Corus Construction & Industrial
The design of steel footbridges
Steel bridges the gap Below: River Aire footbridge, Leeds, 1993 Right: Lowry Footbridge, Manchester
Contents
This guide has been prepared for Corus by:
1. Introduction
D C Iles MSc ACGI DIC CEng MICE Manager – Bridges,
2. Features and forms of construction
The Steel Construction Institute.
for footbridges 3. Conceptual design and detailing
The author gratefully acknowledges the contributions
3.1 General arrangement
made by Mr W Ramsay, Corus and Mr A C G Hayward,
3.2 Selection of type of construction
Cass Hayward and Partners, during the original
3.3 Trusses and vierendeel girder bridges
preparation of the publication.
3.4 Steel beam bridges 3.5 Composite beam bridges 3.6 Cable stayed bridges 3.7 Access ramps and stairs 3.8 Bearings and expansion joints 4. Design codes, standards and guidance 4.1 British Standards 4.2 Departmental standards 4.3 Railway standards 4.4 Design of hollow section joints 4.5 Design of cable stayed and suspension bridges 4.6 Design of steel and composite bridge beams 4.7 Dynamic response 4.8 Protective treatment 4.9 Steel materials 5. Flow charts 6. References
The design of steel footbridges
3
Introduction
1. Introduction Footbridges are needed where a separate pathway has
Longer span bridges and those which form part of a
to be provided for people to cross traffic flows or some
larger scheme are likely to be designed in detail by a
physical obstacle, such as a river. The loads they carry
consultant or local authority. Within such an
are, in relation to highway or railway bridges, quite
organisation the engineer carrying out the design needs
modest, and in most circumstances a fairly light
to be familiar with the particular requirements for
structure is required. They are, however, frequently
footbridges, their features and construction details.
required to give a long clear span, and stiffness then becomes an important consideration. The bridges are
For the engineer in either of these situations, this
often very clearly on view to the public and therefore the
publication presents guidance on the conceptual design
appearance merits careful attention.
of steel and composite footbridges, to aid the selection of an outline design.
Steel offers economic and attractive forms of construction which suit all the requirements demanded
Typical key features are illustrated in section 3,
of a footbridge.
references to codes and sources of further guidance are given in section 4. Simple flow charts showing the
A fully detailed design can be prepared with other contract documents for pricing by tenderers. However, it is common practice, particularly for smaller bridges, for the detailed design of a footbridge to be included as part of a design and construct package. Many fabricators are able to provide such a package, using methods and details of construction developed to suit their particular fabrication facilities and expertise. However, the engineer supervising the work still needs to be acquainted with the different forms of construction which might be used and to be aware of their advantages and limitations.
4
The design of steel footbridges
design steps are presented in section 5.
Features and forms of construction for footbridges
2. Features and forms of construction for footbridges Basic requirements
Truss and vierendeel girder beams
Footbridges, like any other bridge, must be long enough to
Trusses offer a light and economical form of construction,
clear the obstacle which is to be crossed and high enough
particularly when the span is large. The members of the
not to interfere with whatever passes beneath the bridge.
truss can be quite slender and this naturally leads to the
However, the access route onto the footbridge is often
use of structural hollow sections. Hollow sections have
much different from what is familiar to the designer of a
been used for footbridges for over 30 years and some
highway bridge: there is no necessity for a gentle horizontal
fabricators have specialised in this form of construction,
alignment (indeed the preferred route may be sharply at
developing techniques and details which utilise them to the
right angles to the span). Structural continuity is therefore
best advantage.
less common. The principle span is often a simply supported one.
Vierendeel girders using hollow section members offer an alternative but complementary structural form of similar
Provision of suitable access for wheelchairs and cyclists is
proportion by substituting a rectangular form for the
often specified for footbridges. Access ramps must be
triangular arrangement used in trusses.
provided and restricted to a maximum gradient. The consequent length of ramps where access is from the level
Trusses and vierendeel girders are arranged with either
of the road or rail track over which the bridge spans is
half-through or through construction. Half-through
generally much longer than the bridge itself. The form of
construction is used for smaller spans, where the depth
construction suitable for the ramps may have a dominant
needed is relatively shallow. For larger spans, or where the
influence on the final form of the bridge.
truss is clad to provide a complete enclosure for the pedestrians, through trusses are used; the top chords are
The width of a footbridge is usually quite modest, just
then braced together above head level.
sufficient to permit free passage in both directions for pedestrians. Occasionally the bridge will have segregated
Steel beam bridges
provision for pedestrians and cyclists, in which case it will
The simplest method of employing structural steel as the
need to be wider.
prime structural element of a footbridge is to use a pair of girders (fabricated or rolled sections), braced together for
Parapets are provided for the safety of both the pedestrians
stability and acting as beams in bending, with a non-
and traffic flow. Footbridges over railway lines are required
participating walkway surface on top. A typical small
to have higher parapets and be provided with solid panels
bridge deck might for example be formed by timbers
directly over the rail tracks.
placed transversely across the top of the beams. Precast slabs might also be used, without being shear connected to the steel and therefore not participating in global structural action.
Left: Bell’s Bridge, Glasgow Right: Whatman’s Field Bridge, Maidstone
The design of steel footbridges
5
Alternatively the floor might be formed by steel plate,
Although composite construction is usually associated
suitably stiffened to carry the pedestrian loads, in which
with I section girders, a concrete slab can also be used
case the plate could also be made to act structurally as the
with a steel box girder.
top flange of the steel beams. Cable stayed bridges Steel box girder bridges
In seeking to provide a bridge of light appearance, the
Another alternative is to use a small steel box girder. The
use of cable stays is found to be very successful. It
top flange acts as the floor of the bridge, and there are
often affords scope to create a visually striking structure
usually short cantilevers either side of the box. This form
which provides a landmark or a focus for the area in
has the benefits of good torsional stiffness which can
which it is located. Almost any form of construction can
simplify support arrangements and clean surfaces which
be used with stays, though when a cable stayed form is
minimise maintenance.
chosen, the structural requirements are often found to be of secondary consideration to the achievement of a
Composite beam bridges
pleasing appearance.
Composite beams, steel girders with a concrete slab acting as both a walkway floor and participating as a
Enclosed bridges
top flange, are a practical solution for medium span
Enclosure of the sides of a footbridge is often called for
footbridges. They are a lighter version of the form of
to discourage the throwing of objects from the bridge.
composite construction frequently employed in
This is a particular requirement for bridges over railway
highway bridges. Slabs may be cast insitu, though the
lines. Full enclosure, to the sides and the roof of the
lesser requirements for the shear connection and the
walkway, is called for in situations where the users are
lighter design loads on the slab allow greater
to be protected from the environment and where greater
opportunity to employ pre-cast slabs. The slab can also
protection is required over railway lines. Such enclosure
be cast on the beams in the works or other convenient
justifies the use of through truss or vierendeel
site, since the weight and dimensions are often
construction. The form of construction will probably be
sufficiently modest to permit transport and erection of
dictated by consideration of appearance of the bridge
the complete superstructure.
and its relationship to adjacent structures. Whilst the general principles discussed in this guide are applicable, fully enclosed bridges are not specifically dealt with in detail in this guide.
