ICS-II, Task 4 GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
Main Activity 1:
BENCHMARKING REPORT Prepared by German Flores Antonio Karzulovic Karzulovic
December 2002
CONTENTS EXECUTIVE SUMMARY 1.
INTRODUCTION
1
2.
BENCHMARKING
2
3.
DATA PROCESSING
4
4.
GENERAL DATA
7
5.
GEOTECHNICAL DATA
9
5.1.
STRUCTURES
9
5.2.
ROCK MASS
9
5.3.
STRESS ENVIRONMENT
18
5.4.
HYDROGEOLOGY
18
5.5.
GEOTECHNICAL SOFTWARE
22
6.
MINE DESIGN DATA
25
6.1.
SLOPE GEOMETRY
25
6.2.
MINE ACCESSES
25
6.3.
BLOCK HEIGHT AND FOOTPRINT
30
6.4.
CAVING INITIATION
32
6.5.
UNDERCUT LEVEL
35
6.6.
EXTRACTION LEVEL
35
6.7.
SUPPORT
43
6.8.
MATERIAL HANDLING SYSTEM
47
7.
MINE OPERATION DATA
48
8.
GEOTECHNICAL INSTRUMENTATION AND MONITORING DATA
51
9.
GEOTECHNICAL HAZARDS DATA
53
9.1.
COLLAPSES
53
9.2.
ROCKBURSTS
56
9.3.
SUBSIDENCE
61
9.4.
WATER INFLOWS AND MUDRUSHES
68
9.5.
HANGUPS
71
9.6.
FINAL COMMENTS
73
10.
CONCLUSIONS
76
11.
ACKNOWLEDGMENTS
78
12.
REFERENCES
79
Appendix A:
GENERAL DATA ON MINES VISITED
Appendix B:
BENCHMARKING SURVEYS
Appendix C:
DATABASE
CONTENTS EXECUTIVE SUMMARY 1.
INTRODUCTION
1
2.
BENCHMARKING
2
3.
DATA PROCESSING
4
4.
GENERAL DATA
7
5.
GEOTECHNICAL DATA
9
5.1.
STRUCTURES
9
5.2.
ROCK MASS
9
5.3.
STRESS ENVIRONMENT
18
5.4.
HYDROGEOLOGY
18
5.5.
GEOTECHNICAL SOFTWARE
22
6.
MINE DESIGN DATA
25
6.1.
SLOPE GEOMETRY
25
6.2.
MINE ACCESSES
25
6.3.
BLOCK HEIGHT AND FOOTPRINT
30
6.4.
CAVING INITIATION
32
6.5.
UNDERCUT LEVEL
35
6.6.
EXTRACTION LEVEL
35
6.7.
SUPPORT
43
6.8.
MATERIAL HANDLING SYSTEM
47
7.
MINE OPERATION DATA
48
8.
GEOTECHNICAL INSTRUMENTATION AND MONITORING DATA
51
9.
GEOTECHNICAL HAZARDS DATA
53
9.1.
COLLAPSES
53
9.2.
ROCKBURSTS
56
9.3.
SUBSIDENCE
61
9.4.
WATER INFLOWS AND MUDRUSHES
68
9.5.
HANGUPS
71
9.6.
FINAL COMMENTS
73
10.
CONCLUSIONS
76
11.
ACKNOWLEDGMENTS
78
12.
REFERENCES
79
Appendix A:
GENERAL DATA ON MINES VISITED
Appendix B:
BENCHMARKING SURVEYS
Appendix C:
DATABASE
EXECUTIVE SUMMARY In the next 10 to 15 years several mines are considering a transition from open pit to underground cave mining. These include: Argyle Diamond Mine, Bingham Canyon, Chuquicamata, Grasberg, WMC Mount Keith and Newcrest Telfer. Considering this fact, the ICS-II included Task 4 with the goal of providing the project sponsors with practical geotechnical guidelines to develop the transition from open pit to underground cave mining. To achieve this objective, the following main activities have been considered: Benchmarking, Geotechnical Guidelines, Guidelines, worked Example Example and Final Report. Currently, and according to the program approved at the ICS-II Meeting of October 2001, in Santiago, only the first activity, BENCHMARKING, ING, has been developed and it is presented in this report. The benchmarking study was planned and developed according to a program aimed to optimize data collection: 1.
SURVEY DESIGN: This was the first task to be completed. In order to facilitate data collection, an Excel© spreadsheet was designed, and e-mailed to the targeted mines also willing to provide information.
2.
MINE VISITING: VISITING : 17 mines were selected to be visited and relevant information was obtained. The selection criterion was mines which have developed, or are planning to develop, a transition from open pit to underground mining, and also other mines (open pits and underground) that could provide relevant information.
3.
ADDITIONAL DATA COLLECTION : a comprehensive survey of the available technical literature was done in order to collect collect supplementary data. This allows the inclusion inclusion of data on 88 additional mines; nevertheless, in most of the cases, the additional data does not include all the features considered in the benchmarking survey.
4.
DATA PROCESSING: The PROCESSING: The collected data was analyzed in order to develop histograms and, where possible, correlations showing the current practices and tr ends of underground mining by caving methods. methods. When enough data was available available the relative frequency frequency of the different parameters was computed, and when the available data was limited, the relative importance of the different parameters was assessed.
5.
BENCHMARKING REPORT: REPORT : All of the above mentioned, and the conclusions and recommendations recommendations resulting from this benchmarking are presented in this report.
The interpretation of the data collected in this benchmarking has allowed to define the current trends and practices of the underground mining by caving methods. These have been summarized as histograms and/or curves to facilitate their use by the sponsors of ICS-II, especially during the early stages of a new mining project. One of the main results of this study is shown in the following Table which summarizes the current trends for the most relevant design parameters used at the caving mine operations. Finally it must be noted that all the results presented in this report will be used as a starting basis for the development of geotechnical guidelines for a transition from open pit to underground mining, which corresponds to the second main activity of Task 4, and includes the following subjects: 1.
CAVING PROPAGATION
2.
SUBSIDENCE
3.
CROWN-PILLAR
4.
WATER INFLOWS
TYPICAL DESIGN PARAMETERS FOR A BLOCK/PANEL CAVING MINE Mine Design Parameter
Typical Value
Rock Mass Quality
50 ≤ RMR < 60
Acces
Decline
Block Height < 50000 m Footprint Area
50000 a 100000 m > 100000 m
Caving Initiation
l e v e L t u c r e d n U
2
This typical block height could vary ± 20%.
30000 m
2
75000 m
2
170000 m
These typical areas could vary +20%. It is recommended to use equal or larger areas, but not smaller than the typical values. Also, square areas are better than the rectangular ones.
2
2
Area
10000 m
Shape
Square
Measures to Facilitate
Slot
Is highly recommended to facilitate cave initiation.
Hydraulic Radius
20 to 30 m
Avoid being close to the limit in Laubscher’s chart.
Spacing
15 m
Height Width
4m 4m
Could be increased but not decreased.
Undercut Height
8m
Could vary, but be careful if using small undercutting heights.
Undercut Rate
2100 m /month
s t f i r D
o l i t e c v a e r L t x n E
2
If RMR > 60 rock mass cavability must be evaluated carefully. Currently 70% of mines prefer declines, and 20% declines and shafts as mine access.
210 m 2
Comments
Smaller areas are not recommended, specially in massive rock masses. Internal corners must be avoided (e.g. a “L” shaped area).
This is the current practice.
2
Could be increased but be careful with induced seismicity, specially if in a high stress environment.
Crown-Pillar Thickness
17 m
Could vary ± 20% (measured from floor UCL to floor EXT).
Spacing
30 m
Could vary from 26 to 36 m.
Height Width
4m 4m
s t f i r D
Spacing
Draw Points
Influence Area Draw Rates
LHD Equipment
Could be increased but not decreased.
15 m 225 m
Could vary from 13 to 18 m. 2
2
Could vary from 169 to 324 m . This is an average value. Typically lower values are used at the beginning of caving, and higher values are used when over 30% of the block height has been extracted.
0.20 m/day
Capacity
11 ton
It could vary ± 20%.
Traming Distance
140 m
Smaller tramming distances are preferable.
Powder Factor
400 grm/ton
Oversize Limit
3
Subsidence
RMR < 70 RMR > 70
1.8 to 2.0 m α >
45° α > 60°
For undercutting blasting. It could vary ± 20%. It could vary ± 20%. α is
the break angle defining the mean inclination of the crater walls.
Geotechnical Hazards
The project must take account that collapses, rockbursts, subsidence, water inflows and mudrushes, and hangups could occur
Instrumentation & Monitoring
The most common monitoring systems include displacements and seismicity. It is recommended to include a seismic monitoring system, specially in massive hard rock and/or high stress environments..
(1)
These typical values are intended only for the pre-feasibility stage of a mining project.
(2)
RMR values are for Laubscher’s 1990 system.
ICS-II, Task 4
1.
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
INTRODUCTION Several mines are considering a transition from open pit to underground cave mining, in the mid to long term. These include: Argyle Diamond Mine, Bingham Canyon, Chuquicamata, Grasberg, WMC Mount Keith and Newcrest Telfer. Considering this fact, the ICS-II included Task 4 with the goal of providing the project sponsors with practical geotechnical guidelines to develop the transition from open pit to underground cave mining. To achieve this objective, the following has been considered: 1.
BENCHMARKING, to collect data from mines which have developed, or are planning to develop, a transition from open pit to underground mining, and also from other mines (open pits or underground) that could provide relevant information for this research. The collected data was supplemented by a comprehensive review of t he available technical literature.
2.
GEOTECHNICAL GUIDELINES , to develop practical methodologies to deal with the key issues arising in a transition from open pit to underground cave mining. These guidelines will address the following subjects: Caving Propagation, Subsidence, Crown/Buffer-Pillar, and Water Inflows.
3.
WORKED EXAMPLE, to illustrate the use of these geotechnical guidelines by applying them to a real case example: Chuquicamata Mine.
4.
FINAL REPORT, to include the results of the benchmarking, the geotechnical guidelines, and the worked example in a self-contained technical report.
Currently, and according to the program approved at the ICS-II Meeting of October 2001, in Santiago, only the first activity, BENCHMARKING, has been developed and it is presented in this report.
1
ICS-II, Task 4
2.
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
BENCHMARKING The benchmarking study was planned and developed according to a program aimed to optimize data collection: 6.
SURVEY DESIGN: This was the first task to be completed. In order to facilitate data collection, an Excel© spreadsheet was designed, and e-mailed to the targeted mines also willing to provide information. These spreadsheets are included, with the data collected, in Appendix B.
7.
MINE VISITING: 17 mines were selected to be visited and relevant information was obtained. The selection criterion was mines which have developed, or are planning to develop, a transition from open pit to underground mining, and also other mines (open pits and underground) that could provide relevant information. Table 2.1 summarizes the mines that were visited, and in Appendix A general information on these mines is presented.
8.
ADDITIONAL DATA COLLECTION : a comprehensive survey of the available technical literature was done in order to collect supplementary data. This allows the inclusion of data on 88 additional mines; nevertheless, in most of the cases, the additional data does not include all the features considered in the benchmarking survey.
9.
DATA PROCESSING: The collected data was analyzed in order to develop histograms and, where possible, correlations showing the current practices and tr ends of underground mining by caving methods. When enough data was available the relative frequency of the different parameters was computed, and when the available data was limited, the relative importance of the different parameters was assessed. The databases resulting from this data processing are included in Appendix C.
10.
BENCHMARKING REPORT: All of the above mentioned, and the conclusions and recommendations resulting from this benchmarking are presented in t his report.
2
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
Table 2.1 MINES VISITED FOR BENCHMARKING Country
Mine
Comments
Cadia Hill
Open pit mine. Visited October 2002.
Mount Keith
Open pit mine. Project for a transition to underground mining. Visited May 2002
Northparkes
Mine that developed a transition from open pit to underground mining. Underground mining by block caving. Visited October 2002
Ridgeway
Underground mining by sublevel caving. Visited October 2002
Kidd Creek
Mine that developed a transition from open pit to underground mining. Underground mining by open stoping. Visited June 2002
Andina
Open pit mine and underground mining by panel caving. Visited July 2002
Chuquicamata
Open pit mine. Project for a transition to underground mining. Visited July 2002
El Teniente
Underground mining by panel caving. Visited July 2002
Salvador
Underground mining by panel caving. Visited July 2002
Australia
Canada
Chile
Indonesia
Grasberg Underground (DOZ) Grasberg Open Pit
South Africa
Sweden
Underground mining by panel caving. Open pit mine. Project for a transition to underground mining. Visited April 2002
Finsch
Mine that developed a transition from open pit to underground mining. Underground mining by open stoping. Visited May 2002
Koffiefontein
Mine that developed a transition from open pit to underground mining. Underground mining by sublevel / front caving. Visited May 2002
Palabora
Mine developing a transition from open pit to underground mining. Open pit mine and underground mining by panel caving. Visited May 2002
Kiruna
Mine that developed a transition from open pit to underground mining. Underground mining by sublevel caving. Visited June 2002
Bingham Canyon
Open pit mine. Project for a transition to underground mining. Visited June 2002
Henderson
Underground mining by panel caving. Visited June 2002
USA
3
ICS-II, Task 4
3.
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
DATA PROCESSING The collected data was analyzed in order to develop histograms and, if possible, correlations showing the current practice and trends of open pit and underground mining by caving methods. When enough data was available the relative frequency of the different parameters was computed, and when the available data was limited the relative importance of the different parameters was assessed. The collected data included:
GENERAL DATA GEOTECHNICAL DATA MINE DESIGN DATA MINE OPERATION DATA MONITORING DATA GEOTECHNICAL HAZARDS DATA
The process of data collection and processing showed that the number of mines that have developed, are in the process of developing, or will develop a transition from open pit to underground mining, or vice versa, was more than what was expected. Indeed, Table 3.1 summarizes data on 33 mines that are under this condition. Also, the analysis of the data indicated a sudden increase in the pit depths of the mines that will have this transition in a mid or a long term, as illustrated by Figure 3.1. This is especially important because it means that the geotechnical challenges for these projects will be expected to be larger than the ones of the mines that had developed a transition in the past. The pits that will have large depths when initiating the transition process are: Bingham Canyon, USA (747 to 849 m depth) Chuquicamata, Chile (1100 m depth) Grasberg, Indonesia (1000 m depth)
4
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
Table 3.1 MINES THAT DEVELOPED, ARE DEVELOPING OR WILL D EVELOP A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING Country
Mine Argyle Diamond Big Bell
Australia
H PIT (m)
Transition Type Open pit UG mining
→ UG
→ Open
pit
mining →
Mount Keith Open pit
Developments
150 a 300
Mining 2006 (?)
1994
UG mining
Mount Isa
Date
1997
146
1967
344
2015 (?)
UG mining
→
Northparkes
100
1993
1997
76
1963
1964
250
1969
1973
150 (?)
1941
1948
Perseverance Craigmont Canada
Kidd Creek
Open pit
UG mining
→
Stobie Williams Chile
Chuquicamata
Open pit
UG mining
→
Mansa Mina
1100
2016 (?)
400 (?)
2014 (?)
Finland
Pyhasalmi
Open pit
→
UG mining
135
1967
Indonesia
Grasberg
Open pit
→
UG mining
1000
2016 (?)
Open pit
→
UG mining
Russia
South Africa
Sweden
Kirovsky
1959
Mir
455
Finsch
423
Koffiefontein
240
Palabora
1994 1979
1981
803
1996
2000
Premier
189
1945
1946 (?)
Thabazimbi
70 a 240
1988 (?)
Venetia
360 (?)
2011 (?)
230
1958
747 a 899
2012 (?)
Open pit
UG mining
→
Kiruna
Open pit
→
Bingham Canyon
Open pit
→ UG
UG mining mining
Climax USA
1973 UG mining
→ Open
pit
Miami San Manuel Questa
Zambia
1990
Nchanga
UG mining
→ Open
Open pit UG mining
→
→ Open
pit
→
UG mining
UG mining pit
→
150 (?)
UG mining
1979
1983
1937
1939
1955
1957
Gaths Zimbabwe
Miriam
Open pit
→ UG
mining
60
Shabanie
150 (?)
1950 (?)
Shangani
150
1980 (?)
5
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
1200 MINES THAT DEVELOPED A TRANSITION FROM OP TO UG
1100
CHUQUICAMATA
MINES THAT ARE DEVELOPING A TRANSITION FROM OP TO UG MINES THAT WILL DEVELOP A TRANSITION FROM OP TO UG
1000
GRASBERG TREND FROM CASE HISTORIES TREND FROM PROJECT DATA
) 900 m (
H T P E D T I P M U M I X A M
BINGHAM CANYON
800
PALABORA
700 600 500 400 300 200 100 0 1945
1950
1955
1960
1965
1970
1975
1980
1985
1990
1995
2000
2005
2010
2015
2020
EAR
Figure 3.1:
Evolution through time of the trend for t he depth of open pit mines that have developed, are developing, or will develop a transition to underground mining.
