Alshaya Property Development Co. W.L.L.
BURJ ALSHAYA FOUR SEASONS HOTEL AL SOOR STREET, KUWAIT
DESIGN DEVELOPMENT (Core & Shell) BP 3 Structural Works Issued for Tender
DOCUMENT IV BILLS OF QUANTITIES 17th May2012
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
BILLS OF QUANTITIES LIST OF CONTENTS
PAGE NO.
GENERAL NOTES
GN1 - GN/3
TENDER'S DECLARATION
TD1
PREAMBLES
P1 - P9
BILL NO. 01: GENERAL REQUIREMENTS
1/1/1 - 1/1/5
BILL NO. 02: PODIUM
2/2/1 - 2/Summ/1
BILL NO. 03 : OFFICE TOW ER
3/2/1 - 3/Summ/1
BILL NO. 04 : HOTEL TOW ER
4/2/1 - 4/Summ/1
BILL NO. 05 : PROVISIONAL SUMS
5/PS/1 - 5/PS/4
TENDER ADJUSTMENT SCHEDULE
TAS/1 - TAS/4
MAIN SUMMARY
MS/1
ANALYSIS OF PRICES
AP/1
DAYW ORK SCHEDULE
DW /1 - DW -8
KEO/07-2345-0011/BP3-Structural KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
IND/1
Index
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
BILLS OF QUANTITIES LIST OF CONTENTS
PAGE NO.
GENERAL NOTES
GN1 - GN/3
TENDER'S DECLARATION
TD1
PREAMBLES
P1 - P9
BILL NO. 01: GENERAL REQUIREMENTS
1/1/1 - 1/1/5
BILL NO. 02: PODIUM
2/2/1 - 2/Summ/1
BILL NO. 03 : OFFICE TOW ER
3/2/1 - 3/Summ/1
BILL NO. 04 : HOTEL TOW ER
4/2/1 - 4/Summ/1
BILL NO. 05 : PROVISIONAL SUMS
5/PS/1 - 5/PS/4
TENDER ADJUSTMENT SCHEDULE
TAS/1 - TAS/4
MAIN SUMMARY
MS/1
ANALYSIS OF PRICES
AP/1
DAYW ORK SCHEDULE
DW /1 - DW -8
KEO/07-2345-0011/BP3-Structural KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
IND/1
Index
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
GENERAL NOTES
Total of Bills of Quantities The Tenderer should note that the total of all the items in the Bills of Quantities including amounts in respect of Provisional Sums must be equal to the total shown in the Form of Tender against such Bills of Quantities. Quantities The Drawings, Specifications and all other Contract Documents are complementary and if any item is included in any one of them, it shall be considered as if it is included in all of them. Notice is drawn to the f act that the quantities provided in the Bills of Quantities are approximate and the Tenderer should check the same against the information provided in the Drawings, Specifications and other Tender Documents including checking the Site conditions. Should the Tenderer feel that adjustments of any quantities or the addition of any further items are necessary, he shall itemise all such differences or missing items in the Tenderer's Adjustment Schedule immediately immediately prior to the Summary of the Bills of Quantities giving full details of revised quantities, descriptions, rates and extensions. If the Bills of Q uantities do not contain items of work that are shown or required in any of the other Contract Documents, and the Employer wishes wishes to omit or vary such works from the Scope of Work in accordance with the Conditions of Contract, then such Works shall be valued and the Lump Sum adjusted accordingly.
KEO/07-2345-0011/BP3-Structural KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
GN/1
General Notes
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
Units of Measurement Measurement The units of measurement adopted in the Bills of Quantities shall prevail throughout the Contract notwithstanding notwithstanding any trade, local or general custom and shall be used in the adjustment of all measured variations variations or further measurement or remeasurement. remeasurement. All works shall be be measured net as fixed and finished in accordance with the Drawings Drawings and no allowance allowance made for waste. The Units of measurement used herein are : Volume
- Cubic Metre
: m3
Area
- Square Metre
: m2
Length
- Linear Metre
:m
Number Weight
: no - Kilogrammes/Tonnes
: kg/T
Lump sum
: item
Lump sum
: LS
Group
: group
Set
: set
Provisional Provisional Sum
: ps
Pair
: pair
In item descriptions, dimensions dimensions involving involving metres are given in metres metres (Abbreviated m) parts of a metre are given given in centimetres (Abbreviated (Abbreviated cm) or millimetres millimetres (Abbreviated (Abbreviated mm). In certain descriptions dimensions dimensions may be given in British Units viz. inches (Abbreviated (Abbreviated in or ".) Descriptions General directions and descriptions of work and materials given in the Specification are not necessarily repeated repeated in these Bills Bills of Quantities. Reference shall be made made to the Specifications for this information.
Where items in the Bills contain the phrase "as specified", the Contractor shall refer to the Specifications and the Drawings for the full description and the Contractor shall include in his rates for complying with this clause clause whether the phrase phrase "as specified" appears appears in the text or not. Where the word "allow" occurs the cost of the item shall be at the risk of the Contractor.
KEO/07-2345-0011/BP3-Structural KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
GN/2
General Notes
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
Rates The rates to be inserted in the Bills of Quantities are for those works referred to in the Tender Documents and shall cover the execution, completion and defects maintenance of the Works, finished complete in every respect and shown and described in the Tender Documents. These rates shall be the full inclusive value of the work described under the several items including all costs and expenses which may be required in and for the construction of the work described. The costs and expenses of all the general risks, liabilities and obligations, set forth or implied in the conditions of contract shall be deemed to be included in the rates for the work in Divisions 2 to 31 or alternatively may be priced in Division 1. Division 1 of the Bills of Quantities provides the tenderer the opportunity for pricing Division 1 General Requirements of the Specification and also for pricing Documents I and II, Tendering Procedures and Conditions of Contract if required. Where any of these items are not priced it shall be deemed that all costs associated with this section of the tender documents are deemed included in the rates for the work. The Contractor shall be deemed to have fully considered all the conditions, obligations and requirements of the Tender Documents before entering the respective rates against the items included in the Bills of Quantities. Rates should be entered against all priceable items included in the Bills of Quantities, whether quantities are stated or not. Lump sums covering more than one item shall not be given. Items against which no rate is entered will be considered as covered by the other rates in the Bills. Builder's work in connection with specialist sub-contractors is deemed to be included in the rates for those sub-contract works unless specifically mentioned within the Bills. The Contractor must obtain particulars of the position in which chases, holes, mortises, etc., will be required to avoid any unnecessary cutting away. No claims will be considered for the extra cost of cutting away work already built in consequence of any neglect on the part of the Contractor to obtain sufficient particulars beforehand.
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
GN/3
General Notes
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
BILLS OF QUANTITIES
TENDERER'S DECLARATION
I/We declare that I/we have taken into consideration when pricing the individual unit rates and Tender Sum that : The Rates in the Bills of Quantities will be deemed to include for the full cost of t he Works as described in all documents to provide and maintain a complete construction and installation. I/We declare therefore that all the aforesaid has been considered as declared and that I/we shall not make any claim of any nature whatsoever on account of the aforesaid. The total lump sum contract price shall be deemed to include for the full costs and expenses of whatever nature necessary for any work shown anywhere in the Tender Documents, although such work may not be specifically mentioned in the Bills of Quantities.
THE TENDERER
LOCAL PARTNER OR AGENT
Name : Signature : Capacity : Address :
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
TD/1
Tenderer's Declaration
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
PREAMBLES TO THE BILLS OF QUANTITIES
GENERALLY A
The Bills of Quantities herein, including all notes and instructions, form an integral part of the Contract Documents. However, the descriptions contained in the Bills of Quantities for each item are not necessarily complete.
B
The rates for each item must be comprehensive and must include for complying with the Specifications, and all obligations under the Contract including all matters and things necessary for the proper design, construction, completion and maintenance of the Works. No claims for additional payment will be allowed for any error or misunderstanding by the Contractor of the work involved.
C
The rates for each item must allow for all costs and expenses in complying with all general risks, liabilities and obligations set forth in the Drawings, Specifications and Conditions of Contract, including but not limited to t he following : i)
Labour, supervision and all associated costs.
ii)
Materials, goods, consumables and all associated costs.
iii)
Fitting and fixing materials and goods in position
iv)
Provision of plant, equipment and tools
v)
Restriction of working areas and procedures
vi)
Temporary works
vii)
Establishment, administration and overhead charges and profit
viii)
All applicable taxes, duties, charges, government levies, landing charges, transport and the like.
D
The prices and rates entered by the Contractor against items in the Bills of Quantities shall apply throughout the duration of the Contract until the issuance of the Taking Over Certificate to the execution of these items in any location and, except where otherwise provided for, to any additional work ordered by the Engineer and/or the Employer.