6
The design of steel footbridges
Features and forms of construction for footbridges
Left: Swansea Sail Bridge Below: Halfpenny Bridge, Sheffield Right: Millennium Bridge, Gateshead
Decorative features
The use of curved arch-type members is currently quite
In addition to the basic impression made by the form of
popular, as is the use of cable stays. Some recent
construction, the appearance can be greatly influenced
examples are illustrated on this page.
by non-structural decorative features, such as parapets and handrails. Where particular effects are sought, the
Since these landmark structures are generally innovative,
availability of different patterns for posts, rails, etc,
it is inappropriate to try to include design guidance here,
should be investigated. Non-structural embellishments
but the general requirements and design principles given
of supports can also contribute – for example a cable
in the following sections are largely still applicable.
stayed pylon can be extended to a spike or other feature above the level of the topmost stay connection. Landmark structures It is an increasingly common requirement for footbridges in prominent or key locations to be ‘landmark structures’. Particular attention is given to the appearance of the structure and this may result in somewhat unusual forms of construction. Such structures can be allowed to be marginally less efficient (in terms of complexity of fabrication), but if the design is well executed the penalties should be small. There is more scope for innovative design when the structure is not over a road or railway, because the requirements for parapet details need not be so stringent. Parapets are often the most noticeable feature of a footbridge, and the freedom to use more attractive forms and more open post and rail arrangements can lead to a very pleasing appearance.
The design of steel footbridges
7
Conceptual design and detailing
3. Conceptual design and detailing 3.1 General arrangement
Minimum footway
As a first step, the basic requirements for access and safety should be determined. The width and form of
2.0m
access needed depends on the expected pedestrian traffic flow, though minimum dimensions are adequate in 1.15m
most cases. For a simple footway, a minimum clear width of 2.0m is required by the highways authorities. Railway station footbridges can be less wide. To the sides of this footway, parapets are required, which should be 1.15m high over roads or 1.5m high over railways, the height measured from the footway surface in both cases. In areas prone to vandalism, a height of 1.8m may be Footway + cycleway
required over railways. The resulting minimum cross section to be provided is shown in Figure 1. An
2.0m
increased parapet height of 1.3m may be needed in areas of high prevailing wind and for bridges where the headroom under the bridge is more than 10m.
1.4m
Where pedestrians and cyclists share the pathway, the minimum width of 2.0m may be used for low traffic flows but a wider segregated pathway (1.5m + 1.5m minimum) may be required for higher traffic flows. Segregation can be achieved by a white line, colour contrast or difference in surface texture. At the same time the minimum parapet height is increased to 1.4m. The cross section for a combined pathway is also shown in Figure 1. Marked segregation
Dimensional requirements for footbridges are given in Departmental Standard BD 29/03. That document refers
1.5m
1.5m
to BS 7818 for minimum dimensions of parapets. The drainage requirements also affect the cross section, since kerbs will be needed to prevent run-off where the Typically an upstand of 50mm should be provided. This
Footway
Cycleway
upstand can be provided by an edge beam, by the lower chord of a truss or by a flat welded to the floor plate.
Figure 1: Basic sectional dimensions for bridges over highways
8
The design of steel footbridges
1.4m
bridge is above a carriageway, a footpath or rail tracks.
Conceptual design and detailing
5.7m 4.5m
Figure 2: Governing dimensions in elevation
Span
the superstructure to be capable of supporting itself if
Since there is usually no need to align the approaches
one support were to be demolished in an accident.
to a footbridge, the span should normally be arranged square to the obstacle it has to cross.
Clearance Over a highway, the clearance under new footbridges is
The minimum span required is that simply needed to
required to be at least 5.7m (TD 27/96). With this
clear the width of obstacle, carriageway or railway.
clearance the superstructure need not be designed for
However, the span may be increased in order that the
impact loads (see Figure 2). If any relaxation on
supports are positioned far enough from a carriageway
clearance were permitted in special cases it is likely that
or rail track to avoid the risk of impact from an errant
impact loads would have to be considered. This would
vehicle or derailed train. The supports of light structures
be very onerous on the structural design. Clearance over
such as footbridges are particularly prone to the effects
railways is specified by Network Rail with a minimum of
of impact.
4.640m from rail level. The minimum clearance over electrified lines and over lines that might be electrified in
For footbridges over highways, the span is determined
the future is 4.780m. Greater clearances are required
by the dimensions of the carriageways, as given in the
near level crossings and where there is ‘free running’
Departmental Standard TD 27/96.
(where the wires are not attached to the bridge).
To avoid the imposition of impact loads the supports
Clearly, where access to the bridge has to come from
need to be set back 4.5m from the edge of the
carriageway or track level, the rise needed for the stairs
carriageway (see Figure 2). Where this can be arranged,
or ramps is the sum of the clearance plus the
perhaps additionally spanning a footway beside the
superstructure construction depth (walkway surface to
road, the consequent savings in the cost of the
structure soffit). This means that ramps will be long
substructure should be considered. Supports between
(about 120m at each end of the bridge over a road, for a
carriageways should also be avoided if possible.
1 in 20 grade). It also means that the depth of construction (for example the depth of a plate girder)
The space needed for approach ramps and stairs will be
can add significantly to the length of ramp, and thus to
significant in arranging the layout of a footbridge. This
the cost of the whole structure. For this reason, half-
may influence the positioning of the bridge and its
through construction, with a very shallow construction
supports, and thus its span.
depth, is usually preferred.
Footbridges over railways are mostly required to cross
Sufficient vertical camber is needed to ensure drainage
two or four tracks, with resulting span of between 10
of the footbridge to the ends, where the run-off can be
and 25m. Where intermediate supports are placed
carried to drains or a soakaway.
closer than 4.5m to the nearest rail, Network Rail require
The design of steel footbridges
9
Conceptual design and detailing
Spiral ramp, Myton Footbridge, Hull
Stairs and ramps, Christchurch
Stairs and ramps
Stairs are usually arranged in two or three flights with
Where access is required from a lower level, stairs and
intermediate landings, depending on particular
ramps must be provided. Stairs are only suitable for able
arrangements, to comply with normal safety
pedestrians and it is general policy to provide ramps
requirements. They usually have semi-open risers, for
where possible. Such ramps should ideally be no steeper
lighter appearance. Handrails are provided on the inside
than 1 in 20, though gradients of up to 1 in 12 may be
faces of the parapets on stairs and ramps. Minimum
used for straight ramps where space is limited.
widths must be maintained between these handrails.
A ramp can be either a series of straight sections or a
Services
spiral, depending on circumstances and space available
Occasionally the bridge may have to carry a service –
(see Figure 3). The space occupied by a ramp is quite
water pipes or electric cables, for example. It should
significant and may well influence the position of the
normally be arranged that such pipes are supported out
bridge.
of sight, on brackets or cross-members between main beams for example. If a service is positioned inside a box
A single straight ramp can be used where space and the
girder, it is better to put it in a duct, so that any
desired access route permit. If the gradient is steeper
maintenance to the service does not require entry into the
than 1 in 20, the ramp should have intermediate landings
box girder. Gas or water pipes should not be sited inside
(i.e. it should be a series of ramps with horizontal
a box girder, for safety reasons, unless placed in a steel
sections between). Ramps are often arranged in scissor
sleeve which runs the length of the bridge.
fashion (i.e. with a 180º change of direction at an intermediate landing). Spiral ramps must have a minimum inside radius of 5.5m (gradient measured 900mm from the inside edge). The same limits on gradient apply (i.e. a maximum of 1 in 20 is desirable, up to 1 in 12 may be acceptable in some cases). Spiral ramps are unsuitable for a full 6m rise to a footbridge over a highway unless a large radius can be accommodated. Stepped ramps are sometimes used which, with a 125mm step and a 1 in 12 slope between, can effectively achieve a 1 in 6 gradient. For spiral ramps this gives a rise of 6m in under 360º turn.
10 The design of steel footbridges
River Exe Suspension Bridge
3.2 Selection of type of construction
often appropriate, both visually and structurally. Beyond
As mentioned previously, the depth of construction is
about 100m twin pylons should be considered.
very important to the overall extent of the footbridge where access is from the level of the road or railway
Suspension bridges are very rarely considered these
being crossed. In those circumstances it is usually
days, but may still be chosen for appearance reasons
preferable to use a half-through form of construction.
when the span exceeds about 70m.