6
ICS-II, Task 4
4.
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
GENERAL DATA The general data collected include:
Mine name, location, country, and owner.
Mine elevation, ore type, mined out reserves, initial mining method, and initial mining date.
Current mining method, reserves, mean ore grade, mine life, final mine depth, cash and total costs (if provided), ore production, and waste removal. Future mining method, reserves, mean ore grade, mine life, final mine depth, cash and total costs (if provided).
Total work force.
Geotechnical groups (engineers, geologists, technicians)
Additional comments.
All the data obtained for each mine visited are included in Appendix B. The analysis of the production and information on geotechnical groups is summarized in Figure 4.1, and indicates that: (a)
Due to the nature of mining methods open pit mines have much larger ore production than underground mines; therefore, any open pit considering a transition to underground mining must take account of this fact.
(b)
Typically geotechnical groups are larger in underground mines than in open pit mines (of course there are a few exceptions).
(c)
According to the data, it is possible to define a trend between the size of the typical geotechnical group and the ore production for open pit and underground mining. These trends indicate that:
(d)
The larger the ore production the larger the typical geotechnical group in both cases, open pit and underground mining. This trend shows a break or a sudden increase in the number of people in the geotechnical group when the ore production exceeds 25 kTPD in underground mines, and 75 kTPD, in open pit mines.
Therefore, considering a transition to underground mining, any open pit must take this fact into account, and probably will have to increase the number of people in its geotechnical group (in spite of the fact that the underground ore production will be smaller that the open pit production).
7
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
30
) e l p o e p (
G N I N I M ) D D N P U T O R 5 k G 2 R E a n h D t N U r e E m o V I ( S S A M
25
20
P U O R G 15 L A C I N H C 10 E T O E G
N G N I M I ) P I T T P D N 5 k E 7 O P n E t h a V I r e S S m o M A (
UG (< 25 k TPD )
5
OP (< 75 kT PD)
MINING METHOD OPEN PIT UNDERGROUNG
0 0
25
50
75
100
125
150
175
200
225
250
ORE PRODUCTION (kTPD)
Figure 4.1:
Variation of the size of the typical geotechnical group with ore production in open pit and underground mining.
8
ICS-II, Task 4
5.
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
GEOTECHNICAL DATA The geotechnical data collected included information on Structures, Rock Mass, Stress Environment, and Hydrogeology.
5.1. STRUCTURES The data collected on structures include:
Structural domains
Number of structural sets
Geological characteristics: type of structure, infilling, waviness, roughness, and water condition. Geometrical characteristics: dip, dip direction, length, spacing, and gap. Mechanical properties: joint roughness coefficient (JRC), joint wall compressive strength (JCS), dilation angle (i ), cohesion (cJ), friction angle (φ J), normal stiffness (kN), and shear stiffness (kS).
All the data obtained for each mine visited are included in Appendix B. The analysis of the data on the orientation and properties of the structural sets in open pit and underground mines indicates that: (a)
In most underground mines that use caving methods, subvertical structures predominate (subvertical meaning dips steeper than 60°), as shown in Figures 5.1 and 5.2. This conclusion does not mean that there are not subhorizontal or flatter structures, but that the number of subvertical sets (> 60°) exceeds the number of flatter sets (< 60°).
(b)
In underground and open pit mines the data on the orientation of structures is typically much better than the data on their length, spacing, and gap. Generally the data can be ordered from more to less reliable as follows: Dip
→ Dip
Direction
→ Spacing → Length → Gap
(c)
The geotechnical characterization of structures generally is poorer in underground mines than in open pit mines. Perhaps due to the fact that mapping is more difficult underground. This is shown in Figure 5.3 that correlates the magnitude of the cohesion and friction angle, and shows a much better trend in the data from open pits than in the one from underground mines.
(d)
In open pit mines the strength properties of structures are fairly to well known, but the deformability properties are poorly to fairly known.
(e)
In underground mines the strength properties of structures are poorly to fairly known, but their deformability properties are almost unknown.
(f)
In spite of the increasing use of numerical models, the quality of input data on the mechanical properties of structures is, in most of cases, poor.
5.2. ROCK MASS The data collected on rock masses include:
Rock types. Intact rock properties: unit weight (γ), uniaxial compressive strength (UCS), parameter m of the Hoek-Brown criteria (mi), modulus of deformability (E), wave velocity for P and S waves (VP and VS).
9
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
1
85 - 90
3
2
4
3
1
75 - 79
1
1
2
1
2
1
1
1
4
70 - 74
2
65 - 69
1
1
1
6
1
60 - 64
1
50 - 54
1
45 - 49
2
2 1 1
1
1
3
4
3 4
3
1
1
1
2
1
2
11
3
1
1 1
1
1
1
2
1
3
1
1
1
1
2
1
4
2
1
3
3
1
3
1
1
3
2
2
2 1
1 1
1 2 2
1
55 - 59
D
1
80 - 84
1
2
1 1
1
2
1
1
I P
1
40 - 44
1
35 - 39
1
3
1 1
30 - 34
25 - 29
1
20 - 24
1
15 - 19
10 - 14
1
5 - 9
1
0 - 4
0 -1 9
2 0- 3 9
4 0- 5 9
6 0- 7 9
8 0- 9 9
1 00 - 1 19
1 20 - 1 39
1 40 - 1 59
1 60 - 1 79
D IP
Figure 5.1:
1 80 - 1 99
2 00 - 2 19
2 20 - 23 9
24 0 - 25 9
26 0 - 27 9
2 80 - 29 9
3 00 - 3 19
3 20 - 3 39
3 40 - 3 59
D IR EC TI ON
Trend of the orientation (defined by dip and dip direction) of structural sets in underground mines that use caving methods.
RELATIVE FREQUENCY 0.00
0.02
0.04
0.06
0.08
0.10
0.12
0.14
0.16
0.18
0.20
0.22
0
10
20
30
) s s e r 40 g e d (
P I D
50
60
70
80
90
Figure 5.2:
Histogram showing the relative frequency of different dip angles for structural sets in underground mines that use caving methods.
10
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
200
) a P k ( 175
OPEN PIT MINING UNDERGROUND MINING
S E R U 150 T C U R T 125 S L A C I 100 G O L O 75 E G F O 50 N O I S E 25 H O C 0 15
20
25
30
35
40
45
FRICTION ANGLE OF GEOLOGICAL STRUCTURES (degrees)
Figure 5.3:
Variation of the cohesion of structures with their friction angle, for open pit and underground mines.
Rock mass quality: RQD, RMRBIENIAWSKI , RMRLAUBSCHER , Q, GSI. Rock mass properties: cohesion (c), friction angle (φ ), modulus of deformability (E), Poisson’s ratio (ν), bulk modulus (B), shear modulus (G), wave velocity for P and S waves (VP and VS).
All the data obtained for each mine visited are included in Appendix B. The analysis of the data on the rock masses in open pit and underground mines indicates that: (a)
The data on intact rock properties is well known for the unit weight (γ), and the uniaxial strength (UCS); but the data for the other intact rock parameters is poorer.
(b)
Typically UCS values are smaller for open pit mines rocks (averages 80 MPa) that for underground mines rocks (averages 115 to 150 MPa). There is also no major difference in the UCS values for the rocks in different types of underground mining. This is shown in Figure 5.4.
(c)
Typically RQD values are smaller for open pit mines rocks (averages 65%) than for underground mines rocks (averages 70% to 85%). Also there is no major difference in the RQD values for the rocks in different types of underground mining. This is shown in Figure 5.5.
(d)
The most used method for rock mass classification in underground mines is Laubscher’s RMR (53%), followed by Barton’s Q (26%), and Bieniawski’s RMR (15%). The most used method for rock mass classification in open pit mines is Hoek’s GSI (39%), followed by Bieniawski’s RMR (26%), and Laubscher’s RMR (22%). This is shown in Figure 5.6.
11
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.55
MINING METHOD 0.50
OPEN PIT OPEN STOPING SUBLEVEL CAVING
0.45
BLOCK CAVING PANEL CAVING
0.40
Y C N 0.35 E U Q E 0.30 R F E 0.25 V I T A 0.20 L E R 0.15 0.10
0.05
0.00 0
50
100
150
200
250
300
350
400
450
500
IN TA C T R OC K U NIA XIA L C OMP RE SS I E S TR EN GTH , U C S (MPa)
Figure 5.4:
Relative frequency of the intact rock’s uniaxial compressive strength, UCS, in different mining methods.
0.70 MINING METHOD
0.65
OPEN PIT OPEN STOPING
0.60
SUBLEVEL CAVING BLOCK CAVING
0.55
PANEL CAVING
Y 0.50 C N 0.45 E U Q 0.40 E R F 0.35 E V I 0.30 T A 0.25 L E R 0.20 0.15 0.10 0.05 0.00 0
10
20
30
40
R OC K QU AL IT
Figure 5.5:
50
60
70
80
90
100
D ES IGN ATIO N, R QD (%)
Relative frequency of the Rock Quality Designation Index, RQD, in different mining methods.
12
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.55 MINING METHOD 0.50
OPEN PIT UNDERGROUND
0.45 0.40
Y C N 0.35 E U Q E 0.30 R F E 0.25 V I T A 0.20 L E R 0.15 0.10 0.05 0.00 Q (Barton et al.)
RMR (Bieniawski)
RMR (Laubscher)
GSI (Hoek et al.)
ROCK MASS CLASSIFICATION SYSTEM
Figure 5.6:
Methods used in mining for rock mass classification.
(e)
Interpreting all rock mass classification data in terms of Laubscher’s RMR it is clearly evident, as shown in Figure 5.7, that rock mass quality is poorer in open pit mines (averages 40) than in underground mines (averages 50 to 60).
(f)
The typical rock mass rating distribution for different mining conditions are shown in Figures 5.8 to 5.12, which show the following typical RMR ranges: Open Pit Mines RMR: 20 to 40
(g)
Open Stoping Mines:
RMR: 40 to 80
Sublevel Caving Mines:
RMR: 40 to 70
Block Caving Mines:
RMR: 30 to 70
Panel Caving Mines:
RMR: 40 to 80
As shown in Figure 5.13, the average trend relating Laubscher´s RMR and MRMR is: MRMR = 0.9 × RMR
(h)
As shown in Figure 5.14 the cohesion of underground mines rock masses is typically larger than the cohesion of open pit rock masses, probably due to the higher confinement in underground mining. This figure also shows that the trend between rock mass cohesion and rock mass friction angle is better for the case of open pits than for underground mines.
(i)
The geotechnical characterization of rock masses seems to be poorer in underground mining than in open pit mining. Indeed, in spite of the increasing use of numerical models the quality of input data on r ock mass properties is, in most cases, poor to fair.
13
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.60
MINING METHOD 0.55 OPEN PIT OPEN STOPING
0.50
SUBLEVEL CAVING BLOCK CAVING PANEL CAVING
0.45
Y C 0.40 N E U 0.35 Q E R F 0.30 E V I 0.25 T A L 0.20 E R 0.15 0.10
0.05
0.00 0
10
20
30
40
50
60
70
80
90
100
LAUBSCHER´S ROCK MASS RATING, RMR Figure 5.7: Relative frequency of Laubscher’s Rock Mass Rating, RMR, in open pits and underground mines that use different mining methods.
0.60 0.55
0.50
0.45
Y C 0.40 N E U 0.35 Q E R 0.30 F E V 0.25 I T A L 0.20 E R 0.15
0.10
0.05
0.00 0
10
20
30
40
50
60
70
80
90
100
L AU BS C HE R´S R OC K MA SS R AT IN G, R MR
Figure 5.8:
Relative frequency of Laubscher’s Rock Mass Rating, RMR, in open pit mining.
14
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.40
0.35
0.30
Y C N E 0.25 U Q E R 0.20 F E V I T A 0.15 L E R 0.10
0.05
0.00 0
10
20
30
40
50
60
70
80
90
100
L AU BS C HE R´S R OC K MA SS R AT IN G, R MR
Figure 5.9:
Relative frequency of Laubscher’s Rock Mass Rating, RMR, in open stoping mining.
0.40
0.35
0.30
Y C N E 0.25 U Q E R 0.20 F E V I T A 0.15 L E R 0.10
0.05
0.00 0
10
20
30
40
50
60
70
80
90
100
LAUBSCHER´S ROCK MASS RATING, RMR
Figure 5.10: Relative frequency of Laubscher’s Rock Mass Rating, RMR, in sublevel caving mining.
15
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.35
0.30
Y 0.25 C N E U Q 0.20 E R F E V I 0.15 T A L E R 0.10
0.05
0.00 0
10
20
30
40
50
60
70
80
90
100
L AU BS C HE R´S R OC K MA SS R AT IN G, R MR
Figure 5.11: Relative frequency of Laubscher’s Rock Mass Rating, RMR, in block caving mining.
0.40
0.35
0.30
Y C N E 0.25 U Q E R 0.20 F E V I T A 0.15 L E R 0.10
0.05
0.00 0
10
20
30
40
50
60
70
80
90
100
L AU BS C HE R´S R OC K MA SS R AT IN G, R MR
Figure 5.12: Relative frequency of Laubscher’s Rock Mass Rating, RMR, in panel caving mining.
16
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
MRM R / RMR =
90
1.2
1.1
1 .0
0.9
MINING METHOD OPEN PIT
80
0.8
OPEN STOPING SUBLEVEL CAVING
70
0.7
BLOCK CAVING PANEL CAVING
60
0.6
R50 M R M40
0.5
30
20
10
0 0
10
20
30
40
50
60
70
80
90
100
LAUBSCHER´S RMR
Figure 5.13: Relationship between Laubscher’s Rock Mass and Mining Rock Mass Ratings, RMR and MRMR.
10000
5000
) a P k (
2000
N1000 O I S E 500 H O C S 200 S A M 100 K C O 50 R
OPEN PIT MINING
20
UNDERGROUND MINING
10 15
20
25
30
35
40
45
50
55
60
65
70
R OC K MA SS F RIC TION A NG LE (degrees)
Figure 5.14: Relationship between the cohesion and the friction angle of the rock mass in open pit and underground mining.
17
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
5.3. STRESS ENVIRONMENT The data collected on the stress environment include:
Production sector where the stress measurements were made. Stress tensor components: horizontal stress (Sx, Sy, X towards East, Y towards North), vertical stress (Sv), and shear stresses (Sxy, Syz, Szx).
Principal stresses: magnitudes (S1, S2, S3), plunges (α 1, α 2, α 3), and trends ( β 1, β 2, β 3).
Stress measurement method.
All the data obtained for each mine visited are included in Appendix B. The analysis of the data on the stress environment in underground mines indicates that: (a)
Currently the CSIRO Hollow Inclusion Cell is the most used method for in situ stress measurements.
(b)
As shown in Figure 5.15, in underground mines the in situ major principal stress S1 typically varies from 30 to 40 MPa.
(c)
As shown in Figure 5.16, the minimum principal stress S3 typically varies from 10 to 20 MPa.
(d)
As shown in Figure 5.17, the principal stress difference S1 - S3 typically varies from 20 to 30 MPa.
(e)
As shown in Figure 5.18, in underground mines the in situ vertical stress is larger than the lithostatic stress (γz). This result could be due to the fact that several stress measurements could be located in proximity to caves.
(f)
As shown in Figure 5.19, in underground mines the mean value of the stress ratio, KMEAN, is bounded as proposed by Hoek & Brown (1980): 0.5 + (1500/ z)
(g)
≥
KMEAN
≥
0.3 + (100/ z)
As a result of this benchmarking, similar relationships were derived for the minimum and maximum values of the stress ratio, KMIN and KMAX. These relationships are shown in Figures 5.20 and 5.21, and are given by: 0.6 + (1250/ z)
≥
KMIN
1.0 + (1500/ z)
≥
KMAX
≥ ≥
0.2 + (100/ z) 0.3 + (90 / z)
5.4. HYDROGEOLOGY The data collected on the hydrogeology include:
Hydrogeological units.
Maximum and minimum permeabilities (kMAX and kMIN).
General parameters: depth of the phreatic surface, infiltration rate into the mine, and dewatering rate. Operative parameters on drainage systems: drainage tunnels, pumping wells, and subhorizontal drains.
All the data obtained for each mine visited are included in Appendix B. The analysis of the data on the hydrogeology in open pits and underground mines indicates that: (a)
Most mines do not consider the hydrogeological characterization a high priority.
