ConocoPhillips BayuUndan Phase 3 Project Level 3, 53 Ord street West Perth PO Box 1102, West Perth WA 68721 Business 61 (0) 8 9423 6666 Facsimile 61 (0)8 6363 2042
DOCUMENT COVER SHEET Total number of pages of this document
37
DOCUMENT TITLE: Flexible Flowline and Static Umbilical Installation Analysis - Campaign 2
DOCUMENT STATUS:
INFORMATION
FOR REVIEW
AS BUILT (AB)
OTHER
COMPANY’S DOCUMENT No: H8-SSP-00-066-N01-68585
REV: 0
SUPPLIER’S DOCUMENT No: AA0016-ENG-20008
REV: 0
PO/CONTRACT No. : 262163-01-BUP3
APPROVAL
EQUIPMENT TAG No:
NOTES:
EQUIPMENT DATA SHEET No:
DOCUMENT STATUS AS REVIEWED BY CONOCOPHILLIPS
1.
Accepted/Proceed
2.
Revise & Resubmit. Work May Proceed. Incorporate all changes indicated.
3.
Revise & Resubmit. Work May Not Proceed. Review Not Required. Work May Proceed / Information Only
4.
Reviewed By:
Date:
REVISIONS TO COMPANY’S DOCUMENT No. Rev
Date
Description
Signature
A
10.10.2014
Issued for Client Review
JPE
0
28.11.2014
Approved for Construction
JPE
DOC/CMP/TEM/0004 Rev 1
Supplier shall resubmit document in accordance with instructions accompanying returned document. This review and comments, if any, do not alter any of the terms and conditions of the Contract, nor does it relieve the Supplier from any responsibility or liability for the accuracy and completeness of the document, nor shall it be interpreted so as to imply approval of such document, nor shall it be interpreted as an assumption by or imposition on ConocoPhillips of any liability or responsibility as a result of such review
www.subsea7.com
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project 262163-01-BUP3
Flexible Flowline Installation Analysis – Campaign 2 AA0016-ENG-20008
Originator:
Amirhossein GHANIZADEH
Analysis Engineer
Checker:
Julien CAPUL
Senior Analysis Engineer
Approver:
Stephan EYSSAUTIER
0
Approved for Construction
28.11.2014
Rev.
Reason for Issue
Issue Date
Project Engineering Manager Digitally signed by amirhossein.ghaniz
[email protected] DN: cn=amirhossein.gh anizadeh@subsea7. com Date: 2014.11.27 18:19:26 +01'00'
amirhosse in.ghaniza AGH deh@subs ea7.com
Prepared by
Digitally signed by Julien Capul DN: cn=Julien Capul, o=Subsea 7, ou=Engineering, email=julien.capul@ subsea7.com, c=FR Date: 2014.11.27 18:23:58 +01'00'
Julien JCA Capul
Checked by
stephan. eyssauti SEY er@subs ea7.com
Digitally signed by stephan.eyssautier@s ubsea7.com DN: cn=stephan.eyssautie
[email protected] Date: 2014.11.28 09:13:05 +08'00'
Approved by
Client Approval
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 2 of 36
This document is the property of Subsea 7 and its affiliates and subsidiaries and copying and/or disclosure of the information it contains is prohibited without the permission of Subsea 7. It has been reviewed and approved in accordance with management system requirements and where applicable an audit trail is available within the relevant document management system. The most recently approved version is regarded as the controlled copy with all other copies being for information only. It is the holder’s responsibility to ensure that they hold the latest approved version. © Subsea 7
REVISION RECORD SHEET Revision
Issue Date
0.1
01.08.2014
Issued for IDC
A
10.10.2014
Issue for Client Review
Purpose
Description of Updated/Modified Sections (if any)
Implemented IDC comments • • • •
0
28.11.2014
Approved for Construction
• • • •
Implemented IFCR comments Static umbilical scope removed Analysis for Riser EF abandonment/ recovery added (section 5.3) Analysis for Flowline-Flowline intermediate connection laydown added (section 5.4) Dynamic analysis updated throughout the document Sensitivity with max and min WD added Sensitivity with current added Crossing analysis updated with sensitivity on layback and point loading calculations (section 5.5)
DISTRIBUTION Recipient
Company
E-Mail Address
Qty
HOLDS Section
© Copyright Subsea 7
Reason for HOLD
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 3 of 36
TABLE OF CONTENTS 1.
INTRODUCTION .............................................................................................. 4 1.1 OVERALL PROJECT ..................................................................................... 4 1.2 SCOPE OF DOCUMENT................................................................................ 5 1.3 ABBREVIATIONS AND DEFINITIONS ............................................................ 6 1.4 ASSUMPTIONS .......................................................................................... 6 1.5 HOLD LIST ................................................................................................ 6 1.6 REFERENCES............................................................................................. 6
2.
CONCLUSIONS ................................................................................................ 8
3.
ANALYSIS BASIS .......................................................................................... 10 3.1 PRODUCT AND ANCILLARY EQUIPMENT DESCRIPTION ................................. 10 3.2 VESSEL CHARACTERISTICS ...................................................................... 12 3.3 ENVIRONMENT INPUT DATA ...................................................................... 14 3.4 LAY ROUTE DATA..................................................................................... 14 3.5 SOIL FRICTION COEFFICIENTS .................................................................. 14 3.6 LIMITING CRITERIA FOR ANALYSIS ........................................................... 15
4.
METHODOLOGY ............................................................................................. 16 4.1 SOFTWARE ............................................................................................. 16 4.2 WAVE DATA SELECTION AND DIRECTONALITY ............................................ 16 4.3 STATIC ANALYSIS METHODOLOGY............................................................. 18 4.4 DYNAMIC ANALYSIS METHODOLOGY .......................................................... 18
5.
ANALYSES RESULTS ...................................................................................... 21 5.1 NORMAL LAY AND CURVE LAY ................................................................... 21 5.2 FLEXIBLE FLOWLINE TERMINATION ABANDONMENT / RECOVERY .................. 24 5.3 FLEXIBLE RISER TERMINATION ABANDONMENT / RECOVERY ........................ 27 5.4 FLOWLINE-FLOWLINE INTERMEDIATE CONNECTION LAY-DOWN ................... 29 5.5 CROSSING ANALYSIS ............................................................................... 34
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 4 of 36
1.
