The construction & energy law specialists
FIDIC: Red Book (1999) and MDB Harmonised Edition (Pink Book) compared by Frederic Gillion The table below reviews dierences between the FIDIC Conditions o Contract or Construction or Building and Engineering Works Designed by the Employer Employer,, 1999 Edition (the 1999 Red Book) and the Multilateral Development Banks (MDB) Harmonised Edition o the 1999 Red Book (FIDIC Conditions o Contract or Construction), revised June 2010, also known as the MDB Harmonised Edition (the Pink Book), highlighting the eect o the changes on the parties This note includes the “key changes” identied in the ollowing note, FIDIC Pink Book: The MDB Harmonised Edition o the Red Book, by Frederic Gillion, available to view at http://www.enwickelliott.co.uk/articles/contract-issues. For ease o reerence, the entries that are repeated in this note are shown in bold.
Clause 1: General provisions Sub-Clause
Amendment
1.1:: De 1.1 Denit nition ionss
The Pin Pinkk Book Book chan changes ges som some e deni denitio tions ns ro rom m those those use used d in the the 1999 Red Book. For example “Appendix to Tender” becomes “Contract Data” and “Dispute Adjudication Board” becomes “Dispute Board”, to reect the wording avoured by the World Bank. The denition o “Tests ater Completion” in the Pink Book requires tests specied in the Contract to be carried out in accordance with “the Specication” rather than “the provisions o the Particular Conditions” reerred to in the 1999 Red Book. The denition o “Deects Notication Period” in the Pink Book, or notiying deects in “the Works or a Section”, now “extends over 365 days except i otherwise stated in the Contract Data” Data”. The 1999 Red Book reers to the period “as stated in the Appendix to Tender”. The denition o “Plant” in the 1999 Red Book has been extended rom “apparatus, machinery and vehicles intended to orm or orming part o the Permanent Works” to include “vehicles purchased or the Employer and relating to the construction or operation o the Works” in the Pink Book. The denition o “Site” in the 1999 Red Book has been extended so that “the places where the Permanent Works are to be executed” include “storage “storage and working areas” under the Pink Book.
1
The construction & energy law specialists
1.1.4.3 and 1.2: In the Pink Book, the denition o “Cost” in sub-clause 1.1.4.3 Cost and Prot no longer reers to the “reasonable prot” reerred to in the 1999 Red Book: it only reers to “prot”. This is because sub-clause 1.2 provides that “prot” is xed at 5% unless otherwise indicated in the Contract Data. Although contractors might consider this prot to be low, the change is certainly welcomed by employers and banks as it provides some clarity. (For more inormation on “Cost” in the FIDIC suite o contracts, see note by Tom Young FIDIC: “Cost” and prot in FIDIC contracts at http://www.enwickelliott.co.uk/articles/ contract-issues 1.1.6.10: Notice o The Pink Book introduces a denition o “Notice o Dissatisaction” Dissatisaction which requires the Party to indicate its “intention to commence arbitration”. 1.6: Contract The Pink Book only allows deviation rom the requirement to Agreement enter into the Contract Agreement within 28 days i the “Particular Conditions establish otherwise”. 1.8: Care and This sub-clause determines the rights and obligations o the Supply o Employer and Contractor in relation to the custody and care o Documents the Contract, Specications, Drawings and Variations. In the nal paragraph o the sub-clause in the 1999 Red Book, either Party is required to give notice to the other Party i it becomes aware o a deect “o a technical nature” to one o the documents. Under the Pink Book, this requirement is widened to require the Parties to give notice o any deect in the documents. 1.9: Delayed The 1999 Red Book requires the Contractor to give the Engineer Drawing or notice whenever the Works are to be disrupted due to a ailure to Instructions issue drawings or instructions within a particular time. The Pink Book deletes the requirement to provide “the details” o the nature or amount o the delay likely to be suered. 1.13: Compliance Sub-paragraph (a) o the 1999 Red Book requires the Employer to with Laws obtain planning, zoning and other permissions or the Permanent Works and indemniy the Contractor or its ailure to do so. In the Pink Book “building permit” has been added to the list o permissions that have to be obtained by the Employer. Sub-paragraph (b) o the 1999 Red Book requires the Contractor to take all actions required or compliance with applicable Laws and to indemniy the Employer or his ailure to do so. In the Pink Book the indemnity is qualied by the ollowing wording “unless the Contractor is impeded to accomplish these actions and shows evidence o its diligence.”