This usually leads to a selection of a truss or vierendeel girder bridge, though half-through plate girder forms such
A summary of approximate span ranges suitable for the
as that developed by Network Rail may also be used.
various types is given in Table 1.
However, not all bridges are subject to such constraints.
Table 1
Some simply cross, for example, a small river, or span
Span ranges for different types of construction
across a deep cutting. In such cases the depth of
Construction type
Span range (m)
construction is not so important and steel girders or steel
Truss
15 to 60
composite construction may be employed. When the span
Vierendeel girder
15 to 45
Twin steel girders
10 to 25
Steel girders + steel floor plate
10 to 30
construction may well be advantageous. Alternatively,
Steel box girder
20 to 60
cable stayed construction can be employed.
Composite beams
10 to 50
Arches
25 upwards
Cable stayed forms of construction can rarely be
Cable stayed bridge
40 upwards
justified visually below about 40m. For spans up to
Suspension bridge
70 upwards
is long, the dynamic response of the bridge becomes a significant consideration, particularly for the lighter allsteel bridge. The greater stiffness afforded by truss
100m a single pylon on one side of the main span is
1:20
13 risers max
≥ 2m
1:20
Figure 3: Arrangement of typical stairs and ramp
The design of steel footbridges 11
Conceptual design and detailing
3.3 Trusses and vierendeel girder bridges Although trusses and vierendeel girders have a different structural action, there are many similar features when they are constructed of structural hollow section members, as used in footbridges. This section deals with both types of construction. Through and half-through construction Trusses and vierendeel girders for footbridges are normally arranged with the deck at the level of the bottom chord, in either through or half-through construction. Half-through construction is used for smaller spans, where the depth needed is less than the clearance height for people to walk through. For large spans, or where the bridge is clad to provide a complete enclosure for the pedestrians, through construction is used. The top chords can then be braced together above head level. Stability of the top compression chord in half-through construction is provided by the U-frame action of the side members and the cross-members of the deck. In through construction, lateral bracing between the two top chords offers a more direct means of stabilising them.
Below and right: Through truss footbridge
12 The design of steel footbridges
Conceptual design and detailing
Configuration The type of truss usually employed is either a Warren truss or a modified Warren truss. Occasionally a Pratt truss may be used. The different types are illustrated in Figure 4. Warren truss
Warren trusses are the simplest form of truss, with all loads being carried principally as axial loads in the members and with the minimum of members meeting at joints. However, the loads which are carried to the bottom chords from the walkway floor can lead to significant bending in these members when the panels
Modified Warren truss
are large. A modified warren truss reduces the span of these chord members, though the additional vertical members add complexity to the fabrication. Pratt trusses are used where it is preferred that some members are vertical, for example to facilitate the fixing of cladding or decorative panels. Pratt truss
Vierendeel girders have no diagonal members and rely on a combination of axial loading and bending to carry loads. The stiffness of the girder depends crucially on the bending stiffness of vertical and horizontal members and on the stiffness of the joints between the two. As a consequence they are much heavier, for a given span, than a Warren truss. However the appearance, which
Vierendeel girder
only shows vertical and horizontal lines, in harmony with the normal form of parapet (horizontal rails, vertical posts and infill), is often considered more pleasing.
Figure 4: Types of truss and vierendeel girder
For the largest spans, the vierendeel girder will probably be too flexible, though they have been used successfully up to 45m span.
Below: Half-through truss footbridge
Below: Rutherglen station footbridge
The design of steel footbridges 13
Proportions and appearance
by road users. They therefore require careful attention
The familiar image of a truss is probably of a heavy-
and treatment.
looking structure, relatively deep in proportion to span. Such trusses were often used for railway bridges.
Where the depth of the vierendeel girder is determined
However, a truss footbridge can generally be of light
by parapet height, the top chord can often be used as
appearance and of shallow depth/span proportion.
the parapet rail, with suitable infill bars fixed between the vertical members. For longer span vierendeel
With half-through construction, the minimum overall
girders, where the depth is more than the parapet
depth is determined by the parapet height; for a
height, parapet panels complete with top rail can be
crossing over a highway the minimum is about 1.25m.
fixed inside the rectangular panels of the girder. Where a
For spans over about 30 metres the depth will need to
truss is used, the parapet is usually fixed to the inner
be slightly greater, though span/depth ratios in excess
face of the diagonal members. The parapets are less
of 30 can give a pleasing appearance.
conspicuous to road users than the truss members, though they are still evident in silhouette.
For spans over 50m full through construction will probably be necessary. Then the depth is determined by
Construction depth, from footway surface to underside
internal clearance, which is usually specified as 2.3m
of the truss or girder, is normally quite shallow, not more
minimum. To reduce the tunnel effect and to keep the
than the depth of the chord members. This contributes
top bracing away from casual abuse a depth of about
greatly to the light appearance.
3m is needed. Such spans will have a deeper span/depth ratio, though the slender members will still
The top and bottom chords of a truss are usually made
give an impression of lightness.
parallel, but for larger spans a less dominating appearance can be achieved by a hog-back
The arrangement of the bracing and the line of the
configuration, with a gentle curve to the top chord
parapets are the dominant features which are seen
reducing the depth at the ends of the span.
Above: Large-span truss footbridge Left: Vierendeel footbridge Right: Lower chord connection detail Far right: Large-span vierendeel footbridge, A27 Broadmarsh
14 The design of steel footbridges
Conceptual design and detailing
Members and connections – trusses
have a higher buckling resistance than that calculated
Both circular and rectangular structural hollow sections
even when a lower flexibility value is used.
are commonly used in trusses. The bottom chord is generally rectangular, to facilitate connection with deck
The failure loads calculated were relatively insensitive to
and cross-members. Rolled sections or flats are
the actual value of connection stiffness. This showed
sometimes used as cross-members or as stiffeners to
the use of diagonal stiffeners does not significantly add
steel floor plates. Chords and diagonals are usually
to the global strength of tubular U-frame footbridges.
arranged with centrelines intersecting where possible. Standard welding details have been developed for
Where a steel floor plate is used it normally acts as the
hollow section connections.
“bracing” to the bottom chords, to carry the lateral shear (mainly wind forces) back to the supports. If a
For half-through trusses the connection with
non-participating form of floor is used, cross bracing in
cross-members at the lower chord requires particular
the plane of the bottom chord, to resist lateral forces,
attention, since its stiffness and strength are
must be considered.
fundamental to U-frame action. Through trusses, used in longer spans, give lateral Where the bottom chords are of rectangular section,
stability to the top compression chord by means
some designers specify plates slotted diagonally across
of bracing in the plane of the top chord. Such bracing
the section at the position of the cross-members (Figure
will also share in the carrying of any lateral forces,
5) to prevent the chord lozenging or distorting.
especially where the truss is clad on its sides and thus subject to significant wind loads. At the ends of the span
However, cutting slots in the hollow section and welding
these lateral forces have to be carried down to bearing
stiffeners adds to the fabrication cost. Research by the
level through portal action or through a braced frame.
