. 3. 4. 5. 6.
TECHNICAL QUALIFICATIONS INPUT FOR ENGINEERING EXECUTION RESPONSE TO QUESTIONAIRES DELIVERABLE LIST CTR / MANHOURS ESTIMATE INPUT TO SCHEDULE
INPUT TO RFQ FOR MAJOR EQUIPMENT
1. 2. 3. 4. 5. 6. 7. 8.
DOCUMENT CONTROL
PLANNER
OTHER DISCPLINES
MECHANICAL MAJOR PACKAGES PRESSURE VESSELS AND TANKS HEAT EXCHANGERS & COOLERS PUMPS PEDESTAL CRANES COMPRESSORS INSTRUMENTS ANY OTHER EQUIPMENT AS REQUIRED
INPUT TO TECHNICAL BID EVALUATION (QUICK TBE)
VENDOR'S PROPOSAL
Page S M
J. Ray McDermot t Asia Pacifi c Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000
Process Engineering
APPENDIX A MATERIAL BALANCE TABLE Stream number
Units
Stream Description Component Nitrogen
Mol frac
H2S
Mol frac
CO2
Mol frac
Methane
Mol frac
Ethane
Mol frac
Propane
Mol frac
I-Butane
Mol frac
n-Butane
Mol frac
i-Pentane
Mol frac
n-Pentane
Mol frac
Hexanes
Mol frac
C7+
Mol frac
Water
Mol frac
TOTAL
Mol frac
Mass flow Operating temperature Operating pressure Gas flow @ PT
lb/hr deg F psig MMscfd
Gas density @PT Oil flow @ PT
bpd
Oil density @PT Water flow @ PT Water density @PT
bwpd
Rev No.
1
19 of 19 Date
31/03/06
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Line List Checklist
JRM-AP-ENG-3000-001
1.0
Rev No.
0
1 of 2 Date
31/03/06
SCOPE The line list checklist will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
3.0
Comply Not Comply Not Applicable
DETAILED CHECK LIST
No.
Description Line designations complete indicating: Nominal Size Fluid service identifier Line number Piping class Insulation identifier Insulation thickness Heat tracing identifier Line numbering, fluid service identifier, piping class, insulation identifier, heat tracing identifier is consistent with project requirements • •
1.
• • • • •
2. 3.
Line designation is consistent with P&ID
4.
Line origin and destination complete
5.
P&ID reference indicated
6.
Fluid service indicated mentioning presence of H 2S, CO2, sand, waxy nature
7.
Fluid service category, if any indicated
8.
Fluid phase like vapor, liquid or mixed-phase indicated
9.
Extent of tracing/ insulation clearly indicated
10 11. 12.
Changes in line size and insulation thickness for same line number, piping class etc. clearly indicated Operating pressure (maximum/ normal/ minimum) indicated Operating temperature (maximum/ normal/ minimum) indicated
13.
Design pressure indicated
14.
Design temperature indicated
15.
Vacuum condition, if any indicated
16.
Short term variations indicated
17.
Changes in operating and design conditions across a control valve for same line number, piping class clearly indicated
C
N/C
N/A
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-001
No. 18. 19.
Procedure title
Rev No.
Line List Checklist
Description
0
C
N/C
N/A
Reservoir life/ all modes of operation including start-up/ shutdown considered for specifying operating, design and short term conditions Piping class is consistent with service, design and short term conditions
Date
Prepared by
Verified by
2 of 2 Date
31/03/06
Remarks
Page
J. Ray McDermott Asia Pacific Engineering
S M
Procedure number
Procedure title
JRM-AP-ENG-3000-002
1.0
Rev No.
Check List For Process Reports and Studies
0
1 of 2 Date
31/03/06
SCOPE The process reports and studies will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
3.0
Comply Not Comply Not Applicable
DETAILED CHECK LIST GENERAL CHECKLIST
No.
Description
1.
Table of content complete
2.
Executive Summary section complete
3.
4.
5.
6.
-
Calculation objective and purpose of calculation summarized
-
Result and recommendation summarized
Introduction section complete -
Reason for the study defined
-
Objectives defined
-
Assumptions identified
Theory section complete -
Engineering principles applied in the study stated
-
Literature sources, if any stated
Method and Calculations section complete -
Calculations method identified
-
Calculations cases stated
-
Process data presented correct
-
Assumptions, if any identified
-
Deviation from design basis, if any noted
Result section complete -
Calculation results clearly stated
-
Results/ trends plotted where appropriate
C
N/C
N/A
Remarks
Page
J. Ray McDermott Asia Pacific Engineering
S M
Procedure number
Procedure title
JRM-AP-ENG-3000-002
No. 7.