E
A price or rate is to be entered against each item in the Bills of Quantities and any item left unpriced will be deemed to be included for elsewhere in the Bills of Quantities and hence the rate for that item will be taken as Nil.
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
P/1
Preambles
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
A
The description of each item (which description shall imply references to any heading, subheading, preamble or other clause of item which shall apply) shall be held to include all materials, workmanship, taxes, duties, charges, Government levies, landing charges, transport, profit, overheads and all other incidental costs to complete the W orks.
B
The Contractor shall not use these Bills of Quantities as a construction programme or for the purposes of ordering materials or arranging sub-contracts. The references for these activities shall be the Drawings, Specifications and Addenda issued by the Engineer.
C
These preambles are to be read in conjunction with the item descriptions in the Bills of Quantities.
D
„As described‟ means as described in the Specifications. ABBREVIATIONS
E
In the Specification and Bills of Quantities the following abbreviations have the meanings hereby assigned to them :B.S.
means the specification issued by the British Standards Institution.
C.P.
means the Code of Practice issued by the B.S.I.
AASHTO
means the specification issued by the American Association of the State Highway and Transportation Officials
ASTM
means the specification issued by the American Society for Testing and Materials.
PD
means British Standard Provisional Document
DD
means British Standard Draft for Development
Approved/ Approval
means approved by or approval of the Engineer in writing
Submitted/ Submit
means submitted to or submit to the Engineer in writing
Accepted/ Acceptance
means accepted by or acceptance of the Engineer in writing
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
P/2
Preambles
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
Inspected/ Inspection
means inspected by or inspection of the Engineer
Directed
means directed by the Engineer in writing
Authorised/ Authority
means authorised by or authority of the Engineer in writing
Required
means required by the Engineer in writing
Rejected
means rejected by the Engineer in writing
In writing
above shall also mean verbally later confirmed in writing
O.O.E.A.A.
means or other equal and approved
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
P/3
Preambles
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
PREAMBLES A
Rates for various items throughout the Bills of Quantities shall include, unless otherwise stated or measured, for cutting of every description and the consequent waste, for work in girths, widths or heights of less than 300 mm and for all short lengths.
B
Rates for all work shall include for protection and provision of samples.
C
All measurements are net and the rates shall include for all laps, waste, working space and trade or traditional allowances.
D
The pricing of materials shall take account of the following :
E
i)
Pricing Preambles and Specifications shall apply reciprocally between sections of the works unless otherwise described
ii)
Materials shall be of the quality specified unless otherwise directed by the Engineer.
iii)
All materials shall be transported, handled, stored and fixed in accordance with the printed instructions or recommendations of their manufacturers or suppliers.
iv)
Protection of completed work, all casings, temporary coverings, making good, cleaning, polishing and clearing away upon completion.
The Contractor should ascertain, before the work is put in hand, the particulars of positions in which chases, holes, mortices and the like will be required to be formed or left. No claim for the extra cost of cutting away work already built due to the Contractor‟s failure to ascertain these particulars will be admitted.
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
P/4
Preambles
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
PRICING A
The prices shall be comprehensive and must include for complying in all respects with the Instructions to Tenderers, Conditions of Contract, Specifications and Drawings and for all matters and things necessary for the proper construction, completion and maintenance of the whole of the Works. No claims for additional payment will be allowed for any error or misunderstanding by the Contractor of the W ork involved.
B
Lump sums shall not be given where unit rates are applicable.
C
Where the word “allow” is used, the cost of the item shall be the responsibility of the Contractor.
D
The amounts set against any item of overhead shall include for all costs in connection with letters of credit, bank charges, interest charges and insurance after the materials, come under the control of the Contractor.
E
The rates inserted will be used to determine the amount of the Contractor‟s Interim Payments.
F
The Tenderer shall submit the analysis of the “Tender Sum” with a full and detailed rate breakdown of all the BOQ items including spare parts items, together with their tender submission. The breakdown is to show the actual calculations of the General Items, Labour, Plant and Materials, Cost for the Works, the build-up of measured rates with on-costs and overheads and any other allowances used to arrive at the Tender Price. In addition the Tenderer/Contractor will be required to provide the Engineer within 48 hours with a full and detailed breakdown/ any other information if requested.
G
The rates inserted in the Schedule of Dayworks if any, shall be deemed to be the rates used by the Contractor in making up rates for works items in all parts of the Bills of Quantities.
VARIATIONS H
The rates inserted in the Bills of Quantities with the application of the adjustment item will be used to value any variation to the Works, whether omissions or additions. The Contractor shall not be entitled to payment for profit and overheads on the value of any Work s omitted.
SHOP DRAWINGS J
The rates in the appropriate section shall include for design of the elements as specified in the Contract and for providing working drawings, shop drawings, schedules, specifications, calculation, etc., and for obtaining the Engineer‟s approval.
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
P/5
Preambles
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ADJUSTMENT A
The adjustment item shown on the Summary page, if any, shall apply to all Bills (excluding Provisional Sums) unless clearly indicated otherwise. In the event that a Contract is awarded on the basis of this tender, the Adjustment Item, calculated as a percentage of the total tendered sum or the total for the Bills indicated, shall be applied to all rates and items as entered in the Bills of Quantities (including any addenda) and the Contract shall be signed based on the inclusion of the adjusted rates and items. During this Contract, the adjusted rates and items shall be applied during any remeasured works and in the evaluation of Variation Orders. NOMINATED SUB-CONTRACTORS General Attendance on Nominated Sub-Contractors Rates for Assistance by the Contractor in respect of work by Nominated Sub-Contractor or Government or Public Authority shall include, but not be limited to: i) ii) iii) iv) v) vi) vii) viii) ix) x) xi)
xii) xiii) xiv)
xv)
Use of Contractor's administrative arrangements. Use of constructional plant. Use of Contractor's facilities, including messrooms, sanitary accommodation and welfare facilities. Use of temporary works. Space for Sub Contractor's or Authority's offices and stores. Clearing away rubbish. Scaffolding, including the provision, maintenance and removal of any special scaffolding required. Unloading, distributing and placing in position all plant, machinery etc. Provision of electric power for sub-contractor's on-site work, and for lighting, including any 3 - phase or heavy supplies which may be required. Provision of water for the works, including requirements for testing and commissioning Unloading all plant and materials, placing in suitable storage areas, hoisting or lowering to respective floor levels and distributing plant and materials to positions convenient to the nominated sub-contractor for executing his work. General co-ordination and integration of all sub-contract works into the general programme. Entering into an agreement with the nominated sub-contractor based on the conditions laid down in the form of contract. Ascertaining full details of any work to be executed by other trades in connection with the sub-contract works and arranging for such work to be executed at the proper time. Allowing use of all temporary means of access already fixed or placed in position on the site for men and materials.
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
P/6
Preambles
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
Special Attendance on Nominated Sub-Contractors Any services required by a nominated sub-contractor beyond those referred to in the proceeding paragraph have been described in detail under "Special Attendance" f ollowing the Facilities for Direct Works The Contractor shall afford the following facilities free of charge to other contractors appointed i) ii) iii) iv) v)
Allowing use of scaffolding and all temporary means of access already fixed or placed in position on the site for men and materials. Use of messrooms, sanitary accommodation and welfare facilities. Providing water for the Works. Providing power and lighting for the Works. Protecting after installation.
vi)
Clearing away rubbish.
Fixing of Goods or Materials Supplied by Specified Suppliers Rates for fixing goods and materials supplied by the Specified Merchant or Tradesman shall include, but not limited to: i) ii)
Unloading, storing, distributing and hoisting. Arranging for delivery or payment of carriage, where particulars are given.
