Preferred partner
Pressure Protection of Inlet – Inlet – A A Case Study Stavanger, 23.10.2012 Kim Henry Kristiansen| Process Specialist Engineer E ngineer Advanced Process Control Control and Safety, Bergen
Background info ■ Reservoir pressure reduced
■ Maximize choke valve capacity to increase gas production
■ Limiting factor Overpressure Protection
■ Mal-operation of Riser ESV
■ Pipeline - 12 inch, 15 km long
■ Gas production (Fluid GOR: 8000-9000 Sm3/Sm3)
System drawing Mal operation Maximize capacity
Modelling ■ Model choice: ■ Existing training simulator ■ K-Spice (software from Kongsberg Oil & Gas Technologies)
■ Verification of model (significant part of the job) ■ Piping and equipment ■ Important valves: PSV, choke, PV (Pressure valves) ■ Tuning of pipeline roughness ■ Tuning of pressure drop in flare system
Accept critera – Allowable overpressure ■ Design code BS 5500 (all vessels) ■ MAAP Design pressure + 10 %
■ EN13445 can be used for “Exceptional load cases” ■ FEM analysis ■ Can allow for pressures up to test pressure
■ Inlet Separator ■ MAAP = 80 + 8 = 88 barg ■ Test Pressure = 1.5 x Design Pressure = 120 barg
Test Pressures Test Pressure = 1.25 x Design Pressure = 100 barg Test Pressure = 1.5 x Design Pressure = 120 barg
Accept criteria – Allowable overpressure ■ Inlet Separator and Pressure Vessels downstream ■ MAAP chosen due to time constraints in the project ■ To allow for pressures above MAAP FEM analysis on 8 vessels
needed.
■ HP KOD ■ EN13445 already applied ■ Test Pressure: 9.6 barg ■ Piping on outlet nozzle only tested to 9.2 barg.
Analysis performed (through Dynamic Simulations) ■ Primary overpressure protection
■ Secondary overpressure protection (PSV capacity)
■ Highest flare load
■ Reaction Forces (Rho*v2) Evaluation of pipe supports
Analysis - summary ■ Secondary Barrier Test ■ Single Source Scenario (Separator not in operation, outlets closed) ■ Cv = 2x108 ■ Results very sensitive to PSV characteristic ■ Additional Source Scenario (Separator in operation) ■ Cv = 2x108 with limited gas production (background production) ■ Decision to apply administrative control: Operational procedures and messages on operator screens in CCR ■ NB: If administrative control fails Pressure should not exceed Test Pressures
■ Max Flare Load ■ Cv = 2x90 ■ Turns out to be limiting for choke capacity!!! ■ Results very sensitive to control parameters for Pressure Valves (PV) ■ Continue with existing control parameters ■ Control parameters must not be changed without performing new analysis
Secondary Barrier Test – Single Source Scenario • • • •
No primary pressure barrier No background production No Additional flaring No compressor trip
Closed
In-active
Closed
Single source scenario ■ According to existing design documentation Single source scenario probably limiting for choke valve capacity Our starting
point for the analysis ■ Pressure in separator Very sensitive to PSV characteristic
■ No exact characteristic available from manufacturer ■ Pop action at 2-3 % overpressure ■ Full flow capacity at 10 % overpressure ■ Blow down 15% - 25% (Percentage below set point pressure. Valve
closes at this pressure)
Possible PSV characteristics Characteristic A, B og C 100
Chosen characteristic (in agreement with customer)
90
Cv=2x113
80 70 ] % [ 60 t f i L e g 50 a t n e c r 40 e P
Cv=2x90 Kar. A - Opening
Cv=2x108
Kar. B - Opening Kar. C - Opening
30 20 10 0 90
95
100
105
110
Pressure (percentage of set point) [%]
115
120
Chosen PSV characteristic PSV Characteristic 100 90 80
Designed for liquid and vapour. Typical when in gas service: - Pop action - Large blow down percentage
Pop to 90 % only. Conservative for pressure
70 ] % [ 60 t f i L e g 50 a t n e c r 40 e P
Opening Closing
30
25 % Blowdown Conservative for flare load
20 10 0 70
75
80
85
90
95
100
Pressure (percentage of set point) [%]
105
110
115
Secondary Barrier Test – Additional Source Scenario • • • • •
No primary pressure barrier Background production Compressor trip Additional flaring No help from control system
In-active
Freeze
In-active
Trip compressors
Background Production
In-active Freeze
Additional Source Scenario ■ The Additional Source Scenario gives higher pressure build-up than
the Single Source Scenario ■ Reduction of gas production before start-up of pipeline would help
■ Solution: ■ Use administrative control to limit gas production before start-up. ■ BUT! Pressure should not exceed test pressure if administrative control