INTRODUCTION
1.1
OVERALL PROJECT Bayu-Undan consists of two gas and condensate fields located offshore approximately 500km north-west of Darwin in the Timor Sea, and 250km south east of East Timor. The fields are located in approximately 80m water depth.
Figure 1-1: Field Location
Commercial production began in April 2004, delivering 115,000bpd of condensate and LPG through a gas recycle scheme. The next phase of development, the gas phase, began production in February 2006. This involved the extraction of lean gas from the reservoir and transportation to Darwin on Australia’s northern coast via a 500km, 26in pipeline where it is liquefied at a single-train processing plant located at Wickham Point near Darwin then shipped as LNG to customers Tokyo Electric Power Company and Tokyo Gas in Japan. The field will require approximately 26 wells over its lifetime to produce the reserves. Since production start-up, most of the necessary wells to exploit the core area have been drilled from either the Drilling Production and Processing Platform (DPP) or the existing satellite Wellhead Platform (WP1). The field remaining life is estimated to be around 13 to 15 years. However in order to sustain gas and condensate production, access to peripheral areas of the field will be necessary by 2015. For Phase 3 development, two new subsea wells, BU-DS01 and BU-DS02, have been identified and will be tied back to existing Drilling Production and Processing Platform (DPP) through individual subsea flowlines and risers. An umbilical riser shall be routed from DPP topsides to a Subsea Umbilical Distribution Unit (SUDU) near to the base of the platform, but outside of the flare radiation zone, from where two umbilicals shall route one each to BU-DS01 and BU-DS02 running roughly parallel with the flowlines.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 5 of 36
Figure 1-2: Field Schematic
Contractor is responsible for all project management, project services, coordination with Company and Company’s other contractors, design development, detailed engineering, procurement, construction, onshore testing, load-out, transportation, installation, offshore hook-up, pre-commissioning, commissioning support and other activities as pertinent to the Scope of Work. The Scope of Work is for subsea hardware design, flowlines, umbilical and riser system installation engineering, supply (excluding Company Provided Items), Installation and Pre-Commissioning / Commissioning for the Bayu-Undan Phase 3 Field Development: 29km of Umbilicals with a Subsea Distribution Unit and 29km of 10” Flexible Flowlines with 2 Dewatering Manifolds connected to Wellheads by flexible jumpers.
1.2
SCOPE OF DOCUMENT The purpose of this document is to present the installation analysis performed for the flexible flowline of Campaign 2 installed with the Skandi Acergy. Analyses have been done for the following operations: Normal lay and curve lay of flexible flowline Flexible flowline termination abandonment / recovery Flexible riser termination / recovery. Flexible flowline intermediate connection lay-down and sensitivity with riser/flowline intermediate connection lay-down. These analyses are based on the document Campaign 2 – Flexible Flowline Installation Procedure (ref. H8-SSP-00-066-V02-65785).
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 6 of 36
1.3
ABBREVIATIONS AND DEFINITIONS Abbreviation A&R ART EF EL FLS Hs ID MBR OD TDP Tp WD
1.4
ASSUMPTIONS Section Ref. 3.3
1.5
Definition Abandonment & Recovery Anti-Roll Tank End fitting Elevation Flexible Lay System Significant wave height Inner Diameter Minimum Bending Radius (for installation purpose) Outside Diameter Touch Down Point Peak Period Water Depth
Assumption Detail Typical friction coefficients have been taken from previous projects
HOLD LIST Number
1.6
REFERENCES
1.6.1
Documents – Subsea 7 Reference H8-SSP-00-066-V02-65785 H8-SSP-00-066-D06-65812 H8-SSP-00-066-D06-65814 H8-SSP-00-066-N01-65766 H8-SSP-00-066-D06-65818
1.6.2
Reason for Hold
Title Campaign 2 – Flexible Flowline Installation Procedure 10" Flexible Lay Route Drawing BU-DS01 10" Flexible Lay Route Drawing BU-DS02 Flexible Risers Installation Analysis Campaign 2 – Skandi Acergy Deck Layout
Documents – Customer Reference BUP3-000-SE-R02-D-00001 H8-SSP-01-029-D45-2134 H8-SSP-01-029-D45-2138 H8-SSP-01-020-G01-64782
© Copyright Subsea 7
Title Summary of Metocean Conditions Prepared for Bayu Undan Location Bayu Undan Phase 3 DPP Tie-Back Overall Field Layout Bayu Undan Phase 3 DPP Tie-Back Field Layout Schematic Flexible Pipelay Wellstream – Pipe Data Sheets
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 7 of 36
Reference H8-SSP-01-029-D06-64810 H8-SSP-01-029-D06-65050 1.6.3
Title Wellstream - Endfitting Configuration 10" Production Flowline Wellstream - Installation/Pull Head Configuration 55Te SWL Grayloc 12M102 10.0" Riser/Flowline
Documents – 3rd Party / Subcontractor Reference
© Copyright Subsea 7
Title
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 8 of 36
2.
CONCLUSIONS The installation analyses of the flexible flowlines have been performed. The results demonstrate that all operations can be performed in a safe manner with the following allowable sea-states: Installation stage
Allowable Hs (m)*
Lay back range (m)
Vessel heading restriction
Governing parameter
Alternative criteria on vessel motion
No
Clearance with moon pool, MBR
Not required (high Hs)
Min WD: (16-30)
Normal lay Flowline termination abandonment or recovery Riser termination abandonment or recovery Flowline/Flowline intermediate connection laydown Flowline/Riser intermediate connection laydown
2.5
Max WD: (16-35)
2.5
(13-21)
No
Clearance with moon pool, MBR
Not required (high Hs)
2.5
(12-20)
No
Clearance with moon pool, MBR
Not required (high Hs)
2.5
(14-27)
No
Clearance with moon pool, MBR
Not required (high Hs)
No
Clearance with moon pool, MBR
No simple criteria available
2
Without ART: (28.5-30) With ART: (28.533.5)
*Range of Tp covered in Table 4-1
Table 2-1-Allowable sea-states for flexible flowline operations
It is noted that the alternative criteria given on vessel motion is an alternative criteria to the allowable sea-state criteria and can be used if higher sea-states are encountered or in case of doubt on the current seastate or forecast. It is not necessary to check this motion criteria if the actual sea-state is within the prescribed allowable sea-states (see section 4 and results sections for further details). Alternative criteria will be completed for next revision of this document.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 9 of 36
The verification of the installation criteria is provided in Table below.