2
The construction & energy law specialists
1.15: Inspections The insertion o this new sub-clause in the Pink Book allows & Audit by the representatives o the Bank to inspect the Site and/or to inspect Bank and audit the Contractor’s accounts and records relating to the Contract.
Clause 2: The Employer 2.1: Right o The Pink Book amends the 1999 Red Book to require the Employer Access to the Site to grant access to and possession o the Site to the Contractor so that the Programme can proceed “without disruption”. 2.2: Permits, The Pink Book deletes “where he is in a position to do so” rom Licenses or the Employer’s obligation, under the 1999 Red Book, to provide Approvals reasonable assistance in obtaining permits and licences or the project. This removes a ground or the Employer to reuse to assist in this regard. Changes to sub-paragraphs (a) and (b) reect this amendment. 2.4: Employer’s Financial Arrangements
Under the 1999 Red Book, the Employer is required to submit reasonable evidence that nancial arrangements have been made and are being maintained to enable the Employer to pay the Contract Price, within 28 days o the Contractor’s request to do so. The Pink Book requires the Employer to submit the reasonable evidence “beore the Commencement Date” as well as within 28 days o the Contractor’s request. In addition, the evidence that the Employer provides must demonstrate that it is able to pay the Contract price “punctually”.
2.5: Employer’s The amendment to the 1999 Red Book concerns the service o the Claims Employer’s notice o claim. Under the Pink Book, the Employer must still give notice as soon as practicable, but (in any event) the notice must be given within 28 days o the Employer becoming aware, or when it “should have become aware”, o the circumstances giving rise to the notice. This appears to be a more onerous provision or the Employer. However, the words “should have become aware” makes it difcult to operate as a condition precedent.
Clause 3: The Engineer 3.1: The Engineer’s Under the Pink Book, the Employer is allowed to change the duties and authority o the Engineer without the agreement o the Contractor. authority In contrast, under the 1999 Red Book, the Employer has an obligation not to impose “urther constraints on the Engineer’s Authority except as agreed with the Contractor.” This change may be seen as potentially aecting the balance o risk. The second amendment under sub-clause 3.1 requires the Engineer to obtain the Employer’s approval beore taking action under subclauses 4.12, 13.1, 13.3 and 13.4.
3
The construction & energy law specialists
3.5: Determinations
In both the 1999 Red Book and the Pink Book, the Engineer is required to give the Contractor and the Employer notice o its determination o any matter not agreed between the parties. However, the Pink Book is more onerous or the Engineer as it now xes a time limit or the determination (28 days rom receipt o the corresponding claim or request).
Clause 4: The Contractor 4.1: Contractor’s General Obligations
The Pink Book adds to the 1999 Red Book by requiring the contractor to source all equipment, material and services or use on the Works rom an eligible source country (as dened by the Bank). For more inormation, see the IBRD Guidelines o Procurement under IBRD Loans and IDA Credit.