Builder's work in connection with Mechanical, Electrical, Plumbing, Drainage, External The expression “Builder‟s Works” shall mean the ancillary work carried out by the Contractor in connection with the MEP installations, examples of which are given below. The drilling, cutting or leaving of holes or apertures through structural floors, walls, beams, etc. shall be avoided, but where this becomes a necessity, the Contractor must obtain the written approval of the Engineer before work is put in hand. The Contractor shall allow for all builders‟ work in connection with the installations as included in the following list which it should be noted, is not intended to be exhaustive and can be extended at the discretion of the Engineer. i)
Drilling, cutting or leaving of holes for pipes, ducts and the like though walls, floors, partitions, roofs, etc. and subsequently making good/waterproofing where necessary.
ii)
Cutting and pinning ends of supports for pipes, equipment, appliances, fittings and the like to walls, floors, partitions, soffits, etc. and making good. (e.g.. Fixing of MEP items to the structures where weights of the equipment/Pipes are detrimental to the structural elements )
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
P/7
Preambles
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
iii)
Cutting or leaving mortises, sinkings, etc. for holding down bolts, brackets, supports and the like and grouting in.
iv)
Cutting chases for pipes, conduits and the like in walls, floors, partitions, etc. and subsequent making good.
v)
Cutting and filling around, boring holes through and making good of finishings up to pipes, ducts, fans supports, brackets and t he like.
vi)
The construction of concrete, block and/or timber ducts.
vii)
The formation of ducts within concrete slabs.
viii)
The formation of concrete bases, plinths, etc. for plant and equipment including floating floors, isolation pads, inertia bases for chillers and the like.
ix)
The building of timber frames for A/C grilles and ducts penetrations.
x)
The waterproofing of penetrations for all external ductwork and pipework to the Engineer‟s approval.
xi)
Making good finishes after second fix installation.
xii)
Secondary steel framing necessary for support of plant, pipework, lifts, ductwork and the like. ( e.g.: Steel supports required for fixings of equipment, pipes etc. on steel roofs )
xiii)
Concrete encasement to drainage pipes and fittings below slab on grade.
xiv)
The lifting of all plant and equipment into its place, including the lifting of chillers, air handling units, water tanks and window cleaning equipment and the like onto the roof(s) or relevant level (s) from ground floor levels close to the building.
xv)
Surveyor‟s assistance for setting out of positions for fixing of pipe sleeves and cut-outs on floor slabs as required by MEP Subcontractor.
MEP Subcontractor‟s responsibilities in connection with Builders work for Mechanical, Preparation of accurate shop drawings for all builders work requirement including coordination with structural beams and walls.
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
P/8
Preambles
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
Note: The drilling, cutting or leaving of holes or apertures through structural floors, walls, beams, etc., shall be avoided, but where this becomes a necessity, the Contractor must obtain the written approval of the Engineer before work is put in ha Positioning and fixing of sleeves, frames, mark locations for openings required on slabs and wall partitions. For the avoidance of doubt, the sleeves shall be supplied by the MEP Subcontractor. Mark accurate opening sizes on ceilings for recessed light fittings, A/C grilles, access panels or other devices. Protective painting for pipe work supports and brackets Filling of services penetration gaps between pipe sleeves, pipes, cables, ducts, etc. with specified/approved materials.
Note: Services penetration through fire rated walls, floors shall be filled with fire stop material as approved by the local authorities / Engineer. Excavation and backfilling of external pipes or cables service duct trenches. The building of meter pits, sumps, manholes, handles, access chambers and the like. Sealing of incoming cable ducts to and from buildings subject to the Engineers approval. Supply and installation of galvanized steel frames and chequered plates for cable trenches / services trenches, manhole covers as detailed in specification/drawings or B.O.Q
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
P/9
Preambles
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
AMOUNT
BILL NO. 1 - GENERAL REQUIREMENT DIVISION 1 - GENERAL REQUIREMENTS
The pricing of this division should be in respect of the whole contract works. The Contractor is referred to the requirements of Document III - Technical Specifications (Vol. 1) - together with all other documents that jointly form the Contract Documents for the Works under this Contract. Each item is to be priced individually and the Tenderer shall not enter "included" or enter any lump sums grouping more than one or all items.
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
KD
1/1/1
Bill No. 1 - General Requirements Div. 1 - General Requirements
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
DESCRIPTION
ITEM
QTY.
UNIT
RATE
AMOUNT
DIVISION 1 - GENERAL REQUIREMENTS
Allow for the works as referred in Document III Specification Division 1, including the following : Quantified items included below are subject to remeasurement SECTION A
011000
Summary
item
B
012100
Contingency Allowances
item
C
012200
Unit rates
item
D
012600
Contract Modification Procedures
item
E
012900
Payment Procedures
item
F
013100
Project Management And Coordination item
G
013200
Construction Progress Documentation
item
H
013233
Photographic Documentation
item
J
013300
Submittal Procedures
item
K
013529
Health, Safety & Emergency Response Procedures
item
L
014000
Quality Requirements
item
M
014200
References
item
N
015000
Temporary Facilities And Controls
item
P
017300
Execution
item
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
KD
1/1/2
Bill No. 1 - General Requirements Div. 1 - General Requirements
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
DESCRIPTION
ITEM
QTY.
UNIT
RATE
AMOUNT
DIVISION 1 - GENERAL REQUIREMENTS
A
017700
Closeout Procedures
item
B
017839
Project Record Documents
item
C
Allow for the works and obligations referred to in Document I - Tendering Procedures
item
Allow for the works and obligations referred to in Document II - Conditions of Contract
item
D
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
KD
1/1/3
Bill No. 1 - General Requirements Div. 1 - General Requirements
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 1 - GENERAL REQUIREMENTS
Allow for additional items according to the requirements of Document II - General and Particular Conditions of Contract, to be priced as follows: A
B
C
D
E
F
Sub-Clause Performance Security 4.2
item
Sub-Clause Advance Payment Guarantee 14.2
item
Sub-Clause Insurance for Works and Contractor's 18.2 Equipment
item
Sub-Clause Insurance against Injury to Persons and 18.3 Damage to Property
item
Sub-Clause Insurance for Contractor's Personnel 18.4
item
Sub-Clause Professional Indemnity Insuarance 18.5
item
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
KD
1/1/4
Bill No. 1 - General Requirements Div. 1 - General Requirements
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
DESCRIPTION
AMOUNT
DIVISION 1 - GENERAL REQUIREMENTS
COLLECTION Total of Page
1/1/1
Total of Page 1/1/2 Total of Page
1/1/3
Total of Page 1/1/4
CARRIED TO BILL SUMMARY
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
KD
1/1/5
Bill No. 1 - General Requirements Div. 1 - General Requirements
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 02: PODIUM DIVISION 02 - EXISTING CONDITIONS
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 02 3000.13 : SUBSURFACE INVESTIGATION
Site Investigation A
Allow for site investigation and for locating and diverting existing utilities interfering with the Works, sealing existing utilities required to be maintained and removing redundant utilities/ services, including excavation of trial pits
CARRIED TO SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
1
item
KD
2/2/1
Bill no. 2 - Podium Division 2 - Existing Conditions
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 02: PODIUM DIVISION 03 - CONCRETE
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 03 3000 : CAST-IN-PLACE CONCRETE SUBSTRUCTURE
Plain concrete 17MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including formwork and additives A
75mm Blinding
169
m3
527
m3
3,347
m3
Mass concrete fill 17MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including formwork and additives
B
Below raft slab Reinforced concrete 45MPa (Cylindrical) using OPC & PFA & micro silica cement including formwork, water stops, expansion and construction joints, joint filler and additives
C
Raft foundation including pits and trenches
D
300mm Retaining wall
140
m3
E
400mm Retaining wall
172
m3
F
Columns, attached to retaining walls
138
m3
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
2/3/1
Bill no. 2 - Podium Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Reinforced concrete 28MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including, formwork, expansion and construction joints, joint filler and additives A
150mm Suspended slab
25
m3
B
200mm Ditto
21
m3
C
300mm Ditto
2
m3
D
Beams
523
m3
E
700mm Deep rib slab, 125mm thick top slab, 900mm centre to centre rib 575mm deep, 350mm top width and bottom width 250mm.
1,657
m2
700mm Deep rib slab, 125mm thick top slab, 1800mm centre to centre rib 575mm deep, 350mm top width and bottom width 250mm.
1,304
m2
75
m3
F
G
700mm deep Thickening to rib slabs
H
Stairs
J
Upstand
K
Equipment bases
12
m3
1
m3
99
m3
220
m3
3
m3
Reinforced concrete 45MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including formwork, expansion and construction joints, joint filler and additives L
Columns
M
200mm Walls
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
2/3/2
Bill no. 2 - Podium Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
736,340
kg
53,040
kg
5,760
kg
RATE
AMOUNT
DIVISION 03 - CONCRETE
Reinforcement A
Raft @ 220kg/m3
B
Retaining wall @ 170kg/m3
C
Suspended slabs @ 120kg/m3
D
Rib slabs - 700 deep/900 c/c @ 51kg/m2
84,507
kg
E
Rib slabs - 700 deep/1800 c/c @ 28.755kg/m2
37,497
kg
F
Thickening to Rib slabs @ 150kg/m3
11,250
kg
G
Beams @ 180kg/m3
94,140
kg
H
Stairs @ 100kg/m3
1,200
kg
J
Columns @ 240kg/m3
85,920
kg
K
Walls @ 160kg/m3
480
kg
L
Upstands @ 100kg/m3
100
kg
M
Equipment bases @ 70kg/m3
6,930
kg
Finishes N
P
Q
Extra Over Fair face finish, to beams and slabs
m2
Rate only
Extra Over Fair face finish, to rib slabs (measured on plan)
m2
Rate only
Extra Over Fair face finish, to columns and walls
m2
Rate only
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
2/3/3
Bill no. 2 - Podium Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Sundries A
To equipment bases
Item
B
Expansion joint between retaining wall and adjacent existing building including filler and metal flashings
Item
SUPERSTRUCTURE
Reinforced concrete 28MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including, formwork, expansion and construction joints, joint filler and additives C
150mm Suspended slab
10
m3
D
200mm Ditto
10
m3
E
700mm Deep rib slab, 125mm thick top slab, 900mm centre to centre rib 575mm deep, 350mm top width and bottom width 250mm.