Steel Construction Institute for Corus (30) showed an un-stiffened connection designed to BS 5400: Part 3 to
The design of steel footbridges 15
Conceptual design and detailing
Members and connections – Vierendeel girders
Stability of the compression chord again requires
In footbridges, Vierendeel girders normally use
U-frame action of the cross section and this again
rectangular hollow sections for greater stiffness
requires adequate stiffness and strength of the
and strength at the connections between verticals
cross-member to vertical connection at the bottom
and chords.
chord. Even with the heavier sections usually required for a vierendeel girder, it may be necessary to insert
The nature of vierendeel action is that vertical shear is
diagonal plates, as mentioned previously.
carried by shear/bending action of each length of chord, and the vertical members are subject to complementary horizontal shear and bending. Since shear is highest at the ends of the span, the “fixed end moments” are
100 x 100 10 RHS
highest there also. The vertical members therefore need to be strongest at the ends of the span. On the other hand the central portions of the chords
10 thick insert plate slotted into chord
sustain predominantly axial load, whilst the ends sustain predominantly bending load. There is less need to vary the size of the chord members, and usually only thickness is varied, if at all. The consequences are that the vertical members are
Weld ground flush
often wider (in the plane of the girder) at the ends of the span and are sometimes closer together, variations
Figure 5: Detail of diagonal plate through bottom chord
which are clearly visible in silhouette. The strength of the joint between chord and vertical members must be adequate to transmit the fixed end moments. To do this both should have the same width (normal to the plane of the girder). Under the higher moments on the joints toward the ends of the span a simple square joint may have inadequate strength, and either triangular fillets (cut from the same section as the vertical) or reinforcing plates may need to be added to increase stiffness and strength (see Figure 6). The appearance of these additions may not always be acceptable and heavier sections may be preferred.
Figure 6: Detail of a haunched joint in a vierendeel girder
Right: Stiffened plate floor construction Far right: Typical floor construction
16 The design of steel footbridges
Conceptual design and detailing
Floor construction
Where rainwater can be allowed to run off the side of the
The floor of a truss or vierendeel girder footbridge will
bridge (for example over a river), the floor may be slightly
usually be of steel plate, though precast planks have
cambered transversely to facilitate drainage. With
been used with trusses. The lighter steel deck is now
stiffened thin steel plate decks, care also needs to be
generally preferred.
exercised that panels do not dish between stiffeners and allow ponding of water – the spacing of stiffeners is
The plate, typically 6mm or 8mm thick, is supported on
usually limited for this reason. Weld sizes should be kept
and welded to steel cross-members between the
to a minimum, to reduce distortion from welding.
chords. These cross-members form part of the U-frames
(see GN 2.10 (31))
which stabilise the top chord and are themselves usually hollow sections. The plate panels between chords and cross-members are divided transversely and sometimes longitudinally by stiffeners (usually flats) to give added support. On top of this plate a waterproof layer is required for corrosion protection, and to give a non-slip surface for safety. This is usually achieved with a thin membrane (which acts both as waterproofing and as a binder) and a surface dressing of fine aggregate. The total thickness is about 4mm. This surface is often applied in the works and does not add significantly to erection weights. When precast planks are used it is necessary to provide a shelf angle on the inner face of the chords on which the planks can sit. It is very important that the joint between concrete and steel is properly sealed or it could become a moisture and corrosion trap. Where drainage over the edges of the bridge is not permitted, arrangements must be made to carry rainwater to the ends of the bridge and then to drains or a soakaway. A vertical curve or longitudinal camber should be provided on a bridge which otherwise would be level.
The design of steel footbridges 17
Conceptual design and detailing
Parapets
Cladding
Parapets are normally designed to comply with a
Over rail tracks, the highway and rail authorities require
DMRB standard (see section 4.2). The parapet may be
that solid non-climbable cladding be provided on the
either a separate item or may be combined with
inside face of the truss or vierendeel girder. This is
structural members.
usually achieved by profiled steel sheeting, rigidised aluminium, GRP panels or even flat sheets. Fine mesh
For trusses, the parapet is provided as separate units
(maximum 50mm apertures) may be used over non-
fixed to the inside faces of the truss diagonals. The
electrified lines. Although the cladding is only required
diagonals must then be designed to carry lateral loads
over the tracks, a better appearance is often achieved
from the parapet, and the parapet rails must be
by providing the cladding over the full length of the
designed to span between the diagonals which support
span. Great care needs to be exercised in detailing the
them. Parapet posts can alternatively be fixed to the
cladding, to avoid the creation of small inaccessible
footway deck, though the attachment would need to be
sheltered ledges on the top of the lower chord where
strong enough to withstand the overturning moment
moss and debris can accumulate or which may be used
arising from lateral forces on the top rail.
for handholds or footholds.
Where vierendeel girders are used it is convenient to fix parapet panels in the rectangular panels of the girders, effectively using the vertical members as parapet posts. This achieves an integrated appearance and produces a slightly lesser overall width of bridge than with separate parapets on the inner faces of the girder. The top chord of the girder may also function as the top parapet rail, or, if it is higher than the required parapet height, a separate rail can be provided in addition to the top chord.
Left: Parapets in vierendeel girder, Horam Right: In-line splice detail Far right: Erection of Christchurch footpath
18 The design of steel footbridges
Conceptual design and detailing
Supports
Erection
Trusses and vierendeel girders are supported either on
Fortunately, most footbridges can be fabricated as a
bearings (if they span between concrete abutments, for
complete length of the span and then transported, with
example) or directly on top of a simple steel
spans up to about 45m. Although fabrications over 27m
substructure without any bearings.
in length require special permission to travel on the public highway, most fabricators prefer to complete fabrication
At abutments the point of support is normally directly
in the works wherever possible and are familiar with
below the end vertical or diagonal members and thus
arrangements for the movement of long lengths.
does not give rise to local bending of the chord section. Other supports should also preferably be arranged
Bolted hollow section flanged joint details can be used
similarly. Where it is not convenient to do so, for
for site splices, though it may be felt that flange plate
instance when a top landing cantilevers a short distance
end connections are somewhat cumbersome in
beyond the support columns and the support is midway
appearance. In-line splice details are much less
between bracing connections, the bottom chord is
obtrusive, but require more effort in design and
subjected to bending. It is then common to use a
fabrication (see photograph below left). In most cases,
heavier chord section over the last one or two panels of
spans must be complete before lifting, because closure
the truss (see photograph below right).
or possession periods will be very short.
Fabrication of trusses Fabricators who specialise in hollow section fabrication are familiar with all the types of detail needed for truss footbridges and have appropriate equipment, such as profile cutting equipment for tubulars etc. A wide range of sizes of hollow sections is available from the rolling mills, but it must be remembered that the fabricator has to purchase material for each job, either from the mill or from a stockist, and his orders may be subject to minimum quantities and premiums for small quantities. The designer should therefore try as far as possible to standardise his choice of section size and material grade.
The design of steel footbridges 19
Conceptual design and detailing
Left: Footbridge using rolled sections, Swale Right: Footbridge with timber deck and parapets Far right: Box girder footbridge and cycleway, Gablecross
3.4 Steel beam bridges
by the treatment of the parapet rails, posts and any
Types of construction
other feature added to the bridge. The use of simple
Four types of construction are considered in this
parapet details will contribute to a good non-fussy
section:
overall appearance.
•
•
a pair of steel beams with a non-structural floor on top
In some circumstances a distinct curvature in elevation
(e.g. timber)
(more than would suffice just to aid drainage to the
a pair of steel beams with a structurally participating
ends) will add character to the appearance.
steel floor plate •
a steel box girder
The use of a steel box girder extends the clean lines to
•
a half-through plate girder bridge as developed by
the soffit of the bridge. It can be complemented by a
British Rail
simple basic parapet or can be contrasted by embellishment with ornate fixtures and fittings. Typically
The first three are appropriate where depth of
the box would be about 1.0m wide, with short steel
construction is not important. The fourth is appropriate
cantilevers either side to provide the necessary width.
where minimum construction depth is critical. Half-through plate girder bridges will usually have their Proportions and appearance
U-frame stiffeners on the outside faces and generally
For the relatively light loading on a footbridge, the depth
look more heavy. Nevertheless, the half-through plate
of beam in all cases can be arranged to be about 1/30
girder bridge developed by British Rail (see page 22)
of the span. A typical bridge over a river or canal might
achieves a pleasing appearance.
then have a span of 30m and a beam depth of 1m. A simple I-beam bridge with non-structural floor might
Members and connections – I-beams/girders
comprise two girders about 1.5m apart on which is fixed
For economical design, the pair of beams need to be
a floor of, in some instances, timber planks. Parapet
braced together to stabilise them against lateral
posts would be fixed to the top flange or the outer face
torsional buckling. Bracing at several positions in the
of the steel beams.
span will be necessary, roughly at 15 to 20 times the top flange width to achieve reasonable limiting stress levels.