18
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.35
0.30
Y 0.25 C N E U Q 0.20 E R F E V I 0.15 T A L E R 0.10
0.05
0.00 0
10
20
30
40
50
60
70
80
90
100
MAJOR PRINCIPAL STRESS, S 1 (MPa)
Figure 5.15: Histogram showing the relative frequency of major principal stresses, S1, with different magnitudes (measurements in underground mines).
0.35
0.30
Y 0.25 C N E U Q 0.20 E R F E V I 0.15 T A L E R 0.10
0.05
0.00 0
5
10
15
20
25
30
35
40
MINOR PRINCIPAL STRESS, S 3 (MPa)
Figure 5.16: Histogram showing the relative frequency of major principal stresses, S3, with different magnitudes (measurements in underground mines).
19
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.20
0.15
Y C N E U Q E R 0.10 F E V I T A L E R 0.05
0.00 0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
PRINCIPAL STRESS DIFFERENCE, S 1 - S3 (MPa)
Figure 5.17: Histogram showing the relative frequency of major principal stress differences, S1 - S3, with different magnitudes (measurements in underground mines).
VERTICAL STRESS (MPa) 0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
0
250 500
750 1000
) s r e 1250 t e m (
H T P E D
1500
1750
2000 2250
2500 2750
3000
Figure 5.18:
Variation of in situ vertical stresses with depth in underground mines.
20
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
K MEAN 0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00
0
250
500
750
1000
) s r e 1250 t e m ( 1500
H T P 1750 E D 2000 2250
2500 2750
3000
Figure 5.19: Variation of the average value of the in situ stress ratio, KMEAN, with depth in underground mines. The black curves shown the upper and lower boundaries defined by Hoek & Brown (1980), while the red curve is the average between them.
K MIN 0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00
0
250
500
750
1000
) s r e 1250 t e m ( 1500
H T P 1750 E D 2000
2250
2500
2750
3000
Figure 5.20: Variation of the minimum value of the in situ stress ratio, KMIN, with depth in underground mines. The black curves shown the upper and lower boundaries defined in this work, while the red curve is the average between them.
21
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
K MAX 0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00
3.25
3.50
0
250
500
750
1000
) s r e 1250 t e m ( 1500
H T P 1750 E D 2000
2250
2500
2750
3000
Figure 5.21: Variation of the maximum value of the in situ stress ratio, KMAX, with depth in underground mines. The black curves shown the upper and lower boundaries defined in this work, while the red curve is the average between them.
(b)
As shown in Figure 5.22, in open pit mines the most used drainage systems are: subhorizontal drains (38%), drainage tunnels (27%), pumping wells (21%), and sumps (14%).
(c)
As shown in Figure 5.22, in underground mines the most used drainage systems are: sumps (78%), subhorizontal drains (14%), and drainage tunnels (8%).
(d)
The most typical monitoring systems are: observation wells (open holes), piezometers, and flow rate measurement devices.
5.5. GEOTECHNICAL SOFTWARE The data collected on geotechnical software currently being used in open pit and underground mines, included the name and type of software. All the data obtained for each mine visited are included in Appendix B. The analysis of this data indicates that: (a)
As shown in Figure 5.23, for conventional slope stability analyses the most used software are: SLIDE (30%), DIPS (20%), and SWEDGE (17%).
(b)
As shown in Figure 5.24, for two-dimensional numerical analyses the most used software are: FLAC (50%), UDEC (33%), and EXAMINE (10%).
(c)
As shown in Figure 5.25, for three-dimensional numerical analyses the most used software are: FLAC3D (44%), 3DEC (26%), and MAP3D (18%).
22
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.8 UNDERGROUND MINING OPEN PIT MINING 0.7
0.6
Y C N E 0.5 U Q E R 0.4 F E V I T A 0.3 L E R 0.2
0.1
0.0 D RAINA GE TUNNELS
PUM PI NG WELLS
SUBHORIZONTAL DRAI NS
SUMPS
DEWATERING SYSTEM
Figure 5.22: Relative frequency of different dewatering systems used in open pits and underground mines.
0.30 CONVENTIONAL SLOPE STABILITY SOFTWARE CURRENTLY USED IN OPEN PIT MINES
0.25
Y C 0.20 N E U Q E R 0.15 F E V I T A L 0.10 E R
0.05
0.00 SLIDE
DIPS
SWEDGE
XSTABL
ROCFALL
BACKBREAK GALENA
SLOPE/W
UTEXAS
NFOLD
SOFTWARE PACKAGE
Figure 5.23: Relative frequency of software used in open pit mines for conventional slope stability analyses.
23
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.55 2D NUMERICAL ANALYSIS SOFTWARE CURRENTLY USED IN OPEN PIT AND UNDERGROUND MINES
0.50
0.45
0.40
Y C N 0.35 E U Q E 0.30 R F E 0.25 V I T A 0.20 L E R 0.15 0.10
0.05
0.00
FLAC
UDEC
EXAMINE / EXAMINE TAB
PHASE2
SOFTWARE PACKAGE
Figure 5.24:
Relative frequency of software used in open pit and underground mines for twodimensional numerical analyses.
0.45 3D NUMERICAL ANALYSIS SOFTWARE CURRENTLY USE D IN OPEN PIT AND UNDERGROUND MINES
0.40
0.35
Y C 0.30 N E U Q 0.25 E R F E 0.20 V I T A L 0.15 E R 0.10
0.05
0.00
FLAC3D
3DEC
MAP3D
EXAMINE3D
BEFE
ELAST-3
SOFTWARE PACKAGE
Figure 5.25: Relative frequency of software used in open pit and underground mines for threedimensional numerical analyses.
24
ICS-II, Task 4
6.
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
MINE DESIGN DATA On open pit mines the mine design data collected included information on Slopes Geometrical Parameters, Acceptability Criteria, and Tools for Analysis. On underground mines the mine design data collected included information on Mine Accesses, Mining Method, Cave Initiation, Footprint, Block Height, Mine Layout, and Materials Handling Systems. All the data obtained for each mine visited are included in Appendix B.
6.1. SLOPE GEOMETRY The analysis of the data on slope geometries in open pit mines indicates that: (a)
As shown in Figure 6.1, bench heights can vary from 10 to 20 m for single benches, and from 25 to 35 m for double benches. The typical height for single benches is 15 m, while it varies from 25 to 30 m for double benches. In most cases double benches are developed in two stages (i.e. first a single bench is developed, and then it is doubled). This practice is very common for pushbacks that reach the final pit condition, and where the rock mass has a good geotechnical quality.
(b)
As shown in Figure 6.2, in open pit slopes the interramp height can vary widely, from 50 to 250 m; but typically it does not exceed 200 m, and its average value is about 140 m.
(c)
As shown in Figure 6.3, the overall height of open pit slopes can vary widely, from 100 to 900 m; but in most of the cases it varies from 100 to 500 m (more than 70% of the cases), and its average value is about 350 m.
(d)
As shown in Figure 6.4, the bench face inclination can vary from 55° to 90°; but in most of the cases it varies from 65° to 80°, and its average is about 73°. It is important to indicate that to achieve bench face inclinations steeper than 65°, it is a common practice to use controlled blasting techniques.
(e)
As shown in Figure 6.5, the interramp angle can vary from 25º to 60º; but in most of the cases it varies from 40° to 60°, and its average is about 50º.
(f)
As shown in Figure 6.6, the overall slope angle can vary from 25º to 60º; but in most of the cases it varies from 30° to 60°, and its average is about 45º.
(g)
As shown in Figure 6.7, the slope angle is maximum at bench scale, flatter for interramp slopes (typically 20° to 25° flatter), and even flatter for overall slopes (typically 5° flatter than interramp slopes).
(h)
As shown in Figure 6.8, the data for interramp and overall slopes do not show a clear trend between the slope height and the slope angle (probably due to the fact that the data include many different geological-structural-geotechnical settings); nevertheless, for preliminary evaluations the red curve shown in Figure 6.8 could be used to estimate the slope angle for a given slope height.
6.2. MINE ACCESSES The analysis of the data on mine accesses indicates that: (a)
Underground mine accesses can be shafts, declines or both.
(b)
As shown in Figure 6.9 the use of shafts as t he only access shows a decreasing trend since 1970.
(c)
As shown in Figure 6.9 the use of declines as the only access shows an increasing trend since 1970.
25
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.70 SINGLE BENCHES
0.65
DOUBLE BENCHES
0.60 0.55
Y 0.50 C N 0.45 E U Q 0.40 E R F 0.35 E V I 0.30 T A 0.25 L E R 0.20 0.15 0.10 0.05 0.00 0
5
10
15
20
25
30
35
40
BENCH HEIGHT, hb (m)
Figure 6.1:
Histogram showing the relative frequency of different bench heights, for single and double benches in open pit mines.
0.45
0.40
0.35
Y C 0.30 N E U Q 0.25 E R F E 0.20 V I T A L 0.15 E R 0.10
0.05
0.00 0
50
100
150
200
250
300
350
400
INTERRAMP SLOPE HEIGHT, h r (m)
Figure 6.2:
Histogram showing the relative frequency of different interramp slope heights in open pit mines.
26
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.35
0.30
Y 0.25 C N E U Q 0.20 E R F E V 0.15 I T A L E R 0.10
0.05
0.00 0
100
200
300
400
500
600
700
800
900
1000
OVERALL SLOPE HEIGHT, h o (m)
Figure 6.3:
Histogram showing the relative frequency of different overall slope heights in open pit mines.
0.40
0.35
0.30
Y C N E 0.25 U Q E R F 0.20 E V I T A 0.15 L E R 0.10
0.05
0.00 0
5
10
15
20
25
30
35
40
45
50
BENCH FACE INCLINATION,
Figure 6.4:
55
αb
60
65
70
75
80
85
90
(degrees)
Histogram showing the relative frequency of different bench face inclinations in open pit mines.
27
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.40
0.35
0.30
Y C N E 0.25 U Q E R F 0.20 E V I T A 0.15 L E R 0.10
0.05
0.00 0
5
10
15
20
25
30
35
40
45
50
INTERRAMP SLOPE ANGLE,
Figure 6.5:
55
60
α r
65
70
75
80
85
90
(degrees)
Histogram showing the relative frequency of different interramp slope angles in open pit mines.
0.30
0.25
Y C 0.20 N E U Q E R F 0.15 E V I T A L 0.10 E R
0.05
0.00 0
5
10
15
20
25
30
35
40
45
50
OVERALL SLOPE ANGLE,
Figure 6.6:
55
αo
60
65
70
75
80
85
90
(degrees)
Histogram showing the relative frequency of different overall slope angles in open pit mines.
28
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.40 BENCHES INTERRAMP SLOPES
0.35
OVERALL SLOPES
0.30
Y C N E 0.25 U Q E R F 0.20 E V I T A 0.15 L E R 0.10
0.05
0.00 0
5
10
15
20
25
30
35
40
45
SLOPE ANGLE,
Figure 6.7:
50
α
55
60
65
70
75
80
85
90
(degrees)
Histogram showing the relative frequency of different slope angles for benches, interramp and overall slopes in open pit mines.
900 850
INTERRAMP SLOPES OVERALL SLOPES
800 750 700
) 650 m 600 (
h 550 , T 500 H G 450 I E H 400 E 350 P O 300 L S 250 200 150 100 50 0 0
5
10
15
20
25
30
35
40
45
SLOPE ANGLE,
Figure 6.8:
50
α
55
60
65
70
75
80
85
90
(degrees)
Variation of the slope angle with the slope height in open pit mines.
29
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.8 ACCESS TYPE SHAFTS
0.7
DECLINES BOTH TYPES OF ACCESS
S H A F T ´ S
0.6
Y C N E 0.5 U Q E R F 0.4 E V I T A 0.3 L E R
T R E N D
D E N T R ´ S E I N C L D E
E N D ´ S T R B O T H
0.2
0.1
0.0 Before 1970
From 1970 to 1990
After 1990
TIME PERIOD
Figure 6.9:
Evolution through time of the trend for the type of access to underground mines.
(d)
Before 1970 in 70% of the cases shafts were used as accesses, in 30% declines were used, and in 0% both, shafts and declines, were used.
(e)
In the period from 1970 to 1990, in 46% of the cases shafts were used as accesses, in 42% declines were used, and in 13% both, shafts and declines, were used.
(f)
In the period from 1990 to 2002, in 36% of the cases shafts were used as accesses, in 50% declines were used, and in 14% both, shafts and declines, were used.
6.3. BLOCK HEIGHT AND FOOTPRINT The analysis of the data on block heights and footprints indicates that: (a)
As shown in Figure 6.10, since 1970 the block height in block/panel caving mines shows an increasing trend. Before 1970, the typical block height was 100 m; for the period 1970-1990 was 160 m, and for the period 1990-2002 it is 240 m.
(b)
As shown in Figure 6.11, in block/panel caving mines the footprint area varies widely, 2 2 but in 80% of the cases, it is smaller than 250000 m , and its average is 165000 m .
(c)
As shown in Figure 6.12, the footprint geometry is such that the ratio between its length (L) and its width (B) rarely exceeds 3, and in almost 60% of the cases is smaller than 2.
(d)
It seems that most block/panel caving mines have ignored a possible relationship between block height (H) and footprint geometry (defined by its width B). As a preliminary conclusion, and as shown in Figure 6.13, the data collected suggested that: o
o
If H/B ≤ 1 → then the cave will easily connect to surface (or upper level previously mined out). If 2 ≥ H/B > 1 → then the cave probably will connect to surface (or upper level previously mined out).
30
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.60
TIME PERIOD
0.55
Before 1970 From 1970 to 1990
0.50
After 1990
0.45
Y C N E U Q E R F E V I T A L E R
0.40
0.35 0.30
0.25 0.20
0.15
0.10 0.05
0.00 0
50
100
150
200
250
300
350
400
450
500
BLOCK HEIGHT (m)
Figure 6.10: Evolution through time of the trend for the block height in block/panel caving mines.
0.30
0.25
AVERAGE FOOTP RINT AREA = 165 000 m2
Y C 0.20 N E U Q E R F 0.15 E V I T A L 0.10 E R
0.05
0.00 0
100000
200000
300000
400000
500000
600000
700000
800000
900000
1000000
2
FOOTPRINT AREA (m )
Figure 6.11: Relative frequency of the different footprint area ranges in mines by block/panel caving.
31
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
L / W = 1.0
800
1.5
750 700
0 %
650
2.0
600
) m 550 (
H T D I W T N I R P T O O F
1 %
C 3 U M U L A T I V 5 9 % E F R E % Q U 8 1 E N C Y 9 4 %
500 450 400 350 300 250
2.5
3.0 3.5 4.0 4.5 5.0
0 % 1 0
200 150 100 50 0 0
100
200
300
400
500
600
700
800
900
1000
1100
1200
FOOTPRINT LENGTH (m)
Figure 6.12: Trend for the ratio between the footprint length (L) and its width (B) block/panel caving mines.
o
If H/B > 2 → then the cave would have problems to connect to surface (or upper level previously mined out).
Due to the importance of this issue, it will be studied with more accuracy during the development of the geotechnical guidelines that are considered as the second main activity of Task 4.
6.4. CAVING INITIATION The analysis of the data on caving initiation indicates that: (a)
As shown in Figure 6.14, the shape of the initial area for caving is predominantly square or rectangular, but in a few cases other shapes have been used (like triangular shapes).
(b)
As shown in Figure 6.14, the available data indicates that the area for caving initiation 2 2 has an average value of 10000 m , and typically varies form 5000 to 15000 m .
(c)
As shown in Figure 6.15, the hydraulic radius of the initial caving area varies from 15 to 45 m, with an average value in the range from 20 to 30 m.
(d)
As shown in Figure 6.16, to facilitate cave initiation in 53% of the cases slots have been used, in 7% of the cases artificial chimneys have been used (chimneying intentionally used to initiate caving, and not a product of poor cave management), and in 40% of the cases no measures to facilitate cave initiation have been used.
32
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
H = 2B
H=B
500
450
CONNECTION TO SUR FACE
DIFFICULT CONNECTION TO SURFACE ?
400
EASY CONNECTION TO SURFA CE
) 350 m (
T 300 H G I E 250 H K C 200 O L B 150 100
50
0 0
50
100
150
200
250
300
350
400
FOOTPRINT
450
500
550
600
650
700
750
800
IDTH (m)
Figure 6.13: Trend between the block height (H) and the footprint width (B) for block/panel caving mines.
0.35
AREA SHAPE SQUARE
0.30
RECTANGULAR OTHER
Y C N E U Q E R F E V I T A L E R
0.25
0.20
0.15
0.10
0.05
0.00 0
5000
10000
15000
20000
25000
30000
35000
40000
INIT IA L C A IN G A RE A (m2)
Figure 6.14: Relative frequency of different initial caving areas and their shapes in block/panel caving mines.