Criteria
Allowable
Static Results
Dynamic Results
Max departure angle at tulip exit
14deg
6.3deg
12.9deg
Max dynamic top tension in flexible (FLS)
39mT
19.5mT
21.30mT
MBR
4.16m
5.32m
4.26m
Maximum compression
59 kN empty / 137 kN flooded @ 4.16m MBR
None
-3.85kN
MBR
4.22m
6.29m
5.71m
Maximum compression
51 kN empty @ 4.4m MBR
None
-5.29kN
Component
Vessel
Flexible flowline
Flexible riser
Table 2-2- Verification of the installation criteria
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 10 of 36
3.
ANALYSIS BASIS
3.1
PRODUCT AND ANCILLARY EQUIPMENT DESCRIPTION
3.1.1
Flexible Flowline and Flexible Riser - Cross-section The flexible flowlines and flexible risers have the following characteristics:
Data
Unit
Reference
-
Outside Diameter Inside Diameter * Weight in air - empty Weight submerged - empty Bending stiffness @ 23°C Axial stiffness Torsional Stiffness @ 23°C MBRStorage Installation MBR
mm mm t/m t/m kN.m² kN kN.m² m m
Max compression
kN
Flexible Flowline BU-DS01 BU-DS02 H8-SSP-01-020-G0164782 (Rev 1. Issued on 18/12/13) 389.96 260.1 0.174 0.052 151.1 374875 5411 (stiff dir) 2.53 4.16 59 kN empty / 137 kN flooded @ 4.16m MBR
Flexible Riser BU-DS01 BU-DS02 H8-SSP-01-020-G0164782 (Rev 1. Issued on 18/12/13) 413.5 260.0 0.256 0.118 212.3 529147 12100 2.69 4.22 51 kN empty @ 4.4m MBR
Table 3-1 – Flexible flowline and Flexible Riser properties
Note: * For the flexibles, the internal diameter used in Orcaflex is calculated with respect to pipe internal volume (taking into account the volume “inside” the carcass). This allows to model the pipe based on its weight in air empty, and to play on fluid content density (“uniform content” option in Orcaflex) to define the filling configuration of the pipe (empty or flooded). The installation analyses presented in this report have been performed with the flexible flowline empty except for the abandonment of the last section which was done with the flowline flooded. Some analyses have been performed considering the flexible riser data (recovery of subsea end when flooded and lay-down of intermediate connection between riser and first flowline section when catenary is partially flooded).
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 11 of 36
3.1.2
Flexible Flowline and Flexible Riser – End-fitting and pull-head The properties of the flexible flowline end-fitting and pull-head are presented in next table. Flexible Flowline
Parameter
Unit
End Fitting
Pulling Head
Reference
-
H8-SSP-01029-D06-64810 (Rev 2)
H8-SSP-01029-D06-64812 (Rev A),
Length Weight in air Weight water
m kg kg
1.051 821 668
SWL
mT
N/A
0.3 103 88 (est.) 25 (ref: H8-SSP00-066-D0670207)
Flexible Riser End Fitting
Pulling Head
H8-SSP-01029-D0664995 (Rev 1. Issued on 02/07/13) 1.20 1163 941
H8-SSP-01029-D0664811 (Rev A. Issued on 13/12/13) 0.41 430 374
N/A
55
Table 3-2 – Flowline and End-fitting and pull-head properties
Figure 3-1 – Flowline end-fitting
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 12 of 36
3.2
VESSEL CHARACTERISTICS The Skandi Acergy is a DP Class 3 multi-purpose flexlay and offshore construction vessel. Description Length Overall Length between perpendicular Breadth Moulded Operating draft Depth Moulded (to main deck) Speed Deck Working Area (net) Deck Loading / m2 Accommodation Flag
Value 156.9m 137.7m 27m 6.5m – 7.8m 12m 15 knots (max speed 18 knots) 2,100m² 10 t/m² 140 Isle of Man
Table 3-3 – Skandi Acergy Main Properties
Figure 3-2 – Skandi Acergy
Figure 3-3 – Skandi Acergy Deck Layout
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 13 of 36
3.2.1
Flexible Lay System The Skandi Acergy’s Flexible Lay System, comprises of a vertical lay tower on the centreline of the ship directly over the dedicated moonpool. A 3000Te underdeck carousel complete with spooling arm provides storage. There is a 125Te four track tensioner on the Skandi Acergy.
Figure 3-4 – Skandi Acergy FLS Tower and Loadout Spread
Morvin 7m TULIP There is a large tulip which had been designed to allow the maximum possible fleeting angle before contacting the bottom of the moonpool (15 Degrees): ID of top of tulip is 750mm.
Figure 3-5 – Morvin 7m Tulip
Abandonment and recovery Winch (A&R) There is a 120Te A&R winch on top of the Tower. This has a 70mm, 120Te SWL, 750m wire with a closed swivel spelter socket. It is operated from the FLS control cabin and has no Active Heave capabilities. It has a manual spooler connected via a retractable A Frame.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 14 of 36
3.3
ENVIRONMENT INPUT DATA Environmental data used for the analyses are extracted from the meteocean report for the Bayu Undan location (ref. BUP3-000-SE-R02-D-00001). Refer to section 4.2 for detailed explanations on how wave data have been considered. Regarding current effect, sensitivities have been performed to account for current effect in some critical cases. Unless specified otherwise, 70% of the omnidirectional 1-yr velocity profile has been used. This percentage is used to attenuate the strong conservatism in using a full 1-yr current profile (which by definition occurs only once in a year). Strong conservative assumptions have been kept though in the sensitivity calculation by considering the current profile in the same direction through the entire water column and acting in the same plane as the catenary.
