WARNING: If there are conflicts between a stated word and the number/amount/figure described, the stated/spelled word shall prevail. Should there be conflicts between two (2.0) stated quantities, the higher figure shall prevail. IMPORTANT NOTE: For this first reformat of the examination in this subject, the Examinee shall be allowed to make full use (open books) ONLY of Rule VII and Rule VIII of the 2004 Revised Implementing Rules and Regulations (IRR) of the Presidential Decree (P.D.) No. 1096 , otherwise known as the 1977 National Building Code of the Philippines (NBCP) i.e. ONLY AS downloaded and reproduced from the PRBoA website at www.architectureboard.ph . Other IRR versions are specifically disallowed for use during the examination. A. PROJECT NO. 1 TITLE and General General Description: Proposed Open Market Residential Prototype Project consisting of Two (2.0) Storey, Single-Detached House with an 77.0 Sq.M. Total Gross Floor Area (TGFA) cum Site Development Planning Project for a Cluster of Ten (10.0) Prototype House and Lots, on a Site with a Ten Percent (10.0%) Slope B. STATEMENT OF THE ARCHITECTURAL PLANNING and DESIGN DESIGN PROBLEM: PROBLEM:
A Multinational Multinational development development company (the (the “Client”) has has decided that its its property, a one thousand nine hundred thirty four point seventy two square meter (1,934.72 Sq.M.) inside (or regular) lot, with a low density residential (R-1) zoning classification, and located in the better parts of the Municipality of Taytay in Rizal Province (Luzon Island), shall be developed to host an open market residential development. The 10 Prototype Houses shall be exclusive/ semi-upscale structures, 6 of which shall be on lots each with a 132.0Sq.M. Total Lot Area (TLA) and a 12.0m depth. The stated 77.0 Sq.M. TGFA of the Prototype Houses only refers to the enclosed floor areas above grade (or natural ground) level and excludes all other floor areas, if these are still to be introduced at a later time. C. PROJECT SITE FEATURES:
The 1,934.72 Sq.M. Grand Total Lot Area (GTLA) making up the entire Project Site is rectangular in shape and has thirty two (32.0) m wide frontage facing east. The property may be reached via a fifteen meter (15.0 m) wide street i.e. the main road right-of-way right-of-way (RROW) which has 1.8m wide paver-lined sidewalks on each side. The Surface of the main RROW sidewalk closest to the Project Site shall be considered as elevation 0.0 m. An 8.0 m wide cluster street bisects the Project Site at its long axis and intersects the main RROW at the right angle. The Project Site uniformly slopes at ten percent (10.0%) from west to east, which is also the direction of the cluster street serving as the direct access to the 10 lots, 5 on each side of the cluster street. The 2 end lots at the westernmost portion of the Project Site approx. 31.45% wider than the 6 lots at the center of the development. The corner lots defined by the cluster street and main RROW are 2.0 m wider than the 6 lots at the center of the development. D. DESIGN OBJECTIVES:
a. To create exclusive/ semi-upscale, low-rise, single-detached residential building to be sited on a R-1 zoned property; b. To plan and design a closely-knit residential residential cluster that may serve as a model development in the Project host area; c. To plan the development to maximize profits for the developer; and d. To design the Prototype Houses to serve as landmarks in the Project area. Problem No. 1 (Low Density Residential Occupancy)
Page 2
WARNING: If there are conflicts between a stated word and the number/amount/figure described, the stated/spelled word shall prevail. Should there be conflicts between two (2.0) stated quantities, the higher figure shall prevail. IMPORTANT NOTE: For this first reformat of the examination in this subject, the Examinee shall be allowed to make full use (open books) ONLY of Rule VII and Rule VIII of the 2004 Revised Implementing Rules and Regulations (IRR) of the Presidential Decree (P.D.) No. 1096 , otherwise known as the 1977 National Building Code of the Philippines (NBCP) i.e. ONLY AS downloaded and reproduced from the PRBoA website at www.architectureboard.ph . Other IRR versions are specifically disallowed for use during the examination. A. PROJECT NO. 2 TITLE and General Description: A Proposed Medium-Rise APARTMENT BUILDING Project i.e. a development with Basement component and on a Project Site having an 8.0% slope. B. STATEMENT OF THE PROBLEM:
A Development company has decided that its newly-acquired property with a Total Lot Area (the “TLA”) of six thousand square meter (6,000.0 Sq.M.) shall be developed to host a medium-rise apartment building ( the “Project”). The property is zoned as a high density housing lot (Maximum R3), located somewhere in the better parts of Pasig City (the “Project Site”). Only two (2.0) types of rentable/leasable apartment units shall be provided, as follows: 1) Studio-Type apartment units with a twenty two square meter (22.0 Sq.M.) Gross Floor Area (GFA); and 2) One (1.0)-Bedroom (BR) apartment units with a GFA of fifty (50.0) Sq.M. For greater market acceptance, the minimum parking requirements for the Project under the 2004 Revised Implementing Rules and Regulations (R-IRR ) of P.D. No. 1096, otherwise known as the 1977 National Building Code of the Philippines ( NBCP), should be exceeded. C. PROJECT SITE FEATURES:
The Project Site is rectangular in shape and is an interior lot with a fifty (50.0) m. width. As there is no other means of direct access to the Project Site, a two (2) lane right-of-way (ROW) still has to be negotiated with the owner of the adjoining vacant lot that faces north, where a twenty meter (20.0 m) wide street i.e. a road right-of-way (RROW) is located. The said RROW has two point four (2.4) m wide sidewalks on each side. The Project Site uniformly slopes at eight percent (8.0%) towards the vacant lot in front, which is only 80.0 m deep but also uniformly 8.0% slopes toward the RROW. The surface of the sidewalk adjoining the vacant front lot shall be considered as elevation 0.0m. To the left of the Project Site is a private high school building. To its right is a residential condominium building. To the rear of the Project Site are proposed three (3.0)-storey single-detached residences. D. DESIGN OBJECTIVES:
a. To design a medium-rise apartment building , marketable and attractive to middle income renters/lessees; b. To design the apartment building in a way that can maximize rentals and leases for the Developer; the ratio of saleable versus non-saleable spaces shall be 70:30; if attainable, the overall rentable/leasable areas for the building could be at approximately eighty five percent (80.0)% of the TGFA or better, which must include the parking spaces at the basement; and c. To design a building that shall serve as a landmark in the Project area, with sustainable plan/design features and deliverable at the least cost. Problem No. 2 (High Density Residential Occupancy)
Page 3
WARNING: If there are conflicts between a stated word and the number/amount/figure described, the stated/spelled word shall prevail. Should there be conflicts between two (2.0) stated quantities, the higher figure shall prevail. IMPORTANT NOTE: For this first reformat of the examination in this subject, the Examinee shall be allowed to make full use (open books) ONLY of Rule VII and Rule VIII of the 2004 Revised Implementing Rules and Regulations (IRR) of the Presidential Decree (P.D.) No. 1096 , otherwise known as the 1977 National Building Code of the Philippines (NBCP) i.e. ONLY AS downloaded and reproduced from the PRBoA website at www.architectureboard.ph . Other IRR versions are specifically disallowed for use during the examination. A. PROJECT NO. 3 TITLE and General Description: Proposed Medium-Rise OFFICE CONDOMINUM Project [development with Basement, Podium (with covered parking) and Tower components] B. STATEMENT OF THE PROBLEM:
A Developer has decided that its commercial 3 (C-3) property (the “Project Site”), with a Total Lot Area (TLA) of two thousand square meter (2,000.0 Sq.M.) and located in Quezon City (Metropolitan Manila Area), shall host a medium-rise Office Condominium building (the “Project” ). Only four (4.0) types of real estate products shall be provided by the Developer and these are all office units with Gross Floor Area (GFA) measurements of: 1) 2) 3) 4)
Thirty square meters (30.0 sq. m.) Sixty (60.0) sq. m. Ninety (90.0) sq. m.; and One hundred twenty (120.0)sq. m.