8.
9.
10.
11.
Rev No.
Check List For Process Reports and Studies Description
C
0
N/C
N/A
Discussion section complete -
Implication of results, accuracy defined
-
Drawings/ sketches prepared to illustrate arguments
Conclusion and Recommendations -
Conclusion of the study highlighted
-
Action required highlighted
All references complete and accurate -
referenced drawing and documents
-
Design Standards e.g. API etc.
Appendices complete: -
Process Data print out used for calculation
-
Spreadsheet and Software Result print out
-
Backup drawing e.g. isometric, equipments layout
Report / Studies properly documented and stored -
Title block checked
-
Revision marks indicated
12.
Single Discipline Check (SDC)/ IDC done
13.
Client approval obtained
14.
Review comments are properly documented and informed to related discipline and vendor
Date
Prepared by
Verified by
2 of 2 Date
31/03/06
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000-003
1.0
Rev No.
Check List For Process Simulation
1 of 2 Date
0
31/03/06
SCOPE The process simulation will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
3.0 No.
Comply Not Comply Not Applicable
DETAILED CHECK LIST Description
1.
Simulation flow diagram for processing schemes prepared
2.
Simulation model is sufficient to define the system and obtain meaningful results
3.
Simulation model input data consistent with design criteria
4.
All stream numbers clearly shown and correctly assigned
5. 6. 7. 8. 9. 10. 11. 12.
C
N/C
N/A
Remarks
New stream number assigned at each significant change of flowrate, composition or operating conditions Thermodynamic model used is appropriate for mixture being modeled and for the range of temperatures, pressures and compositions simulated Parameters and variables used for sizing and specifying equipment reasonable Simulations converge for all specifications Simulation results like product specification, throughput etc. is as per deign criteria Simulation results like temperature, duty, properties etc. look logical Potential start-up issues like hydrate formation, low temperature check completed File properly named and stored in appropriate network locations
13.
Hysys stream data extracted to Excel spreadsheet
14.
Excel spreadsheet containing heat and material balance transferred to flow sheet drafting
Before beginning a Process Simulation the following information must be available and frozen. No.
Description
1.
Feed Composition (s) and properties frozen
2.
Inlet and outlet conditions defined
3.
Throughput data defined
C
N/C
N/A
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-003
No.
Procedure title
Check List For Process Simulation
Description
4.
Product specifications and requirements defined
5.
Units to be used defined
6. 7.
Rev No.
C
0
N/C
N/A
Preferred order of unit operations (if a choice exists) identified Type of process to perform a particular function (if a choice exists) identified
Date
Prepared by
Verified by
2 of 2 Date
31/03/06
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Check List For SAFE Chart
JRM-AP-ENG-3000-004
1.0
Rev No.
0
1 of 4 Date
31/03/06
SCOPE The SAFE Chart will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
Comply Not Comply Not Applicable
3.0
DETAILED CHECK LIST
3.1
ISSUED FOR APPROVAL
No.
Description
1.
All process systems covered
2.
All utility systems covered
3.
Interpretation of API RP 14C acceptable
4.
Consistent with Company ESD philosophy
5.
Consistent with process and safety shutdown philosophy
6.
Special requirements identified
7.
P&IDs and tag numbers correctly referenced
8.
All “HOLDS” identified
9.
Instrument and electrical group comments incorporated
10.
SAFE Chart numbering as per drawing numbering procedure
11.
Correct revision number and description
12.
SAFE Chart for vendor package covered by Vendor
3.2
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
APPROVED FOR DESIGN
No
Description
1.
Client comment on "for approval" issue incorporated as appropriate
2.
All “HOLDS” removed
3.
Vendor information if any incorporated
4.
Correct revision number and description
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Check List For SAFE Chart
JRM-AP-ENG-3000-004
3.3
2.
Description
31/03/06
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
Client comment on "for design" issue incorporated as appropriate HAZOP and safety recommendations incorporated as appropriate
3.
Vendor information incorporated
4.
Correct revision number and description
3.4
0
Date
APPROVED FOR CONSTRUCTION
No 1.
Rev No.
2 of 4
PRE-ISSUE SAFE CHART CHECK LIST General
No
Description
1.
Drawing number as per numbering procedure
2.