fails. ■ …No reduction of calculated choke Cv compared to the single source scenario
Max Flare Load • • • • •
No primary pressure barrier Background production Compressor trip Additional flaring Control System working
active
active
active
Trip compressors
Background Production
active active
Max Flare Load ■ Assumes that administrative control have failed High gas
production before incident ■ Pressure build-up in the HP Flare system is limiting the choke valve capacity !! Cv = 2x90
■ Evaluation of valve capacity – PV on Inlet Separator ■ 30-40 % more capacity than needed ■ If PV goes fully open in short time – capacity reduction is a good idea ■ With “slow” control parameters the extra 30-40% is not utilized. ■ Conclusion: Control parameters more important than valve capacity
Max Flare Load ■ Evaluation of control parameters – PV’s ■ Keep existing “slow” control parameters ■ Choosing wrong parameters could give too high pressures in HP Flare ■ Change of PV control parameters should not be done without performing
new analysis.
■ Some examples are shown on the next 3 slides ■ Example 1: Using existing control parameters for all 3 PV’s. ■ Example 2: The Inlet Separator PV has got “fast” parameters. ■ Example 3: The 2 PV’s on the glycol contactors have got “fast” control
parameters.
Ex. 1: All 3 PV’s have “slow” contr. par. (Existing)
106
Acceptable overpressure
Ex. 2: PV on Inlet Separator has fast contr. par.
Could help reducing PV capacity
106
Unacceptable overpressure!
Ex. 3: PV’s on Contactors have “fast” contr. par.
106
Unacceptable overpressure!
Main conclusions / Lessons learned ■ Achievement: Choke capacity increased by 50%
■ Initial assumption was wrong: The limiting scenario was not the
single source scenario. ■ Thorough evaluation of the accept criteria and design basis are of
high importance. ■ Perform sensitivity studies. Surprising dynamic effects are often
revealed. ■ PV Control Parameters and the PSV characteristic are important
factors and should not be underestimated.
Copyright and disclaimer Copyright Copyright of all published material including photographs, drawings and images in this document remains vested in Aker Solutions and third party contributors as appropriate. Accordingly, neither the whole nor any part of this document shall be reproduced in any form nor used in any manner without express prior permission and applicable acknowledgements. No trademark, copyright or other notice shall be altered or removed from any reproduction.
Disclaimer This Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and uncertainties that could cause actual results to differ. These statements and this Presentation are based on current expectations, estimates and projections about global economic conditions, the economic conditions of the regions and industries that are major markets for Aker Solutions ASA and Aker Solutions ASA’s (including subsidiaries and affiliates) lines of business. These expe ctations, estimates and projections are generally identifiable by statements containing words such as “expects”, “believes”, “estimates” o r similar expressions. Important factors that could cause actual results to differ materially from those expectations include, among others, economic and market conditions in the geographic areas and industries that are or will be major markets for Aker Solutions’ businesses, oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currency exchange rates and such other factors as may be discussed from time to time in the Presentation. Although Aker Solutions ASA believes that its expectations and the Presentation are based upon reasonable assumptions, it can give no assurance that those expectations will be achieved or that the actual results will be as set out in the Presentation. Aker Solutions ASA is making no representation or warranty, expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Aker Solutions ASA nor any of its directors, officers or employees will have any liability to you or any other persons resulting from your use. Aker Solutions consists of many legally independent entities, constituting their own separate identities. Aker Solutions is used as the common brand or trade mark for most of these entities. In this presentation we may sometimes use “Aker Solutions”, “we” or “u s” when we refer to Aker Solutions companies in general or where no useful purpose is served by identifying any particular Aker Solutions company.