712
m2
700mm Deep rib slab, 125mm thick top slab, 1800mm centre to centre rib 575mm deep, 300mm top width and bottom width 200mm.
845
m2
74
m3
F
G
700mm deep Thickening to rib slabs
H
190mm thick slab to metal deck
J
Beams
499
m3
K
Stairs
34
m3
L
Upstands
3,428
1
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
m2
m3
KD
2/3/4
Bill no. 2 - Podium Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Reinforced concrete 45MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including, formwork, expansion and construction joints, joint filler and additives
A
Columns
344
m3
74
m3
Reinforced concrete 45MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including additives B
Concrete fill to Hollow steel columns Reinforcement
C
Suspended slabs @ 120kg/m3
2,400
kg
D
Rib slabs - 700 deep/900 c/c @ 51kg/m2
36,312
kg
E
Rib slabs - 700 deep/1800 c/c @ 28.755kg/m2
24,298
kg
F
Thickening to Rib slabs @ 150kg/m3
11,100
kg
G
Beams @ 180kg/m3
89,820
kg
H
Stairs @ 100kg/m3
3,400
kg
J
Columns @ 240kg/m3
82,560
kg
K
Upstands @ 100kg/m3
100
kg
L
Metal deck mesh reinforcement
3,428
m2
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
2/3/5
Bill no. 2 - Podium Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Finishes A
B
C
Extra Over Fair face finish, to beams and slabs
m2
Rate only
Extra Over Fair face finish, to rib slabs (measured on plan)
m2
Rate only
Extra Over Fair face finish, to columns and walls
m2
Rate only
03 4100 : PRECAST STRUCTURAL CONCRETE
Precast concrete units including reinforcement, hardware, anchors, mortar fixings, fair face finish and painting to exposed units D
3800 x 1000 x 300mm Access hatch
14
nr
9
m3
03 5200 : LIGHTWEIGHT CONCRETE
Lightweight concrete, 700kg/m3 density, including control joints filled with joint filler E
Filling to make up level
F
Steps
G
150-200mm, to basement roof
1
m3
168
m2
2,261
m2
168
m2
03 5419 : SAND CEMENT SCREED
H
J
50mm Thick, to protect horizontal waterproofing Ditto, to basement roof
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
2/3/6
Bill no. 2 - Podium Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
AMOUNT
DIVISION 03 - CONCRETE
COLLECTION Total of page No. 2/3/1 Total of page No. 2/3/2 Total of page No. 2/3/3 Total of page No. 2/3/4 Total of page No. 2/3/5 Total of page No. 2/3/6
CARRIED TO SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
2/3/7
Bill no. 2 - Podium Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
454,000
kg
74,000
kg
RATE
AMOUNT
BILL NO. 02: PODIUM DIVISION 05 - METALS
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 05 1200 : STRUCTURAL STEEL
Grade 50, Structural steelwork and framing including all bolts, nuts, washers, plates, base plates, stiffening plates, gussets plates, holding down bolts, angle sections, cleats, stiffener rods, bracing and the like including cutting, welding, threading, fixing complete, fire-proofing and priming / f inishing paint as required, and anchor bolts to concrete surfaces A
To Podium
B
To Podium (Grade 36)
C
Grand Stair
1
item
D
1875mm high Stair at 2nd Floor
1
item
E
Connections
1
item
3,428
m2
05 3100 : STEEL DECKING
Galvanized and shop primed steel metal deck including Z purlins, raised pattern ribs, interlocking side laps, fire-proofing, painting and accessories (concrete topping measured separately) F
To Podium
CARRIED TO SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
2/5/1
Bill no. 2 - Podium Division 5 - Metals
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 02: PODIUM DIVISION 07 - THERMAL AND MOISTURE PROTECTION
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 07 1354 : THERMOPLASTIC SHEET WATERPROOFING
Thermoplastic waterproofing system including 2mm thick PVC sheeting, waterstops, injection hose and resin, welding and fixing
A
To raft foundation, horizontal, laid to slopes
2,261
m2
B
To raft foundation and retaining walls, vertically
1,257
m2
168
m2
C
To basement roof, Horizontally Geotextile slip layer
D
To raft foundation, horizontal, laid to slopes
2,261
m2
E
To raft foundation and retaining walls, vertically
1,257
m2
168
m2
F
To basement roof, Horizontally Polythene sheet
G
To raft foundation, horizontal, laid to slopes
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
2,261
m2
KD
2/7/1
Bill no. 2 - Podium Division 7 - Thermal and Moisture Protection
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
A
B
To raft foundation and retaining walls, vertically
402
m2
To basement roof, Horizontally
168
m2
402
m2
855
m2
Protection board C
To raft foundation and retaining walls, vertically Geotextile protection layer
D
To raft foundation and retaining walls, vertically Shotcrete / Plaster applied to face of secant piles including welded wire fabric, reinforcing steel, reinforcement anchors and accessories
E
Shotcrete
402
m2
F
Plaster
402
m2
Rate Only
07811 : SPRAYED FIRE RESISTIVE
G
To structural steel members indicated on the drawings or as required by the authorities, 2 hr fire rated
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
item
KD
2/7/2
Bill no. 2 - Podium Division 7 - Thermal and Moisture Protection
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
AMOUNT
DIVISION 07 - THERMAL AND MOISTURE
COLLECTION Total of page No. 2/7/1 Total of page No. 2/7/2
CARRIED TO SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
2/7/3
Bill no. 2 - Podium Division 7 - Thermal and Moisture Protection
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
4,289
m3
RATE
AMOUNT
BILL NO. 02: PODIUM DIVISION 31 - EARTHWORK
The Contractor is referred to the Specifications and Drawings for all details related to this section of the works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 31 2016 : EARTHWORK
Earthwork including excavation in all materials, backfilling, compaction, eartwork support system and removal of surplus excavated materials from site A
Excavation, to final excavation level Design, supply and install Localised Earthwork support system
B
Localised Earthwork support system including adjustment and maintenance until no longer required
item
31 2319 : DEWATERING
C
D
Allow for operation and maintenance of Dewatering System
15
Allow for demobilizing Dewatering System
month item
31 3116 : TERMITE CONTROL
E
Termite control treatment (area measured on plan)
CARRIED TO SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
2,165
m2
KD
2/31/1
Bill no. 2 - Podium Division 31 - Earthwork
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
REFERENCE
DESCRIPTION
PAGE NO.
AMOUNT
BILL NO. 02: PODIUM SUMMARY
DIVISION 2
EXISTING CONDITIONS
2/2/1
DIVISION 3
CONCRETE
2/3/7
DIVISION 05
METALS
2/5/1
DIVISION 7
THERMAL & MOISTURE PROTECTION
2/7/3
DIVISION 31
EARTHWORK
2/31/1
CARRIED TO MAIN SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
2/Summ/1
Bill no. 2 - Podium Bill Summary
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 03 : OFFICE TOWER DIVISION 02 - EXISTING CONDITIONS
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 02 3000.13 : SUBSURFACE INVESTIGATION
Site Investigation A
Allow for site investigation and for locating and diverting existing utilities interfering with the Works, sealing existing utilities required to be maintained and removing redundant utilities/ services, including excavation of trial pits
CARRIED TO BILL SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
1
item
KD
3/2/1
Bill No. 3 - Office Tower Division 2 - Existing Conditions
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 03 : OFFICE TOWER DIVISION 03 - CONCRETE
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 03 3000 : CAST-IN-PLACE CONCRETE SUBSTRUCTURE
Plain concrete 17MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including formwork and additives A
75mm Blinding
220
m3
3,129
m3
Reinforced concrete 45MPa (Cylindrical) using OPC & PFA & micro silica cement including formwork, water stops, expansion and construction joints, joint f iller and additives B
Raft foundation including pits and trenches
C
300mm Retaining wall
179
m3
D
400mm Retaining wall
181
m3
E
490mm Retaining wall
4
m3
F
200mm Slab-on-grade, to raft
63
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
m3
KD
3/3/1
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Reinforced concrete 60MPa (Cylindrical) (Cylindrical) using OPC & PFA & micro silica cement including formwork, water stops, expansion and construction joints, joint f iller and additives A
Columns, attached to retaining retaining walls
300
m3
Reinforced concrete 45MPa (Cylindrical) (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including formwork, expansion and construction joints, joint f iller and additives B
150mm Su Suspended sl slab
33
m3
C
200mm Ditto
36
m3
D
220mm Ditto
62
m3
E
300mm Ditto
6
m3
F
350mm Ditto
72
m3
G
700m 700mm m Dee Deep p rib rib slab slab,, 125 125mm mm thic thick k top top sla slab, b, 900mm centre to centre rib 575mm deep, 350mm top width and bottom width 250mm.