C. PROJECT SITE FEATURES:
The Project Site is a rectangular inside (or regular) lot. It is located along a fifteen (15.0)m wide street i.e. the road right-of-way (RROW), with a forty meter (40.0 m) wide frontage facing the south. The site slopes very gently towards the street with one point eight (1.8) m wide sidewalks. The surface of the sidewalk shall be considered as elevation 0.0 m. D. DESIGN OBJECTIVES:
a. To design an office condominium, a high intensity commercial building (the “Building” ), marketable and attractive to small to medium size office locators/buyers; b. To design the Building in a way that can maximize profit for the Developer ; the ratio of saleable versus non-saleable spaces; and c. To design the Building to serve as a landmark in the Project host area
Problem No. 3 (Commercial Occupancy)
Page 4
WARNING: If there are conflicts between a stated word and the number/amount/figure described, the stated/spelled word shall prevail. Should there be conflicts between two (2.0) stated quantities, the higher figure shall prevail. IMPORTANT NOTE: For this first reformat of the examination in this subject, the Examinee shall be allowed to make full use (open books) ONLY of Rule VII and Rule VIII of the 2004 Revised Implementing Rules and Regulations (IRR) of the Presidential Decree (P.D.) No. 1096 , otherwise known as the 1977 National Building Code of the Philippines (NBCP) i.e. ONLY AS downloaded and reproduced from the PRBoA website at www.architectureboard.ph . Other IRR versions are specifically disallowed for use during the examination. A. PROJECT NO. 4 TITLE and General Description: A Proposed Low-Rise NATIONAL GOVERNMENT OFFICE Project [development with Basement, Podium (with covered parking) and Tower components] B. STATEMENT OF THE PROBLEM:
A National Government-Owned and Controlled Corporation (GOCC) has decided that its eight thousand square meter (8,000.0 sq. m.) property located somewhere in Quezon City shall host a low-rise office building (the “Project” ) to serve as their headquarters. C. PROJECT SITE FEATURES:
The Project Site is a rectangular through lot with an esplanade at its north property line. It has an eighty meter (8.0 m) wide frontage with a full southern exposure. The primary access to the front of the property as a high traffic thirty (30.0) m wide street i.e. the road right-of-way (RROW). The site slopes very gently towards the esplanade composed of a one point two (1.2) m wide sidewalk, a six (6.0) m wide carriage way and a three (3.0) m wide promenade and plant strip. The high flood waterline (100years return) is at least one (1.0) m lower than the esplanade sidewalk, which shall be considered as elevation 0.0m for the proposed building. The 30.0 m wide street has 2.4m wide sidewalks on both sides, but was recently declared an arcaded street by city ordinance. The proposed building is also covered by a separate Green Building Ordinance. To the east of the property are 2 other large National Government office complexes. Across the property is a long row of arcaded private low-rise commercial buildings. D. DESIGN OBJECTIVES:
a. To design a National Government Office Building , a high intensity institutional building (the “Building” ); b. To design the Building in a way that can maximize the delivery of services required by the general public; and c. To design the Building to serve as a landmark in the Project area, with sustainable design provisions and delivered at the least cost.
Problem No. 4 (Institutional Occupancy)
Page 5
WARNING: If there are conflicts between a stated word and the number/amount/figure described, the stated/spelled word shall prevail. Should there be conflicts between two (2.0) stated quantities, the higher figure shall prevail. IMPORTANT NOTE: For this first reformat of the examination in this subject, the Examinee shall be allowed to make full use (open books) ONLY of Rule VII and Rule VIII of the 2004 Revised Implementing Rules and Regulations (IRR) of the Presidential Decree (P.D.) No. 1096 , otherwise known as the 1977 National Building Code of the Philippines (NBCP) i.e. ONLY AS downloaded and reproduced from the PRBoA website at www.architectureboard.ph . Other IRR versions are specifically disallowed for use during the examination. A. PROJECT NO. 5 TITLE and General Description: A Proposed Medium-Rise GARMENT AND UNDERGARMENT FACTORY Project [development with Basement and Tower components only] B. STATEMENT OF THE PROBLEM:
A Garment Firm based outside Metro Manila has decided that its newly acquired property with an industrial 3 (I-3) zoning classification, located in Parañaque City (near airport), shall host a medium-rise Garment and Undergarment Factory Building (the “Project” ) The Garment Firm specializes in hard/ tie-dyed shirts; dresses; men’s and ladies’ undergarments, all for the export market. Based on their consultant’s research, the entire operations of the Garment Firm i.e. which start from receipt/ storage of raw materials to finishing, packaging and containerizing, should be moved to the new facility to save on time and freight/ handling costs. The Garment Firm has about two hundred twenty (200.0) rank and file employees (including factory workers who must be housed at the new facility. C. PROJECT SITE FEATURES:
The Project Site has a ten thousand square meter (10,000.0 Sq.M.) Total Lot Area (TLA), is rectangular in shape, and is a corner lot abutting three (3) streets and 6.0 meter (m) wide creek . Its primary access is through a thirty (30.0) m wide street with two point four (2.4) m wide sidewalks on either side [collectively the “primary road right-of-way (RROW)]. The said primary RROW is intersected at right angles by 2 minor streets each with a six (6.0) m wide RROW. The 2 intersects (corners) have six (6.0) m wide chaflans i.e. with legs of 4.25 m. The Project Site has an eighty (80.0) m wide frontage that faces the west and serves as the main access for the container vans/trucks on a 24-hour basis. The Project Site slopes at four percent (4.0%) towards the creek. The surface of the sidewalk at the primary RROW shall be considered as elevation 0.0. To the left of the Project Site is a private office building. To its right is a ceramics factory building and directly across the street are two (2.0) videoke bars and a restaurant-bar with live band performances. Across the creek are two point five (2.5) storey row-houses. D. DESIGN OBJECTIVES:
a. To design a Garment and undergarment factory building that can maximize profits for the Garment Firm through a good process flow/vertical spatial interrelationship and space planning efficiency; and b. To design a Building that shall be sustainably planned/designed, delivered at the least cost and that shall serve as a landmark in the Project area. Problem No. 5 (Industrial Occupancy/Special Problem)
Page 6
Situation 1 – Project No. 01
1.