Steel girders with a structural participating steel floor
Bracing can simply be an X brace with single tie at each
plate would be of similar overall proportions. Parapets
position, bolted to stiffeners on the inside faces of the
would be fixed on top of the floor plate.
webs. For the main girders, fabricated I-sections are likely to be lighter and more economic than Universal
With both forms, the girders can have a clean web over
Beams. Castellated beams can provide a weight saving
their full length, as web stiffeners are needed only at
in some circumstances whilst offering an interesting and
supports and on the inner faces for attachment of
different appearance.
bracing. The structural element therefore looks clean and simple. The appearance will be influenced strongly
20 The design of steel footbridges
Conceptual design and detailing
A non-structural deck, such as timber planking, can be
To improve appearance it is common to use slightly
simply bolted down to the top flange of the I-beams.
sloping webs, creating a trapezoidal cross section.
Particular attention should be paid to detailing, to minimise crevices where dirt and moisture can
The use of steel box girders has the advantage of
accumulate.
torsional strength and stiffness. They can be used in continuous construction to simplify supports or to curve
In many instances steel plate is used for the floor of the
the bridge in plan when desired for appearance. In a
bridge. The plate, typically about 6mm or 8mm thick, is
straight bridge, torsional restraint (usually by means of
usually welded to the main girders and can therefore be
twin bearings) is needed only at the ends: a single
assumed to act structurally with them. Cross-members
bearing will suffice at intermediate supports, thus
will be required to carry the floor loading to the main
allowing the use of a single slender column.
beams and these are sometimes extended by short steel cantilevers outside the beam web, in which case an edge beam is provided to give a neat face and to give support to the parapet. A thin waterproof wearing surface is normally specified, dressed with fine aggregate for grip and durability. The surface is often applied in the works. Members and connections – box girders Box girders are essentially similar to the paired plate girders with steel deck, as described above, except that the bottom flange joins the two webs and encloses the space between. They are usually considered only for spans over about 30m. The thickness of the top flange which also forms the floor plate will be determined by overall bending strength rather than local floor loading. The plate is typically supported by transverse stiffeners which cantilever to edge beams. Two or three longitudinal stiffeners may be provided to stiffen the floor
Figure 7: Cross section through a typical box girder footbridge
plate when acting as the compression flange of the box. Diaphragms are needed at supports and are often provided at several positions along the length of the girder (typically the third points) to control distortion. Large holes will be required in the diaphragms if access is required during fabrication or maintenance.
The design of steel footbridges 21
Conceptual design and detailing
Members and connections – half through girders
Fabrication
Half through plate girder footbridges are often used over
Whether using rolled I-beams or fabricated I-section
railways. The solid web provides the required screening
girders, the processes of drilling holes, adding stiffeners
without the need for any non-structural additions. This
etc. poses no difficulty to the fabricator. The fabricated
form has developed from the half-through plate girder
I-section can either be made using jigs and semi-
concept often seen in railway bridges. A particular form
automatic welding or by a T and I automatic welding
developed by the former Midland Region of British Rail
machine. Curvature in elevation is easily achieved with
is illustrated in photographs shown above. Two features
fabricated girders, and universal beams can readily be
to note are: the use of a hollow section as top flange,
curved by specialist bending companies prior to
turned through 45° it forms a steeple cope, which
fabrication. Fabrication of box sections requires more
discourages walking along the flange; the absence of
traditional methods, and the completion of the closed
any projection of the bottom flange prevents climbing
box makes it almost essential for manual work internally.
along the outer face.
Details should be arranged for ease of access for work and inspection.
U-frame action is provided by the flat intermediate stiffeners to web and bottom flange. Typically they are
Splices
provided about every 1.5m.
For spans up to around 40m, it is quite likely that the beams would be transported full length and splices
Parapets
would not be needed. Over 40m they would be split
Where there are no cantilevers the parapet can either be
into at least two lengths; site connections would
fixed to the top flange of the box or to the web of the
normally be bolted.
girder. The attachment positions should coincide with bracing or cross-members, to provide restraint against
Bolted splices are quite conventional, with few problems.
rotation under lateral loads on the parapet rail.
If a completely clean face is sought,it will be necessary to have a site welded joint.
Where there are cantilevers, either the posts should coincide with the cantilever positions or they should be mounted on a torsionally stiff hollow section edge beam.
22 The design of steel footbridges
3.5 Composite beam bridges
Members and connections
Types of construction
Composite construction produces a much heavier
Composite construction is seen in footbridges in two
structure than an all-steel footbridge; the dead
forms – a concrete slab on top of two I-girders or a
load accounts for over half of the total load in most
concrete slab on top of a closed steel box girder. The
cases. The extra weight and consequent stiffness of this
open steel box form with slab which is sometimes used
form of construction has the advantage of being less
in highway bridges is not normally seen in footbridges
responsive to dynamic excitation.
Slabs may be cast insitu, though the relatively modest
Where transverse joints between precast units are not
extent of the shear connection and lighter design loads
designed to carry transverse shear, plan bracing will
on the slab allow greater opportunity to employ pre-cast
also be needed.
slabs. Such slabs are provided with open pockets to fit over the shear connectors. The pockets and the joints
Floor construction
between slab sections are filled with concrete to create
Reinforced concrete slabs for footbridges are typically
the necessary structural continuity.
about 150mm thick. They can be constructed insitu on falsework or by using precast slabs.
Proportions and appearance Composite footbridges typically have a span/depth ratio
Sometimes they can be cast in the fabrication yard, and
of about 20 (depth measured from top of slab to
the complete composite structure transported to site
underside of girder).
and erected.
Short cantilevers outside the lines of the webs will give
A waterproofing membrane is required, plus some form
a better appearance, in the same way as they do for
of durable wearing surface. A combined membrane and
highway bridges. A small upstand is needed at the
wearing course with aggregate dressing, similar to that
edges to provide a mounting for the parapets and to act
used on steel decks, can be used.
as a drainage upstand. A thick edge beam would create a rather heavy appearance.
Parapets As for other forms of construction, parapets must comply with DMRB or Network Rail requirements. The parapet posts are fixed to the concrete slab or edge beam with conventional holding down bolts.
Opposite page: Half through plate girder footbridge, Network Rail Above: Composite curved ‘I’ beam footbridge, Washington
The design of steel footbridges 23
Conceptual design and detailing
3.6 Cable stayed bridges
A single backstay is usually sufficient, anchored to the
Footbridges carry only relatively light loading. However,
girder at the abutment which supports the end of the
when the main span is long, the requirements of
backspan. Further backstays are only needed if the
supporting its own dead load and of providing a
backspan is long and requires intermediate support. The
sufficiently stiff structure lead toward a much more
stays are normally anchored at floor level to longitudinal
substantial structure than would seem appropriate for a
beams. The beams need to be stiff and strong enough to
“mere” footbridge. As a result, an increasingly popular
span between anchor points and they may need to be
solution for longer spans is the use of a cable stayed
fairly deep. A lighter appearance, with shallow beam/floor
arrangement. This effectively divides the span into shorter
depth, might be achieved by using a vierendeel girder and
lengths, for which lighter beams can be used. The pylons
half-through construction. Footbridge pylons are usually
for these bridges also add a strong visual feature which is
steel box or circular sections, for slender appearance,
often welcomed.
ease of construction and economy.