H
700m 700mm m dee deep p Thi Thick cken enin ing g to to rib rib slab slabs s
J
Beams
K
Stairs
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
1,440
m2
55
m3
135
m3
32
m3
KD
3/3/2
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Reinforced concrete 60MPa (Cylindrical) (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including formwork, expansion and construction joints, joint f iller and additives A
Columns
79
m3
B
800mm Core W alls
438
m3
C
400mm Ditto
210
m3
D
200mm W alls
2
m3
E
250mm W alls
7
m3
F
Spandrel beams
79
m3
G
Upstands
1
m3
H
Corbe rbels suppo upport rtiing stai stairs rs
1
m3
Reinforcement 563,220
kg
Retaining wall @ 170kg/m3
61,880
kg
L
Suspended slabs @ 130kg/m3
27,170
kg
M
Rib slabs - 700 deep/900 c/c @ 51kg/m2
73,440
kg
N
Thickening to Rib slabs @ 150kg/m3
8,250
kg
P
Beams @ 150kg/m3
20,250
kg kg
J
Raft @ 180kg/m3
K
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
3/3/3
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
A
Stairs @ 100kg/m3
3,200
kg
B
Columns @ 250kg/m3
94,750
kg
C
Core W alls @ 120kg/m3
77,760
kg
D
Spandrel beams @ 150kg/m3
11,850
kg
E
Corbels @ 120kg/m3
120
kg
F
W alls @ 160kg/m3
1,440
kg
G
Upstands @ 100kg/m3
100
kg
H
Slab on grade mesh reinforcement
315
m2
Finishes J
K
L
Extr Extra a Ove Overr Fai Fairr face face fini finish sh,, to beam beams s and and slabs
m2
Rate only
Extra Extra Ov Over er Fair Fair face face fin finis ish, h, to rib rib slab slabs s (measured on plan)
m2
Rate only
Extra Extra Ov Over er Fair Fair face face fin finis ish, h, to colu column mns s and and walls
m2
Rate only
Sundries M
Expa Expans nsio ion n join jointt betw betwee een n reta retain inin ing g wall wall and and adjacent existing building including filler and metal flashings
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
Item
KD
3/3/4
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE SUPERSTRUCTURE
Reinforced concrete 45MPa (Cylindrical) (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including, formwork, expansion and construction joints, joint f iller and additives A
125mm Suspended Suspended slab
B
35
m3
150mm Ditto
913
m3
C
180mm Ditto
4
m3
D
200mm Ditto
302
m3
E
220mm Ditto
2,249
m3
F
250mm Ditto
359
m3
G
300mm Ditto
24
m3
H
700m 700mm m Dee Deep p rib rib slab slab,, 125 125mm mm thic thick k top top sla slab, b, 900mm centre to centre rib 575mm deep, 350mm top width and bottom width 250mm.
J
3,224
m2
700m 700mm m Dee Deep p rib rib slab slab,, 125m 125mm m thic thick k top top sla slab, b, 1800mm centre to centre rib 575mm deep, 300mm top width and bottom width 200mm.
33,301
m2
K
700m 700mm m dee deep p Thi Thick cken enin ing g to to rib rib slab slabs s
1,950
m3
L
Be Beams
4,111
m3
M
Stairs
N
Parapet
19
m3
P
W at ater tank upstand
20
m3
34
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
m3
KD
3/3/5
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Reinforced concrete 60MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including, formwork, expansion and construction joints, joint f iller and additives A
Columns
B
3,366
m3
Circular columns
90
m3
C
Inclined columns
80
m3
D
400mm Core wall
5,201
m3
E
600mm, Ditto
2,788
m3
F
800mm, Ditto
4,728
m3
G
200mm Walls
122
m3
H
250mm Walls
88
m3
J
300mm Walls
14
m3
K
Spandrel beams
1,478
m3
L
Corbels supporting stairs
11
m3
Reinforcement M
Suspended slabs @ 130kg/m3
505,180
kg
N
Rib slabs - 700 deep/900 c/c @ 51kg/m2
164,424
kg
P
Rib slabs - 700 deep/1800 c/c @ 28.755kg/m2
957,571
kg
Q
Thickening to Rib slabs @ 150kg/m3
292,500
kg
R
Beams @ 150kg/m3
616,650
kg
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
3/3/6
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
A
Stairs @ 100kg/m3
3,400
kg
B
Columns @ 250kg/m3
884,000
kg
C
Core Walls @ 120kg/m3
1,526,040
kg
D
Spandrel beams @ 150kg/m3
221,700
kg
E
Corbels @ 120kg/m3
1,320
kg
F
Walls @ 160kg/m3
35,840
kg
G
Upstands @ 100kg/m3
3,900
kg
Finishes H
J
K
Extra Over Fair face finish, to beams and slabs
m2
Rate only
Extra Over Fair face finish, to rib slabs (measured on plan)
m2
Rate only
Extra Over Fair face finish, to columns and walls
m2
Rate only
03 4100 : PRECAST STRUCTURAL CONCRETE
SUBSTRUCTURE Precast concrete stairs 6210 x 1600mm wide L
1500mm high
4
no
M
2180mm high
2
no
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
3/3/7
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
SUPERSTRUCTURE Precast concrete stairs 6210 x 1600mm wide A
1250mm high
8
no
B
1440mm high
2
no
C
1520mm high
4
no
D
1680mm high
4
no
E
1710mm high
2
no
F
2000mm high
2
no
G
2100mm high
68
no
H
2250mm high
2
no
Precast concrete stairs 6675 x 1550mm wide J
900mm high
2
no
K
1440mm high
2
no
L
1710mm high
2
no
M
2100mm high
74
no
N
2250mm high
2
no
P
3150mm high
2
no
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
3/3/8
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Precast concrete stairs 7165 x 1550mm wide A
900mm high
2
no
B
1710mm high
2
no
C
2100mm high
36
no
D
2250mm high
2
no
E
3150mm high
2
no
Precast concrete stairs 7500 x 1550mm wide F
1250mm high
8
no
G
1440mm high
2
no
H
2000mm high
2
no
J
2100mm high
38
no
Precast concrete stairs 7850 x 1550mm wide K
1250mm high
8
no
L
1520mm high
4
no
M
1680mm high
4
no
N
2000mm high
2
no
Precast concrete access panels & covers P
2900 x 950 x 150mm thick
6
no
Q
1400 x 700mm pit cover
2
no
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
3/3/9
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE 03 5200 : LIGHTWEIGHT CONCRETE
Lightweight concrete, 700kg/m3 density, including control joints filled with joint filler A
Filling to make up level
1
m3
B
Steps
1
m3
C
Ramp
1
m3
D
150-200mm, to basement roof
168
m2
2,076
m2
168
m2
03 5419 : SAND CEMENT SCREED
E
F
50mm Thick, to protect horizontal waterproofing Ditto, to basement roof
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
3/3/10
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
AMOUNT
DIVISION 03 - CONCRETE
COLLECTION Total of page No. 3/3/1 Total of page No. 3/3/2 Total of page No. 3/3/3 Total of page No. 3/3/4 Total of page No. 3/3/5 Total of page No. 3/3/6 Total of page No. 3/3/7 Total of page No. 3/3/8 Total of page No. 3/3/9 Total of page No. 3/3/10
CARRIED TO BILL SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
3/3/11
Bill No. 3 - Office Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 03 : OFFICE TOWER DIVISION 07 - THERMAL AND MOISTURE PROTECTION
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions
07 1354 : THERMOPLASTIC SHEET WATERPROOFING
Thermoplastic waterproofing system including 2mm thick PVC sheeting, waterstops, injection hose and resin, welding and fixing
A
To raft foundation, horizontal, laid to slopes
2,076
m2
B
To raft foundation and retaining walls, vertically
1,802
m2
168
m2
C
To basement roof, Horizontally Geotextile slip layer
D
To raft foundation, horizontal, laid to slopes
2,076
m2
E
To raft foundation and retaining walls, vertically
1,802
m2
168
m2
F
To basement roof, Horizontally
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
3/7/1
Bill No. 3 - Office Tower Division 7 - Thermal and Moisture Protection
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
Polythene sheet A
To raft foundation, horizontal, laid to slopes
B
To basement roof, Horizontally
2,076
m2
168
m2
1,802
m2
60
no
Geotextile protection layer C
To raft foundation and retaining walls, vertically Pile head treatment including 25mm thick micro concrete grouting and High performance fluid resin encapsulation,
D
1500mm Diameter Shotcrete / Plaster applied to face of secant piles including welded wire fabric, reinforcing steel, reinforcement anchors and accessories
E
Shotcrete
F
Plaster
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
80
m2
1,265
m2
KD
3/7/2
Bill No. 3 - Office Tower Division 7 - Thermal and Moisture Protection
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
AMOUNT
DIVISION 07 - THERMAL AND MOISTURE
COLLECTION Total of page No. 3/7/1 Total of page No. 3/7/2
CARRIED TO SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
3/7/3
Bill No. 3 - Office Tower Division 7 - Thermal and Moisture Protection
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
4,351
m3
607
m3
RATE
AMOUNT
BILL NO. 03 : OFFICE TOWER DIVISION 31 - EARTHWORK
The Contractor is referred to the Specifications and Drawings for all details related to this section of the works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions
31 2016 : EARTHWORK
Earthwork including excavation in all materials, backfilling, compaction, eartwork support system and removal of surplus excavated materials from site A
Excavation, to final excavation level Backfilling including compaction
B
Sand fill, to slab on grade Design, supply and install Localised Earthwork support system
C
Localised Earthwork support system including adjustment and maintenance until no longer required
item
31 2319 : DEWATERING
D
E
Allow for operation and maintenance of Dewatering System
15
Allow for demobilizing Dewatering System
month item
31 3116 : TERMITE CONTROL
F
Termite control treatment (area measured on plan)
CARRIED TO BILL SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
1,785
m2
KD
3/31/1
Bill No. 3 - Office Tower Division 31 - Earthwork
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
REFERENCE
DESCRIPTION
PAGE NO.