4.2: Perormance The Pink Book requires the Perormance Security to be issued by “a Security reputable bank or nancial institution” selected by the Contractor. Unlike the Red Book there is no requirement or the Employer to approve the entity and country (or other jurisdiction) rom which it is issued Sub-paragraphs (a) to (d) o the 1999 Red Book contain a list o circumstances under which the Employer is entitled to make a call under the Perormance Security provisions. The Pink Book removes this list. The Employer is now able to make a call in respect o amounts to which it is entitled under the Contract. This may be seen as an extension o the Employer’s rights. However, the recommended text or the perormance (which stipulates that the ICC Uniorm Rules or Demand Guarantees, Rule 458, shall govern the guarantee) should provide sufcient protection as this lists the events giving rise to a call as well as the reasons or such a call. The Pink Book adds a new paragraph to the end o the sub-clause, allowing the Engineer to request a prompt increase or decrease o the Perormance Security, where a Variation or determination results in a reduction o the Contract Price by more than 25% o the portion o the Contract Price payable in a specic currency. The adjustment to the Perormance Security will be the equivalent o the percentage change to the Contract Price.
4
The construction & energy law specialists
4.3: Contractor’s The second paragraph in this sub-clause requires the Contractor to Representative submit the name and particulars o the person who it proposes to be the Contractor’s Representative (i not named in the Contract). This process must be repeated where the Engineer withholds or revokes consent or the Contractor’s appointee, or where the appointee ails to act as the Contractor’s Representative. The Pink Book reiterates that the Engineer’s withholding or revocation o consent or the Contractor’s Representative must be based on the grounds in sub-clause 6.9. 4.4: Subcontractor
The Pink Book: • •
4.15: Access Route
Expandscondentialityrequirementstocoverthisclause. Encourages the use of sub-contractors from the country in which the project is being constructed.
The Pink Book now includes the words “Base Date”, to provide certainty on when the Contractor should have been deemed satised as to the suitability o the Access Route.
Clause 5: Nominated Subcontractors 5.2: Objection to The Pink Book has a number o additional grounds upon which the Nomination Contractor can object to a Nominated Sub Contractor.
Clause 6: Staf and labour 6.1: Engagement o Sta and Labour
The Pink Book amends the 1999 Red Book to try to encourage Contractors to employ sta and labour rom the country where the Works are carried out. This is not an obligation, but reects the MDB’s desire to encourage local enterprise.
6.2: Rates o The Pink Book obliges the Contractor to inorm all Contractor Wages and Personnel about their liability to pay personal income taxes in the Conditions o Country. Labour 6.7: Health and The Pink Book includes a specic provision whereby the World Bank Saety tries to reduce the transer o AIDS through HIV-AIDS awareness campaigns.
5
The construction & energy law specialists
6.12 to 6.22: These sub-clauses, which used to be ound in the 1999 Red Book’s Particular locality Particular Conditions to take account o local labour and health and sub-clauses saety regulations, are no longer optional under the Pink Book. They cover issues such as: • Foreign personnel. • Supply of foodstus. • Supply of water. • Measuresagainstinsectandpestnuisance. • Alcoholic liquor or drugs. • Arms and munitions. • Religious customs. The impact o these sub-clauses is to increase the Contractor’s administrative costs, in particular sub-clause 6.22 (which deals with employment records o workers and requires “complete and accurate records o the employment o labour”). 6.23: Workers’ The Pink Book introduces a provision that recognises the workers’ Organisations rights to orm and to join workers’ organisations o their choice, and to bargain collectively, without intererence by the Contractor. 6.24: NonDiscrimination and Equal Opportunity
The Pink Book introduces a provision requiring the Contractor to base the employment relationship on principles o “equal opportunity and air treatment”.
Clause 7: Plant, materials and workmanship 7.7: Ownership o Under the Pink Book, any Plant or Materials become the property o Plant & Materials the Employer either when they are incorporated into the Works or when the Contractor is paid or them.
Clause 8: Commencement, delays and suspension 8.1: Commencement o Works
The rst paragraph o the 1999 Red Book has been replaced in the Pink Book: the Project cannot commence unless the Contract Agreement has been signed by both parties, the Contractor has reasonable proo that the Employer can und the Project and the Contractor has received any advance payment to which it is entitled. However, it is less clear when the actual commencement date is, as the maximum 42 day limit has been removed.