33
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.40
0.35
0.30
Y C N E 0.25 U Q E R F 0.20 E V I T A 0.15 L E R 0.10
0.05
0.00 0
5
10
15
20
25
30
35
40
45
50
H YD RAU LIC R AD IU S OF INIT IAL C A IN G A RE A (m)
Figure 6.15: Relative frequency of different hydraulic radius for the initial caving area in block/panel caving mines.
0.55
0.50
0.45
0.40
Y C N 0.35 E U Q E 0.30 R F E 0.25 V I T A 0.20 L E R 0.15
0.10
0.05
0.00
SLOT
ARTIFICIAL CHIMNEY
NONE
ME AS UR ES TO FA C ILIT AT E C A IN G IN IT IA TI ON
Figure 6.16: Relative frequency of different measures to facilitate caving initiation in block/panel caving mines.
34
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
6.5. UNDERCUT LEVEL The analysis of the data on the undercut level indicates that: (a)
As shown in Figure 6.17, the distance between undercut drifts varies from 10 to 35 m, with an average from 20 to 25 m.
(b)
As shown in Figure 6.18, the width of undercut drifts shows an increasing trend through time. Before 1970 it has an average from 2 to 3 m, in the period 1970-1990 its average was 3 m, and in the period 1990-2002 its average is 4 m.
(c)
As shown in Figure 6.19, the height of undercut drifts shows an increasing trend through time. Before 1970 it has an average from 2.0 to 2.5 m, in the period 19701990 its average was 3.0 to 3.5 m, and in the period 1990-2002 its average is from 3.5 to 4.0 m.
(d)
As shown in Figure 6.20, the undercut height shows no time-dependent trends. It varies from 3 to 20 m, with an average from 8 to 12 m.
(e)
As shown in Figure 6.21, the undercut rate varies from 500 to 5000 m /month, with an 2 average from 2000 to 2500 m /month.
2
6.6. EXTRACTION LEVEL The analysis of the data on the extraction level indicates that: (a)
As shown in Figure 6.22, the nominal crown-pillar thickness (from floor extraction level to floor undercut level) shows an increasing trend through time. Before 1970 its average was from 7.5 to 10.0 m, in the period 1970-1990 it was 12.5, and in the period 1990-2002 it is from 15.0 to 17.5 m.
(b)
As shown in Figure 6.23, the spacing between extraction level drifts shows an increasing trend through time. Before 1970 its average was from 12 to 16 m, in the period 1970-1990 it was from 20 to 24 m, and in the period 1990-2002 it is from 26 to 28 m.
(c)
As shown in Figure 6.24, the width of extraction level drifts shows an increasing trend through time. Before 1970 it has an average of 2.5 m. In the period 1970-1990 its average was from 3.0 to 3.5 m, and in the period 1990-2002 its average is from 4.0 to 4.5 m.
(d)
As shown in Figure 6.25, the height of extraction level drifts shows an increasing trend through time. Before 1970 it has an average from 2.0 to 2.5 m. In the period 1970-1990 its average was 3.0 to 3.5 m, and in the period 1990-2002 its average is from 3.5 to 4.5 m.
(e)
As shown in Figure 6.26, the draw point spacing shows an increasing trend through time. Before 1970 it has an average of 8 m. In the period 1970-1990 its average was 12 m, and in the period 1990-2002 its average is 15 m.
(f)
As shown in Figure 6.27, the influence area of draw points shows an increasing trend 2 through time. Before 1970 it has an average of 50 m . In the period 1970-1990 its 2 2 average was 125 m , and in the period 1990-2002 its average is from 200 to 225 m .
(g)
As shown in Figure 6.28, the most used geometry for the extraction level is the herringbone layout (54% of the cases), followed by El Teniente layout (layout 40% of the cases).
(h)
As shown in Figure 6.29, the average draw rate is from 0.20 to 0.25 m/day.
(i)
The current practice is to use draw rates that increase with the percentage of block extraction, as shown in Figure 6.30.
35
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.35
0.30
Y 0.25 C N E U Q 0.20 E R F E V 0.15 I T A L E R 0.10
0.05
0.00 0
5
10
15
20
25
30
35
NOMINAL DISTANCE BETWEEN DRIFTS UCL (m)
Figure 6.17: Relative frequency of different nominal distances between undercut level drifts in caving mines.
0.90
TIME PERIOD
0.85
Before 1970
0.80
From 1970 to 1990
0.75
After 1990
0.70
Y 0.65 C 0.60 N E 0.55 U Q 0.50 E R F 0.45 E 0.40 V I T 0.35 A L 0.30 E R 0.25 0.20 0.15 0.10 0.05 0.00 0
1
2
3
4
5
6
7
8
NOMINAL WIDTH DRIFTS UCL (m)
Figure 6.18: Time trend of the relative frequency for the nominal width of undercut level drifts in caving mines.
36
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.80
TIME PERIOD
0.75
Before 1970
0.70
From 1970 to 1990 After 1990
0.65 0.60
Y C 0.55 N E 0.50 U Q 0.45 E R F 0.40 E 0.35 V I T A 0.30 L E 0.25 R 0.20 0.15 0.10 0.05 0.00 0
1
2
3
4
5
6
NOMINAL HEIGHT DRIFTS UCL (m)
Figure 6.19: Time trend of the relative frequency for the nominal height of undercut level drifts in caving mines.
0.45
TIME PERIOD Before 1970
0.40
From 1970 to 1990 After 1990
0.35
Y C 0.30 N E U Q 0.25 E R F E 0.20 V I T A L 0.15 E R 0.10
0.05
0.00 0
4
8
12
16
20
UNDERCUT HEIGHT (m)
Figure 6.20: Relative frequency of different undercut heights in caving mines.
37
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.30
0.25
Y C 0.20 N E U Q E R 0.15 F E V I T A L 0.10 E R
0.05
0.00 0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
A ERA GE U ND ERC UT R ATE (m /month) 2
Figure 6.21: Relative frequency of different undercut rates in caving mines.
0.90
TIME PERIOD
0.85
Before 1970
0.80
From 1970 to 1990
0.75
After 1990
0.70
Y 0.65 C 0.60 N E 0.55 U Q 0.50 E R 0.45 F E 0.40 V I T 0.35 A L 0.30 E R 0.25 0.20 0.15 0.10 0.05 0.00 0.0
2.5
5.0
7.5
10.0
12.5
15.0
17.5
20.0
22.5
25.0
27.5
30.0
32.5
35.0
NOMINAL CROWN-PILLAR THICKNESS (m)
Figure 6.22: Evolution through time of the trend for nominal crown-pillar thickness in mines by caving methods.
38
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.55
TIME PERIOD 0.50
Before 1970 From 1970 to 1990 After 1990
0.45
0.40
Y C N 0.35 E U Q E 0.30 R F E 0.25 V I T A 0.20 L E R 0.15 0.10
0.05
0.00 0
4
8
12
16
20
24
28
32
36
40
PRODUCTION DRIFTS SPACING (m)
Figure 6.23: Evolution through time of the trend for production drifts spacing in mines by caving.
0.70
TIME PERIOD
0.65
Before 1970 From 1970 to 1990
0.60
After 1990
0.55
Y 0.50 C N 0.45 E U Q 0.40 E R F 0.35 E V 0.30 I T A 0.25 L E R 0.20 0.15 0.10 0.05 0.00 0
1
2
3
4
5
6
7
8
N OMIN AL W ID TH D RIF TS E XT RA CT ION L E E L (m)
Figure 6.24: Evolution through time of the trend for the width of extraction level drifts in mines by caving methods.
39
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.70
TIME PERIOD
0.65
Before 1970 From 1970 to 1990
0.60
After 1990
0.55
Y 0.50 C N 0.45 E U Q 0.40 E R F 0.35 E V I 0.30 T A 0.25 L E R 0.20 0.15 0.10 0.05 0.00 0
1
2
3
4
5
6
N OMIN AL H EIG HT D RIF TS E XTR AC TIO N L E E L (m)
Figure 6.25: Evolution through time of the trend for the height of extraction level drifts in mines by caving methods.
0.45
TIME PERIOD Before 1970
0.40
From 1970 to 1990 After 1990
0.35
Y C 0.30 N E U Q 0.25 E R F E 0.20 V I T A L 0.15 E R 0.10
0.05
0.00 0
2
4
6
8
10
12
14
16
18
20
22
24
DRAW POINT SPACING (m)
Figure 6.26: Evolution through time of the trend for draw point spacing in mines by block and panel caving methods.
40
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.55
TIME PERIOD 0.50
Before 1970 From 1970 to 1990 After 1990
0.45
0.40
Y C N 0.35 E U Q E 0.30 R F E 0.25 V I T A 0.20 L E R 0.15 0.10
0.05
0.00 0
25
50
75
100
125
150
175
200
225
250
275
300
325
350
IN FL UEN CE A RE A OF D RA W P OIN TS (m2)
Figure 6.27: Evolution through time of the trend for the influence area of draw points in mines by block and panel caving methods.
0.60
0.55
0.50
0.45
Y C 0.40 N E U 0.35 Q E R 0.30 F E V 0.25 I T A L 0.20 E R 0.15
0.10
0.05
0.00
HERRINGBONE
TENIENTE
OTHER
EXTRACTION LE EL LAYOUT
Figure 6.28: Relative frequency of different extraction level layouts in mines by block and panel caving methods.
41
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.40
0.35
0.30
Y C N E 0.25 U Q E R 0.20 F E V I T 0.15 A L E R 0.10
0.05
0.00 0.00
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
0.45
0.50
0.55
0.60
0.65
0.70
A ERAGE DRAW RATE (m/day)
Figure 6.29: Relative frequency of different average draw rates in mines by caving methods.
0.50
0.45
0.40
) 0.35 y a d / m0.30 (
E T 0.25 A R W0.20 A R D 0.15 Pilar Sub 6 - Esmeralda Sector Hw / Central, Initial Caving Pilar Sub 6 - Esmeralda Sector Fw, Initial Caving
0.10
Esmeralda, Initial Caving Diab lo-Regimiento Project, Initial Caving Pala bora, Initial Caving
0.05
A verage for Initial Caving E l Teniente trend for Steady-State Caving
0.00 0
10
20
30
40
50
60
70
BLOCK EXTRACTION (%)
Figure 6.30: Examples of the variation of the draw rate as a function of the percentage of block extraction, in mines by block/panel caving.
42
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
6.7. SUPPORT The analysis of the data on support indicates that: (a)
In most underground mines by caving the support at the undercut level includes only bolts; nevertheless, in some mines this support also included mesh and shotcrete.
(b)
In most underground mines by caving the support at the extraction level includes bolts (typically from 1.8 to 2.4 m long, at spacings from 1.0 to 1.3 m), mesh and shotcrete (typically 2”), and in many cases also cables (typically at intersections, with lengths from 5 to 8 m). Also some mines used straps and osro-straps, as shown in Photograph 6.1.
(c)
As shown in Figure 6.31, the bolt length varies from 1.25 to 3.75 m, with an average from 2.00 to 2.25 m, for the Undercut Level, and from 2.00 to 2.50 m for the Extraction Level.
(d)
As shown in Figure 6.32, the bolt spacing varies from 0.6 to 1.40 m, being typically 1.0 m for both: Undercut and Extraction Levels (50% of cases). The average bolt spacing is from 1.0 to 1.1 m, also for both levels.
(e)
The variation of bolt lengths with the width of the drifts is shown in Figure 6.33, which indicates that: o
There is no clear difference between the Undercut and Extraction Levels.
o
In most cases the bolt length is such that: 1.5
o
(f)
≤
B / L
≤
3.0
For preliminary estimations of bolt length, the following relationships are suggested (the drift width, B, expressed in m): For poor quality rock masses (20 ≤ RMR ≤ 40):
L (m) = 0.60 B + 0.60
For fair quality rock masses (40 ≤ RMR ≤ 60):
L (m) = 0.45 B + 0.45
For good quality rock masses (60 ≤ RMR ≤ 80):
L (m) = 0.30 B + 0.30
The variation of bolt spacing (s) with the bolt length (L) is shown in Figure 6.34, which indicates that:: o
There is no clear difference between the Undercut and Extraction Levels.
o
In most cases the bolt length is such that: 1.5
≤
L / s
≤
2.5
Photograph 6.1: Extraction level support by bolts, mesh and osro-straps at a South African underground mine.
43
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.45 UNDERCUT LEVEL EXTRACTION LEVEL
0.40
Fit 1: Normal 0.35
Y C 0.30 N E U Q 0.25 E R F E 0.20 V I T A L 0.15 E R 0.10
0.05
0.00 0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
BOLT LENGTH (m)
Figure 6.31: Relative frequency of different bolt lengths in mines by caving methods.
0.50 UNDERCUT LEVEL EXTRACTION LEVEL
0.45
Fit 1: Normal 0.40
Y 0.35 C N E U 0.30 Q E R 0.25 F E V I 0.20 T A L E 0.15 R 0.10
0.05
0.00 0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
BOLT SPACING (m)
Figure 6.32: Relative frequency of different bolt spacings in mines by caving methods.
44
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
B / L = 1.0
4.0
1.5
3.5
O R P O
) m3.0 (
C K R O
S S M A
T Y , A L I Q U
0 L =
.6 0 B
+
0 0 .6
S S M A O C K R R F A I
L , H T G 2.5 N E L T L O 2.0 B
, L L I T Y Q U A
+ . 4 5 B = 0
0. 4 5
2.0
2.5
0, 3 0 B + 0 , 3 0 L = , Y L I T Q UA A S S C K M O R D G O O
3.0
3.5 4.0
1.5
4.5 UNDERCUT LEVEL DATA
5.0
EXTRACTION LEVEL DATA BEST FIT FOR B < 5 m
1.0 3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
D RIF T WID TH , B (m)
Figure 6.33: Variation of the bolt length with the nominal width of the drift in mines by caving methods.
L / s = 1.0
1.5
1.5
2.0
1.4
2.5
D G O O
L I T Y Q UA A S S M K R O C
1.3 F A I R
) 1.2 m (
s , 1.1 G N I C 1.0 A P S 0.9 T L O B 0.8
3.0
3.5
. 9 + 0 0 L 0. 1 5 s =
+ 5 L 0 .1 2 s =
K R O C
L I T Y Q UA MA S S
C K R R O P O O
T Y UA L I S Q M A S
4.0
0. 8
4.5 0. 7 L + 0 . 1 0 0 s =
5.0
0.7
0.6
UNDERCUT LEVEL DATA EXTRACTION LEVEL DATA
0.5 1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
B OL T L EN GTH , L (m)
Figure 6.34: Variation of the bolt spacing with the bolt length in mines by caving methods.
45
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
o
For preliminary estimations of bolt spacing, the following relationships are suggested (the bolt length, L, expressed in m): For poor quality rock masses (20 ≤ RMR ≤ 40):
s (m) = 0.100 L + 0.7
For fair quality rock masses (40 ≤ RMR ≤ 60):
s (m) = 0.125 B + 0.8
For good quality rock masses (60 ≤ RMR ≤ 80):
s (m) = 0.150 B + 0.9
(g)
Underground mines by caving caving methods methods and under under rockburst risk, have have also used mesh and lacing as a complementary support for extraction level drifts.
(h)
The support of the draw points changes changes from one mine mine to another, but but in most cases cases it includes steel arches, cablebolts and concrete and/or shotcrete. The number of steel arches had varied from 2 to 7, but currently most mines used 2 to 3 steel arches. Photographs 6.2 and 6.2 and 6.3 show 6.3 show some examples of draw point support.
Photograph 6.2: Draw point support using steel sets and concrete at a North American mine by caving
point Photograph 6.3: Draw support using steel sets and concrete at a South African mine by caving
46
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.6
0.5
Y C 0.4 N E U Q E R F 0.3 E V I T A L 0.2 E R
0.1
0.0 SHAFTS
CONVEYOR BELTS
TRUCKS
TRAINS
MATERIAL HANDLING SYSTEM Figure 6.35: Relative frequency of different different material handling systems used in underground underground mines by caving methods.
6.8. MATERIAL HANDLING SYSTEM The analysis of the data on material handling systems systems indicates that: (a)
As shown in Figure 6.35, 6.35, in 57% of the cases underground mines by caving use production shafts; in 27% of the cases they use conveyor belts; in 12% of the cases they use trains; and in 4% of the cases they use trucks.
47
ICS-II, Task 4
7.
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
MINE OPERATION DATA The mine operation data collected include:
Operational parameters for the undercut and extraction levels.