Correct revision number and description
Process Components No
Description
1.
Wellheads and flowlines covered
2.
Wellhead injections lines covered
3.
Headers/ Manifold covered
4.
All pressure vessels covered
5.
All atmospheric vessels covered
6.
All Pumps covered
7.
All Compressors covered
8.
All Heat Exchangers covered
9.
Pipelines covered
10.
Fired and Exhaust heated components covered
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Rev No.
Check List For SAFE Chart
JRM-AP-ENG-3000-004
0
3 of 4 Date
31/03/06
Safety Analysis Checklist No 1. 2.
Description
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
All process components with appropriate tag numbers and service defined Appropriate SAC reference number identified for each process components
3.
All safety devices identified by their tag numbers
4.
Appropriate function for all safety devices identified
5.
Alternate protection device identified
6.
All shutdown valves identified
7.
Deviation from API 14C recommendations if any identified
Shutdown Systems No 1.
Description All levels of Emergency shutdown systems (ESD) identified as per Company ESD philosophy
2.
Appropriate function for each level of ESD identified
3.
Process shutdown system (PSD) identified
4.
Appropriate function for PSD identified
5.
Unit shutdown system (USD) identified
6.
Appropriate function for USD identified
Special Requir ements No
Description
1.
Shutdown valve closure time identified
2.
Pump interlocks identified
3.
Compressor interlocks identified
4.
Pump auto start/stop function identified
5.
Compressor auto start/stop function identified
6.
Pre alarms identified
7.
Cascade trip identified
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-004
Procedure title
Rev No.
Check List For SAFE Chart
0
4 of 4 Date
31/03/06
Special Requir ements No
Description
8.
Shutdown bypass function identified for different modes of operation
9.
Shutdown through voting logic identified
10.
Appropriate notes from Company ESD philosophy defined
11.
Interface with vendor packages defined
12.
Interface with external facilities like onshore processing, FPSO etc defined
13.
HAZOP and safety studies recommendations incorporated
Date
Prepared by
C
N/C
N/A
Verified by
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Check List For PFD
JRM-AP-ENG-3000-005
1.0
Rev No.
0
1 of 2 Date
31/03/06
SCOPE The PFD will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
Comply Not Comply Not Applicable
3.0
DETAILED CHECK LIST
3.1
ISSUED FOR APPROVAL
No.
Description
1.
Major processing scheme(s) covered
2.
Processing scheme(s) clear and logical
3.
All stream numbers clearly shown and correctly assigned
4. 5. 6. 7.
New stream number assigned at each significant change of flowrate, composition or operating conditions Stream number consistent with that used in process simulation model Stream summary in Heat & Material Balance tables provides operating data and frequently used properties (rated/ normal/ minimum) Stream compositional data is accurate to 2 significant figures
8.
All material is accounted for in balances
9.
If two or more parallel trains exist, detail of only one tr ain shown
10.
Throughput per train clearly shown
11. 12.
Major equipment(s) shown complete with equipment numbers Major vendor package(s) shown complete with package numbers
13.
Major process control(s) defined
14.
All “HOLDS” identified
15.
Interdisciplinary comments incorporated
16.
PFD numbering is as per drawing numbering procedure
17.
Correct revision number and description
18.
PFD preparation is inline with JRMAPE Procedure JRM AP-ENG-4000, Section 6.1, Process Flow Diagrams
C
N/C
N/A
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Check List For PFD
JRM-AP-ENG-3000-005
3.2
2.
Description
31/03/06
C
N/C
N/A
Remarks
Client comment on "for approval" issue incorporated as appropriate Major equipment(s) duty, size and design conditions defined
3.
Major vendor package(s) PFD included
4.
All “HOLDS” removed
5.
Correct revision number and description
3.3
0
Date
APPROVED FOR DESIGN
No 1.
Rev No.
2 of 2
PRE-ISSUE PFD CHECK LIST Before the PFD is prepared the following information must be available and frozen.
No
Description
1.
Feed Composition (s) and properties frozen
2.
Inlet and outlet conditions defined
3.
Throughput data defined
4.
Product specifications and requirements defined
5.
Units to be used defined
6. 7.
C
N/C
N/A
Preferred order of unit operations (if a choice exists) identified Type of process to perform a particular function (if a choice exists) identified
Date
Prepared by
Verified by
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Check List For MFD (P&ID)
JRM-AP-ENG-3000-006
1.0
Rev No.