8.4: Extension o Time or Completion
Under the Pink Book, the Contractor is now entitled to an extension o time or delays caused by the Employer’s other contractors anywhere (not just restricted to the Site).
6
The construction & energy law specialists
8.6: Rate o Progress
The Contractor is entitled to payment or the costs o acceleration. However, in the Pink Book, the sub-clause states that the Contractor is not entitled to “any other additional benet”. It is not clear i this means prot.
8.12: Resumption Under the Pink Book, ollowing suspension, the Contractor should o Work only make good any deterioration or deect in or loss to the Works, Plant or Materials ater having received an instruction rom the Engineer.
Clause 11: Deects liability 11.3: Extension o Deects Notication Period
Due to an amendment in the Pink Book (compared to the 1999 Red Book), it would appear that the Employer can only claim or an extension to the Deects Notication Period, i the damage can be attributed to the Contractor.
Clause 12: Measurement and evaluation 12.1: Works to be The Pink Book requires the Contractor to show, in each application Measured or payment (both interim and/or nal), quantities or particulars detailing the amounts which the Contractor considers itsel to be entitled to. 12.3: Evaluation
The thresholds or the rates that can trigger the use o rates other than those specied in the Contract have been increased in the Pink Book, compared to the 1999 Red Book. Furthermore, any item that was not priced in the Bill o Quantities is to be included in other rates and prices in the Bill o Quantities and will not be paid or separately. This could mean that the Contractor is responsible or additional costs accruing rom any omission.
Clause 13: Variations and adjustments 13.1: Right to Vary Under the Pink Book, the Contractor is not bound to execute a variation i it would “trigger a substantial change in the sequence or progress o the Works.” The Contractor has the obligation to demonstrate the substantial change.
7
The construction & energy law specialists
13.7: Adjustments Under the Pink Book, the Contractor is not entitled to an ex tension or Changes in o time and/or costs under this sub-clause, i they have already Legislation been taken into account elsewhere.
Clause 14: Contract price and payment 14.1: The Contract Under the Pink Book, Construction Equipment is now exempt rom Price import duties when imported. 14.2: Advance Payment
The Pink Book requires the guarantee to be issued by “a reputable bank or nancial institution” selected by the Contractor. Unlike the Red Book, there is no requirement or the Employer to approve the entity and country (or other jurisdiction) rom which it is issued. In the event o a termination o the contract by the Employer or convenience, the Contractor is not required (unlike under the Red Book) to repay the balance o the advance payment.
14.7: Payment
The Pink Book amends the 1999 Red Book, to take account o the event where a Bank loan or credit is suspended.
14.9: Payment and Under the Pink Book, a bank guarantee can be provided in lieu o Retention Money a retention.
Clause 15: Termination by Employer 15.5: Employer’s Entitlement to Termination or Convenience
The Pink Book imposes limits on the Employer’s right to terminate at his own convenience: the Employer cannot terminate the Contract just because he wants to pre-empt the Contractor’s termination.
15.6: Corrupt or Fraudulent Practices
A new clause dealing with corrupt or raudulent practices has been inserted into the Pink Book. The amendment is consistent with the global trend to seek to prevent raud and corruption. The contractual sanction is that the Employer may terminate the Contract i it determines “based on reasonable evidence” that the Contractor has engaged in a raudulent practice. The denition o “raudulent practice” is very broad (“misrepresentation or omission o acts in order to inuence a procurement process or the execution o a contract”) and may have ar-reaching implications or the Contractor in the administration o the Contract.
