Minimizing Minimizin g Quarryi Quarrying ng Costs by Corre Correct ct Shotrock Fragmentation and In-pit Crushing
Oct. 2006, Rev A Jarmo Eloranta
Contents • Quarry process in general Comparison of different different shotrock shotrock fragmentat fragmentations ions • Comparison
• Comparison of different crushing methods • Conclusions • Enclosures
2
© Metso
Contents • Quarry process in general Comparison of different different shotrock shotrock fragmentat fragmentations ions • Comparison
• Comparison of different crushing methods • Conclusions • Enclosures
2
© Metso
Challenge in Quarry Development
‘real’ optimum
Source: Technical University Trondheim, Norway
$/to n What about the hauling distance?
3
© Metso
Distance
Quarry Process Stationary Crushers
4
© Metso
Quarry Process Mobile Crusher(s)
Mobile primary crushing
All crushers mobile
5
© Metso
Example of Quarry Cost distribution
Crushing & Screening Drilling
6
© Metso
Blasting Loading Hauling
Approach Based on Two Phases • Comparison of different shotrock fragmentations, including:
- drilling and blasting - boulder handling - loading - hauling - crushing (traditional stationary) • Comparison of different crushing methods, including:
- stationary - inpit, semimobile - inpit, fully mobile 7
© Metso
Optimum drilling and blasting Cost Effective Quarry Practise
Optimum crushing
Comparison of Different Shotrock Fragmentations
Comparison of different shotrock fragmentations
Starting Point: Stationary Three-stage Plant with a Capacity of 1600t/h. Final Product 0-20mm MAIN DATA
Drillig: Nr.of units Drilling pattern (m2) Blasting: Specific charge (kg/m3) K50 (mm), L Number of operators Loading by excavators Bucket size (m3) Nr.of units Hauling by trucks: Pay-load (t) Distance (km) Nr.of units Crushing: Primary crusher type Nr.of primary units Nr.of sec.&tertary units General Drillability & blastability Work index (kWh/t) Drill hole dia (mm) Bench height (m) Explosive Interest rate (%) / Quarry life (y) Fuel price ($/liter) / Energy ($/kWh) Wages ($/hour)
Case 1
Case 2
Case 3
Case 4
Case 5
3 9
4 6,4
5 5,8
6 4,5
8 3,3
0,53 410
0,76 290
0,9 250 18-22
1,15 200
1,56 150
12 2-7 depending on blast configuration (or bigger buckets) 50 2 8-10 depending on blast configuration Nordberg C160 jaw 2 5 45 / 0,7 15 89 10 Anfo 10 / 20 0,5 / 0,1 17
All together more than 50 different cases were analysed 9
© Metso
Comparison of different shotrock fragmentations
General Selection of Drilling Method
) i s p ( S C U , h t g n e r t S e v i s s e r p m o C
Top Hammer
Down-the-Hole
(Pneumatic & Hydraulic)
(Pneumatic)
50,000 100,000 40,000 80,000 30,000 60,000 20,000 40,000 10,000
Rotary
(Drag bits)
(Roller bits)
2
3
Source: Metso Minerals & Tamrock studies
© Metso
20,000
Rotary
1
10
120,000
4
5
6
7
8
9
10 11
12 13
14 15
Drillhole Diameter (‘’)
) b l ( t h g i e W n w o d l l u P y r a t o R
Comparison of different shotrock fragmentations
Impact of drillhole diameter to drilling and blasting costs
Impact of drillhole diameter to drilling and blasting costs K50 = 250, drillability = medium, blastability = good
] t / D S U [ s t s o c l a t o T
1,50 1,40 1,30 1,20 1,10 1,00 0,90 0,80 0,70 0,60 0,50 0,40 0,30 0,20 0,10 0,00
0,50
0,30 0,20 0,10 0,00 64
89 Drillhole diameter [mm]
Source: Metso Minerals & Tamrock studies
11
© Metso
Blasting
0,40
115
] t / D S U [ s t s o C
Drilling Drilling Blasting
Comparison of different shotrock fragmentations
Impact of Drillhole Diameter
Boulder count
) n o t / D S U ( t s a l B & l l i r D
Blasting
Source: Metso Minerals & Tamrock studies
12
© Metso
Fragment elongation ratio % Fines in shotrock Micro-crack damage of fragments
Drilling
Hole Diameter (mm )
Fines in feed
n o t r e p y t i t n a u Q
Hole Diameter (mm )
Cost1.pre/A. Lislerud
Comparison of different shotrock fragmentations
Boulder Handling Sort boulders from muck pile Downsize the boulders Minimize boulder count using tighter drill patterns or reduced uncharged height
13
© Metso
Comparison of different shotrock fragmentations
Example of Direct Costs Caused by Boulders. Customer case, breakage before loading
Hammering Costs ($/tonnes) h60 / s r 50 e d l u40 o b f 30 o r e 20 b m u10 n
0 0
0,05
0,1
0,15 $/tonnes
14
© Metso
0,2
0,25
0,3
Comparison of different shotrock fragmentations
Key Issue • Removal of bolder breakage outside process
• -> improved plant utilization
15
© Metso
Comparison of different shotrock fragmentations
Impact of Blast Distribution on Loading Costs
K50 definition