0
1 of 9 Date
31/03/06
SCOPE The MFD (P&ID) will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
Comply Not Comply Not Applicable
3.0
DETAILED CHECK LIST
3.1
ISSUED FOR APPROVAL
No. 1. 2.
Description
4.
All safety valves shown
5.
Block and bleed isolation valves shown
6.
Major vendor packages shown complete with package numbers
7.
Special items shown
8.
Future piping and equipment indicated
9.
API RP 14C analysis completed
10.
Company’s isolation philosophy incorporated
11.
Check with design criteria completed
12.
HOLDS clearly identified
13.
Interdisciplinary comments incorporated
14.
Correct revision number and description
1. 2. 3.
N/A
Remarks
C
N/C
N/A
Remarks
All major equipments shown complete with equipment numbers All control valves shown
No.
N/C
All major process/utility lines shown and sized
3.
3.2
C
APPROVED FOR DESIGN Description Client comment on "for approval" issue incorporated as appropriate All lines shown with commodity, size, series number and insulation details All equipments duty, size and design conditions defined
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000-006
No.
Rev No.
Check List For MFD (P&ID) Description
4.
All control valves shown with size and tag numbers
5.
All instrumentations shown with 'tag numbers
6.
All block and isolation valves size shown
8.
All vessel elevations shown
9.
All vendor skids shown complete with connecting services (applicable to machinery and packages)
10.
All 'SP' items shown complete with tag numbers
11.
All sample connections shown complete with coolers where appropriate
12.
All chemical injection points shown
13.
Correct revision number and description
Description
1.
Client comment on "approved for design" issue incorporated as appropriate
2.
All "Holds" removed
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
All HAZOP and Safety studies recommendations incorporated
4.
Vendor information added as necessary
5.
Silencers and acoustic insulation shown
6.
Correct revision number and description
3.4
31/03/06
APPROVED FOR CONSTRUCTION
No
3.
Date
All safety valves shown with size, set pressure and tag numbers
7.
3.3
0
2 of 9
PRE-ISSUE P&ID CHECK LIST General
No
Description
1.
Drawing and revision number as per procedure
2.
Symbols are in accordance with job symbol sheet
3.
All equipments and packages numbered
4.
Major equipments and packages have data blocks consistent with data sheets
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000-006
Rev No.
Check List For MFD (P&ID)
0
3 of 9 Date
31/03/06
General No
Description
5.
All specialty items shown and tagged
6.
Battery limits of packaged equipment indicated
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
Piping / Valves No. 1. 2. 3.
Description Flow direction indicated on all lines Origin/destination correctly shown for all lines coming on/leaving drawings All lines numbered in accordance with job format and consistent with line list
4.
All line sizes, rating, materials or service indicated
5.
Spec. break points indicated and correctly located
6. 7. 8. 9.
Seal legs and overflows dimensioned with regard to liquid levels Piping notations: 'No Pockets', 'Gravity Flow', 'Straight length’, 'Slope', 'symmetrical piping' and changes in applicable piping code indicated Special piping items such as removable spools, hose connections, strainers, traps etc. indicated Specialty items such as, mixers, pulsation dampeners, ejectors, silencers, flame arrestors, weather hoods etc. indicated and tagged
10.
Reducers indicated
11.
Elevation required to supply NPSH to pumps and flowmeters indicated
12.
Depressurization and draining facilities provided
13.
Insulation and heat tracing, if required provided
14. 15. 16. 17. 18.
Permanent connection between process and utility lines avoided Sample points correctly shown with regard to 'hot' and toxic services Valves and blinds indicated and tagged Valves that are normally closed during operation are shown as closed Valves that have to be locked in a specific position are indicated
19.
Valves that have to be interlocked are shown and tagged
20.
Valves that have to be full bore are indicated
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-006
Procedure title
Rev No.
Check List For MFD (P&ID)
0
4 of 9 Date
31/03/06
Piping / Valves No. 21.
Description
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
Check valves on riser designed to allow passage of pig.
Instruments No.
Description
1.
All instruments are numbered
2.
Instrument symbols are in accordance with job symbol sheet
3.
Instrument legend sheet finalized
4.
Important/guaranteed process and utility parameters can be satisfactorily measured
5.
Necessary alarms and pre-alarms indicated
6.
All necessary trips provided
7. 8. 9.
Set points for pressure, temperature and level switches indicated Special instrument notes if required e.g. 'Minimum Stop,' 'Reset,' 'Locate Local to' etc indicated Block, bypass and drain valves associated with control valves indicated as per isolation philosophy
10.