AMOUNT
BILL NO. 03 : OFFICE TOWER SUMMARY
DIVISION 2
EXISTING CONDITIONS
DIVISION 3
CONCRETE
DIVISION 7
THERMAL & MOISTURE PROTECTION
DIVISION 31
EARTHWORK
3/3/11
3/7/3 3/31/1
CARRIED TO MAIN SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
3/2/1
KD
3/Summ/1
Bill No. 3 - Office Tower Bill Summary
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 04 : HOTEL TOWER DIVISION 02 - EXISTING CONDITIONS
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 02 3000.13 : SUBSURFACE INVESTIGATION
Site Investigation A
Allow for site investigation and for locating and diverting existing utilities interfering with the Works, sealing existing utilities required to be maintained and removing redundant utilities/ services, including excavation of trial pits
CARRIED TO BILL SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
1
item
KD
4/2/1
Bill No. 4 - Hotel Tower Division 2 - Existing Conditions
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 04 : HOTEL TOWER DIVISION 03 - CONCRETE
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 03 3000 : CAST-IN-PLACE CONCRETE SUBSTRUCTURE
Plain concrete 17MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including formwork and additives A
75mm Blinding
220
m3
6,656
m3
Reinforced concrete 45MPa (Cylindrical) using OPC & PFA & micro silica cement including formwork, water stops, expansion and construction joints, joint filler and additives
B
Raft foundation including pits and trenches
C
300mm Retaining wall
226
m3
D
400mm Retaining wall
283
m3
160
m3
Reinforced concrete 60MPa (Cylindrical) using OPC & PFA & micro silica cement including formwork, water stops, expansion and construction joints, joint filler and additives E
Columns, attached to retaining walls
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/3/1
Bill No. 4 - Hotel Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Reinforced concrete 45MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including formwork, expansion and construction joints, joint filler and additives A
150mm Suspended slab
16
m3
B
200mm, Ditto
28
m3
C
250mm, Ditto
108
m3
D
300mm, Ditto
86
m3
E
350mm, Ditto
200
m3
F
Beams
G
700mm Deep rib slab, 125mm thick top slab, 900mm centre to centre rib 575mm deep, 350mm top width and bottom width 250mm.
H
700mm deep Thickening to rib slabs
J
Stairs
K
Equipment bases
m3
2,139
m2
75
m3
10 14
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
305
m3 m3
KD
4/3/2
Bill No. 4 - Hotel Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Reinforced concrete 60MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including formwork, expansion and construction joints, joint filler and additives A
Columns
167
m3
B
400mm Core Walls
253
m3
C
300mm Ditto
48
m3
D
300mm Water tank walls
301
m3
E
Spandrel beams
30
m3
F
Upstands
2
m3
G
Corbels supporting stairs
1
m3
Reinforcement 1,198,080
kg
Retaining wall @ 170kg/m3
86,530
kg
K
Suspended slabs @ 130kg/m3
56,940
kg
L
Rib slabs - 700 deep/900 c/c @ 51kg/m2
109,089
kg
M
Thickening to Rib slabs @ 150kg/m3
11,250
kg
N
Beams @ 150kg/m3
45,750
kg
P
Stairs @ 100kg/m3
1,000
kg
Q
Columns @ 250kg/m3
81,750
kg
R
Core Walls @ 120kg/m3
36,120
kg
H
Raft @ 180kg/m3
J
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/3/3
Bill No. 4 - Hotel Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
A
Spandrel beams @ 150kg/m3
4,500
kg
B
Corbels @ 120kg/m3
120
kg
C
Walls @ 160kg/m3
48,160
kg
D
Upstands @ 100kg/m3
200
kg
E
Equipment bases @ 70kg/m3
980
kg
Finishes F
G
H
Extra Over Fair face finish, to beams and slabs
m2
Rate only
Extra Over Fair face finish, to rib slabs (measured on plan)
m2
Rate only
Extra Over Fair face finish, to columns and walls
m2
Rate only
Sundries J
To equipment bases
Item
K
Expansion joint between retaining wall and adjacent existing building including filler and metal flashings
Item
SUPERSTRUCTURE
Reinforced concrete 45MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including, formwork, expansion and construction joints, joint filler and additives
L
150mm Suspended slab
242
m3
M
200mm Ditto
372
m3
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/3/4
Bill No. 4 - Hotel Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
A
250mm Ditto
244
m3
B
300mm Ditto
25
m3
C
400mm Ditto
40
m3
D
700mm Deep rib slab, 125mm thick top slab, 900mm centre to centre rib 575mm deep, 350mm top width and bottom width 250mm.
E
9,151
m2
20,867
m2
650mm Deep rib slab, 125mm thick top slab, 1700mm centre to centre rib 525mm deep, 300mm top width and bottom width 200mm.