3.4
LAY ROUTE DATA Water depths and lay curve radius considered in the analysis have been extracted from the alignment sheets in references and are listed in the table below for the various items: Line
76-109 71-80
Smallest curve radius (m) 100; 200 150
108
N/A
71
N/A
Water depths (m)
Flexible flowline BU-DS01 Flexible flowline BU-DS02 Last EF/EF connection BU-DS01 Last EF/EF connection BU-DS02
Table 3-4 – Water depths and curve radius considered – Flexible flowline
3.5
SOIL FRICTION COEFFICIENTS Soil friction coefficients have been considered from previous projects: Axial friction coefficient 0.51
Lateral friction coefficient 0.38
Table 3-5 – Soil Friction Coefficients
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 15 of 36
3.6
LIMITING CRITERIA FOR ANALYSIS The limitation criteria for the analysis are presented in the table below.
Component
Vessel
Flexible flowline
Criteria
Allowable
Max departure angle at tulip exit
14deg
Max dynamic top tension in flexible (FLS)
39mT
MBR
4.16m
Maximum compression
59 kN empty / 137 kN flooded @ 4.16m MBR
MBR
4.22m
Maximum compression
51 kN empty @ 4.4m MBR
Flexible riser
Table 3-6 – Limiting Criteria
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 16 of 36
4.
METHODOLOGY
4.1
SOFTWARE Calculations have been performed with Orcaflex (Version 9.5d)., a marine program for static and dynamic analysis of flexible pipeline and cable systems in offshore environments. It is widely used in the offshore industry for analyses of flexible risers and installation of Subsea equipment. This software is a fully 3D non-linear time domain finite element program capable of dealing with ship motions, environmental conditions, random waves, buoys, cables etc. Cable weight, structure characteristics, environmental conditions and lay vessel motions can be accurately modelled with Orcaflex.
4.2
WAVE DATA SELECTION AND DIRECTONALITY The 1yr return period wave data is considered too conservative for the installation analyses; therefore a methodology has been used to define a more appropriate seastate. The objective is to reduce the computation time while ensuring that the seastates analysed are representative of the weather conditions experienced and monitored during operations. The figures below show the sea-state scatter diagrams (Hs-Tp) extracted from H8GEN-00-095-R02-2000 for the months of January and February, period during which the Campaign 2 operations will be performed.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 17 of 36
Figure 4-1 – Omnidirectional Hs-Tp Scatter diagram for the months of January and February (Ref. H8-GEN-00-095-R02-2000)
The table below summarizes for each Tp bin in the scatter diagrams above the maximum Hs considered to obtain an overall operability of about 90% during the considered months.
Tp From 2 4 6 8 10 12 14 16 18 20 22
To 4 6 8 10 12 14 16 18 20 22 24 TOTAL
Hs max 2.0 2.5 2.5 2.5 2.5 2.5 2.0 -
% occurence in January 0 19.02 36.77 7.33 4.14 13.85 9.72 2.16 0 0 0 93
% occurence in February 0 16.16 31.27 9.73 8.11 13.39 8.6 2.05 0 0 0 89.3
Table 4-1 – Hs-Tp values considered in dynamic analysis
The dynamic analysis will be based on the worst Hs values in this table. This means that if an operation is proved by analysis to be safe for all sea-states listed above the operability will be at least 93% in January and 89% in February.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 18 of 36
Whenever possible, the installation vessel is positioned in-line with the Swell, with a typical heading tolerance of +/-15° which will be included in the dynamic cases matrix. It is noted that no operation during campaign 2 has been identified that would constrain the vessel to a particular heading. Therefore all dynamic analyses will be done with the vessel aligned with the swell and accounting for a tolerance of +/15deg. Sensitivity analyses are performed considering the 1-yr current profile.
4.3
STATIC ANALYSIS METHODOLOGY Static analysis is the first step in installation analysis and aims at establishing the static equilibrium configuration at various stages of the installation. It defines the starting point for subsequent dynamic analyses. Installation of the flexible flowline is divided into the following main stages: 1. Recovery of flexible riser subsea end-fitting on installation vessel 2. Connection of the first section of flexible flowline on riser end-fitting and laydown of intermediate end-fitting connection between riser and 3. Normal lay and curve lay of flowline 4. Lay-down of intermediate end-fitting connection between flowline sections 5. Repeat step 3 and 4 for as many flowline sections to be laid 6. 2nd end abandonment of last flowline section to be installed
4.4
DYNAMIC ANALYSIS METHODOLOGY Dynamic calculations are performed to ensure that static parameters calculated are valid and that limiting criteria are still ensured when both functional and environmental loads are applied. They also determine the maximum allowable vessel motions and sea-states with regards to limiting criteria, which includes the maximum loading of the product (tension, MBR, bending moment, etc.). For that purpose, a set of the most critical steps are selected from the static analyses to be checked with a full dynamic calculation methodology. These static steps are selected based on the limiting criteria. If the integrity of the product or its ancillary equipment or any vessel equipment is compromised with maximum wave heights, the Hs is reduced until these requirements are met. Different methodologies can be adopted to perform the full dynamic calculations in time domain. These simulations can be based on regular waves or on irregular waves. Irregular waves are generally less conservative compared to regular waves but require more calculation time. In order to optimise calculation time and to cover a large range of sea state events, a methodology involving both regular wave time domain analysis and vessel motions spectral calculations is used. This method is described hereafter:
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 19 of 36
First, dynamic time domain simulations with regular waves are run for the parameters presented in Table 4-1 in a previous section and considering the vessel heading to be aligned with the swell with a +/-22.5deg tolerance. A typical factor of 1.86 is considered to convert the significant wave height Hs into a maximum wave height Hmax for a typical sea-state duration of 3hrs. This factor is derived from the reference [“Random Seas and Design of Maritime Structures” – Y. GODA].
with N the number of waves. To estimate the maximum wave height of a storm with 3 hour persistence and a mean period of 10 s this results in Hmax = 1.86·Hs. The objectives of this first set of dynamic calculations are: •
As a conservative approach, it can be used to estimate quickly the allowable wave Hs for the various periods and directions. If all governing parameters are fulfilled at this stage, then the allowable sea-states for the considered operation are the ones shown in Table 4-1 and the resulting operability of the operation is at least 90%. Hence, no further dynamic analysis is required.