Control valve sizes indicated
11.
Failure position indicated for each control valve and SDV
12.
Tight shut off (TSO) requirements for control valves indicated
13.
SDVs are located close to vessel outlet
14.
Closure time for SDVs indicated
15.
SDV on riser designed to allow passage of Pig
16. 17. 18. 19.
Pressure gauge provided for calibration of self actuated pressure control valves Straight length requirement for flow instruments indicated. For ultrasonic flowmeter straight length requirement refer to attached vendor recommendations. Pressure, temperature compensation for gas flow meters provided Strainers upstream of turbine meters on dirty f luid service provided
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Rev No.
Check List For MFD (P&ID)
JRM-AP-ENG-3000-006
0
5 of 9 Date
31/03/06
Pressure / Vacuum Relief Valves and Piping No.
Description
1.
PSV's/PVRV's numbered
2.
PSV provided on all pressure vessels
3.
Blanket gas/ PVRV provided on atmospheric tanks
4.
Set pressures, size and sizing case indicated and consistent with instrument data sheets
5.
Set points staggered for multiple PSV installation
6.
PSV sparing is as per sparing philosophy
7. 8.
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
Isolation valves as per isolation philosophy provided and are shown ‘Interlocked’ or 'Locked Open/close' PSV nozzle size, type and ratings are as per instrument data sheet
9.
Provision for online testing and maintenance provided
10.
PSV tail pipes routed to correct disposal point
11.
PSV heat tracing if required indicated
12.
PSV on dirty or corrosive services provided with adequate protection
13.
Piping size and arrangement is in accordance with API 520
14.
Inlet and outlet line size equal to or greater than PSV nozzles
15.
PSV outlet lines sized to avoid noise induced vibration
16.
Piping is free draining to the process on the upstream side of PSV and to the relief header on the downstream side
17.
PSV discharge piping enters the relief header on top
18.
PSV outlet piping rating and spec. consistent with built-up back pressure and relieving temperature
Centrifugal Pumps No.
Description
1.
Suction strainers provided
2.
Check valve provided in the discharge line
3.
Minimum flow recycle provided
4.
Check valve installed downstream of recycle line
5.
Pressure rating of the pump discharge piping consistent with maximum pressure developed by pump
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Rev No.
Check List For MFD (P&ID)
JRM-AP-ENG-3000-006
0
6 of 9 Date
31/03/06
Centrifugal Pumps No.
Description
6.
Suction piping and valves rated for full discharge pressure or other means of suction overpressure protection provided
7.
Pump vent and drain connections with valve provided
8.
Driver type indicated
9.
Necessary interlocks to the process, local and remote start/stop buttons indicated
10.
Automatic start/stop loops indicated
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
Positive Displacement Pumps No.
Description
1.
Suction strainers provided
2.
Check valve provided in the discharge line
3.
Pump discharge piping protected by a relief valve upstream of the first block valve
4.
Pressure controlled spillback provided
5. 6.
Pulsation dampener installed on the suction and discharge lines of the pump Suction piping and valves rated for full discharge pressure or other means of suction overpressure protection provided
7.
Pump vent and drain connections with valve provided
8.
Driver type indicated
9.
Necessary interlocks to the process, local and remote start/stop buttons indicated
10.
Automatic start/stop loops indicated
11.
Note for maximum suction length indicated
Centrifugal Compressors No.
Description
1.
Suction strainers provided
2.
Suction overpressure protection provided
3.
Suction piping straight length requirement before the inlet nozzle indicated
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Rev No.
Check List For MFD (P&ID)
JRM-AP-ENG-3000-006
0
7 of 9 Date
31/03/06
Centrifugal Compressors No.
Description
4.
Check valve provided in the discharge line
5.
Minimum flow bypass (surge) loop provided
6.
Discharge overpressure protection provided
7.
Discharge high temperature protection provided
8. 9. 10. 11. 12.
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
Start-up lines, control valve bypasses and any special requirement indicated. Blanked inert gas/ purge connections provided on suction and discharge piping Driver type indicated Necessary interlocks between driver controls and process control indicated Separate P&ID for turbine and compressor utility system provided
Reciprocating Compressors No.
Description
1.
Suction strainers provided
2.
Suction overpressure protection provided
3. 4.
Suction piping straight length requirement before the inlet nozzle indicated Pulsation suppression device installed on suction and discharge of the compressor cylinder where appropriate
5.