8
The construction & energy law specialists
Clause 16: Suspension and termination by Contractor 16.1: Contractor’s I the Bank suspends payment o the unds rom which the Entitlement to Contractor is paid, and no alternative unds are available, the Suspend Work Contractor can suspend or reduce the rate o work it perorms at any time (having received a notice rom the Bank). 16.2: Termination The grounds on which the Contractor can terminate the Contract by Contractor have been amended in the Pink Book. It is not enough or the Employer to ail to perorm its obligations under the Contract. The Employer’s breaches must “materially and adversely aect the economic balance o the Contract and/or the ability o the Contractor to perorm the Contract.” The Pink Book includes two new grounds or termination: • IftheBanksuspendstheloanorcreditfromwhichthe Contractor is paid and 14 days ater the Contractor has ollowed the payment mechanism under sub-clause 14.7, it has still not received the sums due to it, the Contractor can suspend work, reduce its rate o work or terminate the Contract. • IftheContractordoesnotreceivetheEngineer’sinstruction to commence work 180 days ater the Letter o Acceptance, the Contractor may terminate the Contract.
Clause 17: Risk and responsibility 17.1: Indemnities
17.3: risks
The Pink Book’s indemnity rom the Contractor is enlarged (compared to the 1999 Red Book) rom that caused by the Contractor to cover all damage or loss however arising, except that only attributable to the Employer.
Employer’s The Employer’s risks under the Pink Book have been amended slightly rom the 1999 Red Book and are less onerous or the Employer.
17.6: Limitation o The limitation o liability under the Pink Book claries the liabilities Liability that are not covered by the limitation. The cap contained in the 1999 Red Book is replaced by a multiplier.
Clause 18: Insurance 18.1: General Under the Pink Book, the Contractor must approve any insurance Requirements or taken out by the Employer. When the Contractor is the Insuring Insurances Party under clause 18, it is entitled to take out insurance with insurers rom any eligible country.
9
The construction & energy law specialists
Clause 19: Force Majeure 19.1: Denition o The Pink Book expands “Force Majeure” to include sabotage by any Force Majeure persons other than the Contractor’s Personnel. 19.2: Notice o In order to claim Force Majeure, the claiming party must have been Force Majeure prevented rom perorming “its substantial obligations.” 19.4: The Contractor’s entitlement, i Force Majeure is demonstrated, has Consequences o been expanded under the MDB Harmonised Edition. Force Majeure 19.6: Optional Termination, Payment and Release The Pink Book has been amended so that the Contractor can only claim amounts reasonably and necessarily incurred by the Contractor.
Clause 20: Claims, disputes and arbitration 20.2: The Pink Book does not signicantly amend the Dispute Resolution Appointment o Procedure under clause 20. The main amendments relate to the the Dispute Board Dispute Adjudication Board, now described as Dispute Board (DB). One o these amendments is that the DB members need to be uent in the language or communication o the Contract and be proessionals experienced in the work o the Contract. 20.4: Obtaining Under the Pink Book, i any party issues a Notice o Dissatisaction, Dispute Board’s the notice should state that, i an amicable settlement is not Decision reached, the Party has the “intention to commence arbitration”. 20.6: Arbitration
Under the Pink Book, i the Contract is with a oreign contractor, the rules applicable to the arbitration will depend on the entity providing the nancing: • “ForcontractsnancedbyallparticipatingBanks(exceptthe Asian Development Bank)” the arbitration is to be administered (1) by the institution specied in the Contract Data, under the rules o that institution, or (2) i specied in the Contract Data, arbitration in accordance with UNCITRAL rules, or (3) i neither are specied in the Contract Data, proceedings are to be administered by the ICC under ICC rules. • “ForcontractsnancedbytheAsianDevelopmentBank”,the arbitration is to be administered (1) by the institution specied in the Contract Data, under the rules o that institution, unless it is specied that the arbitration is to be conducted in accordance with UNCITRAL rules, or (2) i an arbitration institution is not specied in the Contract Data, proceedings are to be administered by the Singapore International Arbitration Centre (“SIAC”) under SIAC rules.
Reproduced rom PLC with the permission o the publishers. For urther inormation visit www.practicallaw.com or call 020 7202 1200.
10