Project No. 1. Under the 2004 Revised IRR of P.D. no. 1096 or NBCP, what should be the applicable Building Height Limit (BHL) for each of the 10 lots (in number of storeys)? A. 5 B. 12
2.
Project No. 1. Under the NBCP, what shall be the BHL for each of the 10 lots (in meters)? A. 10 B. 36
3.
C. 11 D. 9
Project No. 1. Under the NBCP, what is covered by the BHL for the Project? A. B. C. D.
5.
C. 54 D. 15
Project No. 1. What is the width (in meters) of the 6 lots at the center of the development? A. 13 B. 15
4.
C. 3 D. 18
antenna deck roof level parapet wall, if introduced electrical or electronic devices mounted on top of the parapet wall, if introduced mast
Project No. 1. Under the NBCP, what is the generally permitted range for number of storeys for a low-rise building project? A. 1 to 5 B. 3 to 6
C. 1 to 3 D. 6 to 9
Situation 2 – Project No. 01
6.
Project No. 1. Given the Project Site orientation, from what direction shall the “amihan” wind come from? A. East B. SouthWest (SW)
7.
C. SouthEast (SE) D. NorthEast (NE)
Project No. 1. Where on the 10 lots are the best sites to plant large trees that will serve as “habagat” wind buffers? A. North, NorthEast (NE) and East perimeters. B. West, NorthWest (NW) and North perimeters. C. East, SouthEast (SE) and South perimeters. D. West, SouthWest (SW) and South perimeters.
8.
Project No. 1. Given the street position, what are the main orientations of the road right-o-way (RROW) view corridor? A. B. C. D.
9.
NorthEast (NE) and NorthWest (NW) SouthEast (SE) and SouthWest (SW) North and South East and West.
Project No. 1. Given the Project Site orientation and the cluster street orientation, where are the BEST sites on each of the 10 lots to plant large shade trees? A. B. C. D.
Right and Left side yards. NorthEast (NE) corners. Front and Rear yards. SouthEast (SE) corners.
Page 7
10.
Project No. 1. Given the Project Site orientation, what are the dominant sun-paths for the property? A. SW to SE and NW to NE B. SE to NW and NE to SW
C. SE to SW and NE to NW D. SW to NE and NW to SE
Situation 3 – Project No. 01
11.
Project No. 1. Assuming one (1) of the 2 end lots shall host common provisions, which of the following is NOT considered an amenity provision for the Project? A. B. C. D.
12.
Gameroom Homeowners’ association office Swimming pool Clubhouse
Project No. 1. Which of the following is NOT considered a facility provision for the Project? A. Gym B. Gameroom
13.
Project No. 1. Which of the following is NOT considered a service provision for the Project? A. Gardener’s room B. Security quarters
14.
C. Workshop D. Overhead Water tank
Project No. 1. Which of the following is NOT considered a utility provision for the Project? A. Generator room B. Domestic water cistern
15.
C. Guest parking D. Homeowners’ association office
C. Sewage treatment plant (STP), if introduced D. Guest parking
Project No. 1. Which of the following provisions should NOT be situated close to one another? A. Security quarters, locker and shower B. Guest parking slots, cluster street, disabled ramps, etc. C. Homeowners’ association office and generator room D. Cistern and sewage treatment plant, if introduced
Situation 4 – Project No. 01
16.
Project No. 1. Given the Project Site location, budget and target market, which mix of architectural archetypes BEST suit/s the Project? A. Residential and recreational B. Residential and business (home office) C. Residential and entertainment D. Residential and commercial (retail)
17.
Project No. 1. Which architectural image can BEST suit the Project? A. Fun, Frivolous and carefree. B. Attractive but aloof and business like. C. Inviting relaxed and laid back. D. Warm, safe and comfortable.
18.
Project No. 1. Which architectural style may BEST suit the Project to help cut cost? A. Stylized Neo-Classical or Classical B. Tropical American Country
19.
C. Modern with clean but textured lines D. Mediterranean
Project No. 1. Given the bulk of the Prototype House, what architectural lines need to emphasized? A. Vertical B. Diagonal
C. Horizontal D. Curvilinear Page 8
20.