Check valve provided in the discharge line
6.
Pressure controlled spillback provided
7.
Discharge piping protected by a relief valve upstream of the first block valve
8.
Discharge high temperature protection provided
9.
Vibration monitoring system provided
10. 11.
Start-up lines, control valve bypasses and any special requirement indicated Blanked inert gas/ purge connections provided on suction and discharge piping
12.
Driver type indicated
13.
Necessary interlocks between driver controls and process control indicated
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
Rev No.
Check List For MFD (P&ID)
JRM-AP-ENG-3000-006
0
8 of 9 Date
31/03/06
Pressure Vessels No. 1.
Description
All nozzle sizes indicated
3.
Vessel internals like packing, mist eliminator etc. indicated
4.
Baffles and vortex breakers indicated
5.
Liquid levels indicated
6.
Vessel elevation indicated
7.
Vent and drain connections provided
8.
Review requirement of RO on drain lines to minimize gas blow by
9.
Purge connection indicated
10.
Instrumentation on vessels indicated
11.
Vessel trim material indicated
13.
N/C
N/A
Remarks
C
N/C
N/A
Remarks
All vessel nozzles in their relative positions to vessel geometry and internals indicated
2.
12.
C
Automatic or manual vapor depressurization facility provided Pressure sensing devices and PSV located upstream of mesh pad or other restrictions
14.
Insulation if required provided
15.
Heat tracing for level bridles if required, provided
16.
Spectacle blinds/ spacers as per isolation philosophy provided
17.
Three nozzles provided for interface level measurement
18.
Man-ways and hand-holes as required are provided
19.
Validation with data sheet completed
Heat Exchangers No.
Description
1.
Each shell is indicated
2.
Hot and cold stream going to the proper side of the exchanger indicated
3.
Nozzle type, size and number indicated
4.
Instruments if any on the exchanger nozzle are indicated
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-006
Procedure title
Rev No.
Check List For MFD (P&ID)
0
9 of 9 Date
31/03/06
Heat Exchangers No.
Description
5.
Vent and drain connections indicated
6.
Protective device provided on the low pressure side
7.
Thermal relief safety valve on cold side provided
8.
Insulation requirement indicated
9.
Isolation connection as per isolation philosophy provided
10.
Review high temperature protection downstream of exchanger
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
Ai r Co olers No. 1. 2. 3. 4. 5.
Description Correct number of bays and fans in each bay indicated Correct nozzle configuration for each bay, nozzle size indicated Correct orientation for inlet piping as required for process stream distribution to various bays and tube bundles indicated. Check if symmetrical piping is required Fan motor control center and interlocks including vibration switches and start/ stop buttons indicated Auto-variable fans and their control loops if required indicated
6.
Louvers and louver control loops if required indicated
7.
Vent and drain connections indicated
8.
Isolation connection as per isolation philosophy provided
9.
Review high temperature protection downstream of cooler
Date
Prepared by
Verified by
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000-007
1.0
Rev No.
Check List For Process Calculation
0
1 of 1 Date
31/03/06
SCOPE The Process Calculation will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
3.0
Comply Not Comply Not Applicable
DETAILED CHECK LIST
No.
Description
1.
Calculation objective and purpose of calculation identified
2.
Process sketch prepared
3. 4.
All assumptions properly identified and defined
6.
All references complete and accurate
7.
Appropriate calculation tools selected
8.
Validated spreadsheets used
9.
Calculation adequate for intended purpose
10.
Appropriate units identified and used
11.
Appropriate constant identified and used
12.
Results checked against past project to confirm reasonableness
13.
Single Discipline Check (SDC) done
15.
16.
N/C
N/A
Appropriate parameters for calculations used (Design Basis, Simulation, Heat and Material Balance, Datasheets, etc.) Special requirement incorporated notes in datasheets etc.
5.
14.
C
Calculation properly documented and stored Title block checked Revision marks indicated Appropriate calculation results incorporated in affected documents P&IDs Datasheets etc. Calculation in line with JRMFEE Procedure JRM-AP-ENG2900, Design (Analysis and Calculations)
Date
Prepared by
Verified by
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-007
Procedure title
Check List For Process Calculation
Rev No.
0
2 of 1 Date
31/03/06
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000-008
1.0
Rev No.
Check List For Datasheets - Equipment
1 of 2 Date
0
31/03/06
SCOPE The Datasheets – Equipment will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
3.0
Comply Not Comply Not Applicable
DETAILED CHECK LIST
No.