Production blasting
Fragmentation
Oversize limits
Draw rates
Equipment
Repair frequencies
All the data obtained for each mine visited are are included in Appendix B. B. The analysis of the mine operation data indicates that: (a)
As shown in Figure 7.1, 7.1, the powder factor for undercut blasting varies widely, from 200 to 1000 grm/ton; with an average from 400 to 500 grm/ton, and a typical or most used value from 300 to 600 grm/ton.
(b)
As shown in Figure 7.2, 7.2, the LHD capacity varies from 7 to 19 tons, with an average of 11 tons.
(c)
As shown in Figure 7.3, 7.3, the LHD tramming distance varies widely, from 25 to 300 m, with an average from 125 to 150 m.
(d)
As shown in Figure 7.4, 7.4, the oversize limit in most cases (almost 50%) varies form 1.8 to 2.0 3 3 3 m ; nevertheless, its range is wide, from 0.4 to 2.4 m . The average oversize limit limit is 1.6 m .
0.30
0.25
Y C 0.20 N E U Q E R F 0.15 E V I T A L 0.10 E R
0.05
0.00 0
100
200
300
400
500
600
700
800
900
1000
1100
1200
POWDE POWDER R FACTO FACTOR (grm/ton)
Figure 7.1:
Relative frequency frequency of different values of the powder factor factor used for undercut undercut blasting in mines by caving methods.
48
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.35
0.30
Y 0.25 C N E U Q 0.20 E R F E V I 0.15 T A L E R 0.10
0.05
0.00 0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
LHD CAPACITY (tons)
Figure 7.2:
Relative frequency of different LHD capacities used in mines by caving methods.
0.35
0.30
Y 0.25 C N E U Q 0.20 E R F E V I 0.15 T A L E R 0.10
0.05
0.00 0
25
50
75
100
125
150
175
200
225
250
275
300
LHD TRAMMING DISTANCE (m)
Figure 7.3:
Relative frequency of different LHD tramming distances used in mines by caving methods.
49
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.50
0.45
0.40
Y 0.35 C N E U 0.30 Q E R 0.25 F E V I T 0.20 A L E R 0.15 0.10
0.05
0.00 0 .0
0.2
0.4
0 .6
0.8
1.0
1 .2
1 .4
1.6
1 .8
2 .0
2.2
2.4
2.6
2.8
3.0
3
O ER S SIIZE LIMIT (m )
Figure 7.4:
Relative frequency frequency of different oversize oversize limits in mines mines by caving methods. methods.
50
ICS-II, Task 4
8.
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
GEOTECHNICAL INSTRUMENTATION AND MONITORING DATA The data on geotechnical instrumentation instrumentation and monitoring include:
Parameters to be monitored.
Purpose.
Instruments.
Number.
Length.
Frequency of readings.
Threshold values.
Degree of satisfaction.
All the data obtained for each mine visited are are included in Appendix B. B. The analysis of the geotechnical instrumentation and monitoring data indicates that: (a)
As shown in Figure 8.1, 8.1, in open pit mines the frequency of use and degree of satisfaction (DS) with monitoring is: Frequency of Use
Most used
Second most used
Third most used
(b)
Monitoring System
Degree of Satisfaction Range
Average
Field inspections (100%)
Fair to Very High
High
Global displacements (100%)
Fair to Very High
Fair to High
Local displacements (78%)
Very Low to Very High
Fair
Groundwater monitoring (67%)
Fair to Very High
Fair
Aerial photography (44%)
High
High
TDR (33%)
Very Low to Fair
Fair
As shown in Figure 8.2, 8.2, in underground mines by caving methods the frequency of use and degree of satisfaction (DS) with monitoring is: Frequency of Use
Most used
Second most used
Monitoring System
Degree of Satisfaction Range
Average
Field inspections (100%)
Low to High
High
Local displacements (82%)
Very Low to Very High
Fair
Seismic System (64%)
Fair to Very High
High
TDR (64%)
Low to Very High
High
Convergence (36%)
High to Very High
High
Observation Boreholes (36%)
Low to Very High
Fair
Third most used
51
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
DEGREE DEGREE OF SATIS SATISFAC FACTI TION ON VERY LOW
G N I N I M T I P N E P O N I
LOW
FAIR
HIGH
VERY HIGH
FREQUENCY OF USE
78%
LOCAL DISPLACEMENTS
100%
GLOBAL DISPLACEMENTS
G N I R O T I TIME N O M L A C I N H C E T O E G
GROUNDWATER
67%
DOMAIN REFLECTOMETER
33%
RECONCILIATION
11%
AERIAL PHOTOGRAPHS
44%
Figure 8.1:
100%
FIELD INSPECTIONS
Relative frequency and and degree degree of satisfaction for different geotechnical geotechnical instrumentainstrumentation and monitoring systems used in open pit mines.
DEGREE DEGREE OF SATI SATISFACTI SFACTION ON G N I N I M D N U O R G R E D N U N I
VERY LOW
FAIR
HIGH
VERY HIGH
FREQUENCY OF USE
CONVERGENCE
36%
LOCAL DISPLACEMENTS
82%
GLOBAL DISPLACEMENTS
9%
STRESSES
27%
WATER FLOW
18%
G N I OVERBREAK R O T I TIME DOMAIN REFLECTOMETER (CAVE BACK) N O OBSERVATION BOREHOLES M (CAVE BACK) L A C SEISMIC SYSTEMS I N H AERIAL PHOTOGRAPHS C (SUBSIDENCE) E T O FIELD INSPECTIONS E G
Figure 8.2:
LOW
18% 64% 36% 64% 27% 100%
Relative frequency and and degree degree of satisfaction for different geotechnical geotechnical instrumentainstrumentation and monitoring systems used in underground mines by caving methods.
52
ICS-II, Task 4
9.
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
GEOTECHNICAL HAZARDS DATA The geotechnical hazards considered in the bench marking includes:
Open pit hazards (rock falls, wedge/planar failures and slides). Underground mines hazards (rib pillar failures, pillar instabilities, stope instabilities, early dilution, water inflows and mudrushes, collapses, hangups, rockbursts and subsidence).
All the data obtained for each mine visited are included in Appendix B.
9.1. COLLAPSES A collapse is a type of hazards that frequently affects the extraction level of underground mines by caving methods, causing important damage not only at the undercut level but also at the extraction level, as illustrated by t he example shown in Photographs 9.1 and 9.2. The analysis of the data on collapses indicates that: (a)
As shown in Figure 9.1 the area affected by a single collapse varies from 140 to 2 2 17500 m , with an average of 3700 m .
(b)
As shown in Figure 9.2 the main causes of collapses are: o
(c)
Draw rate / Draw management
o
Structures
o
Mine planning / Mining sequence
As shown in Figure 9.3 the most frequent remedial measures for collapses are: o
Draw rate / Draw management
o
Support
o
Improving geological-geotechnical data
1,5 m
Photograph 9.1:
Collapse at an undercut level drift of Teniente 4 Sur (1989).
53
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
1,5 m
CONCRETE DAMAGE
CONCRETE DAMAGE
Photograph 9.2:
Collapse at an extraction level drift of T eniente 4 Sur (1989).
0.40
0.35
0.30
Y C N E U Q E R F E V I T A L E R
0.25
0.20
0.15
0.10
0.05
0.00 0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
AREA AFFECTED BY A SINGLE COLLAPSE (m 2 )
Figure 9.1:
Relative frequency of the area affected by a single collapse in underground mines by caving.
54
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
1.00 0.95
FIRST MORE IMPORTANT CAUSE
0.90
SECOND MORE IMPORTANT CAUSE
0.85
THIRD MORE IMPORTANT CAUSE
0.80 0.75
Y C N E U Q E R F E V I T A L E R
0.70 0.65 0.60 0.55 0.50 0.45 0.40 0.35 0.30 0.25 0.20 0.15 0.10 0.05 0.00 GEOLOGY STRUCTURES
WATER
MINE LAYOUT DESIGN
SUPPORT
MINE PLANNING MINING SEQUENCE
DRAW RATE DRAW MANAGEMENT
BLASTING
MA IN CA USE S OF A C OLL AP SE
Figure 9.2:
Relative frequency of the different main causes of collapses in mines by caving.
1.00
FIRST MOST COMMON REMEDIAL MEASURE
0.95
SECOND MOST COMMON REMEDIAL MEASURE THIRD MOST COMMON REMEDIAL MEASURE
0.90 0.85 0.80 0.75
Y C N E U Q E R F E V I T A L E R
0.70 0.65 0.60 0.55 0.50 0.45 0.40 0.35 0.30 0.25 0.20 0.15 0.10 0.05 0.00 IMPROVED GEOLOGICAL GEOTECHNICAL DATA
DRAINAGE
SUPPORT
MINE PLANNING MINING SEQUENCE
DRAW RATE DRAW MANAGEMENT
CONTROLLED BLASTING
MA IN R EM EDI AL M EA SU RE S FO R A CO LL AP SE
Figure 9.3:
Relative frequency of the different remedial measures against collapses that have been used in underground mines by caving.
55
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
9.2. ROCKBURSTS A rockburst is a seismic event that causes damage. In most cases the damage has no clear structural control, as shown in Picture 9.3, but in certain cases like the one shown in Picture 9.4, the damage has a clear structural control because the seismic event triggered the fall of blocks. The intensity of this damage can vary widely, but for the purposes of this report it will be considered that a rockburst can produce three levels of damage: heavy, moderated, and light damage. These classes of damage are illustrated by the examples shown in Pictures 9.5 to 9.7.
Photograph 9.3:
Typical major rockburst damage, without structural control, due to a seismic event that affected a drift at the undercut level of Teniente Sub 6 (1991).
Photograph 9.4: Typical major rockburst damage, with structural control, due to a seismic event that affected a drift at the ventilation level of Teniente Sub 6 (1990).
56
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
Photograph 9.5:
Example of HEAVY rockburst damage.
Photograph 9.5: Example of MODERATE rockburst damage.
57
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
Photograph 9.7: Example rockburst damage.
of
LIGHT
Due to the fact that not all mines by caving suffer rockbursts, and considering that most of the data collected came from El Teniente Sub 6 experience, the numerical conclusions presented below are based on the analysis of these data. The analysis of the data on rockbursts indicates that: (a)
Rockburst can affect not only the undercut level, but also different levels below the UCL, reaching up to the haulage level.
(b)
The major rockbursts that damaged Teniente Sub 6 caused different kinds of damage at different levels, and at different distances form the caving front.
(c)
As shown in Figure 9.4 the heavy damage at different levels varies with the distance to the caving front as follows: Level
Distance to Caving Front of Damaged Zone
Most Damaged Sector
Undercut
0 to 150 m
0 to 50 m
Extraction
< 0 to 150 m
0 to 50 m
Ventilation
50 to 150 m
100 to 150 m
Haulage
< 0 to 150 m
100 to 150 m
58
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
) m 200 (
T S R U B K C O R E L G N I S A Y B D E G A M A D H T G N E L T F I R D
HEAVY ROCKBURST DAMAGE TEN SUB 6 (1989 - 1992)
180
UNDERCUT LEVEL EXTRACTION LEVEL
160
VENTILATION LEVEL HAULAGE LEVEL
140
120
100
80
60
40
20
0
< 0
0 to 50
50 to 100
100 to 150
DIS TA NCE TO CA ING FR ONT (m)
Figure 9.4:
(d)
(e)
(f)
Relative frequency of the heavy rockburst damaged zones at different levels, and at different distances from the caving front.
As shown in Figure 9.5 the moderate damage at different levels varies with the distance to the caving front as follows: Level
Distance to Caving Front of Damaged Zone
Most Damaged Sector
Undercut
0 to 150 m
0 to 50 m
Extraction
< 0 to 150 m
100 to 150 m
Ventilation
< 0 to 150 m
< 0 to 150 m
Haulage
< 0 to 150 m
0 to 50 m
As shown in Figure 9.6 the light damage at different levels varies with the distance to the caving front as follows: Level
Distance to Caving Front of Damaged Zone
Most Damaged Sector
Undercut
0 to 150 m
100 to 150 m
Extraction
< 0 to 150 m
0 to 50 m
Ventilation
50 to 150 m
100 to 150 m
Haulage
< 0 to 150 m
0 to 50 m
As shown in Figure 9.7 the main causes of rockburst are: HIGH INFLUENCE:
Structures Stress environment Mining sequence Undercutting rate Draw rate
59
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
) m 300 (
T S R U B K C O R E L G N I S A Y B D E G A M A D H T G N E L T F I R D
280 260 240 220
MODERATE ROCKBURST DAMAGE TEN SUB 6 (1989 - 1992) UNDERCUT LEVEL EXTRACTION LEVEL VENTILATION LEVEL HAULAGE LEVEL
200 180 160 140 120 100 80 60 40 20 0
< 0
0 to 50
50 to 100
100 to 150
DIS TA NCE TO CA ING FR ONT (m)
Figure 9.5:
Relative frequency of the moderate rockburst damaged zones at different levels, and at different distances from the caving front.
) m 400 (
T S R U B K C O R E L G N I S A Y B D E G A M A D H T G N E L T F I R D
380 360 340 320 300
LIGHT ROCKBURST DAMAGE TEN SUB 6 (19 89 - 1992) UNDERCUT LEVEL EXTRACTION LEVEL VENTILATION LEVEL HAULAGE LEVEL
280 260 240 220 200 180 160 140 120 100 80 60 40 20 0
< 0
0 to 50
50 to 100
100 to 150
D IS TAN CE TO C A IN G FR ON T (m)
Figure 9.6:
Relative frequency of the light rockburst damaged zones at different levels, and at different distances from the caving front.
60
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
3
E C N A T R O P M I E V I T A L E R
2
1
0 STRUCTURES STRESS ENVIRONMENT
MINING SEQUENCE
UNDERCUTING RATE
DRAW RATE
ROCK MASS QUALITY
MINE LAYOUT
ROCK SUPPORT
UNDERCUTING MANAGEMENT BLASTING
MAIN CAUSES OF A ROCKBURST
Figure 9.7:
Relative importance of the different causes of rockbursts in underground mines by caving methods.
MODERATE INFLUENCE:
(g)
Rock mass quality Mine layout Rock support Undercutting management Blasting
As shown in Figure 9.8 the main remedial measures for rockburst are: HIGH INFLUENCE:
Monitoring Mining sequence Draw rate Contingency plans
MODERATE INFLUENCE:
Rock mass conditioning Draw management Support Technological improvements
9.3. SUBSIDENCE The connection of the cave back with the ground surface generates a subsidence crater, like the ones illustrated in Pictures 9.8 to 9.10, for sublevel, block, and panel caving mines. Usually the crater perimeter is subcircular, but in certain cases like the one shown in Picture 9.11, it could have a special shape. On the other hand the development of the subsidence crater could affect other mines located nearby, like the example shown in Picture 9.12. Of course, this will also be the case of any open pit mine developing a transition to underground mining by caving methods, like the example shown in Picture 9.13.
61
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
3
E C N2 A T R O P M I E V I T A L 1 E R
0 MONITORING
MINING SEQUENCE
DRAW RATE
CONTINGENCY ROCK MASS DRAW PLANS CONDITIONING MANAGEMENT
SUPPORT
TECHNOLOGICAL IMPROVEMENTS
REMEDIAL MEASURES FOR ROCKBURSTS
Figure 9.8:
Photograph 9.8:
Relative importance of the different remedial measures for rockbursts in underground mines by caving methods.
Initiation of a subsidence crater due to the cave back connection to ground surface at a sublevel caving mine, Ridgeway, Australia.
62
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
Photograph 9.10: Typical subsidence crater of a panel caving mine, Grasberg IOZ, Indonesia. Photograph 9.9:
Typical subsidence crater of a block caving mine, II Panel, Andina Mine, Chile.
Quebrada Teniente
Teniente 5 Pilares
Teniente 4 Fortuna
Teniente Sub 6
Teniente 4 Regimiento Regimiento
Teniente 3 Isla
Teniente 4 Sur
Photograph 9.11: Non typical, horse shoe shaped subsidence crater of a panel caving operation with several productive sector around a central pipe, El Teniente, Chile.
63
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
OPEN PIT MINE DISPUTADA
SUBSIDENCE CRATER UG PANEL CAVING MINE III PANEL, ANDINA
Photograph 9.12: Example of the interaction between the subsidence crater of an underground panel caving mine (Andina), and a nearby open pit mine (Disputada), Chile.
PERIMETER OF THE SUBSIDENCE CRATER
Photograph 9.13: Example of the subsidence problem in a transition from open pit to underground mining by block caving, San Manuel, United States.