Project No. 1. Assuming a 42.0 Sq.M. TGFA for a Prototype House ground floor, about how many pieces of 0.30 m by 0.30 m ceramic tiles shall be needed for its flooring, assuming that the bathroom measures 1.35 m by 1.7 m? A. 480 B. 502
C. 441 D. 408
Situation 5 – Project No. 01
21.
Project No. 1. What should be the nominal thickness of the concrete hollow block unit (in meters) for the interior walls of the Prototype House? A. 0.20 B. 0.15
22.
Project No. 1. What should be the nominal thickness of the concrete hollow block unit (in meters) for the perimeter property wall of the Prototype House? A. 0.18 B. 0.15
23.
C. 0.20 D. 0.10
Project No. 1. Assuming a very heavily forested hillside location for the Project Site and the budget constraint, what type of roof structure should be introduced for the Prototype Houses? A. B. C. D.
24.
C. 0.10 D. 0.25
Steep, gable-shaped metal roof on welded steel frame. Very steep, asphalt shingle roofing on marine plywood on assembled metal frame. Low-pitch, steel deck roof. Composite deck roof with 3% slope
Project No. 1. Assuming a Project Site location that is 150.0 meters (m) away from a very highvoltage transmission line, what type of building projections should NOT be introduced for the Prototype? A. Extended eaves B. Sun-breakers
25.
C. Balconies D. Canopy
Project No. 1. Assuming that a firewall-quality wall thickness is required by an Owner, what should be the nominal thickness of the concrete hollow block unit (in meters) for the exterior walls of the Prototype House? A. 0.10 B. 0.20
C. 0.25 D. 0.15
Situation 6 – Project No. 01
26.
Project No. 1. Which of the following is NOT a good keyhole center height (in meters) for the knobtype lockset of the Prototype House main door? A. 1.155 B. 1.055
27.
Project No. 1. Which of the following is NOT considered a good fixed counter depth (in meters) for the Prototype House? A. 0.30 B. 0.45
28.
C. 0.975 D. 0.963
C. 0.55 D. 0.40
Project No. 1. What is NOT considered an equipment item? A. Exhaust or transfer fan B. Wall or ceiling fan
C. Dome-type CCTV camera D. Soup dispenser
Page 9
29.
Project No. 1. What is NOT considered a furniture item? A. Sofa Coffee table
30.
C. Wall-mounted flat TV D. Dresser
B.
Project No. 1. What is NOT considered a furnishing item? A. B. C. D.
Ceiling fan with lights 80% Life-size wall mirror Freestanding indoor sculpture Acrylic painting
Situation 7 – Project No. 02
31.
Project No. 2. Under 2004 Revised IRR of P.D. 1096 or NBCP, what shall be the applicable range of the Floor to Lot Area (FLAR) for the Project? A. 1.6 to 1.8 B. 7.1 to 8.1
32.
Project No. 2. Using the prescribed FLAR designation/ rights under the NBCP, what shall be the maximum Gross Floor Area (GFA, in square meters) that can be generated for the Project? A. 64, 800 B. 48, 600
33.
C. 68, 400 D. 46, 800
Project No. 2. Under the NBCP and based on the maximum GFA (in square meters), what shall be the maximum Total Gross Floor Area (TGFA) for the Project? A. 77, 760 B. 82, 080
34.
C. 1.8 to 2.1 D. 6.0 to 9.0
C. 56, 160 D. 58, 320
Project No. 2. Under the NBCP, which is part of the GFA for the Project? A. Covered parking B. Roof deck, if introduced
35.
C. ACCU balcony D. Lobby
Project No. 2. Under the NBCP, which is NOT part of the GFA for the Project? A. Basement parking area, if introduced B. Balcony
C. Corridor D. Elevator lobby
Situation 8 – Project No. 02
36.
Project No. 2. Given the Project Site orientation , from what direction shall the “Amihan” wind come from? A. East B. NorthEast (NE)
37.
C. SouthEast (SE) D. SouthWest (SW)
Project No. 2. Where on the property is the best site to plant large trees that will serve as “Habagat” wind buffers for the Projects lower floors? A. B. C. D.
West, SouthWest (SW) and South perimeters East, SouthEast (SE) and South perimeters North, NorthEast (NE) and East perimeters West, NorthWest (NW) and North perimeters
Page 10
38.
Project No. 2. Given the street position, what are the main orientations of the road right-of-way (RROW) view corridor? A. B. C. D.
39.
Project No. 2. Given the Project Site orientation, where on the property is the best site to plant large shade trees for the lower floors? A. B. C. D.
40.
