ELECTRICAL MECHANICAL COMPLETION CHECK SHEETS
MULTI CABLE TRANSIT
SANTOS (SAMPANG ) PTY LTD
Project Name
: WORTEL FIELD DEVELOPMENT PROJECT
Customer
: SANTOS (Sampang) Pty. Ltd.
Drawing Reff. / Rev
:
System / Sub No.
: 9820-U-009
Single Line No. / Rev
:
System Desc.
: Control Room Building System
Location / Area
: E/I Building
Sub System Desc.
: 9820-U-009-1
E03MC
Tag No.
No.
Inspection Check List
1
Check frame material have correct specifiction and size
2
Check frame design accordance with design drawing
3
Check frame have correct dimension accordance to design drawing
4
Check that frame have completed fabrication work
5
Check that MCT frame location refer to layout
6
Check that support have completed finishing work
7
Check MCT specification specification refer to MTO and company specification specification
8
Check that MCT installed at correct location refer to layout
9
Check that MCT installation arrangement arrangement refer to installation detail
10
Check that MCT accessories are installed correctly
11 12 Notes :
Description Company
Signature
Print Name Date
Performed by
W itnessed / Approved by
W itnessed / Approved by
ELECTRICAL MECHANICAL COMPLETION CHECK SHEETS
MULTI CABLE TRANSIT
SANTOS (SAMPANG ) PTY LTD
Project Name
: WORTEL FIELD DEVELOPMENT PROJECT
Customer
: SANTOS (Sampang) Pty. Ltd.
Drawing Reff. / Rev
: 9820-64-352-2
System / Sub No.
: 9820-U-009
Single Line No. / Rev
:
System Desc.
: Control Room Building System
Location / Area
: E/I Building
Sub System Desc.
: 9820-U-009-1
E03MC
Tag No. 9820-MCT-E01
No.
Inspection Check List
1
Check frame material have correct specifiction and size
2
Check frame design accordance with design drawing
3
Check frame have correct dimension accordance to design drawing
4
Check that frame have completed fabrication work
5
Check that MCT frame location refer to layout
6
Check that support have completed finishing work
7
Check MCT specification refer to MTO and company specification
8
Check that MCT installed at correct location refer to layout
9
Check that MCT installation arrangement refer to installation detail
10
Check that MCT accessories are installed correctly
N I D O K O M A S
P A L
S A N T O S
Notes :
Description Company
Signature
Print Name Date
Performed by
Witnessed / Approved by
Witnessed / Approved by
ELECTRICAL MECHANICAL COMPLETION CHECK SHEETS
MULTI CABLE TRANSIT
SANTOS (SAMPANG ) PTY LTD
Project Name
: WORTEL FIELD DEVELOPMENT PROJECT
Customer
: SANTOS (Sampang) Pty. Ltd.
Drawing Reff. / Rev
: 9820-64-352-2
System / Sub No.
: 9820-U-009
Single Line No. / Rev
:
System Desc.
: Control Room Building System
Location / Area
: E/I Building
Sub System Desc.
: 9820-U-009-1
E03MC
Tag No. 9820-MCT-E02
No.
Inspection Check List
1
Check frame material have correct specifiction and size
2
Check frame design accordance with design drawing
3
Check frame have correct dimension accordance to design drawing
4
Check that frame have completed fabrication work
5
Check that MCT frame location refer to layout
6
Check that support have completed finishing work
7
Check MCT specification refer to MTO and company specification
8
Check that MCT installed at correct location refer to layout
9
Check that MCT installation arrangement refer to installation detail
10
Check that MCT accessories are installed correctly
S A N T O S
Notes :
Description Company
Signature
Print Name Date
Performed by
Witnessed / Approved by
Witnessed / Approved by
ELECTRICAL MECHANICAL COMPLETION CHECK SHEETS
MULTI CABLE TRANSIT
SANTOS (SAMPANG ) PTY LTD
Project Name
: WORTEL FIELD DEVELOPMENT PROJECT
Customer
: SANTOS (Sampang) Pty. Ltd.
Drawing Reff. / Rev
:
System / Sub No.
:
Single Line No. / Rev
:
System Desc.
:
Location / Area
:
Sub System Desc.
:
E03MC
Tag No. 9820-MCT-E03
No.
Inspection Check List
1
Check frame material have correct specifiction and size
2
Check frame design accordance with design drawing
3
Check frame have correct dimension accordance to design drawing
4
Check that frame have completed fabrication work
5
Check that MCT frame location refer to layout
6
Check that support have completed finishing work
7
Check MCT specification refer to MTO and company specification
8
Check that MCT installed at correct location refer to layout
9
Check that MCT installation arrangement refer to installation detail
10
Check that MCT accessories are installed correctly
N I D O K O M A S
P A L
S A N T O S
Notes :
Description Company
Signature
Print Name Date
Performed by
Witnessed / Approved by
Witnessed / Approved by
ELECTRICAL MECHANICAL COMPLETION CHECK SHEETS
MULTI CABLE TRANSIT
SANTOS (SAMPANG ) PTY LTD
Project Name
: WORTEL FIELD DEVELOPMENT PROJECT
Customer
: SANTOS (Sampang) Pty. Ltd.
Drawing Reff. / Rev
:
System / Sub No.
: 9820-U-009
Single Line No. / Rev
:
System Desc.
: Control Room Building System
Location / Area
: E/I Building
Sub System Desc.
: 9820-U-009-1
E03MC
Tag No.
No.
9 8 2 0 - M
Inspection Check List
C T E - 0 6
1
Check frame material have correct specification and size
2
Check frame design accordance with design drawing
3
Check frame have correct dimension accordance to design drawing
4
Check that frame have completed fabrication work
5
Check that MCT frame location refer to layout
6
Check that support have completed finishing work
7
Check MCT specification refer to MTO and company specification
8
Check that MCT installed at correct location refer to layout
9
Check that MCT installation arrangement refer to installation detail
10
Check that MCT accessories are installed correctly