•
It allows to understand the frequency content of the system response and determine any peak response periods due to potential resonance effect or peak vessel excitation periods
•
It can be used to determine the relationship between vessel motions and the response of the catenary. Indeed, the dynamic responses of the catenary are closely linked to the vessel motions and a direct relationship is expected to be found for most installation stages. For example, the catenary tension at hang off point is likely to be strongly correlated with the vertical acceleration at the hang-off point.
If the first set of regular wave time domain calculations has concluded on low allowable sea-states, the following methods can then be used: •
If a strong correlation between one particular vessel motion (e.g. hang-off vertical velocity) and one of the critical governing parameter (e.g. MBR) has been found, then the maximum allowable value of that specific motion (e.g. maximum hang-off vertical velocity of 1.5m/s) is determined in order to ensure that the governing parameter limiting criteria (e.g. MBR of 2m) will never be infringed. Then, by using simple spectral calculation method to calculate the vessel motions for various sea-states, it is possible to define what would be the maximum allowable sea-states that will ensure this particular vessel motion is always below the limit defined above. Furthermore, this criterion on a maximum vessel motion can be used as an alternative criterion to the traditional allowable sea-state criterion to help the decision process offshore. This method is called Vessel Motion Based Criteria (VMBC) and aims at reducing the conservatisms underlying the
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 20 of 36
traditional approach using allowable sea-states and thus improving the operability of the vessel. •
If no satisfying correlation are found or correlation with too many different vessel motion parameters, then a time domain analysis using irregular wave can be used. Due to the time consuming aspect of irregular wave calculations, a careful selection of sea-states should be performed to minimize the computation time. Appropriate sea-states should be selected to at least capture any peak response periods (system natural periods, vessel natural periods) and capture the maximum vessel motions at hang-off points (as a minimum: vertical motion, velocity and acceleration, pitch, roll).
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 21 of 36
5.
ANALYSES RESULTS
5.1
NORMAL LAY AND CURVE LAY Analysis was performed to calculate the layback boundaries for normal lay. Minimum and maximum water depths have been studied considering the routes of both flowlines BU-DS01 and BU-DS02, refer to Table 3-4. Curve laying stability is also checked. The acceptable layback range is established based on static and dynamic analysis. The lower layback limit is normally governed by MBR criteria and the compression limit of the product. The upper layback limit is normally governed by the maximum allowable tension at hang-off or at TDP, in some cases the departure angle.
5.1.1
Static Results Layback ranges – straight line laying The following results are presented assuming normal lay operation is performed with flowline empty.
Case
Layback (m)
Angle at tulip exit (°)
Top Tension (mT)
TDP Tension (kN)
MBR (m)
16
1.25
6.08
0.73
10.49
30
5.21
6.46
4.49
15.62
16
0.71
8.01
0.60
10.30
35
4.02
8.43
4.82
16.09
-
14
39
-
4.16
Min WD (71m) Minimum layback Min WD (71m) Maximum layback Max WD (108m) Minimum layback Max WD (108) Maximum layback Installation Criteria
Note: maximum layback given is valid for both straight and curve laying operations (see Table 5-2).
Table 5-1 – Layback range and static results for straight line laying
Layback ranges – curve laying A maximum tension must not be exceeded to ensure line stability on seabed during laying in curve. The maximum allowable TDP tension for laying in curve can be obtained from the following formula:
TCurve = Where:
𝑢.𝑊.𝑟 𝑆𝐹
;
TCurve: TDP Tension for a curve laying (kN)
𝑢: Lateral friction coefficient
W: product weight in water
𝑟: Curve radius
SF: Dynamic Factor (1.5)
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 22 of 36
The maximum tension capacity for curve laying is presented in the table below. Parameter
Value
Lateral Friction Coefficient*
0.38
Flowline weight in Water (kN/m)
0.51
Max TDP tension (kN)
100m: 12.92
for various curve radius
200m: 25.84
*Taken from previous projects Table 5-2 – Maximum allowable TDP tension for curve laying
5.1.2
Dynamic results Conservative dynamic analysis using regular wave up to 3m Hs has been performed for normal lay operation. For this operation, the vessel has the possibility to weathervane, therefore only head sea +/-15deg has been considered. Dynamic results are presented in next table.
Case Min WD (71m) Minimum layback Min WD (71m) Maximum layback Max WD (108m) Minimum layback Max WD (108) Maximum layback Installation Criteria
Max Angle at tulip exit (°)
Max Top Tension (mT)
Max TDP Tension (kN)
MBR (m)
6.09
6.98
4.38
8.08
9.37
7.47
10.46
10.40
5.57
9.32
3.79
7.94
8.23
9.88
10.93
10.75
14
39
12.92 & 25.84
4.16
Note: maximum layback given is valid for both straight and curve laying operations (see Table 5-2).
Table 5-3 – Dynamic results for straight line laying
As all parameters are within their allowable limit, hence the normal lay operation can be performed safely up to a maximum allowable Hs of 2.5m within the specified layback range of 23m +/- 7m and 25.5 m +/- 9.5m for the minimum and maximum water depths respectively. It is also noted that the maximum layback is driven by the product top angle. Since maximum TDP tensions are below the maximum allowable TDP tension for curves
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 23 of 36
introduced in Table 5-2, therefore the maximum laybacks for each water depth is valid for both straight and curve laying operations. Since, the resulting maximum allowable Hs is high, no alternative criteria on vessel motion is deemed required. 5.1.3
Sensitivity with current With respect to current effect on normal lay configuration, the same conclusions as for the flowline-flowline intermediate connection lay-down (see 5.4.3) can be drawn as the catenary shape is very similar and dynamic results are better. In terms of MBR, since minimum bending radius for normal lay (Table 5-3) is further away from the limit than for intermediate connection lay-down, no issue is expected on MBR. In terms of product departure angle at tulip exit, a lower maximum departure angle is observed for normal lay than for intermediate connection lay-down (10° vs. 9.4°) an furthermore the maximum angle is well below the limit (14°).