Description
1.
Title block (Tag No.) correct
2.
Equipment service defined
3.
No of equipments correct
4.
Equipment type defined
5. 6.
Design condition provided and consistent with P&IDs / PFDs / Equipment List Operating condition ( Normal / Maximum / Minimum ) provided and consistent with P&IDs / PFDs
7.
Short term transient condition defined
8.
Design cases defined
9. 10. 11. 12.
Appropriate preliminary sizing calculation done considering full range of duties (Min / Normal / Max ) Equipment dimension provided and consistent with calculation result and P&IDs Equipment performance and rating (duty / capacity) provided Process data for all cases provided and consistent with Heat and Material Balance or Simulation
13.
Simulation’s print out attached for documentation
14.
Design margin / turndown requirement defined
15.
Severe/corrosive component such as CO2, H2S, solid, wax indicated
16.
Material of construction indicated
17.
Internals and other design feature requirement defined
18.
Utilities condition defined
19.
Scope of supply defined
20.
Standard Code or Specification to comply with, defined
21.
Special requirement in design basis and specification indicated in NOTES
C
N/C
N/A
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-008
No.
Procedure title
Check List For Datasheets - Equipment Description
22.
Information to be confirmed by vendor marked
23.
Equipment sketch provided
24.
Nozzles schedule indicated in sketch and sizes consistent with P&IDs
25.
HOLDs clearly indicated
26.
Single Discipline Check done
27.
IDC done where required
28.
Revision marks indicated
29.
Client comments and approval obtained
30.
Incorporate changes on master mark-ups of the PFDs and P&IDs
31.
Datasheet properly documented
Date
Rev No.
Prepared by
C
0 N/C
N/A
Verified by
2 of 2 Date
31/03/06 Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000-009
1.0
Rev No.
Check List For Datasheets - Instrument
1 of 2 Date
0
31/03/06
SCOPE The Datasheets – Equipment will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
3.0 No.
Comply Not Comply Not Applicable
DETAILED CHECK LIST Description
1.
Title block (Tag No.) correct
2.
Service description provided
3.
Instrument location provided e.g. Line number or vessel tag no.
4.
Line size and schedule provided where required
5.
P&ID number provided
6.
Type of instrument provided (e.g. PSV : conventional / bellow / pilot)
7.
Size provided
8.
End connection size and rating provided, consistent with P&ID
9.
Material of Construction provided
10.
Appropriate performance criteria defined e.g.: Allowable pressure drop Fail Position Set Point
11.
Design cases defined
12.
Short term transient condition defined
13.
Preliminary sizing done covering full range of duty (Min / Normal / Max)
14.
Calculation sheets and simulation print out attached
15.
Process Data complete for all cases and consistent with Heat and Material Balance and Simulation.
16.
Code, Standard, and Specification to comply with, defined
17.
Severe / corrosive component such as CO2, H2S, solid and wax indicated
18.
Information to be confirmed by vendor marked
19.
Special requirement in design basis and specification indicated in NOTES
20.
HOLDs clearly indicated
C
N/C
N/A
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-009
Procedure title
Check List For Datasheets - Instrument
No.
Description
21.
Single discipline check done
22.
IDC done where required
23.
Revision marks indicated
24.
Client comments and approval obtained
25.
Incorporated changes and confirmed that they are reflected on Master Mark-ups of the PFDs and P&IDs
26.
Datasheet properly documented
Date
Rev No.
C
Prepared by
N/C
2 of 2 Date
0
31/03/06
N/A
Remarks
Verified by
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
Procedure title
JRM-AP-ENG-3000-010
1.0
Rev No.
Check List For Layout Drawings
1 of 4 Date
0
31/03/06
SCOPE The Datasheets – Equipment will include (as a minimum) the following for each issue.
2.0
ABBREVIATIONS C N/C N/A
3.0
Comply Not Comply Not Applicable
DETAILED CHECK LIST EQUIPMENT LAYOUT CHECKLIST
No. 1. 2. 3. 4. 5. 6. 7. 8.
9. 10. 11. 12. 13. 14.