F
650mm deep Thickening to rib slabs
260
m3
G
700mm deep Thickening to rib slabs
115
m3
H
Beams
3,754
m3
J
Stairs
K
Equipment bases
L
Upstands
19
m3
47
m3
4
m3
Reinforced concrete 60MPa (Cylindrical) using Ordinary Portland Cement ASTM C150 (Type I) including, formwork, expansion and construction joints, joint filler and additives
M
Columns
N
300mm Core wall
P
400mm, Ditto
1,747
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
m3
862
m3
2,507
m3
KD
4/3/5
Bill No. 4 - Hotel Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
A
300mm Walls
107
m3
B
Spandrel beams
324
m3
4
m3
Corbels supporting stairs Reinforcement C
Suspended slabs @ 130kg/m3
119,990
kg
D
Rib slabs - 700 deep/900 c/c @ 51kg/m2
466,701
kg
E
Rib slabs - 650 deep/1700 c/c @ 27.54kg/m2
574,678
kg
F
Thickening to Rib slabs @ 150kg/m3
56,250
kg
G
Beams @ 150kg/m3
563,100
kg
H
Stairs @ 100kg/m3
1,900
kg
J
Columns @ 250kg/m3
436,750
kg
K
Core Walls @ 120kg/m3
404,280
kg
L
Spandrel beams @ 150kg/m3
48,600
kg
M
Corbels @ 120kg/m3
600
kg
N
Walls @ 160kg/m3
17,120
kg
P
Upstands @ 100kg/m3
400
kg
Q
Equipment bases @ 70kg/m3
3,290
kg
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/3/6
Bill No. 4 - Hotel Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
Finishes A
B
C
Extra Over Fair face finish, to beams and slabs
m2
Rate only
Extra Over Fair face finish, to rib slabs (measured on plan)
m2
Rate only
Extra Over Fair face finish, to columns and walls
m2
Rate only
Styropore fill D
Styropore fill, to make up levels
33
m3
E
Styropore fill, to equipment bases
72
m3
03 4100 : PRECAST STRUCTURAL CONCRETE
SUBSTRUCTURE Precast concrete stairs 6300 x 1575mm wide
F
1260mm high
8
no
G
1280mm high
8
no
SUPERSTRUCTURE Precast concrete stairs 6300 x 1575mm wide
H
1250mm high
16
no
J
1410mm high
2
no
K
1500mm high
16
no
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/3/7
Bill No. 4 - Hotel Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 03 - CONCRETE
A
1530mm high
8
no
B
1690mm high
4
no
C
1900mm high
40
no
D
2000mm high
8
no
E
2060mm high
4
no
F
2100mm high
16
no
G
2140mm high
4
no
Precast concrete access panels & covers H
4000 x 900 x 150mm thick
4
no
J
1295 x 815mm pit cover
1
no
K
1400 x 700mm pit cover
3
no
03 5200 : LIGHTWEIGHT CONCRETE
Lightweight concrete, 700kg/m3 density, including control joints filled with joint filler L
Filling to make up level
M
Lightweight concrete steps
N
150-200mm, to basement roof
54
m3
7
m3
168
m2
2,922
m2
168
m2
03 5419 : SAND CEMENT SCREED
P
Q
50mm Thick, to protect horizontal waterproofing Ditto, to basement roof
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/3/8
Bill No. 4 - Hotel Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
AMOUNT
DIVISION 03 - CONCRETE
COLLECTION Total of page No. 4/3/1 Total of page No. 4/3/2 Total of page No. 4/3/3 Total of page No. 4/3/4 Total of page No. 4/3/5 Total of page No. 4/3/6 Total of page No. 4/3/7 Total of page No. 4/3/8
CARRIED TO BILL SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/3/9
Bill No. 4 - Hotel Tower Division 3 - Concrete
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 04 : HOTEL TOWER DIVISION 07 - THERMAL AND MOISTURE PROTECTION
The Contractor is referred to the Specifications and Drawings for all details related to this section of the Works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 07 1354 : THERMOPLASTIC SHEET WATERPROOFING
Thermoplastic waterproofing system including 2mm thick PVC sheeting, waterstops, injection hose and resin, welding and fixing
A
To raft foundation, horizontal, laid to slopes
2,922
m2
B
To raft foundation and retaining walls, vertically
1,943
m2
168
m2
C
To basement roof, Horizontally Geotextile slip layer
D
To raft foundation, horizontal, laid to slopes
2,922
m2
E
To raft foundation and retaining walls, vertically
1,943
m2
168
m2
F
To basement roof, Horizontally
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/7/1
Bill No. 4 - Hotel Tower Division 7 - Thermal and Moisture Protection
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
Polythene sheet A
To raft foundation, horizontal, laid to slopes
2,922
m2
B
To raft foundation and retaining walls, vertically
1,292
m2
168
m2
1,292
m2
651
m2
C
To basement roof, Horizontally Protection board
D
To raft foundation and retaining walls, vertically Geotextile protection layer
E
To raft foundation and retaining walls, vertically
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/7/2
Bill No. 4 - Hotel Tower Division 7 - Thermal and Moisture Protection
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
AMOUNT
DIVISION 07 - THERMAL AND MOISTURE
COLLECTION Total of page No. 4/7/1 Total of page No. 4/7/2
CARRIED TO SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/7/3
Bill No. 4 - Hotel Tower Division 7 - Thermal and Moisture Protection
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
5,289
m3
RATE
AMOUNT
BILL NO. 04 : HOTEL TOWER DIVISION 31 - EARTHWORK
The Contractor is referred to the Specifications and Drawings for all details related to this section of the works and he is to include for complying with all the requirements contained therein, whether or not they are specifically mentioned within the item descriptions 31 2016 : EARTHWORK
Earthwork including excavation in all materials, backfilling, compaction, eartwork support system and removal of surplus excavated materials from site A
Excavation, to final excavation level Design, supply and install Localised Earthwork support system
B
Localised Earthwork support system including adjustment and maintenance until no longer required
item
31 2319 : DEWATERING
C
D
Allow for operation and maintenance of Dewatering System
15
Allow for demobilizing Dewatering System
month item
31 3116 : TERMITE CONTROL
E
Termite control treatment (area measured on plan)
CARRIED TO BILL SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
2,436
m2
KD
4/31/1
Bill No. 4 - Hotel Tower Division 31 - Earthwork
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
REFERENCE
DESCRIPTION
PAGE NO.
AMOUNT
BILL NO. 04 : HOTEL TOWER SUMMARY
DIVISION 2
EXISTING CONDITIONS
4/2/1
DIVISION 3
CONCRETE
4/3/9
DIVISION 7
THERMAL & MOISTURE PROTECTION
4/7/3
DIVISION 31
EARTHWORK
4/31/1
CARRIED TO MAIN SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
4/Summ/1
Bill No. 4 - Hotel Tower Bill Summary
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
BILL NO. 05 : PROVISIONAL SUMS
The following Provisional Sums are designated for the execution of work, supply of Goods, Materials, Plant or services, specialist sub-contractors, or for contingencies, which sums may be used in whole or in part or not at all, on the instructions of the Engineer. (Overheads and profit are paid only when Plant, Materials or services are purchased from a nominated Subcontractor) BP3A - CONVEYING SYSTEMS
A
B
C
Allow the Provisional Sum of KD Three Million Fifty Thousand Only (KD 3,050,000) for Conveying system
PS
Allow for Main Contractor's Overheads and profit
%
Allow for Attendance by Main Contractor
3,050,000
Lump Sum
BP3B - EXTERIOR ENVELOPE
External envelope including, but not limited to, glazed curtain wall systems, louvers, glass & glazing, stone cladding, prefinished metal cladding systems, structural steel and galvanized steel support systems, etc.
D
Allow the Provisional Sum of KD Nine Million Nine Hundred Thousand Only (KD 9,900,000) PS
E
F
Allow for Main Contractor's Overheads and profit Allow for Attendance by Main Contractor
% Lump Sum
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
9,900,000
KD
5/PS/1
Provisional Sums
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
PROVISIONAL SUMS BP3C - BUILDING MAINTENANCE SYSTEM
A
B
C
Allow the Provisional Sum of KD Three Hundred Eighty Five Thousand Only (KD 385,000) for Building Maintenance
PS
Allow for Main Contractor's Overheads and profit
%
Allow for Attendance by Main Contractor
385,000
Lump Sum
BP3D - ARCHITECTURAL WORKS
Architectural works in BOH areas including, but not limited to, Light weight concrete and concrete block walls, finishes including floor, wall, ceiling and skirting, waterproofing, acoustic underlays, screeds, partitioning walls, toilet fixtures, vanity tops, toilet accessories, doors including hardware and finishes, interface doors between BOH and FOH (finishes on only on BOH side), linen chute, FFE & cupboards, metal works, kitchen equipments, roofing, etc.
D
E
F
Allow the Provisional Sum of KD Eleven Million Six Hundred Thousand Only (KD 11,600,000)
PS
Allow for Main Contractor's Overheads and profit
%
Allow for Attendance by Main Contractor
Lump Sum
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
11,600,000
KD
5/PS/2
Provisional Sums
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
PROVISIONAL SUMS BP3E - MEP WORKS
MEP works including, but not limited to, complete MEP works for BOH areas, MEP equipments for FOH and BOH areas, building management systems, permanent connection charges for water, electricity, drainage, telephone, coordination with local authority, Façade lighting and external landscape lighting, provision of electrical services for other trades, etc.(Excluding Distribution system for FOH area) A
B
C
Allow the Provisional Sum of KD Twenty Two Million Six Hundred Thousand Only (KD 22,600,000)
PS
Allow for Main Contractor's Overheads and profit
%
Allow for Attendance by Main Contractor
Lump Sum
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
22,600,000
KD
5/PS/3
Provisional Sums
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
AMOUNT
PROVISIONAL SUMS
COLLECTION Total of page No. 5/PS/1 Total of page No. 5/PS/2 Total of page No. 5/PS/3
CARRIED TO SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
5/PS/4
Provisional Sums
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
AMOUNT
TENDERER'S ADJUSTMENT SCHEDULE
A
No alterations shall be made by the Tenderer to the printed text of the foregoing Bills of Quantities.
B
Any alterations to the Bills of Quantities will be ignored and the text read as originally printed.
C
The Tenderer shall detail in the following pages any items which he requires in addition to those in the Bills of Quantities, or any of the printed items which he feels should be omitted from the Bills of Quantities.
D
Items detailed shall be shown as unit quantities, in t he same format as the Bills of Quantities, each item having a rate duly extended and the whole totalled and carried to the Summary.
E
Should further pages be required by the Tenderer he shall include these and amend the Summaries to suit the revised pages.
F
This Section shall be deemed to be the whole of the Additions and Omissions required by the Tenderer.