64
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
DRIFT AFFECTED BY THE CRATER DRIFTS AFFECTED BYSUBSIDENCE THE SUBSIDENCE (INFLUENCE(INFLUENCE ZONE OFZONE) THE CRATER)
SURFACE SURFACE
CRATER CRATERWALL WALL
BROKEN ROCK BROKEN ROCK
z
Crater Crater Depth Depth
Crater Wall Mean Crater Wall’s Mean Inclination Inclination
Figure 9.9:
Parameters describing the overall geometry of a subsidence crater: crater wall depth, H, and crater wall mean inclination or break angle, α.
The overall geometry of a subsidence crater can be described as shown in Figure 9.9, by the depth (H) and mean inclination (α) of its walls will. The mean inclination of the crater wall is also known as break angle. The analysis of the data on subsidence indicates that: (a)
As shown in Figure 9.10, the height of the subsidence crater walls varies from less than 100 to 1400 m; but most data are below 700 m, and the average is about 450 (of course the height of a subsidence crater walls depends on the terrain topography).
(b)
As shown in Figure 9.11, the break angle defining the mean inclination of the crater walls varies from 40° to 90° (even in few cases there are overhanging walls), increased with rock mass quality, but most data are in the range from 50° to 90°, and if RMR > 70 the recorded break angles are all larger than 60°. It is very important to note that most of the data are for long term conditions (i.e. after the end of the block extraction).
(c)
Available data indicates that it could be possible to find a relationship between rock mass rating, RMR, the break angle, α, and the depth of the crater walls, H. This trend is illustrated in Figure 9.12. This topic will be included in the development of the geotechnical guidelines that are the second main activity of Task 4.
(d)
As shown in Figure 9.13 the main causes of subsidence are: HIGH INFLUENCE:
Structures Rock mass quality Block height Draw rate Draw management
MODERATE INFLUENCE:
Water conditions Footprint geometry Caving initiation Mining sequence Undercutting management
65
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.20
0.15
Y C N E U Q E R F E V I T A L E R
0.10
0.05
0.00 0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
DEPTH OF SUBSIDENCE CRATER WALL (m)
Figure 9.10: Relative frequency of different crater wall depths for underground mines by caving.
0.70 0.65 0.60 0.55
Y C N E U Q E R F E V I T A L E R
0.50 0.45 0.40 0.35 0.30 0.25 0.20 0.15 70 < RMR
0.10
60 < RMR < 70 50 < RMR < 60
0.05
40 < RMR < 50
0.00 0
10
20
30
40
BREAK ANGLE MEAN
50
60
70
80
90
ALUE (degrees)
Figure 9.11: Relative frequency of break angles for different rock mass qualities (Laubscher’s RMR), in the subsidence craters of underground mines by caving methods.
66
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
1400
Laubscher's RMR 1300
41 to 50 51 to 60
1200
61 to 70
) 1100 s r e t e 1000 m (
H T P E D L L A W R E T A R C
> 71
900 800 700 600 500 400 300 200 100 0 40
45
50
55
60
65
70
75
80
85
90
B R EA K A NGL E (degrees)
Figure 9.12: Tentative relationship between the rock mass quality (Laubscher’s RMR), the break angle (α), and the depth of the c rater walls (H) in underground mines by caving.
3
E C N A T R O P M I E V I T A L E R
2
1
0 BLOCK HEIGHT
STRUCTURES ROCK MASS QUALITY
DRAW MANAGEMENT DRAW RATE
FOOTPRINT GEOMETRY WATER CONDITIONS
MINING SEQUENCE CAVING INITIATION
UNDERCUTING MANAGEMENT
M AIN C AU SE S O F S UB SID ENC E
Figure 9.13: Relative importance of the main causes of subsidence in underground mines by caving methods.
67
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
3
E C N 2 A T R O P M I E V I T A L 1 E R
0 MONITORING
MINING SEQUENCE
DRAW RATE
RELOCATE BLASTING INFRASTRUCTURE
DRAW CONTINGENCY DRAINAGE MANAGEMENT PLANS
REMEDIAL MEASURES FOR SUBSIDENCE
Figure 9.14: Relative importance of the different remedial measures for subsidence in underground mines by caving methods.
(e)
As shown in Figure 9.14 the main remedial measures for subsidence are: HIGH INFLUENCE:
Monitoring Mining sequence Draw rate Relocate infrastructure
MODERATE INFLUENCE:
Blasting Draw management Contingency plans Drainage
9.4. WATER INFLOWS AND MUDRUSHES Water inflows and mudrushes have caused important damage to underground mines by caving methods, such as the example shown in Picture 9.14. These phenomena are sudden inflows of water and/or mud from drawpoints or other underground openings. Due to its own flow nature these phenomena propagate rapidly, endangering people, equipments, and infrastructure. Due to the fact that the amount of collected data on water inflows and mudrushes is limited, the analysis developed was mainly qualitative. The analysis of the data on water inflows and mudrushes indicates that:
68
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
Photograph 9.14: Example of the damage caused by a mudrush in an underground mine by caving methods.
(a)
(b)
As shown in Figure 9.15 the main causes of water inflows and mudrushes are: Most Frequent:
Wet ore / Clayey ore
Moderately Frequent:
Fine fragmentation Water collector crater Slope failures
Less Frequent:
Clayey overburden Warm rains / Rains Crown-Pillar failures Water above underground mine Backfill failures
As shown in Figure 9.16 the main remedial measures for water inflows and mudrushes are: Most Frequent:
Surface stabilization Draw management Contingency plans Drainage
Moderately Frequent:
Monitoring Technological improvements Relocate infrastructure Blasting
69
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.25
0.20
Y C N E U Q E R F E V I T A L E R
0.15
0.10
0.05
0.00 CLAYEY ORE WET ORE
WATER-COLLECTOR CRATER FINE FRAGMENTATION
CLAYEY OVERBURDEN
SLOPE FAILURE
RAIN WARM RAIN
WATER ABOVE UG MINE CROWN-PILLAR FAILURE
BACKFILL FAILURE
MA IN C AU SE S OF MU DR US HE S A ND WA TE R IN FLO WS
Figure 9.15: Relative importance of the main causes of water inflows and mudrushes in underground mines by caving methods.
3
E C N 2 A T R O P M I E V I T A L 1 E R
0 DRAW MANAGEMENT CONTINGENCY SURFACE PLANS STABILIZATION
DRAINAGE MONITORING
TECHNO BLASTING IMPROVEMENTS RELOCATE INFRASTRUCTURE
REMEDIAL MEASURES FOR WATER INFLOWS & MUDRUSHES
Figure 9.16: Relative importance of the main remedial measures for water inflows and mudrushes in underground mines by caving methods.
70
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
9.5. HANGUPS The ceasing of cave propagation due to the formation of stable geometry generates a hangup. This does not only stop the continuous breakage of rock, affecting the draw, but also generates a risk of a sudden failure of the stable geometry that could generate an air blast, causing important damage in the underground mine. After the failure of this stable geometry, usually the cave back reaches the ground surface generating a crater like the one shown in Picture 9.15.
Photograph 9.15: Example of the formation of a chimney crater immediately after the failure of the hangup at Inca West Sector, Salvador Mine, Chile (December 5, 1999).
The analysis of the data on hangups indicates that: (a)
As shown in Figure 9.17, the area of a hangup could vary widely, from less than 1000 2 2 2 m to more than 35000 m . Nevertheless, most reported data are below 15000 m , 2 and the average is 12000 m .
(b)
Reported data on air-blasts are related to hangups with areas larger than 10000 m .
(c)
As shown in Figure 9.18 the main causes of hangups are:
(d)
2
Most Frequent:
Geological changes Underestimation of rock mass quality
Moderately Frequent:
Low stress environment Changes in the undercut height
Less Frequent:
Draw rate / Draw management Undercutting sequence No measures taken to facilitate cave initiation Non standard undercut geometry
As shown in Figure 9.19 the main remedial measures for hangups are: Most Frequent:
Increase of the undercut area Conditioning the rock mass
Moderately Frequent:
Weakening of the boundaries of the hangup Draw rate / Draw management
71
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.30
0.25
Y C N E U Q E R F E V I T A L E R
0.20
SALVADOR, SALVADOR, 05.12.1999 05.12.1999 0.15
0.10
0.05
AIRBLAST 0.00 0
5000
10000
15000
20000
25000
30000
35000
40000
HANGUP AREA (m2)
Figure 9.17: Relative frequency of different hangup areas in underground mines by caving.
0.35
0.30
Y C N E U Q E R F E V I T A L E R
0.25
SALVADOR, SALVADOR, 05.12.1999 05.12.1999
0.20
0.15
0.10
0.05
0.00 GEOLOGICAL CHANGES
UNDERESTIMATED ROCK MASS QUALITY
LOW STRESS ENVIRONMENT
CHANGES IN UNDERCUT HEIGHT
DRAW RATE DRAW MANAGEMENT
UNDERCUTTING SEQUENCE
NO MEASURES NON STANDARD TO FACILITATE UNDERCUT CAVING INITIATION GEOMETRY
MAIN C AUSES OF HA NGUP S
Figure 9.18: Relative importance of the main causes of hangups in underground mines by caving.
72
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
0.45
0.40
0.35
Y C N E U Q E R F E V I T A L E R
0.30
SALVADOR, SALVADOR, 05.12.1999 05.12.1999
0.25
0.20
0.15
0.10
0.05
0.00
INCREASE UNDERCUT AREA
CONDITIONING THE ROCK MASS
WEAKENING THE BOUNDARIES
DRAW RATE DRAW MANAGEMENT
REMEDIAL MEASURES FOR HANGUPS
Figure 9.19: Relative importance of the main remedial measures for hangups in underground mines by caving.
9.6. FINAL COMMENTS The evaluation of the different causes for geotechnical hazards allows the grouping and classification of these causes as follows: Causes of Geotechnical Origin: Structures (presence of major geological structures) Rock mass quality (strength/cavability of the rock mass) Stress environment (in situ stresses) Water conditions (groundwater, hydrogeology, hydrology)
Causes Related to Mine Design: Block height (column of solid rock above the UCL) Footprint geometry (area and geometry) Caving initiation (area, geometry, location, undercut height, measures to facilitate caving) Mine layout (drift orientation, spacing, size, draw point geometry and spacing) Support (drift support, draw point support, etc.)
Causes Related to Mine Planning: Mining sequence (caving front orientation, geometry, advance direction, detentions, changes, etc.) 2 Undercutting rates (magnitude (m /month) and changes of magnitude) Draw rate (magnitude (m/day) and changes of magnitude, draw strategy)
73
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
Causes Related to Mine Operation: Undercutting management (tactical development of the undercutting: steps, operative sequence, short term rate) Draw management (tactical development of the extraction: uniformity, local changes, short term rate) Blasting (blast induced damage, remnant pillars, poor drilling/blasting operation)
The evaluation of the relative frequency of each one of these causes in the reported geotechnical hazards, allow classifying them as causes of high influence, moderated influence, and low influence for each type of geotechnical hazard. This is shown in Figure 9.20, which indicates that the most important causes of geotechnical hazards are: STRUCTURES (geotechnical, present in all geotechnical hazards) DRAW RATE (mine planning, present in 4 of 5 geotechnical hazards) DRAW MANAGEMENT (mine operation, present in 3 of 5 geotechnical hazards) The evaluation of the different remedial measures for geotechnical hazards, allow the grouping and classification of these remedial measures as follows: Remedial Measures of Geotechnical Origin: Monitoring (seismic monitoring, displacements, field inspections, etc.) Rock mass conditioning (distressing, hydrofracturing, boundary weakening, etc.)
Remedial Measures Related to Mine Design: Support (additional support, repair, backfilling, etc.)
Remedial Measures Related to Mine Planning: Mining sequence (caving front orientation, geometry, advance direction, detentions, changes, etc.) Draw rate (magnitude (m/day) and changes of magnitude, draw strategy) Technological improvements (remote controlled equipment, new chute design, etc.) Surface stabilization (stabilization of slopes, mine waste deposits, etc.) Relocate infrastructure (changing the location of infrastructure affected by/causing a geotechnical hazard)
Remedial Measures Related to Mine Operation: Draw management (tactical development of the extraction: uniformity, local changes, short term rate) Contingency plans (restrict access, evacuate people and equipment, sealing drifts or other cavities, etc.) Blasting (improved blasting techniques, blasting of remnant pillars, etc.) Drainage (surface and underground drainage measures, improving dewatering capacity, etc.) Undercutting management (tactical development of the undercutting: steps, operative sequence, short term rate)
The evaluation of the relative frequency of each one of these remedial measures in the reported geotechnical hazards, allow classifying them as remedial measures of high influence, moderate influence, and low influence for each type of geotechnical hazard. This is shown in Figure 9.21, which indicates that the most important remedial measures for geotechnical hazards are: MINING SEQUENCE (mine planning, present in 4 of 5 geotechnical hazards) MONITORING (geotechnical, present in 3 of 5 geotechnical hazards) DRAW MANAGEMENT (mine operation, present in 3 of 5 geotechnical hazards)
74
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
MAIN CAUSES
CAUSES
OF
GEOTECHNICAL
MINE DESIGN
PLANNING
OPERATION
GEOTECHNICAL HAZARDS IN R O C K
UNDERGROUND MINES BY CAVING S T R U C T U R E S
G E O T E C H N I C A L
M A S S Q U A L I T Y
S T R E S S
E N V I R O N M E N T
W A T E R
F O O T P R I N T
B L O C K
C O N D I T I O N S
H E I G H T
G E O M E T R Y
C A V I N G
I N I T I A T I O N
M I N I N G
R O C K
M I N E
S U P P O R T
L A Y O U T
S E Q U E N C E
U N D E R C U T I N G
R A T E
U N D E R C U T I N G
D R A W
R A T E
D R A W B L A S T I N G
M A N A G E M E N T
M A N A G E M E N T
COLLAPSES H A Z A R D S
ROCKBURSTS SUBSIDENCE WATER INFLOWS & MUDRUSHES HANGUPS
HIGH INFLUENCE
MODERATE INFLUENCE
LOW INFLUENCE
Figure 9.20: Relative influence of the main causes of geotechnical hazards in underground mining by caving.
MAIN
R E M E DI A L
REMEDIAL & MANAGEMENT
GEOTECH
M E A SU R E S
PLANNING
DESIGN
OPERATION
MEASURES
R
R
FOR
O
GEOTECHNICAL HAZARDS
C
S
K
UNDERGROUND MINES
M
BY CAVING M
A
O
S
N
S
I T
C
O
O
R
N
I
D
N
I
G
T
I C
I
H
A
A
R
N
N
C
T
A
O
E
E
W
G
A
I
S
I
M
W
M
T
N
A
P
A
F
N
B
R
A
P P
S
O
E
R
R
R
Q
A
O
I
A
G
T
U
T
V
L
S
E
E
E
E
I
T
M
M
Z
R
E
C
E
A
U
N
E
N
T
C
T
T
I
T
S
O
U
N
R
N
O N T I N
B
D
G
L
R
E
A
A
N
S
I
C
T
N
Y
I
A
N
G
G
E
P L A N S
E
COLLAPSES
E
N
D
U
I
H
C
R
N
C
O
F
N
G
E
C
R
C
S
N
T
L
E M
D
O
O
U
I
I
G
E
T
H A
ROCKBURSTS
Z A
SUBSIDENCE
R D S
WATER INFLOWS & MUDRUSHES
A L
HANGUPS
HIGH INFLUENCE
MODERATE INFLUENCE
LOW INFLUENCE
Figure 9.21: Relative influence of the main remedial measures for geotechnical hazards in underground mining by caving.
75
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
10. CONCLUSIONS To develop this benchmarking 17 mines in 7 countries were visited, in order to collect relevant information. Also a comprehensive literature review was done to get complementary data, allowing to obtain information on up to 88 additional mines; nevertheless, in most cases the additional data do not include all the aspects considered in the benchmarking survey. The interpretation of the data collected in this benchmarking has allowed to define the current trends and practices of the underground mining by caving methods. These have been summarized as histograms and/or curves to facilitate their use by the sponsors of ICS-II, especially during the early stages of a new mining project. To make even easier the use of this information, Table 10.2 summarizes the current trends for the most relevant design parameters, and it can be used for pre-feasibility studies. It is also important to realize when a problem originates and when it is detected during the different stages of a mining project. As a first attempt, it is suggested use Table 10.1.
Table 10.1 POSSIBLE DISTRIBUTION OF THE ORIGIN AND DETECTION OF PROBLEMS DURING THE DIFFERENT STAGES OF A MINING PROJECT Stage of the Project
Origin of the Problem
Detection of the Problem
Pre-Feasibility Study
0% to 20%
0%
Feasibility Study
20% to 60%
0% to 5%
Basic Engineering
20% to 40%
0% to 5%
Detailed Engineering
10% to 20%
0% to 5%
Construction
10% to 20%
10% to 30%
Operation
20% to 60%
50% to 90%
(*) Modified from Sowers (1993)
Finally it must be noted that all the results presented in this report will be used as a starting basis for the development of geotechnical guidelines for a transition from open pit to underground mining, which corresponds to the second main activity of Task 4, and includes the following subjects: 5.