16
© Metso
Comparison of different shotrock fragmentations
Loading Operations; Examples
Typical toe problem requiring auxiliary hyd. excavator work and/or use of secondary blasting
Auxiliary machines required for quarry floor cleanup after blasting for loaders with poor mobility Source: Metso Minerals & Tamrock studies
17
© Metso
Tight muckpile (poor diggability) due to insufficient heave and throw
Comparison of different shotrock fragmentations
Optimum Shotrock Profiles for Loading Operations
Hmax
Front Shovels
Wheel Loaders
High productivity Minimal cleanup area Safe for operator
Low productivity Muckpile too tight Muckpile too high Dangerous for
operator
Hmax dependent on loader size and type for optimum loading capacity conditions
Hmax
New floor
Shotrock throw onto old (poor loadability) floor
Source: Metso Minerals & Tamrock studies
18
© Metso
Front Shovels Loaders
Wheel
Moderate productivity productivity Large cleanup area loose Safe for operator operator
High Muckpile is Safe for
Comparison of different shotrock fragmentations
And Feeding by Excavator
Cat recommendations
19
© Metso
Comparison of different shotrock fragmentations
Impact of Blast Distribution on Hauling Costs with Dumbers
20
© Metso
Comparison of different shotrock fragmentations
Why Coarser Blast Distribution Impacts on Loading and Hauling Costs? • Material is more difficult to load due to:
- more likely toe problems - bigger boulders • Scope of equipment changes due to more difficult and/or longer cycle times
• With respect to the equipment there is
- more wear - more maintenance
21
© Metso
Comparison of different shotrock fragmentations
Results K50 is 50% point of fraction distribution
Total costs / produced ton 4 ] n o t d e c u d o r p / D S U [ s t s o C
Case
3
Hauling Loading Hammering Crushing Blasting Drilling
2
1 0
Case 1 Case 2 Case 3 Case 4 Case 5
22
© Metso
K50 (mm)
Case 1
410
Case 2
290
Case 3
250
Case 4
200
Case 5
150
Comparison of different shotrock fragmentations
Conclusions of Shotrock Fragmentation
• From the total product cost point of view, there is an optimum shotrock fragmentation. In the case study, the optimum was k 50 ~ 250 mm.
• The crushing cost share is almost unchanged with different K 50 values because the blast impacts only on primary crushing
• Even smaller drillhole diameters than used here (89mm) can be economical, because: - Smaller drillhole diameters produce fewer fines. In many cases this is considered waste - There are fewer boulders to be handled
- There are fewer micro cracks in the blasted rock, due to more ‘gentle blasting’. In many cases, this generates better final aggregate quality
• Boulder management is important
23
© Metso
Comparison of Different Crushing Methods
Comparison of different crushing methods
Starting Points for Crushing Method Comparisons
• k50=250mm is being used as shotrock fragmentation • The following quarrying methods are under comparison:
- stationary: -
25
© Metso
• Material is transported by dump trucks into crushing plants inpit, semimobile • material is transported by dump trucks into the semimobile primary jaw crusher, and from there by conveyors to the secondary & tertiary crushing plants inpit, fully mobile • primary crushing done at a quarry face with a highly mobile track mounted jaw crusher, and taken from there by conveyors into the secondary and tertiary crushing plants. No dump trucks are used.
Comparison of different crushing methods
Stationary Crushers Primary crusher cannot normally be moved
Typical distance 2km
26
© Metso
Comparison of different crushing methods
Semimobile Inpit Crushing Primary crusher can be moved but only on a non-frequent basis.
27
© Metso
Comparison of different crushing methods
In-pit Fully Mobile Crushing Primary crusher is track mounted, compact and movable within 5-10 minutes.
28
© Metso
Comparison of different crushing methods
In-pit Fully Mobile Crushing Movable and steerable Lokolink conveyor system is a key component
29
© Metso
Comparison of different crushing methods
Truck Transport Versus Conveyor Belt
2,50
Horizontal Hauling USD/t Belt; Cost per ton
2,00 Truck; Cost per ton 1,50
t / D S U
1,00
0,50
0,00 0,5 1,0 2,0 3,0 4,0 5,0 0,5 1,0 2,0 3,0 4,0 5,0 0,5 1,0 2,0 3,0 4,0 5,0 0,5 1,0 2,0 3,0 4,0 5,0 0,5 0,5 0,5 0,5 0,5 0,5 1 1 1 1 1 1 5 5 5 5 5 5 10 10 10 10 10 10 L (km) & Capacity (million t/y)
Cost comparison between conveyor belt transport and dump truck haulage hauling distance and annual capacity.