Types of construction
Members and connections
Cable stays can be used with any of the forms of
The cable stays will normally be made from wire rope or
construction previously described, though to complement
spiral strand. Strands are made by winding together, or
the light appearance, a slim form of deck construction is
laying up, a number of galvanised steel wires. Ropes are
likely to be more appropriate for all except the largest
made up of a number of small strands wound together.
spans. Supports can be provided to the main beams at
Ropes and spiral strands have a lower effective modulus
about 10m to 15m spacing, which facilitates the use of a
than solid steel. Parallel wire strands are also available.
slender deck.
Advice should be sought from specialist manufacturers on the selection of strands.
For most footbridges, twin planes of cable stays will normally be used, one to each side of the bridge deck. A pylon at one end of the main span will suffice up to about 100m span. Very long spans may require the use of pylons at both ends. 'A' frame pylons are popular, with the two stay planes inclined. Alternatively, individual pylon legs for each cable plane can be arranged, or a “goal-post” arrangement can be used; the stays can then lie in a vertical plane. Usually, at least two forestays should be provided in each plane – a single stay is hard to justify on economic or appearance grounds. The minimum span for a cable stayed bridge with two forestays is thus around 35m.
24 The design of steel footbridges
Conceptual design and detailing
In the dead load condition the stays are effectively
For very long spans, the deflection under load changes
prestressed. It is important to calculate accurately the
the geometry of the structure. If the sag of the stays is
stretch of the stays in the dead load condition, so that
significant they will act as non-linear springs. Both these
the correct geometry of the structure is achieved.
effects should be taken into account in the analysis.
Provision should be made for length adjustment in the
Computer programs are available which automatically
stays, to accommodate tolerances and errors.
take account of the non-linear effects of varying geometry under load.
Stays must obviously be sufficiently strong to support the beams, but often more significant for small bridges
Whilst ropes and strand can last the life of the bridge,
is the need to provide sufficiently stiff supports to the
experience has shown that they should be
beams and to avoid slack stays which will be easily
inspected from time to time to check for corrosion and
vibrated.
fatigue, particularly at the lower ends. The stay anchorages should be accessible for such inspection
With twin planes of stays, the natural arrangement for
and maintenance. The design should also be such that
the deck structure is with main beams at either edge, to
any one stay can be removed and replaced.
which the stays are attached. The floor then spans transversely between the beams. A single plane of stays
Dynamic response
can only be used where a torsionally stiff box girder is
Cable stayed bridges are relatively flexible and are more
provided; the stays would be attached on the centreline
prone to oscillation under wind or under deliberate
of the bridge. This is not normally convenient for a
excitation by users. An all-steel construction results in a
single footway.
very low level of structural damping, which can allow the oscillations to grow significantly. The dynamic response
As well as provision for adjustment in length during
of the bridge should therefore be checked carefully.
installation, attachment details should also be arranged
Artificial damping, such as tuned mass dampers, can be
such that any stay can be replaced if need be. It is good
provided if necessary.
practice to make sure that the anchorages are as strong at ULS as the breaking load of the stays.
Floor construction Deck construction is usually of stiffened steel plate,
Under the action of live load the stays provide stiff
though timber or reinforced concrete are sometimes
support to the main beams and they thus behave
used instead.
essentially as continuous beams. Axial load is also transmitted to the beams by the stays, so the beams must be designed for the combined load effects.
Far left: Cable stayed ‘I’ beam footbridge, Cumbernauld Left: Royal Victoria Dock Bridge, London Right: Cable stay anchorage
The design of steel footbridges 25
Conceptual design and detailing
3.7 Access ramps and stairs
Handrails must be provided on the inside faces of
Where approach ramps or stairs are needed they are
parapets on stairs and ramps, for safety reasons. A
usually structurally independent, except for the need to
clear gap of at least 40mm is desirable between the rails
be supported at the top end either on the footbridge
and any adjacent members.
superstructure or on a common substructure support. They can therefore be of a structurally different form.
Stairs normally have semi-open risers. Fully open risers
However, it is generally preferable to achieve harmony
are not permitted by BD 29/03.
of appearance between the two and to use a similar construction form.
At the bottom of flights of stairs, details should be chosen which avoid acute corners, since they can trap
Stairs usually require, at most, one intermediate support
debris. To avoid this, stairs can be supported just above
beneath the landing at mid-flight. Ramps require more
the bottom of the flight, so that there is a clear gap
supports and indeed are small bridges themselves. Even
between the underside of the stringers and ground level.
for ramps, the number of intermediate supports should be kept as small as possible, with spans of at least 10m. Supports should also be as simple as possible – a T-shaped column and crosshead should be sufficient in most cases (provided that resistance to impact is not necessary). Where supports may be subject to impact loads, they will need to be significantly more substantial. The foundations will also have to be larger. In these circumstances the designer can choose either reinforced concrete columns or a robust steel structure. Since landings are nominally level, care needs to be exercised to avoid ponding of water and accumulation of debris. Extra drain holes in these areas together with a small fall will suffice.
Below: Stairs showing open treads and handrails Right: Scissor ramp
26 The design of steel footbridges
Conceptual design and detailing
3.8 Bearings and expansion joints
Consideration should be given to fixing long ramps at
The provisions for restraint or the accommodation of
the bottom end. Maximum longitudinal movement at the
movement due to expansion or other reasons depends
far end therefore occurs where the columns are tallest
very much on the general arrangement of the bridge,
and most able to accommodate it.
ramps and stairs. Stairs should preferably be fixed at the bottom and When the bridge spans between bankseats or
bolted to column supports. This effectively provides a
abutments, expansion joints are needed, and the
restraint for any ramp or bridge connected to the top of
structure will sit on bearings. At one end the bearings
a straight flight.
may be fixed longitudinally, but if laminated bearings are used, both ends can be 'free', as long as the bearings
For light all-steel bridges, all support details, bearings or
can transmit any longitudinal forces.
direct connections to columns, should be designed to resist at least a nominal uplift.
Expansion joints need to accommodate movement ranges of about 20mm, depending on span. Even at ends which are longitudinally restrained there has to be some provision for movement at deck level, owing to rotational movements under live load. For footbridge expansion joints, a simple detail should be chosen, one which does not collect dirt or debris and which can be dismantled for maintenance if required. A simple leaf plate fixed to the bridge on one side and sliding on a second plate on the fixed side can usually be arranged in most circumstances. Particular attention should always be given to the avoidance of steps facing uphill, even as little as 5mm, since they always tend to accumulate material washed down by run-off. Where the bridge spans between steel column supports, no bearings are needed. The bridge is simply bolted down to the tops of the columns. Expansion is accommodated by flexing of the columns and no expansion joints are needed.
Below: Expansion joint leaf plate Right: End bearing box girder
The design of steel footbridges 27
Design codes, standards and guidance
4. Design codes, standards and guidance 4.1 British Standards
4.5m of the edge of the carriageway and to
In most circumstances, the British Standard BS 5400 (1)
superstructures which have less than 5.7m clearance
will apply to the design and construction of footbridges.
above the surface of the carriageway.
In some cases, possibly where the bridge is connected to a building, BS 5950 (2) might be called for.
Other standards and advice notes also relate to the design of footbridges. Design criteria for footbridges are
For design of steel and composite structures, the
given in BD 29 (5). Highway cross sections and headroom
following Parts of BS 5400 are applicable
are given in TD 27 (6). Selected information from these two documents is included in section 3. Standard TD 27
Part 2
Specification for loads
specifies a minimum clearance for footbridges of 5.7m.