CAVING PROPAGATION
6.
SUBSIDENCE
7.
CROWN-PILLAR
8.
WATER INFLOWS & MUDRUSHES
76
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
Table 10.2 TYPICAL DESIGN PARAMETERS FOR A BLOCK/PANEL CAVING MINE Mine Design Parameter
Typical Value
Rock Mass Quality
50 ≤ RMR < 60
Acces
Decline
Block Height < 50000 m Footprint Area
50000 a 100000 m > 100000 m
Caving Initiation
l e v e L t u c r e d n U
2
This typical block height could vary ± 20%.
30000 m
2
75000 m
2
170000 m
These typical areas could vary +20%. It is recommended to use equal or larger areas, but not smaller than the typical values. Also, square areas are better than the rectangular ones.
2
2
Area
10000 m
Shape
Square
Measures to Facilitate
Slot
Is highly recommended to facilitate cave initiation.
Hydraulic Radius
20 to 30 m
Avoid being close to the limit in Laubscher’s chart.
Spacing
15 m
Height Width
4m 4m
Could be increased but not decreased.
Undercut Height
8m
Could vary, but be careful if using small undercutting heights.
Undercut Rate
2100 m /month
s t f i r D
o l i t e c v a e r t L x E n
2
If RMR > 60 rock mass cavability must be evaluated carefully. Currently 70% of mines prefer declines, and 20% declines and shafts as mine access.
210 m 2
Comments
Smaller areas are not recommended, specially in massive rock masses. Internal corners must be avoided (e.g. a “L” shaped area).
This is the current practice.
2
Could be increased but be careful with induced seismicity, specially if in a high stress environment.
Crown-Pillar Thickness
17 m
Could vary ± 20% (measured from floor UCL to floor EXT).
Spacing
30 m
Could vary from 26 to 36 m.
Height Width
4m 4m
s t f i r D
Spacing
Draw Points
Influence Area Draw Rates
LHD Equipment
Could be increased but not decreased.
15 m 225 m
Could vary from 13 to 18 m. 2
2
Could vary from 169 to 324 m . This is an average value. Typically lower values are used at the beginning of caving, and higher values are used when over 30% of the block height has been extracted.
0.20 m/day
Capacity
11 ton
It could vary ± 20%.
Traming Distance
140 m
Smaller tramming distances are preferable.
Powder Factor
400 grm/ton
Oversize Limit
3
Subsidence
RMR < 70 RMR > 70
1.8 to 2.0 m α >
45° α > 60°
For undercutting blasting. It could vary ± 20%. It could vary ± 20%. α is
the break angle defining the mean inclination of the crater walls.
Geotechnical Hazards
The project must take account that collapses, rockbursts, subsidence, water inflows and mudrushes, and hangups could occur (see Figure 9.20 for main causes and Figure 9.21 for the most common remedial measures).
Instrumentation & Monitoring
The most common monitoring systems include displacements and seismicity. It is recommended to include a seismic monitoring system, specially in massive hard rock and/or high stress environments..
(1)
These typical values are intended only for the pre-feasibility stage of a mining project.
(2)
RMR values are for Laubscher’s 1990 system.
77
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
11. ACKNOWLEDGMENTS The authors of this report want to thank all the sponsors for giving them the possibility of developing this work. The authors also want to express their sincere gratitude to all the colleagues that helped them to collect the information at each mine visited: Andina, Bingham Canyon, Cadia, Chuquicamata, El Teniente, Finsch, Grasberg Open Pit, Grasberg Underground (DOZ), Henderson, Kidd Creek, Kiruna, Koffiefontein, Mount Keith, Northparkes, Palabora, Ridgeway, Salvador. It is important to note that Grasberg, Henderson and Kidd Creek mines do not participate as sponsors of the ICS-II Study, but they were willing to help the authors in developing this benchmarking study. Finally, the authors want to acknowledge specially the support provided by Chuquicamata Mine of Codelco to develop this work.
78
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
12. REFERENCES [1]
Agapitio, J. & Shoemaker, D. (1987): Ground Stability and Support in Block Caving Operations at Moth lycorp’s Questa Mine, ROCK MECHANICS, Proceedings of 28 US Symposium on Rock Mechanics, edited by I. Farmer et al., Balkema.
[2]
Aimin, Z. & Yongxue, S. (2000): Application of Block Caving System in the Tongkuangyu Copper Mine, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[3]
Alanis, M.; Hormazábal, E. & Karzulovic, A. (2000): Aplicación del Metodo Observacional al Sector SW de Mina Chuquicamata. Informe Técnico elaborado por la Superintendencia de Ingeniería Geotécnica, Subgerencia de Geología y Geotecnia, División Chuquicamata de CODELCO.
[4]
Antikainen. J. (1990): Open Stope Design Under Adverse Rock Mechanical Conditions at Pyhäsalmi st Mine, ROCK MECHANICS CONTRIBUTIONS AND CHALLENGES, Proceedings of the 31 U.S. Symposium, W. Hustrulid & G. Johnson editors, Balkema.
[5]
Antikanien, J.; Simonen, A. & Mäkinen, I. (1993): 3D Modelling of the central pillar en the Pyhäsalmi ST mine, INNOVATIVE MINE DESIGN FOR THE 21 CENTURY, Proceedings of the International Congress on Mine Design, W. Bawden & J . Archibald editors, Balkema.
[6]
Apablaza, R. (2002): Personal communication.
[7]
Arjang, B. (1997): DGround Stress Determination at the 6800 Level, kidd Mining Division. Work performed for Falconbridge Ltd., Kidd Mining Division; Mining and Mineral Sciences Laboratories, Report MMSL 96-047 (CR), Job Nº 51422, CANMET.
[8]
Austin, G. (2002): DPersonal Communication.
[9]
Baase, R.; Diment, W. & Petrina, A. (1998): Sublevel Caving at Craigmont Mines Ltd., Chapter 37 in TECHNIQUES IN UNDERGROUND MINING, Selections from Underground Mining Methods Handbook, Edited by R. Gertsh and R. Bullock, SME.
[10]
Barber, J.; Dirdjosuwondo, S.; Casten, T. & Thomas, L. (2001): Block Caving the EESS Deposit at P.T. Freeport Indonesia, Chapter 53 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid and R. Bullock, SME.
[11]
Barber, J.; Thomas, L. & Casten, T. (2000): Freeport Indonesia’s Deep Ore Zone Mine, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[12]
Barlett, P. (2001): Premier Diamond Mine, Chapter 52 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid, and R. Bullock, SME.
[13]
Barlett, P. & Croll, A. (2000): Cave Mining at Premier Diamond Mine, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[14]
Barlett, P. & Raubenheimer, M. (1988): Collapse of the Gabbro Sill above an Open Stope at Premier Mine, SANGORM SYMPOSYUM, Rock Mechanics in Africa, Nov. 1988.
[15]
Barnett, W.; Guest, A.; Terbrugge, P. & Walker, D. (2001): Probabilistic Pit Slope Design in the Lim popo Metamorphic Rock at Venetia Mine, J. S. Afr. Inst. Min. Metall.
[16]
Barraza, M. & Crorkan, P. (2000): Esmeralda Mine Exploitation Project, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[17]
Bates, G. (1998): Open Stope Mining at the Magmont Mine, Bixby, Missouri , Chapter 7 in TECHNIQUES IN UNDERGROUND MINING, Selections from Underground Mining Methods Handbook, Edited by R. Gertsh and R. Bullock, SME.
[18]
Bawden, W. (1994): Integrated Seismic-Stress-Geomechanical Analysis of a Cable Bolted Back Failure, Mines Gaspe, Canada, ROCK MECHANICS; MODELS AND MEASUREMENTS CHALLENGES st FROM INDUSTRY, Proceedings of the 1 North American Rock Mechanics Symposium, , P. Nelson & S. Laubach editors, Balkema.
[19]
Beck, D.; Brady, B. & Grant, D. (1996): Analysis of Seismicity and Rock Deformation During Open Stoping of a Deep Orebody , PREDICTIONS AND PERFORMANCE IN ROCK MECHANICS AND ROCK ENGINEERING, ISRM International Symposium EUROCK’96, Volume 2, edited by G. Barla, Balkema.
[20]
Blondell, J. (2002): Personal Communication.
[21]
Blondel, J.; Aguirre, E.; Behn, G. & Toledo, C. (1993): Seismic Refraction and Tomography studies in ST the El Teniente copper mine, INNOVATIVE MINE DESIGN FOR THE 21 CENTURY, Proceedings of the International Congress on Mine Design, W. Bawden & J. Archibald editors, Balkema.
79
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
[22]
Board, M.; Seldon, S.; Brummer, R. & Pakalnis, R. (2000): Analysis of the Failure of a Large Hangingwall Wedge: Kidd Mining Division, Falconbridge, Ltd., CIM Bulletin, Vol. 93, N º 1043, September 2000.
[23]
Bonani, A. (2002): Personal Communication.
[24]
Bronkhorst, D; Rheault, J. & Ley, G. (1993): Geotechnical Principles Governing Mine Design at the WilST liams Mine, INNOVATIVE MINE DESIGN FOR THE 21 CENTURY, Proceedings of the International Congress on Mine Design, W. Bawden & J. Archibald editors, Balkema.
[25]
Broome, M. & Sandy, M. (1988): Rock Mechanics Investigations at Mufulira mine, Zambia, Transactions of the Institution of Mining and Metallurgy, (Section A, Mining Industry), Volume 97, January 1988.
[26]
Brown, E. & Ferguson, G. (1979): Prediction of Progressive Hanging-Wall Caving, Gath’s Mine, Rhodesia, Transactions of the Institution of Mining and Metallurgy, (Section A, Mining Industry), Volume 88, January 1988.
[27]
Brumleve, C. (1988): Rock Reinforcement of a Caving Block in Variable ground Conditions, King Mine, Zimbabwe, Transactions of the Institution of Mining and Metallurgy, (Section A, Mining Industry), Volume 97, April 1988.
[28]
Brumleve C. & Maier, M. (1981): Applied Investigations of Rock Mass Response to Panel Caving, Henderson Mine, Colorado, USA, Chapter 19 in DESIGN AND OPERATION OF CAVING AND SUBLEVEL STOPING MINES, Volume I, edited by D. Stewart, SME, New York.
[29]
Buksa, H. (2001): Sublevel Cave Mining Update at INCO’s Stobie Mine, Chapter 44 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid and R. Bullock, SME.
[30]
Butcher, R. (2002): Personal Communication.
[31]
Calder, K.; Townsend, P. & Russell F. (2001): Palabora Underground Mine Project , Chapter 49 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid and R. Bullock, SME.
[32]
Calderón, A.; Torres, R.; Suárez, C.; Díaz, M.; Karzulovic, A. & Barahona P. (1988): Diseño Geotécnico Taludes Mina Chuquicamata, Informe Técnico, Superintendencia Ingeniería Geotécnica, Dirección de Planificación, Subgerencia Planificación y Gestión Estratégica, División Chuquicamata de CODELCO.
[33]
Callahan, M.; Keskimaki, K. & Rech, W. (2000): A Case History of the Crusher Level Development at Henderson, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[34]
Carter, C. & Russell, F. (2000): Modelling and Design of Block Caving at Bingham Canyon, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[35]
Casten, T.; Golden, R.; Mulyadi, A. & Barber, J. (2000): Excavation Design and Ground Support of the Gyratory Crusher Installation at the DOZ Mine, PT Freeport Indonesia, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[36]
Catalán, A.; Hormazábal, E. & Karzulovic, A. (2000): Aplicación del Método Observacional al Sector SE de Mina Chuquicamata, Informe Técnico elaborado por la Superintendencia de Ingeniería Geotécnica, Subgerencia de Geología y Geotecnia, División Chuquicamata de CODELCO.
[37]
Chen, D (1996): Geotechnical Assessment of Block Cave Mining in Northparkes Mines, NSW, AUSTRAnd ROCK MECHANICS, TOOLS AND TECHNIQUES, Proceedings of the 2 North American Rock Mechanics Symposium: NARMS’96, Volume 1; edited by M. Aubertin, F. Hassani & H. Mitri, Balkema. LIA,
[38]
Chileshe, P. (1996): Interaction Between Underground and Opencast Workings at Nchanga Mine, Chingola, Zambia, SURFACE MINING 1996, Johannesburg, SAIMM.
[39]
Chileshe, P. (1997): Ground Stress and Movement Associated with Block Caving of the flat 25º dipping st Orebody at Nchanga Mine, Chingola, Zambia, SARES 97, 1 Southern African Rock, Engineering Symposium, Proceedings.
[40]
Chileshe, P. & Phiri, S. (1994): New Production from “Exhausted” Block-Caving Areas at Nchanga TH Mine, XV CMMI CONGRESS, Johannesburg, SAIMM.
[41]
Contador, N. & Glavic F. (2001): Sublevel Open Stoping at El Soldado Mine: A Geomechanic Challenge, Chapter 29 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid and R. Bullock, SME.
[42]
Dahner, C. (2002): Personal Communication.
[43]
De Nicola, R. & Fishwick, M. (2000): An Underground Air Blast – Codelco Chile - Division Salvador , MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
80
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
[44]
DeWolfe, V. (1981): Draw Control in Principle and Practice at Henderson Mine, Chapter 56 in DESIGN AND OPERATION OF CAVING AND SUBLEVEL STOPING MINES, Volume II, edited by D. Ste wart, SME, New York.
[45]
Díaz, J.; Espinoza, C. & Karzulovic, A. (2000): Evaluación y Análisis Colapso en Nivel 16 Producción LHD, III Panel, Mina Río Blanco, Estudio DA - CG - 00 - 003, informe técnico de AKL para División Andina de CODELCO.
[46]
Dinkowitz, S. (2002): Personal Communication..
[47]
Doepken, W. (1998): The Henderson Mine, Chapter 44 in TECHNIQUES IN UNDERGROUND MINING, Selections from Underground Mining Methods Handbook, Edited by R. Gertsh and R. Bullock, SME.
[48]
Dolipas, R. (2000): Rock Mechanics as Applied in Philex Block Cave Operations, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[49]
Dube, S. (2002): Personal Communication.
[50]
Duffield, S. (2000): Design of the Second Block Cave at Northparkes E26 Mine, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[51]
Dunne, K. & Pakalnis R. (1996): Dilution Aspects of a Sublevel Retreat Stope at Detour Lake Mine, nd ROCK MECHANICS, TOOLS AND TECHNIQUES, Proceedings of the 2 North American Rock Mechanics Symposium: NARMS’96, Volume 1; edited by M. Aubertin, F. Hassani & H. Mitri, Balkema.
[52]
Espinoza, C. (1996): Analisis y Diseño de Crown Pillars, Memoria de Título, Depto. Ingeniería de Minas, Universidad de Santiago de Chile.
[53]
Fletcher, J. (1960): Ground Movements and Subsidence from Block Caving at Miami Mine, AIME Trans., Vol.217, 1960. San Francisco Meeting.
[54]
Flores, G. (1993): A new Mining Sequence to Minimize Stability Problems in Block Caving Mines, MSc Thesis (unpublished), Colorado School of Mines, Golden, Colorado.
[55]
Flores, G. & Karzulovic, A. (2001): The Role of the Geotechnical Group in an Open Pit: Chuquicamata th Mine, Chile, 4 International Symposium on slope Stability in Surface Mining, Denver C olorado.
[56]
Gallager, J. & Teuscher, J. (1998): Henderson Mine: Preparing for the Future; Mining Engineering, a publication of SME, August 1998, Vol. 50, Nº 8.
[57]
Goodrich, R.; Hardy, M. & Brechtel, C. (2001): Geotechnical Characterization and Structural Mine Design at the Murray Mine, Northeasten Nevada, ROCK MECHANICS IN THE NATIONAL INTEREST, th Proceedings of the 38 U.S. Rock Mechanics Symposium, Volume I, Edited by D. Elsworth, J. Tinucci & K. Heasley, Balkema.
[58]
Grant, D & DeKruijff, S. (2000): Mount Isa Mines - 1100 Orebody, 35 Years On, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[59]
Guarascio, M.; Antonietti, M.; Fry, R. & Gallavresi, F. (1993): Stabilization of Unconsolidated Backfill at Tara Mine, ASSESSMENT AND PREVENTION OF FAILURE PHENOMENA IN ROCK ENGINEERING, A. Pasamehmetoglu et al. editors, Balkema.