North and South SouthEast (SE) and SouthWest (SW) NorthEast (NE) and NorthWest (NW) East and West
Right and left side yards front and rear yards SouthEast (SE) corner of the property NorthEast (NE) corner of the property
Project No. 2. Given the Project Site orientation, what are the dominant sun-paths for the property? A. SW to NE and NW to SE B. SE to SW and NE to NW
C. SE to NW and NE to SW D. SW to SE and NW to NE
Situation 9 – Project No. 02
41.
Project No. 2. Under the NBCP, which of the following does NOT form part of the footprint of the Project? A. B. C. D.
42.
Project No. 2. Under the NBCP, which of the following still do NOT form part of the footprint of the Project? A. B. C. D.
43.
Elevator lobby and service stairs at ground floor Garden mall at ground floor Main lobby and reception area at ground floor Utility rooms at ground floor
Project No. 2. Which of the following should NOT be provided for the Project? A. B. C. D.
44.
Exterior walls of the building at ground floor Podium ground floor Tower ground floor Basement level
Executive lounge Elevator lobby and service stairs Clubhouse or social area Utility rooms
Project No. 2. Which of the following should preferably NOT be provided near the Project lobby? A. Garbage chute B. Utility room
45.
C. Service stairs D. Fire escape
Project No. 2. Which of the following should NOT be provided at the basement component of the Project? A. B. C. D.
Elevator lobby and service stairs Solid waste storage Enclosures for electronic equipment Covered parking slots, driveways, ramps, etc.
Page 11
Situation 10 – Project No. 02
46.
Project No. 2. In term of architectural exterior finishing, which of the following material set can best convey that the Project is a place for multi-storey budget residences? A. B. C. D.
47.
Project No. 2. In term of architectural exterior finishing and energy conservation, which of the following material set is NOT a good material and finish combination for the southern face of the Project? A. B. C. D.
48.
Substantial use of masonry and some glass Much glass, some metal and limited masonry Some glass, plastics and engineered stone Much glass, much metal and some hard wood
Transparent glass and dark color-painted masonry Heavily tinted glass and medium color-painted masonry Translucent glass and light color-painted masonry Transparent glass and light colored metal panels
Project No. 2. In term of architectural exterior finishing and building insulation, which of the following is NOT a good color for the Project deckroof, if introduced? A. Light gray B. Medium gray
49.
Project No. 2. In term of architectural exterior finishing and building insulation, which of the following is NOT a good material and color combination for the Project roofing? A. B. C. D.
50.
C. Medium blue D. Dark gray and black
Light red polycarbonate panels Light brown metal roofing Dark green metal roofing Medium blue metal roofing
Project No. 2. In term of operating and maintenance costs, which of the following materials should carry a minimum 5-year warranty on materials and installation? A. B. C. D.
Deck roof waterproofing Glass of operable windows Surface of laminated flooring Indoor toilet waterproofing
Situation 11 – Project No. 02
51.
Project No. 2. To fit 3 vehicles per structural bay (meter times meters, center to center), which of the following should NOT be a recommended bay measurement for the Project? A. 7.25 x 8.0 B. 9.05 x 9.8
52.
Project No. 2. To fit 3 vehicles side by side within the main driveway located between 2 columns, which clear measurement (in meters) should NOT be used as the distance between column faces? A. 6.6 B. 8.2
53.
C. 8.75 x 9.5 D. 8.55 x 9.0
C. 7.8 D. 8.6
Project No. 2. To attain overall design economy and minimized structural stability, where should the perimeter beam centrelines for typical floors be aligned or positioned, in relation to the building’s perimeter column? A. positioned near the column interior face B. aligned with the column centerlines C. positioned near the column exterior face
D. positioned outside the column interior face
Page 12
54.
Project No. 2. To attain overall design economy, particularly on operation and maintenance consideration, where should the downspouts be positioned with respect to the building mass? A. B. C. D.
55.
at the building center along the property walls at the rear side of the building at the building perimeter
Project No. 2. Under Appendix A of the IRR of B.P. No. 344, what should be the minimum clear dimensions (in meters by meters) of the elevator shaft? A. 1.5 x 1.8 B. 1.2 x 1.5
C. 2.1 x 2.4 D. 1.8 x 2.1
Situation 12 – Project No. 02
56.
Project No. 2. Which of the following is considered an economical flooring material for the main lobby of the Project? A. Italian Granite tile B. Italian Granite Slab
57.
Project No. 2. Which of the following is a resilient architectural flooring material for use on the Project’s rentable units? A. Clay tile B. Vinyl Strips
58.
C. carpet tile D. lockset
Project No. 2. Which of the following is NOT a Hardware item? A. door stop B. door closer
60.