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 24 of 36
5.2
FLEXIBLE FLOWLINE TERMINATION ABANDONMENT / RECOVERY
5.2.1
Static results Analysis is done for flowline termination abandonment this will also cover the recovery operation as this is the reverse operation of abandonment. The catenary will be flooded during this operation; the water depth is 71m. Table below summarizes the steps for abandonment of flowline termination. Figure 5-1 shows the snapshots for this operation.
Step
A&R Length (m)
Vessel Step move (m)
Layback (m)
Pull head height above seabed (m)
MBR in flowline (m)
NA, top angle 1.1° Deploying pulling head subsea
13.5
0
17.0
1 2 3 4 5 6 7 8
63.17 63.17 68.17 68.17 73.17 73.17 80.17 80.17
0 4 0 4 0 4 0 4
15.0 21.0 14.0 19.0 13.0 18.0 10.0 15.0
20.2 20.4 15.2 15.4 10.2 10.4 3.1 3.3
8.5 9.9 8.2 9.5 8.1 9.1 10.9 11.2
9
85.17
0
5.2
0.3
52.6
-
4.16
Install. Criteria
0
-
-
A&R wire angle at tulip exit (°)
-
NA
8.9
Pull Head Tension (mT)
Remarks
11.93
Release of the last endfitting off the tensioner and held above the VLS. Pull head 20m above sea bed Vessel move A&R payout Vessel move A&R payout Vessel move A&R payout Vessel move
2.0
3.0
4.3 1.6 3.8 1.2 3.5 0.6 2.6
3.2 2.4 2.6 1.8 2.0 1.2 1.2
0.4
0.0
A&R payout, Pull in head landed on sea bed
-
-
14
Table 5-4 – Static results for flowline termination abandonment, 71m WD
Figure 5-1- Flowline termination abandonment
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 25 of 36
5.2.2
Dynamic results Conservative dynamic analysis using regular wave has been performed (as described in section 4). For this operation, the vessel has the possibility to weathervane, therefore only head sea +/-15deg has been considered. Step 2 (max layback) and Step 5 (min layback) of Table 5-4 are chosen for dynamic analysis as they are associated with max angle and lowest MBR respectively. Step 0 is also included for max dynamic top tension.
A&R Winch
Flowline
Max Angle at tulip exit(deg)
Max Hook Load (mT)
Max TDP Tension (kN)
MBR (m)
Compression (kN)
Step 0 -Max top Tension
2.57
13.04
6.52
7.02
-2.06
Step 2 -max layback (21m)
11.04
3.73
8.97
7.48
-0.92
Step 5 -min layback (13m)
8.08
2.20
4.87
6.28
-3.85
Installation Criteria
14
-
-
4.16
-59
Step
Table 5-5 – Dynamic results for flowline termination abandonment, 71m WD
As all parameters are within their allowable limit, the flowline termination abandonment can be performed safely up to a maximum allowable Hs of 2.5m with layback range maintained between 13m and 21m during the operation. 5.2.3
Sensitivity at 108m WD As previous calculations were done for the smallest WD (conservative in terms of MBR and top angle), a sensitivity analysis has been performed at the maximum WD (108m) to determine the maximum load on the recovery pull-head. A&R hook load is directly correlated with crane tip heave acceleration, hence only the dynamic case leading to the maximum hook acceleration has been run for the 108m WD case. Resulting static hook load in 108m WD is 15.8mT and maximum dynamic load is 17.6mT.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 26 of 36
5.2.4
Sensitivity on content As laydown prior to interim mobilisation will be performed with an empty product; static analysis described in 5.2.1 is now performed with catenary empty. Table below summarizes the static results.
Step
A&R Length (m)
Vessel Step move (m)
Layback (m)
Pull head height above seabed (m)
MBR in flowline (m)
A&R wire angle at tulip exit (°)
Pull Head Tension (mT)
63.17 63.17 68.17 68.17 73.17 73.17 80.17 80.17
0 4 0 4 0 4 0 4
17.0 22.0 16.0 21.0 15.0 20.0 12.0 16.0
59.8 59.7 64.8 64.7 69.8 69.7 76.9 76.7
10.5 12.3 10.2 12.0 10.4 12.0 15.0 15.7
1.3
1.7
3.3 0.9 3.0 0.7 2.8 0.5 2.5
1.9 1.4 1.6 1.2 1.3 0.9 0.9
9
85.17
0
5.0
79.7
68.4
0.4
0.0
Install. Criteria
1 2 3 4 5 6 7 8
-
-
-
-
4.16
14
-
Table 5-6 – Static results for flowline termination abandonment, 71m WD, empty product
As indicated in the above table static results are improved comparing with flooded case (larger MBR for step 5 and smaller angle for step2). Therefore the layback range obtained for flooded case is also valid for empty case. FLS load transfer top tension checks Dynamic analysis has been performed for calculating max dynamic top tension of the flowline when it is suspended from A&R above the tensioner tracks (~30m above sea level); this is done with catenary empty.
WD (m) 71 108
Max Hs (m) 2.5 2.5
Static Top Tension (mT)
Max Dynamic Top Tension (mT)
10.39 12.27
11.71 13.94
Table 5-7 – Top tension of flowline suspended 30m above sea level
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 27 of 36
5.3
FLEXIBLE RISER TERMINATION ABANDONMENT / RECOVERY
5.3.1
Static results Analysis is done for flexible riser termination abandonment this will also cover the recovery operation as this is the reverse operation of abandonment. The catenary is flooded during this operation; the water depth is 77m.