[60]
Hancock, F. & Mattson, R. (1982): Sublevel Caving at Granduc , Chapter 4 in UNDERGROUND MINING METHODS HANDBOOK, W. Hustrulid editor, New York, SME
[61]
Hannweg, L. (2002): Personal Communication.
[62]
Harrison, E. (2002): Personal Communication.
[63]
Harvey P.; Bloss, M. & Bouliane, N. (2000): Cannington Mine – 30 Million Ounces of Silver per Year from a 300-m Cube, Chapter 27 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid and R. Bullock, SME.
[64]
Heden, H.; Lidin, K. & Malmström, R. (1998): Sublevel Caving at LKAB’s Kirunavaara Mine, Chapter 39 in TECHNIQUES IN UNDERGROUND MINING, Selections from Underground Mining Methods Handbook, Edited by R. Gertsh and R. Bullock, SME.
[65]
Henry, E. & Dahnér-Linqvist, C. (2000): Footwall Stability at the LKAB’s Kiruna Sublevel Caving Operation, Sweden, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[66]
Hepworth, N. (2002): Personal communication.
[67]
Henry, E. & Marcotte, D. (2001): Developments in Ground Control Planning enhaced by RQD Geostatistical Analyses at the LKAB’s Kiruna Mine, Sweden, ROCK MECHANICS - A CHALLENGE FOR SOCIETY, Särkkä & Eloranta editors, Balkema.
81
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
[68]
Hewson, S. (2002): Personal Communication.
[69]
Hickson, R. (1991): Grasberg Open Pit: Ertsberg’s Big Brothest Comes on Stream in Indonesia, Mining Engineering, April 1991.
[70]
Hornsby, B. & Sullivan, B. (1998): Excavations Design and Mining Methods in the 1100 Orebody, Mount Isa Mine, Australia, Chapter 10 in TECHNIQUES IN UNDERGROUND MINING, Selections from Underground Mining Methods Handbook, Edited by R. Gertsh and R. Bullock, SME.
[71]
House, M.; van As, A. & Dudley, J. (2001): Block Caving Lift 1 of the Northparkes E26 Mine, Chapter 50 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid, and R. Bullock, SME.
[72]
Ingeroc (2000): Estudio de Medición de Esfuerzos, Informe Final para División Andina de CODELCO, Ingeniería de Rocas Ltda.
[73]
Internal Note (2002): Kidd Creek Mine – Kidd Mining Division – Underground Tour Guidebook.
[74]
Jofre, J.; Yáñez, P. & Ferguson, G. (2000): Evolution in Panel Caving Undercutting and Drawbell Excavation, El Teniente Mine, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[75]
Johnson, G. (1998): Sublevel Caving at the Stobie Mine, INCO Metals Co., Chapter 38 in TECHNIQUES IN UNDERGROUND MINING, Selections from Underground Mining Methods Handbook, Edited by R. Gertsh and R. Bullock, SME.
[76]
Johnson, G. & Soulé, J. (1963): Measurements of Surface Subsidence, San Manuel Mine, Pinal Country, Arizona, Report of Investigation 6204, U.S. Dept. of the Interior, BUREAU OF MINES, Washington.
[77]
Jude, C. (1990): Structural Analysis of a Mechanized LHD trench undercut caving system, ROCK MEst CHANICS CONTRIBUTIONS AND CHALLENGES, Proceedings of the 31 U.S. Symposium, W. Hustrulid & G. Johnson editors, Balkema.
[78]
Karzulovic, A.; Cavieres, P. & Gaete, S. (1994): Evaluación Geotécnica-Geomecánica del Teniente Sub-6, Sector NFW1 y su Impacto en el Mediano-Largo Plazo, Mina El Teniente EM-10/94, Depto. Estudios y Métodos Operacionales, División El Teniente de CODELCO.
[79]
Karzulovic; A. Cavieres, P. & Pardo, C. (1999): Caving Subsidence at El Teniente, Proc. Symp. Mining Engineering, SIMIN 99, Universidad de Santiago.
[80]
Karzulovic, KA. & Flores, G (2002): Visitas Técnicas.
[81]
Karzulovic, A.; Galeb, M. & Quiñones, L. (1991): Evaluación de la Experiencia Adquirida Durante el Desarrollo y Explotación de los Paneles I y II de la Mina Río Blanco, informe técnico de Ingeniería y Geotecnia Ltda. para División Andina de CODELCO.
[82]
Keskimaki, K. & Jensen, E. (1992): Advances in Equipment Technology at the Henderson Mine, MASSMIN’92, The South African Institute of Mining and Metallurgy, SAIMM, Johannesburg.
[83]
Kozyrev, A. et al. (2001): Underground Mining in the Kola Peninsula, Russia, Chapter 30 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid and R. Bullock, SME.
[84]
Kvapil, R. (1982): The Mechanics and Design of Sublevel Caving Systems. Underground Mining Methods Handbook, Editor W. A. Hustrulid, Pages 880-897. Society of Mining Engineers, AIME, New York.
[85]
Kvapil, R. (1992): Sublevel Caving . SME Mining Engineering Handbook, 2 Edition, Editor H. l. Hartman, Vol 2: 1789-1814. Society for Mining, Metallurgy and Exploration: Littleton, Colorado.
[86]
Kvapil, R., Baeza, L., Rosenthal, J. & Flores, G. (1989): Block Caving at El Teniente Mine, Chile. Transactions of the Institution of Mining and Metallurgy, section A: Mining Industry, Vol 98,: A43-56.
[87]
Lacasse, M. & Legast, P. (1981): Change from Grizzly to LHD Extraction System, Chapter 10 in DESING AND OPERATION OF CAVING AND SUBLEVEL STOPING MINES, edited by D. Stewart, SME, New York.
[88]
Leach, A.; Naidoo, K. & Bartlett, P. (2000): Considerations for Design of Production Level Drawpoint Layouts for a Deep Block Cave, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia.
[89]
Li, T. & Cribb, B. (1999): Shotcrete Trials and Aplications in Poor Ground Conditions at Mount Isa Mines, ROCK SUPPORT AND REINFORCEMENT PRACTICE IN MINING, Villaescusa, Windsor & Thompson editors, Balkema.
[90]
Libby, D.J. et al. (1985): The Tara Mines Story , Transactions of the Institution of Mining and Metallurgy, (Section A, Mining Industry), Volume 94, January 1985.
[91]
Lupo, J. (1997): Progressive Failure of Hangingwall and Footwall Kiirunavaara Mine, Sweden, Int. Journal of Rock Mechanics & Mining Sciences, Vol. 34 Nº 3-4, paper Nº 184, Elsevier.
nd
82
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
[92]
Lupo, J. (1999): Numerical Simulation of Progressive Failure from Underground Bulk Mining Operath tions, ROCK MECHANICS FOR INDUSTRY, Proceedings of the 37 U.S. Rock Mechanics Symposium, B. Amadei et al. editors, Balkema.
[93]
Malmgren, L. & Svenson, T. (1999): Investigations of Important Parameters for Unreinforced Shotcrete as Rock Support in the Kiirunavaara Mine, Sweden, ROCK MECHANICS FOR INDUSTRY, Proceedth ings of the 37 U.S. Rock Mechanics Symposium, B. Amadei et al. editors, Balkema.
[94]
Management and Staff Ecstall Mining Limited (1974): The Ecstall Story , CIM Bulletin, Volume 67, Nº 745, May 1974.
[95]
McMurray, D. (1982): Sublevel Caving Practice at Shabanie Mine, Rhodesia, Chapter 7 in UNDERGROUND MINING METHODS HANDBOOK, edited by W. Hustrulid, SME.
[96]
McMurray, S. (1982): Mining Below the Gabro-sill, Premier Mine, Cullinam, South Africa, Chapter 5 in UNDERGROUND MINING METHODS HANDBOOK, edited by W. Hustrulid, SME.
[97]
Merino, L. & Tapia, R. (2001): Cavability of Inca Sector, El Salvador Mine, FLAC AND NUMERICAL MODELLING IN GEOMECHANICS, Billaux et al. editors, Balkema.
[98]
Moss, A. (2002): Personal Communication.
[99]
Mossop, D. (2002): Personal Communication.
[100] Moyano, A. & Viene J. (1993): Remote Operation of LHD and Pick Hammers in Rock Burst Conditions ST at El Teniente Mine, INNOVATIVE MINE DESIGN FOR THE 21 CENTURY, Proceedings of the International Congress on Mine Design, W. Bawden & J. Archibald editors, Balkema. [101] Page, C. & Brennen, R. (1983): Stability of Large Open Stopes in Weak Rock , Chapter 15 in STABILITY IN UNDERGROUND MINING, American Institute of Mining, Metallurgical and Petroleum Enginners, Inc., C.O. Brawner editor, New York. [102] Pastén, O. (1999): Evaluacion de la Socavacion de Baja Altura en Teniente 4 Sur , Memoria de Título, Depto. Ingeniería de Minas, Universidad de Santiago de Chile. [103] Perason, N. (1981): The Development and Control of Block Caving at the Chingola Division of Nchanga Consolidated Copper Mines Limited, Zambia, Chapter 18 in DESIGN AND OPERATION OF CAVING AND SUBLEVEL STOPING MINES, Volume I, edited by D. Stewart, SME, New York. [104] Player, J. (2001): Longitudinal Sublevel Caving, Big Bell Mine, Chapter 45 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid, and R. Bullock, SME. [105] Plessis, L. & Martin, D. (?):Numerical Modelling Studies for Design of High Rock Slopes at Palabora TH Copper Mine, PROC. 7 INTERNATIONAL CONGRESS ON ROCK MECHANICS, A AACHE, VOL 1, A. A. B ALKEMA. [106] Pothitos, F. (2002): Personal Communication. [107] Power, G. (2002): Personal Communication. [108] Preece, C. (2001): Finsch Mine: Open Pit to Open Stoping to Block Caving , Chapter 54 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid and R. Bullock, SME. [109] Preece, C (2002): Personal Communication. [110] Quinteiro, C.; Quinteiro, M. & Hedström, O. (2000): Underground Iron Ore Mining at LKAB, Sweden, Chapter 43 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by Hustrulid and Bullock, SME. [111] Ran, J.; Seldon, S. & Counter, D. (2001): Underground Mining Induced Remobilization of a Hangingwall Wedge and Movement of Footwall Structures at Kidd Mine - A Case Study , paper to be published. [112] Rech, W. (2001): Henderson Mine, Chapter 48 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid and R. Bullock, SME. [113] Rech, W. & Lorig, L. (1992): Predictive Numerical Stress Analysis of Panel Caving at the Henderson Mine, MASSMIN’92, The South African Institute of Mining and Metallurgy, SAIMM, Johannesburg. [114] Rech, W.; Keskimaki, K. & Stewart, D. (2000): An Update on Cave Development and Draw Control at the Henderson Mine, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia. [115] Rech, W. & Watson, D. (1994): Cave Initiation and Growth Monitoring at the Henderson Mine, SME Annual Meeting, Albuquerque, New Mexico. [116] Revista Minería Chilena, Nº 254, Agosto 2002. [117] Rojas, E. (2002): Personal Communication.
83
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
[118] Rojas, E.; Cavieres, P.; Dunlop, R. & Gaete, S. (2000): Control of Induced Seismicity at El Teniente Mine, Codelco-Chile, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia. [119] Rojas, E.; Molina, R.; Bonani, A. and Constanzo, H. (2000):The Pre-Undercut Caving Method at the El Teniente Mine, Codelco Chile, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia. [120] Rojas, E.; Molina, R. & Cavieres, P. (2001): Pre-undercut Caving in El Teniente Mine, Chile, Chapter 51 in UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by Hustrulid and Bullock, SME. [121] Sandy, M. & Player, J. (1999): Reinforcement Design Investigations at Big Bell , ROCK SUPPORT AND REINFORCEMENT PRACTICE IN MINING, Villaescusa, Windsor & T hompson editors, A. Balkema. [122] Schroeder, K. (2002): Personal Communication. [123] Stawski, M. (2002): Personal Communication. [124] Stevens, C.; Sandbak, L. & Hunter, J. (1987): LHD Production and Design Modifications at the San th Manuel Mine, ROCK MECHANICS, Proceedings of 28 US Symposium on Rock Mechanics, edited by I. Farmer et al., Balkema. [125] Stewart, R. &d Sacrison, R. (1983): Geological Engineering – A Bridge Between Geologist and Miner , in Chapter 12 in SME - AIME Fall Meeting, Salt Lake City, Utah - October 19 - 21, 1983. [126] Streeton, G. (2000): Geotechnical Aspects of Open Stope Design at BHP Cannington, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia. [127] Struthers, M.; Turner, M.; McNabb, K. & Jenkins, P. (2000): Rock Mechanics Design and Practice for Squeezing Ground and High Stress Conditions at Perseverance Mine, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia. [128] Suarez, C. (2002): Personal communications. [129] Szwedzicki, T. (1989): Pillar Recovery at Manghura Copper Mines, Zimbabwe, Transactions of the Institution of Mining and Metallurgy, (Section A, Mining Industry), Volume 98, September-December 1989. [130] Tannant, D.; Martin, C. & Kaiser, P. (1997): Site Characterisation of the 6800 to 7800 Mining Block , Technical Report submitted to Falconbridge Limited - Kidd Mining Division by the Geomechanics Research Centre at Laurentian University. [131] Taylor, J. & Chinamatira, R. (2000): The Evolution of Sublevel Caving at Trojan Mine, Bindura, Zimbabw e, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia. [132] Terbrugge, P. & Hanif, M. (1981): Discussion of a Large Scale on the Footwall of the Nchanga Open Pit, Zambia, Proceedings of the International Symposium on Weak Rock, Tokyo, September 1981. [133] Thompson, P. (1989): Slope Stability at Finsh Mine, ROCK SLOPE STABILITY, Sangorm Symposium, March 1989. [134] Tobie, R. & Julin, D. (1982): Block Caving: General Description, UNDERGROUND MINING METHODS HANDBOOK, edited by W. Hustrulid, SME. [135] Tobie, R.; Thomas, L. & Richards, H. (1998): San Manuel Mine, Chapter 43 in Techniques in UNDERGROUND MINING, Selections from Underground Mining Methods Handbook, Edited by R. Gertsh and R. Bullock, SME. [136] Turner, M. & Player, J. (2000): Seismicity at Big Bell Mine, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia. [137] Uggalla, S. (2001): Sublevel Open Stoping – Design and Planing at the Olympic Dam Mine, UNDERGROUND MINING METHODS, Engineering Fundamentals and International Case Studies, Edited by W. Hustrulid and R. Bullock, SME. [138] Van As, A. (2002): Personal communication. [139] Van As, A. and Jeffrey, R. (2000): Caving Induced by Hydraulic Fracturing at Northparkes Mines, PACIFICS ROCKS, “ROCK AROUND THE RIM”, Proceedings of the Fourth North American Rock Mechanics Symposium: NARMS 2000, Washington; Girard, J; Liebman, M; Breeds, C and Doe, T . editors, A. Balkema. [140] Vera, S. (1981): Caving at Climax , Chapter 14 in Design and OPERATION OF CAVING AND SUBLEVEL STOPING MINES, Volume I, edited by D. Stewart, SME, New York. [141] Wilkes, T. (1992): The Support of Highly Fractured Rock in shallow Open Stopes at Koffiefountain Mine, Orange Free State, Republic of South Africa, ROCK SUPPORT IN MINING AND UNDERGROUND CONSTRUCTION, Kaiser & McCreath editors, Balkema.
84
ICS-II, Task 4
GEOTECHNICAL GUIDELINES FOR A TRANSITION FROM OPEN PIT TO UNDERGROUND MINING
[142] Wilkie, N. and Holt, W. (1961): A Description of Open Pit Mining at Nchanga Consolidated Cooper th Mines Limited, Northern Rhodesia, Commonwealth Mining and Metallurgical Congress, 7 , May 1961, Johannesburg. [143] Wilson, A. (2000): The Past Focuses Support for the Future, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia. [144] Wilson, D. (2002): Personal Communication. [145] Wood, P.; Jenkins, P. and Jones, I. (2000): Sublevel Cave Drop Down Strategy at Perseverance Mine, Leinster Nickel Operations, MASSMIN 2000, Proceedings, Brisbane, Qld, Australia. [146] Zappia, M. (1981): Gravity Caving and Production Hoisting at the San Manuel Mine, Chapter 16 in DESIGN AND OPERATION OF CAVING AND SUBLEVEL STOPING MINES, Volume I, edited by D. Stewart, SME, New York. [147] Zerga, R. (1981): Development and Production Equipment in Use at San Manuel, Chapter 50 in DESIGN AND OPERATION OF CAVING AND SUBLEVEL STOPING MINES, Volume II, edited by D. Stewart, SME, New York.
85