METHOD STATEMENT SOFT LANDSCAPING WORKS Reference Drawings: Planting Plan: L-P1-701 to L-P1-712 & L-P2-601 to L-P2-612 Specification: SECTION - 32 91 13 Scope of Work : This method statement describes the procedures for Soft landscaping works which includes Planting media, & Planting. Equipments & Materials:
Sweet soil Compost Fertilizers Plants Hand trowel Wheel barrow Tree stakes Tree ties Bobcat Shovel Crane
Personal Protective Equipment: The basic P.P.E will be provided as
Safety Shoes Safety Helmets Hand Gloves Goggles
Procedure 1. Based on the approved shop drawings the filling of selected materials will commence on top of waterproofing and drainage layers by bobcat and wheelbarrows. 2. Irrigation works will be commenced after the filling (refer to the irrigation method of statement)
METHOD STATEMENT FOR SOFT LANDSCAPPING WORK
Project: Green Community West, Extension PHASE III, DIP, Dubai
3. Sweet soil will be filled to the areas on top of the formation levels . 4. All the filled sweet soil will be protected from the contaminants. 5. Approved compost and fertilizers will be added to the sweet soil to have unique planting media. 6. Irrigation works will commission and wetting of the planted areas will be done to commence planting. 7. Ornamental trees will be planted as per details; stakes and ties will be provided as a wind protection to minimize the root disturbances. 8. Shrubs and ground covers will be set out for final approval and planting will commence after the receipt of approval.. 9. The planted areas will be cleaned and bark mulching done as approved.
.
10. Sample for each materials will be submitted and same shall be used to Compare the material delivery at site 11. All materials will be stored in proper place allocated by the main contractor. 13. All the materials will be inspected before using it for installation and damaged Materials will be rejected: Verification 1. Setting out 2. Sample of plants at site 3. Plants inspection at nurseries
Safety
A safety induction talk will be conducted prior to commencement of works. Akar supervisor will be having regular visits to ensure the safe working environment.