C. Ceramic tile D. Granite tile
Project No. 2. Which of the following is considered a millwork item? A. cornice moulding B. Vinyl baseplate
59.
C. local marble slabs D. Greekl marble slabs
C. lockset D. door casing
Project No. 2. Which of the following is NOT anymore considered an appropriate lighting element for the lease units? A. LED lighting B. halogen lamps
C. CFL D. Fluorescent lighting
Situation 13 – Project No. 03
61.
Project No. 3. Under the 2004 Revised IRR of P.D. No. 1096 or NBCP, what shall be the minimum required number of parking slots for the 30.0 sqm GFA units of the Project? A. 1 parking slot : 1 unit B. 1 parking slot : 4 units
62.
Project No. 3. Under the NBCP, what shall be the minimum required number of parking slots for the 60.0 sqm GFA units of the Project? A. 2 parking slots : 1 unit B. 1 parking slot : 3 units
63.
C. 1 parking slot : 3 units D. 1 parking slot : 2 units
C. 1 parking slot : 2 units D. 1 parking slot : 1 units
Project No. 3. Under Appendix A of the IRR of B.P. No. 344 (1983 Law to Enhance Mobility of Disabled persons), what should be the minimum width (in meters) of the disabled parking slot? A. 2.5 B. 3.3
C. 3.7 D. 2.9 Page 13
64.
Project No. 3. Under Appendix A of the IRR of B.P. No. 344, what shall be the minimum clear width (in meters) of the elevator door? A. 0.80 B. 0.89
65.
C. 0.87 D. 0.83
Project No. 3. Under Appendix A of the IRR of B.P. No. 344, what shall be the minimum clear width (in meters) of the disabled water closet stall? A. 1.80 B. 1.50
C. 1.70 D. 0.90
Situation 14 – Project No. 03
66.
Project No. 3. Under the 2004 Revised IRR of P.D. No. 1096 or NBCP, what is the minimum unpaved surface area (USA) for the Project Site (zone as C-3)? The answer is a percentage (%) of the Total Lot Area (TLA). A. 20 B. 15
67.
Project No. 3. For the Project Site (zone as C-3 under the NBCP), how much is the minimum USA (in square meters)? A. 300 B. 200
68.
C. 15 D. 20
Project No. 3. For the Project Site (zone as C-3 under the NBCP), how much is the maximum allowable ISA (in square meters)? A. 200 B. 400
70.
C. 100 D. 400
Project No. 3. Under the NBCP, what is the maximum allowable impervious surface area (ISA) for the Project Site (zoned as C-3), if the building shall NOT have a firewall? The answer is percentage (%) of the Total Lot Area (TLA). A. 10 B. 5
69.
C. 5 D. 10
C. 100 D. 300
Project No. 3. For the Project Site (zone as C-3 under the NBCP), how much is the combined total for the maximum allowable ISA plus the minimum USA (in square meters)? A. 135 B. 535
C. 400 D. 270
Situation 14 – Project No. 03
71.
Project No. 3. Under the NBCP, which of the following does NOT form part of the footprint of the Project? A. B. C. D.
72.
Exterior walls of the building at ground floor Basement Level Tower ground floor Podium ground floor
Project No. 3. Under the NBCP, which of the following still do NOT form part of the footprint of the Project? A. B. C. D.
Main lobby and reception area at ground floor Elevator lobby and service stairs at ground floor Patio at ground floor Utility rooms at ground floor Page 14
73.
Project No. 3. Which of the following should NOT be provided at the tower component of the Project? A. B. C. D.
74.
Project No. 3. Which of the following should NOT be provided at the ground level of the podium component of the Project? A. B. C. D.
75.
Elevator lobby and service stairs Clubhouse or social area Workshop and carpentry room Utility rooms
Main lobby and reception area Driver lounge Utility rooms Elevator lobby and service stairs
Project No. 3. Which of the following should NOT be provided at the basement component of the project? A. B. C. D.
Elevator lobby and services stairs Covered parking slots, driveways, ramps, etc. Enclosures for electronic equipment Solid waste storage
Situation 16 - Project No. 03
76.
Project No. 3. Which is NOT considered a Green Architecture concern? A. Lowering the building carbon footprint B. Building energy consumption
77.
Project No. 3. In terms of material production, which of the following flooring materials is considered to have the lowest carbon footprint? A. High-pressure laminate flooring B. Baked clay tiles
78.
C. Polycarbonate sheet D. Gypsum board
Project No. 3. Considering the building size, intended image and occupancy type, what would be the best generic main door type and material for the building? A. Revolving/hardwood B. Double sliding/steel
80.