CARRIED TO COLLECTION KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
TAS/1
Tender Adjustment Schedule
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
TENDERER'S ADJUSTMENT SCHEDULE
ADDITIONS
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
TAS/2
Tender Adjustment Schedule
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
TENDERER'S ADJUSTMENT SCHEDULE
OMISSIONS
CARRIED TO COLLECTION
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
KD
TAS/3
Tender Adjustment Schedule
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
DESCRIPTION
QTY.
UNIT
RATE
AMOUNT
TENDERER'S ADJUSTMENT SCHEDULE
SUMMARY
ADDITIONS Total of Page TAS/2
Total Additions
KD
OMISSIONS Total of Page TAS/3
Total Omissions
KD
Total of NET ADDITIONS/OMISSIONS * FOR TENDERER'S ADJUSTMENT SCHEDULE
* Delete as required
TENDERER'S ADJUSTMENT SCHEDULE CARRIED TO SUMMARY
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
TAS/4
KD
Tender Adjustment Schedule
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ITEM
REFERENCE
DESCRIPTION
PAGE NO.
AMOUNT
MAIN SUMMARY
BILL NO. 01: GENERAL REQUIREMENTS
1/1/5
BILL NO. 02: PODIUM
2/Summ/1
BILL NO. 03 : OFFICE TOWER
3/Summ/1
BILL NO. 04 : HOTEL TOWER
4/Summ/1
BILL NO. 05 : PROVISIONAL SUMS
5/PS/4
TENDERER'S ADJUSTMENT SCHEDULE * ADDITIONS/OMISSION
TAS/6
Sub-Total
KD
TENDERER'S PRICE ADJUSTMENT * ADDITIONS/OMISSIONS
KD
TOTAL CARRIED TO FORM OF TENDER (IN WORDS) KUWAITI DINARS
KD
SIGNATURE OF TENDERER :
STAMP
* Delete as appropriate
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
MS/1
Main Summary
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ANALYSIS OF PRICES
The Tenderer is required to complete the following Schedule in every respect for all rates and prices in the Bills of Quantities. The sample schedule provided shall be copied as necessary. The total amount quoted shall equate to the full unit rate or lump sum as inserted against each respective item in the Bills of Quantities. Tenderers who offer lump sum or percentage Tenderer's Price Adjustments may be requested to submit Analyses of Prices for rates after adjustment of Tender Price Adjustment. Prior to the acceptance of the Tender, the T enderer may be required to provide further substantiating details and/or amend any unreasonable rates of analysis. Where no Subcontractor's OH & P is declared, Contractor's OH & P is deemed to include all OH & P including any subcontractors or suppliers OH & P.
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
AP/1
Analysis of Prices
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
ANALYSIS OF PRICES
ITEM
BILL OF UNIT RATE QUANTITIES OR PRICE ITEM KD
LABOUR KD
PLANT KD
KEO/07-2345-0011/BP3-Structural Works Burj Alshaya
MATERIAL KD
SUB-TOTAL 1 KD
SUBCONTRACTOR'S CONTRACTOR'S OH & P SUB-TOTAL 2 OH & P % KD KD % KD
AP/2
TOTAL KD
Analysis of Prices
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
DESCRIPTION
DAYWORK SCHEDULE
General Tenderers are to note that the pricing of the following schedule of daywork rates is not to be carried to the Summary or to the Form of Tender. The prices inserted against these items will form a basis for assessing the value of any dayworks which may become necessary during the course and within the terms of the Contract. Rates quoted for dayworks will be taken into consideration when Tenders are examined and they shall bear a reasonable relationship with the unit rates entered elsewhere in these documents. If any rates are found upon examination to be excessive or abnormal then the successful Tenderer will be called upon to revise such rates prior to the signing of the Contract. Failure to do so may lead to rejection of the Tender. Time engaged in the actual works will be the time allowed.
AMOUNT
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
DESCRIPTION
AMOUNT
DAYWORK SCHEDULE
General Tenderers are to note that the pricing of the following schedule of daywork rates is not to be carried to the Summary or to the Form of Tender. The prices inserted against these items will form a basis for assessing the value of any dayworks which may become necessary during the course and within the terms of the Contract. Rates quoted for dayworks will be taken into consideration when Tenders are examined and they shall bear a reasonable relationship with the unit rates entered elsewhere in these documents. If any rates are found upon examination to be excessive or abnormal then the successful Tenderer will be called upon to revise such rates prior to the signing of the Contract. Failure to do so may lead to rejection of the Tender. Time engaged in the actual works will be the time allowed. The signature of the Engineer on Daywork Records will be for record purposes only and the Engineer reserves the right to measure and value any works for which daywork records have been kept. Subject to the provisions of the preceding clause, the Contractor will be paid for dayworks carried out during the course of the Contract, while other operations are in progress at the rates set down by him in this schedule. Rates quoted for dayworks shall be applicable to any day of the week and to any time of day or night irrespective of any trade, local or other custom. Supervision costs including foremen are included in the percentage on cost.
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
DW/1
Dayworks
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
LABOUR
HOURLY RATE
Daywork rates quoted for labour shall be the net amounts payable to the employee and shall be detailed in the appropriate section below: Labour on Site A
_____________________________
B
_____________________________
C
_____________________________
D
_____________________________
E
_____________________________
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
DW/2
Dayworks
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
Labour On Costs
PERCENT
The Tenderer shall append his required percentage addition within the space provided below for all on-costs on his basic labour cost. This percentage shall be deemed to include for: i)
Complying with the Labour Law and all of its up to-date amendments, together with any additional costs for inducements required to attract and retain labour on the site.
ii)
The use of all hand tools, the use of all ordinary non mechanical plant including staging, scaffolding, etc., where not erected solely for execution of the daywork item, the use of all electric light and power supplies and access to and use of all the Contractor's site f acilities
iii) All overtime payments including non-productive overtime and travelling time other than that specifically ordered by the Engineer at the time of instructing the daywork. iv)
The cost of all supervision of labour employed on the daywork item including engineers, clerks, store-keepers etc.
v)
Overhead and profit including both head office and site overheads. Percentage addition required to be added to basic labour rates as detailed for on-costs as described:
%
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
DW/3
Dayworks
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
MATERIALS Materials used on Daywork items shall be of the same quality as specified for the whole of the Works. The rates used will be the NET price of the respective materials delivered to site and shall include for all costs of loading at source of supply and transporting to the Site. In the case of materials specifically imported for use on daywork items at the instruction of the Engineer the rates used will include, in addition to the requirements listed above, for freight charges, insurance, custom duties and port landing charges. All material rates used on daywork will require to be substantiated by invoices and in the event of no invoices being forthcoming, the Engineer may, at his own discretion, replace the rate claimed by the Contractor with the lowest current market price for that material.
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
DW/4
Dayworks
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
Materials On-Costs
PERCENT
The Tenderer shall append his required percentage addition within the space provided below for all on-costs on his basic material costs and this percentage shall be deemed to include for: i)
Unloading at site, storage and protection, transporting around the Site and unloading at the working area, breakages, waste and checking materials.
ii)
Overheads and profit include both head office and site overheads. Percentage addition required to be added to basic material rates as detailed for on-costs as described:
%
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
DW/5
Dayworks
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
PLANT The Contractor is to insert in following schedule the hire rates, which will be applicable for the duration of the contract for all plant he proposed to have on Site. Should plant other than that already on site be required for any item of daywork then the rates included on the daywork returns will be the local hire rates current at the time of the work. The rates inserted on the schedule by the Contractor are to include for drivers, attendants, operators, maintenance of plant in proper working order, attendance in starting up and shutting down, refueling including all fuel, power, lubricating oil and grease, regular cleaning, all cleaning materials, replacement and/or sharpening of tools, ancillary items and consumable spares. Plant hired from local plant hire companies must have insurance cover at least equal to that of the Contractor's plant on site and no payment will be made for mechanics or maintenance time which shall be deemed to be included in the spread over the rates for the plant concerned. The hourly rate for plant will apply to the time when the plant is on Site only. Plant On-Cost
PERCENT
The Tenderer shall append his required percentage addition within the space provided below for all on-cost on his hourly rates for plant and this percentage shall be deemed to include for: i)
Transporting plant to and from the site
ii)
Overheads and profits including both head office and site overheads. Percentage addition required to be added to the hourly rates of plant as detailed for on-costs as described
%
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
DW/6
Dayworks
BURJ AL SHAYA BP3 - STRUCTURAL WORKS KUWAIT
Schedule of Plant on Site for Use on Daywork Items
HOURLY RATE
DAYWORKS SCHEDULE
Plant List A
_____________________________
B
_____________________________
C
_____________________________
D
_____________________________
E
_____________________________
F
_____________________________
G
_____________________________
H
_____________________________
J
_____________________________
KEO/07-2345-0011/BP3-Structural W orks Burj Alshaya
DW/7
Dayworks