Step
A&R Length (m)
0
Vessel Step move (m)
NA
0
Layback (m)
Pull head height above seabed (m)
MBR in Riser (m)
15.0
NA
8.9
A&R wire angle at tulip exit (°)
Pull Head Tension (mT)
1.6
16.1
Remarks
Riser EF at worktable
Deploying pulling head subsea 63.17 63.17 68.17 68.17 73.17 73.17 80.17 80.17
0 4 0 4 0 4 0 4
15.0 20.0 13.0 18.0 12.0 17.0 10.0 14.0
20.2 20.4 15.2 15.4 10.2 10.4 3.1 3.3
8.1 9.3 7.8 8.8 7.6 8.5 10.0 10.3
9
85.17
0
4.8
0.3
82.1
-
4.4
Install. Criteria
1 2 3 4 5 6 7 8
-
-
-
2.2
4.6
4.6 1.8 4.2 1.3 3.7 0.6 2.7
5.0 3.7 4.0 2.8 3.0 1.7 1.8
0.4
0.0
6
Pull head 20m above sea bed Vessel move A&R payout Vessel move A&R payout Vessel move A&R payout Vessel move A&R payout, Pull in head landed on sea bed
-
-
Table 5-8 – Static results for riser termination abandonment, 77m WD
5.3.2
Dynamic results Conservative dynamic analysis using regular wave has been performed (as described in section 4). For this operation, the vessel has the possibility to weathervane, therefore only head sea +/-15deg has been considered. Step 2 (max layback) and Step 5 (min layback) of Table 5-8 are chosen for dynamic analysis as they are associated with max angle and lowest MBR respectively. Step 0 is also included for max dynamic top tension.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 28 of 36
A&R Winch
Riser
Max Angle at tulip exit(deg)
Max Hook Load (mT)
Max TDP Tension (kN)
MBR (m)
Compression (kN)
Step 0 -Max top Tension
3.55
17.54
8.2
7.52
-0.02
Step 2 -max layback (20m)
12.72
5.97
15.04
7.47
-0.16
Step 5 -min layback (12m)
8.27
3.23
5.41
6.19
-5.29
Installation Criteria
14
-
-
4.4
-51
Step
Table 5-9 – Dynamic results for riser termination abandonment, 77m WD
As all parameters are within their allowable limit, the riser termination abandonment can be performed safely up to a maximum allowable Hs of 2.5m with layback range maintained between 12m and 20m during the operation.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 29 of 36
5.4
FLOWLINE-FLOWLINE INTERMEDIATE CONNECTION LAY-DOWN
5.4.1
Static results Static analysis is performed for laying-down the intermediate connection between two sections of flowline when the catenary is empty; this is done for the minimum water depth (71m). The table below summarizes the static results of the lay-down for maximum and minimum laybacks. The results are presented when intermediate connection is in its critical position in sagbend. Figure 5-2 shows the intermediate connection in the critical position for MBR in the sagbend. It is noted that two anodes of 25kg each have been considered on each side of the intermediate connection.
Case Min Layback Max Layback Installation Criteria
Layback (m)
Angle at tulip exit (°)
Top Tension (mT)
TDP Tension (kN)
MBR (m)
14
1.9
6.67
0.94
5.32
27
6.3
6.99
5.78
6.36
-
14°
39
-
4.16
Table 5-10 – Static results for flowline-flowline intermediate connection laydown, 71m WD
Figure 5-2- Flexible Flowline intermediate connection laydown
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 30 of 36
For the landing of the intermediate connection on seabed, a layback value in range of 14m to 27m has to be maintained to ensure appropriate bending radius in the flexible and maintain the departure angle at the work table within an acceptable limit. 5.4.2
Dynamic results Conservative dynamic analysis using regular wave up to 3m Hs has been performed on these two steps. For this operation, the vessel has the possibility to weathervane, therefore only head sea +/-15deg has been considered. Dynamic results are presented in the next table. One case (Step 0) is also included for max dynamic top tension, this is when intermediate connection is at worktable and tensioner is engaged. Step
Step 0 –Max top Tension Min Layback Max Layback Installation Criteria
Max Hs (m)
Angle at tulip exit (deg)
Max Top Tension (mT)
Max TDP Tension (kN)
MBR (m)
2.5
5.4
9.33
10.5
10.42
2.5 2.5
6.42 9.97
7.42 7.84
5.43 12.84
4.55 5.23
-
14°
39
-
4.16
Table 5-11 – Dynamic results for flowline intermediate connection lay-down
As all parameters are within their allowable limit, the intermediate connection laydown can be performed safely up to a maximum allowable Hs of 2.5m with layback range maintained between 14m and 27m during the operation. Since, the resulting maximum allowable Hs is high, no alternative criteria on vessel motion is deemed required. 5.4.3
Sensitivity with current Sensitivity with current is performed for both laybacks. Current profile described in section 3.3 is used. Current is applied in the catenary plane. Results and comparison with nominal case are presented in table below.
Layback of 27m – No current Layback of 27m – With current Layback of 14m – No current Layback of 14m – With current
Max Hs (m) 2.5 2.5 2.5 2.5
Angle at tulip exit (deg) 9.97 11.3 6.42 7.43
Installation Criteria
-
14
Connection in sagbend case
MBR (m) 5.23 5.21 4.55 4.39 4.16
Table 5-12 – Dynamic results in presence of current for flowline intermediate connection lay-down
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 31 of 36
The results show that the MBR of the flowline and its top angle remain within their limit. 5.4.4
Sensitivity with maximum water depth The same analysis detailed in section 5.4.1 is performed for maximum water depth (108m). Following table shows the dynamic results in present of current for the same range of layback.
Step Min Layback (14m) Max Layback (27m) Installation Criteria
Max Hs (m)
Angle at tulip exit (deg)
Max Top Tension (mT)
Max TDP Tension (kN)
MBR (m)
2.5
7.31
7.42
5.43
4.55
2.5
9.97
7.84
12.84
5.23
-
14°
39
-
4.16
Table 5-13 – Dynamic results in presence of current for flowline intermediate connection lay-down, 108m WD
As all parameters are within their allowable limit, therefore the intermediate connection lay-down can be performed safely up to a maximum allowable Hs of 2.5m with layback range maintained between 14m and 27m during the operation for both maximum and minimum water depths. Resulting static top tension in 108m WD is 10.25mT and maximum dynamic load is 11.54mT. 5.4.5
Sensitivity with flowline-riser intermediate connection lay-down Similar analysis as in section 5.4.1 is performed for laying the intermediate connection of flowline and riser. In this case riser is flooded but flowline is empty. Water depth for this operation is 77m. Figure 5-3 shows the intermediate connection in the critical position for MBR in the sagbend.