30
© Metso
Comparison of different crushing methods
Truck Transport Versus Conveyor Belt Vertical Hauling USD/t
s : 1 t o 8) 1,40 1,20
Belt; Cost per ton
1,00
Truck; Cost per ton
t 0,80 / D S U 0,60
0,40 0,20 0,00 50 0,5
100 0,5
150 0,5
200 0,5
50 1
100 1
150 1
200 1
50 5
100 5
150 5
200 5
50 10
100 10
150 10
200 10
H (m) & Capacity (million t/y)
Cost comparison between conveyor belt transport and dump truck haulage as a function of vertical hauling distance and annual capacity given a haulage length to height ratio of 8 : 1.
31
© Metso
Comparison of different crushing methods
Starting Point: Three Different Plant Configurations with a Capacity of 1600t/h. Final Product 0-20mm
Primary crusher type Size Number of units Loaders, excavators: Bucket size (m3) Number of units Dump trucks: Size (t) Number of units Haulage distance (km) Conveyor length (km) Number of operators Secondary & tertiary crushers and screens *) Other variables *) = K10 in Hong-Kong
32
© Metso
Stationary plant
Semimobile primary plant
Fully mobile in-pit primary plant
Fixed Jaw C160 2
Semimobile Jaw C140 2
Track mounted Jaw C125 2
12 2
5,5 3
5,5 2
50 8 2 20
35 7 1 1 20 Secondaries: 2 * Nordberg OC 1560 Tertiaries: 3 * Nordberg HP500 Seven Screens: 10-20m2 As in previous drilling & blasting example
4 11
Comparison of different crushing methods
Results Total costs / produced ton K50 = 250mm, Feed rate 1600t/h ] n o t
d e c u d o r p / D S U [ s t s o C
3,5 3 Hauling Loading Hammering Crushing Blasting Drilling
2,5 2 1,5 1 0,5 0
Stationary
Semimobile
Fully mobile
Difference between stationary and fully mobile is about 25%.
33
© Metso
Comparison of different crushing methods
Another Example Total costs / produced ton Spreadsheet lines 141 - 146
Costs [USD/produced ton] 0
0,5
1
1,5
2
2,5
3
3,5
Case 6a: K50=410 Case 7a: K50=290
4
y r a m i r r e p h y r s a u r n c o i t a t S
Case 8a: K50=250 Case 10a: K50=200
y r a r m e i r h p s e u l i r c b o M
Case 11a: K50=150 Case 16a: K50=410 Case 17a: K50=290 Case 18a: K50=250 Case 19a: K50=200
Case 20a: K50=150
Drilling Total 2
34
© Metso
Blasting
Crushing
Hammering
Loading
Hauling
Tools Available 1) Process Integration and Optimization (PIO) Services This is not a case of … • Increasing the powder factor to increase plant throughput
•
Opt(blast) +…+ Opt(crush)
Max($$$)
2) Calculation & simulation tools
Total Cost vs. work category Utilities
2,00
Crushing
n o 1,00 t / $
Haulage
0,00
It is… The development of a quarrying and processing strategy which minimizes the overall cost per tonne treated and maximizes company profit. Opt(blast +…+
crush&screen) = Max($$$) 35
© Metso
DT-system
LT-system
Total Cost vs. cost category 1,50
Capital
1,00
Mainten an Energy
n o t 0,50 / $
0,00 DT-system
LT-system
Work continues …
Conclusions for Quarry Development • From the total product cost point of view, there is an optimum shotrock fragmentation.
• Oversize boulder frequency has a significant impact on capacity and cost.
• A smaller drillhole diameter produces fewer
fines. In many cases, this is considered waste.
• The crushing cost share is almost unchanged
with different K50 values when the crushing method is the same. The optimum selection is dependent on: - Rock type due to abrasion - ‘Case-specific factors’ like the life of the quarry, investment possibilities etc.
• Whole quarry process optimization instead of the suboptimization of individual components
• Inpit crushing can generate remarkable benefits 36
© Metso
Enclosures • Operational targets for a typical aggregate producer • K50 feed sizes • Example: Norwegian case
37
© Metso
Operational Targets for a Typical Aggregate Producer
USD / tonne
Product price curve v e r s u s product quality Product cost curve
Opt.
Shotrock fragmentation
Return 38
© Metso
K50 Feed Sizes
% 100
K410 80
K290
K250 K200
60
K150 40
20
0
Return
39
© Metso
Example: Norwegian Case
shotrock
Rock type
Anorthosite
Explosive
Slurrit 50-10
Blast size tonnes
~50 000
40
0 - 300 mm weigh t
32 - 70 mm
25 70 weigh t
0 - 32 mm
Source: Metso Minerals & Tamrock studies
40
© Metso
m m 2 35 3 0 f o 30 e g a t n e 20 c r e P
Ø114 Ø102 Ø89
Large SUB’ from prior bench level
Ø76
80
90
100
110
120
Hole diameter (mm)
Return
Basic Selection of Loading Equipment
Source: Cat presentations
41
© Metso