Description All equipments as per P&ID indicated Installation of future equipment, platforms or pipelines considered Layout reflects a logical progression of the process t o minimize cross-deck piping runs Related equipment modularized e.g. compressor with associated knock out drum and after-cooler Living quarters, control room, radio room etc. located away from hazardous process equipment, wellhead area, high noise sources, hot exhausts etc. Separation of fuel and ignition sources considered Sources of ignition minimized in the process and well bay area Helideck located on the prevailing upwind side of the platform and away from exhausts of fired equipment, generators etc. Prevailing wind direction considered in the location of flare, vent boom and with due regard to the location of drilling derrick, platform crane, helideck and living quarters Appropriate escape routes provided Electrical equipments installed in appropriate classified areas Drilling and wellhead area separated from processing and utility areas Pig launchers and receivers and equipments protected from external impact such as dropped objects Equipment containing high pressure gas located in the upper decks
15.
Liquid vessels located lower than gas equipment
16.
Low pressure equipment containing large amount of hydrocarbon liquid located and arranged to minimize exposure to jet fires or otherwise need for passive fire protection evaluated
C
N/C
N/A
Remarks
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-010
No.
17.
18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 30. 31. 32.
Procedure title
Rev No.
Check List For Layout Drawings
Description
0
2 of 4 Date
31/03/06
C
N/C
N/A
Remarks
C
N/C
N/A
Remarks
Vessels elevation adequate to meet pump NPSH requirements, to avoid flashing upstream liquid outlet control valves and any other specific requirements identified in the P&ID Electrostatic coalescer/ treater elevation enable liquid full operation Compressor and coolers located above scrubbers Hot oil expansion tank located at the highest point in the heating medium system Chemical injection system located in safe area. Fill area located at higher elevation with gravity feed to storage tanks Flare/ vent KO drum location meets flare/ vent header slope requirement Flare/ vent boom length is consistent with P&ID Pumps located as low as possible to secure sufficient NPSHA Hazardous open drain tank and pump located in Hazardous area Non-hazardous open drain tank and pump located in nonhazardous/ hazardous area Open drain tank located to allow gravity draining from all sources Closed drain tank located to allow gravity draining from all sources Pig launchers and receivers located in open, naturally ventilated areas, at the periphery of the platform and with hatches directed away from equipment or structures Risers SDV located in open naturally ventilated areas as close to the sea as practicable For risers coming up the structure below the living quarter’s area, protection against riser failure provided Space for handling pigs provided
PIPING LAYOUT CHECKLIST No.
Description
1.
Cold and hot piping grouped separately
2.
Routing of hydrocarbon piping through utility areas minimized and flanges avoided
3.
Hydrocarbon piping not routed in the living quarter areas
4. 5.
Liquid piping not routed though electrical, instrument and control room Straight piping runs provided where appropriate e.g. meter runs, compressor suction lines etc.
Page S M
J. Ray McDermott Asia Pacific Engineering
Procedure number
JRM-AP-ENG-3000-010
No. 6. 7. 8. 9. 10. 11. 12.
Procedure title
Check List For Layout Drawings Description
Vapor lines in wet carbon dioxide or corrosive service have no liquid pockets Utility headers for water, air, steam etc. arranged on top of multi-tiered pipe racks All valves requiring operation during normal or emergency conditions are accessible Check valves installed in vertical lines is having flow in upwards direction Control valves located as near as possible to the relevant equipment Control valve operated by a local controller is located within the visual range of the controller Control valves in bubble point liquid service is located to avoid possibility of flashing at the valve inlet
13.
PI visible from self actuated pressure control valves (PCV)
14.
Piping to pressure relief valves as short as possible
15. 16.
Slopes provided on flare and vent piping to the knock out vessel Where pocket is unavoidable on relief/ vent headers, approved means of continuous draining for the header provided
17.
Branch connections on relief/ vent header enter from top
18.
Slopes provided on open drain system piping
19.
Hazardous and non-hazardous piping segregated
20. 21. 22. 23. 24. 25.
Firewater pump discharge overboard line is as short as possible and with minimum bends Firewater discharge line from building and from engine routed directly to overboard Pump suction lines have no vapor pockets and is as short as possible with minimum bends No Pockets in Compressor suction lines and is sloping towards suction scrubber Anti-surge line is sloped with the anti-surge valve at the highest point Main piping after methanol injection is sloping towards cooler
26.
Two phase lines from coolers free drain to the scrubber
27.
No pockets in two phase line to minimize potential slugging
28. 29. 30. 31.
Rev No.
Piping routing from scrubber to Glycol Contactor is minimized Fuel gas line between the scrubber and heater is sloping towards the scrubber Fuel gas line between the heater and gas turbine is not pocketed Symmetrical piping is provided wherever required
0 C
N/C
N/A
3 of 4 Date
31/03/06 Remarks