Part 3
Code of practice for design of steel bridges
This avoids the necessity of applying the impact
Part 4
Code of practice for design of concrete bridges
requirements of BD 37 on the superstructure, which
Part 5
Code of practice for design of composite bridges
would be particularly onerous on a light structure such
Part 6
Specification for materials and workmanship, steel
as a footbridge.
These codes cover all aspects of design for footbridges
Where supports need to be close to the edge of the
of beam and truss construction. Design of tubular joints
carriageway, they are required to be provided with
is not covered in detail within Part 3 – see section 4.4
protective plinths and designed for impact loads. Where
for further guidance. Similarly, the design of cable stays,
they can be kept back from the carriageway, perhaps to
the strands and their anchorages, are not covered by
span a footway beside the road, the consequent savings
these codes – refer to section 4.5 for guidance.
in the cost of the substructure should be considered. Supports between carriageways should also be avoided
Dimensional and safety requirements for stairs are given
(unless they can be located more than 4.5m from the
in BS 5395 (3). These requirements are amended slightly by
road, which is not usually feasible).
the departmental standard for footbridges. The design of parapets on footbridges is referred by
4.2 Departmental standards
BD 29 to the Interim Rules for Road Restraint Systems
The requirements of the four UK highways authority (the
IRRRS). The IRRRS (7) is a Highways Agency document,
Highways Agency, the Scottish Executive, the Welsh
not currently part of the DMRB, although it does state
Assembly Government and the Department for Regional
that it supersedes a number of DMRB documents, such
Development Northern Ireland) are set out in the Design
as the earlier BD 52/93. The IRRRS refers to BS 7818 (8),
Manual for Roads and Bridges (DMRB). This manual is a
which gives dimensional requirements, design
collection of individual standards (BD documents) and
requirements and a specification for construction of
advice notes (BA documents).
metal parapets, and it specifies the design loading classes for rails, posts and infill.
Each of the design code parts of BS 5400 is implemented by a BD standard (4), and some of
4.3 Railway standards
these standards vary certain aspects of the part that
Network Rail are particularly concerned with prevention
they implement (notably BD 37 for Part 2 and BD 16 for
of unauthorised access and are legally obliged to fence
Part 5). For footbridges, a particular point to note is that
its boundaries. Network Rail and the Railway Safety and
the requirements in relation to loads resulting from
Standards Board also have more stringent requirements
collision of vehicles with the structure have been
in relation to collision loads. Reference should be made
significantly modified. The impact loads and the
to GC/RC5510: Recommendations for the Design of
circumstances in which they should be applied are
Bridges (27). The following comments are based on advice
specified in BD 60 & BD 37 (the DMRB version of BS
given in recent projects.
5400 Part 2) and an amendment to it. The provisions relate to the impact loads on supports located within
28 The design of steel footbridges
Design codes, standards and guidance
In considering the prevention of unauthorised access,
be found in a Corus publication (12). Adequacy of both
not only must the pedestrian face of the bridge be
the bracing member and the chord member must be
designed to be non-climbable, it must also be
checked. If necessary, reinforcement of the joint can
impossible to climb along the outer face from the ends
be designed.
of the bridge – this usually means that trusses are clad chords or parapets must be arranged so that they are
4.5 Design of cable stayed and suspension bridges
impossible to walk along.
For general guidance on the design of cable stayed
either side of the diagonals at the ends. The top flanges,
bridges, reference should be made to standard texts, The zone within 4.5m of the outermost running rail is
such as Walther (14) or Troitsky (15). These are
considered a danger zone; if any support is located
comprehensive books, but they do include specific
within that zone, collision effects must be considered.
comment on footbridges with illustrated examples.
Any substructure column must be able to withstand an impact load, and the superstructure must be able to
The provisions of BS 5400 do not cover in detail the
continue to carry some live load without support from
design of wire ropes or similar elements, nor is there any
the column. Design recommendations are given in
other appropriate national code. The designer therefore
GC/RC5510.
needs to base his detailed design on an empirical approach, based on load effects calculated in the usual
4.4 Design of hollow section joints
manner according to BS 5400 and adopting the general
The design of hollow section joints is not fully covered
objectives of the code.
by the requirements of BS 5400: Part 3. There is however extensive background research into the
Details of the specification of wire ropes and strands
behaviour of tubular joints and various documents have
can be found by reference to BS 302 (16), and of the
been published which provide guidance.
sockets by reference to BS 463 (17). The cold drawn wire used for ropes and strands does not have a linear
For triangulated structures, where the joints transmit
stress/strain relationship, with a definite yield plateau,
essentially axial loads from one member to another, the
as does structural steel. The relationship is generally
design of the joint involves checks on (a) the adequacy
smooth, with decreasing tangent modulus as load
of the welds at the end of the member and (b) the
increases. Design of stays has therefore been based
bending of the walls of the hollow sections (which are
traditionally on permissible stresses calculated by
subjected to out of plane forces).
dividing the ultimate or breaking strength by a suitably large factor (i.e. a working stress philosophy). In the
Guidance literature is available both for circular sections and for rectangular sections. General guidance is given
absence of formal codes on a limit state basis, division of this strength by a partial factor γm of about 2.0 at
in CIDECT publications (9), (10) & (11) and guidance in relation
ULS, in conjunction with normal values of γƒ1 and γƒ3
to BS 5950: Part 1 is given in a Corus publication. (12)
gives results consistent with the traditional approach.
Design rules in both of these documents may be applied using partial factors appropriate to BS 5400. Similar
Guidance on the design of suspension bridges can be
rules will be included in EN 1993-1-8 (13).
found in texts such as Pugsley (18). The tensile elements may be wire rope or strand, as for cable stayed bridges,
The extent of guidance on the design of joints for the
though high tensile steel rods may be used for the main
moments associated with vierendeel action (or with
tension members.
U-frame action) is more limited, though there has also been research on this topic. A stiffer and more efficient joint is achieved when the bracing member is the same width (normal to the moment plane) as the chord member. Design guidance for this type of joint can also
The design of steel footbridges 29
Design codes, Standards and Guidance
4.6 Design of steel and composite bridge beams
For Network Rail owned bridges, the protective
Guidance on the design of composite highway bridges
Network Rail line standard RT/CE/S/039 (28). Advice is
is given in a series of publications by The Steel
given in RT/CE/C/002 (29).
treatment and walkway surfacing must comply with
Construction Institute (19). These can be used as general guidance in the design of footbridges in accordance
For other bridges, the HA specifications, or alternatives,
with BS 5400, both for composite beam and all-steel
may be used, with the clients agreement.
beam designs. In some circumstances, Weather Resistant Steels might Guidance on a wide range of practical aspects related to
be used, provided that environmental constraints can be
steel bridge construction is given in a series of Guidance
met. (23), (24)
Notes produced by the Steel Bridge Group (31).
4.9 Steel materials 4.7 Dynamic response
Steel material for plates, rolled sections and structural
Limitations on the dynamic response of footbridges are
hollow sections is covered by British Standards
given in HA standard BD 37. The vertical natural
EN 10025, EN 10210 (25). Information about the products
frequency of many footbridges will be below 5Hz and
available from Corus (26) can be obtained from the Corus
the response must be checked. If the horizontal natural
Construction Centre. Contact details are on the back of
frequency is less than 1.5Hz, checks must be made for
this brochure.
possible lateral excitation. The susceptibility of a footbridge to aerodynamic excitation has to be checked in accordance with BD 49 (20). Bridges under 30m span are unlikely to be susceptible. Detailed rules are given in BD 49 for bridges that are susceptible.
4.8 Protective treatment For bridges subject to highways authority requirements, the protective treatment specifications should be selected from those listed in the guidance notes to the Specifications for Highway Works (SHW) (21), (22). When using those notes, access conditions should normally be taken as “difficult”, which will result in use of metal spray for the first coat. Galvanising may be suitable for small components, such as parapets.