Figure 5-3- Flowline-Riser intermediate connection laydown
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 32 of 36
To obtain a range for layback during installation conservative dynamic analysis using regular wave has been performed for intermediate connection lay-down. For this operation, the vessel has the possibility to weathervane, therefore only head sea +/-15deg has been considered. Dynamic results in presence of current are presented in the next table. One case (Step 0) is also included for max dynamic top tension, this is when intermediate connection is at worktable and tensioner is engaged. Step Step 0 –Max top Tension Min Layback (28.5m) Max Layback (30.0m) Installation Criteria
Max Hs (m)
Angle at tulip exit (deg)
Max Top Tension (mT)
Max TDP Tension (kN)
2.5
9.54
21.30*
21.59
2
11.78
8.85
13.16
2
12.90
8.49
12.48
-
14°
39
-
MBR (m) 10.61 (riser) 4.26 (flowline) 4.34 (flowline) 4.16 (flowline)/ 4.44 (riser)
*The static top tension is 19.47mT
Table 5-14 – Dynamic results in presence of current for flowline-riser intermediate connection lay-down
As all parameters are within their allowable limit, therefore the flowline-riser intermediate connection lay-down can be performed safely up to a maximum allowable Hs of 2m with layback range maintained between 28.5m and 30m during the operation. It is noted that limiting parameters for minimum and maximum laybacks are catenary MBR and product top angle respectively. No vessel motion criteria could be obtained for this operation.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 33 of 36
Sensitivity with ART As mentioned before the limiting parameter for minimum layback is MBR. Lowest value for MBR happens in head see; therefore ART will not affect the minimum layback value that was given in Table 5-14. However the maximum angle at tulip exit occurs when roll motion is introduced by waves. Therefore maximum layback can be increased using ART. Following table presents the dynamic results when ART is in use in presence of current.
Step Min Layback (28.5m) Max Layback (33.5m) Installation Criteria
Max Hs (m)
Angle at tulip exit (deg)
Max Top Tension (mT)
Max TDP Tension (kN)
MBR (m)*
2
10.38
8.85
13.29
4.26
2
11.09
8.90
16.25
4.50
-
14°
39
-
4.16
*Lowest catenary MBR happens on flowline side
Table 5-15 – Dynamic results in presence of current for flowline-riser intermediate connection lay-down
As all parameters are within their allowable limit, therefore the flowline-riser intermediate connection lay-down can be performed safely up to a maximum allowable Hs of 2m with layback range maintained between 28.5m and 33.5m provided that ART is active during the operation.
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 34 of 36
5.5
CROSSING ANALYSIS
5.5.1
Crossing support height Point loading on the 18” WP1 production pipeline is not permitted. Therefore a minimum clearance should be maintained between the flexible flowline and the pipeline at crossing point. Analysis has been performed to determine the required height of the mattresses on either side of the pipeline to ensure that the gap between the flexible and pipeline will be sufficient. The mattresses are located 4m from centreline of the pipeline and installed at the edge of this tolerance with consideration to the potential lateral movement of the pipeline (Figure 5-4). Max deflection of flowline over the free span happens assuming flow line is fixed at one end and free (no tension) at the second end. When the line is flooded max deflection is 25 cm.
Figure 5-4 – Crossing support arrangement
Therefore the total height (h) of the mattresses required can be calculated as below: hmax = ODWP1 + Required clearance + max deflection of flooded line Parameter
Value
Remarks
OD of production pipeline
66cm
Required clearance
30cm
Including 10cm contingency
Max deflection
25cm
Under no back tension
hmax
121cm
-
Including concrete coating and marine growth; also no pipeline burial is assumed
Table 5-16 - Maximum required mattress height
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 35 of 36
Sensitivity has been performed with different residual tensions and contents for a mattress height of 1.5m above mudline. The residual tension is obtained by simulating the laying over the mattress with various laybacks. It is noted that the layback range simulated here will cover the layback range specified for the offshore operations. Results are shown in table below and the configuration modelled is shown in snapshot after.
Layback (m)
Fluid content (kg/m3)
40 40 30 30 20 20 15 15
1025 0 1025 0 1025 0 1025 0
TDP Max tension deflection (kN) (m) 15.5 7.1 9.3 4.5 4.7 1.8 1.9 0.64
0.131 -0.045 0.134 -0.064 0.126 -0.100 0.170 -0.122
Max point loading (kN) 17.1 9.22 16.45 9.09 16.1 8.47 14.6 8.48 Allowable MBR:
Min bending radius (m) 10.0 15.2 9.4 14.5 8.9 14.7 9.4 14.1 4.16
Table 5-17: Sensitivity on residual tension and content
Figure 5-5: Flowline configuration for sensitivity check
From these results the conclusions are: •
No MBR issue is encountered, the safety factor on MBR is always greater than 2.0 so above any operating, storage, accidental requirements
•
Point loading is mainly depend on fluid content,
•
Point load is less dependent on residual tension (hence layback)
© Copyright Subsea 7
seabed-to-surface
AA0016-ENG-20008
ConocoPhillips Pty Ltd Bayu Undan Phase 3 Project
28.11.2014
Revision: 0
Flexible Flowline Installation Analysis – Campaign 2
Page 36 of 36
5.5.2
Current stability Stability of the flexible flowline against 100-year return period omni-directional current when resting over the mattresses is investigated here. The analysis is done assuming the flowline is empty. The flowline is considered stable if friction force between the mattress and flowline is greater than drag force produced by current (Ffric > Fdrag). Drag and friction forces can be calculated using the following formulas respectively. Fdrag = 0.5×ρ×Cd×L×OD×U² (drag force term in Morison's equation) Ffric = 9.81×L×w×f (lateral friction force before sliding)
Parameter
Value
Remarks
L
40m
length of flexible over which the current is applied
OD
0.39m
OD of flexible
Cd
1.2
Drag coefficient
rho
1.025 t/m3
Seawater density
U
0.4 m/s
Current velocity
Fdrag
1.54 kN
-
Table 5-18 – Drag force calculation
Parameter
Value
Remarks
L
4m
length of contact between flexible and mattress
w
0.175 t/m
Mass per unit length of flexible empty
f
0.3
Friction coefficient flexible/mattress
Ffric
2.06 kN
-
Table 5-19 – Friction force calculation
To conclude as shown the two above tables; Ffric > Fdrag and therefore the flowline is stable.
© Copyright Subsea 7
seabed-to-surface