30 The design of steel footbridges
Flow charts
5. Flow charts Figure 5.1: Flow diagram for the design of footbridges
DMRB Standards for highway cross section and headroom
Schemespecific details
DMRB Standards for footbridges
Determine geometric constraints
Choose structural form
Trusses and vierendeel girders
Steel beams
Composite beams
Cable stayed bridges
(Figure 5.2)
(Figure 5.3)
(Figure 5.4)
(Figure 5.5)
Ramps and stairs
Far left: Renaissance Bridge, Bedford Left: Smithkline Beecham, Marlow
The design of steel footbridges 31
Flow charts
Figure 5.2: Flow chart for trusses and vierendeel girders
Global analysis Global analysis 12.3
Longitudinal effects
Yes
Lateral effects
No Triangulated truss?
Check combined bending and axial effects
Check as a ‘truss’
Check adequacy of lateral bracing
12.1
12.6
Tension members
Compression members
Tension members
Compression members
Check adequacy at ULS
Determine effective lengths
Check adequacy at ULS
Determine effective lengths
12.4 12.5
12.2 11.5.1
Check adequacy at ULS
Strength adequate? Yes
10.6.1
11.5.2 9.9
Check adequacy at ULS
Strength adequate? Yes
Slender or compact? Yes
I=a* 12.5.1
10.6.2 10.6.3 9.9
Check U-Frame action
12.5
Strength adequate? Yes
Strength adequate? 12.2.3 No Yes
Check adequacy at SLS 12.2.3 10.6.2 10.6.3 Strength adequate?
Yes
Satisfactory
* For in-plane buckling, use the length between intersections (a); for out of plane buckling use (a) if there are effective lateral restraints or use 12.5.1 otherwise.
32 The design of steel footbridges
Flow charts
Figure 5.3: Flow chart for steel beams Global analysis
No
Yes Box girder?
Determine limiting stresses for LTB
Determine effective section
9.6 9.7 9.8
9.4
Determine limiting stresses and check capacities
Check ULS moment and shear capacities
9.10 9.11
9.9
Check diaphragms and crossframes
Unsymmetric compact section? No
Yes
9.16 9.17
Check adequacy at SLS
9.9.8
Check bearing stiffeners 9.14
All strengths adequate?
All strengths adequate? Yes
Yes
Satisfactory
The design of steel footbridges 33
Flow charts
Figure 5.5: Flow chart for cable stayed bridges
Figure 5.4: Flow chart for composite beams
Global analysis
Global analysis
Check beam adequacy at ULS
Check adequacy of members as trusses or beams
Non-linear analysis if deflections or DL sag of stays are significant
9.9 Include effects during replacement of each stay Check slab adequacy at ULS
Check adequacy of cable stays
5/6.1.2 4/4.8.3
Unsymmetric compact I-beam?
Check local effects at cable anchorages
Yes
No
Check beam adequacy at SLS
Check adequacy of pylon
9.9.8 9.9.5.2
Check slab adequacy at ULS
Determine dead load prestress in stays
5/5.2.4.2 5/5.2.6 4/4.1.1.1
Check bearing stiffeners All strengths adequate? 9.14 Yes
All strengths adequate? Yes
Satisfactory
34 The design of steel footbridges
Satisfactory
References
6 References 1.
British Standards Institution BS 5400: Steel, concrete and composite bridges – Parts 1 to 10, BSI, London (various dates)
2.
British Standards Institution BS 5950, Structural use of steelwork in building, BSI, London
3.
British Standards Institution BS 5395, Stairs, ladders and walkways, BSI, London
4.
Highways Agency Design manual for roads and bridges, Volume 1 Section 3: BD 13, Design of steel bridges: use of BS 5400 Part 3; BD 16, Design of composite bridges:use of BS 5400: Part 5; BD 37; Loads for highway bridges, BD 60; The design of highway bridges for vehicle collision loads, The Stationery Office
5.
6.
Highways Agency Design manual for roads and bridges, Volume 2, Section 2, BD 29 Design criteria for footbridges, The Stationery Office Highways Agency Design manual for roads and bridges, Volume 6 Section 1, TD 27 Cross-sections and headroom, The Stationery Office
20. Highways Agency Design manual for roads and bridges, Volume 1, Section 3, BD 49, Design rules for aerodynamic effects on bridges, The Stationery Office 21. Highways Agency Manual of contract documents for highway works, The Stationery Office; Volume 1: Specifications for highway works series 1900, Protection of steel against corrosion Volume 2: Notes for guidance on the specification for highway works, Series NG1900, Protection of steelwork against corrosion 22. Corus Corrosion Protection of Steel Bridges, 2002 23. Highways Agency Design manual for roads and bridges, Volume 2, Section 3, BD 7, Weathering steel for highway structures, The Stationery Office 24. Corus Weathering Steel Bridges, 2002 25. British Standards Institution BS EN 10025: 2004, Hot rolled products of structural steels. BS EN 10210, Hot finished structural hollow sections of non-alloy and fine grain structural steels, Part 1: 1994 Technical delivery requirements.
7.
Highways Agency Interim Requirements for Road Restraint Systems (IRRRS), The Highways Agency, 2002 (contact the Highways Agency for copies)
8.
British Standards Institution BS 7818:1995 Specification for pedestrian restraint systems in metal
26. Corus Product & Technical brochures Structural sections Structural plates Structural hollow sections
9.
CIDECT Design guide for circular hollow sections (RHS) under predominantly static loading, Verlag TÜV, Cologne, 1991
27.
10. CIDECT Design guide for rectangular hollow sections (RHS) joints under predominantly static loading, TÜV, Cologne, 1992 11.
CIDECT Structural stability of hollow sections, Verlag TÜV, Cologne, 1992
12. Corus Tubes Design of SHS welded joints, CT16, Corus Tubes, Corby 2001 13. British Standards Institution prEN 1993-1-8, Design of Steel Structures, Design of Joints, December 2003 14. Walther, R. et al, Cable stayed bridges, Thomas Telford, London, 1988 15. Troitsky, M. S., Cable-stayed bridges, BSP, Oxford, 1988 16.
British Standards Institution BS 302, Stranded steel wire ropes, BSI, London
17.
British Standards Institution BS 463: Part 2:1970 Specification for sockets for wire ropes (metric units), BSI, London
18.
Pugsley, A. The theory of suspension bridges, Edward Arnold, London, 1957
Railway Safety and Standards Board Group Standard GC/RC5510: Recommendations for the Design of Bridges
28. Network Rail Line Standard RT/CE/S/039; Specification RT98 - Protective Treatment for Railtrack Infrastructure 29. Network Rail Line Standard RT/CE/C/002: Application and Reapplication of protective treatment to Railtrack Infrastructure 30. Corus Tubes Connection flexibility in tubular U frame footbridges RT 451, December 1994 31.
Evans, J. E. and Iles, D. C. Steel Bridge Group: Guidance notes on best practice in steel bridge construction (P185), The Steel Construction Institute, 2002
19. Iles, D. C. Design guide for composite highway bridges (P289) Design guide for composite highway bridges: Worked examples (P290) The Steel Construction Institute, 2001
The design of steel footbridges 35
www.corusgroup.com Care has been taken to ensure that this information is accurate, but Corus Group plc, including its subsidiaries, does not accept responsibility or liability for errors or information which is found to be misleading. Copyright 2005 Corus Designed and produced by Orchard Corporate Ltd.
Corus Construction & Industrial PO Box 1 Brigg Road Scunthorpe North Lincolnshire DN16 1BP T +44 (0) 1724 405060 F +44 (0) 1724 404224 E
[email protected] www.corusconstruction.com English language version
CD:3000:UK:01/2005