C. Hand-cut natural stone D. ceramic tiles
Project No. 3. In terms of production, transportation and installation, which of the following ceiling materials is considered to have the highest embodied energy? A. Plywood B. Recycled cardboard egg crate
79.
C. Construction timetable D. Rainwater harvesting
C. Accordion/PVC D. Quadruple leaf swing/glass
Project No. 3. If the office condominium units on the 5 th floor area are NOT to be air-conditioned, what shall be the minimum distance (in meters) between the FFL, as provided for under the NBCP? A. 2.10 B. 2.70
C. 2.40 D. 3.00
Page 15
Situation 17 - Project No. 03
81.
Project No. 3. To fit 3 vehicles per structural bay (meters times meters, center to center), which of the following should NOT be a recommended bat measurement for the Project? A. 8.75 x 9.50 B. 7.25 x 8.0
82.
Project No. 3. To fit 2 vehicles side by side within a driveway located between the 2 columns, which clear measurement (in meters) should NOT be used as the distance between column faces? A. 5.2 B. 5.8
83.
C. 8.55 x 9.0 D. 9.05 x 9.8
C. 4.6 D. 6.4
Project No. 3. To attain the overall design economy and maximized structural stability, where should the perimeter beam centerlines for typical floors be aligned or positioned, in relation to the building’s perimeter column? A. Positioned outside the column interior face B. Positioned near the column exterior face C. Positioned near the column interior face D. Aligned with the column centerlines
84.
Project No. 3. To attain overall design economy, particularly on operations and maintenance considerations, where should the downspouts be positioned with respect to the building’s perimeter columns? A. At the exposed exterior sides of columns (and positioned nearest but outside the architectural cladding) B. At the exposed exterior faces of columns (and positioned farthest outside the architectural cladding) C. Enclosed by CHB or masonry at the interior faces of columns D. Inside the columns
85.
Project No. 3. Under Appendix A of the IRR of B.P. No. 344, what should be the minimum clear dimensions (in meters by meters) of the elevator shaft? A. 1.5 x 1.8 B. 1.7 x 2.0
C. 1.3 x 1.6 D. 1.9 x 2.2
Situation 18 – Project No. 3
86.
Project No. 3. Which of the following is NOT considered a good keyhole center height (in meters) for the main door lockset of a typical office unit? A. 1.17 B. 0.96
87.
Project No. 3. Which of the following is NOT a good fixed counter depth (in meters) for a typical office unit? A. 0.35 B. 0.60
88.
C. 0.98 D. 1.00
C. 0.50 D. 0.45
Project No. 3. For the smallest saleable office unit (without a toilet and without a balcony), what is the depth (in meters) if the unit width (at wall center) is 4.0 meters (m)? A. 8.5 B. 8.0
C. 7.5 D. 7.5
Page 16
89.
Project No. 3. For the smallest saleable office unit (without a toilet and without a balcony), with a unit width (at wall centers) of 4.0 meters (m), how many pieces of whole 0.30 m by 2.5 mm thick vinyl tiles shall be needed for its flooring? A. 358 B. 334
90.
C. 312 D. 346
Project No. 3. For another variant of the smallest saleable office unit, with approximate clear dimesions of 3.5 meters (m) by 8.5 m, what would be the minimum number of pieces of the required vinyl, tile flooring (0.30m by 0.30m x 2.5 mm thick)? A. 327 B. 331
C. 335 D. 323
Situation 19 – Project No. 04
91.
Project No. 4. Under the 2004 Revised IRR of P.D. No. 1096 or NBCP, what shall be the applicable Floor to Lot Area Ratio (FLAR) for the Project? A. 1.5 B. 3.5
92.
Project 4. Using the prescribed FLAR designation/rights under the NBCP, what shall be the maximum Gross Floor Area (GFA) that can be generated for the Project? A. 26,000 sqm. B. 24,000 sqm.
93.
C. 25% D. 20%
Project 4. Under the NBCP, which is part of the GFA for the Project? A. ACCU Balcony B. Covered parking
95.
C. 20,000 sqm. D. 22,000 sqm.
Project 4. Based on the Maximum GFA under the NBCP, what is the stated conversion factor to arrive at the Total Gross Floor Area (TGFA) for the Project which is an institutional building? A. 33% B. Not stated D. 20%
94.
C. 2.5 D. 3.0
C. Lobby D. Roof Deck, if introduced
Project 4. Under the NBCP, which is NOT part of the GFA for the Project? A. Cooling tower area, if introduced B. Elevator Lobby
C. Balcony D. Corridor
Situation 20 – Project No. 04
96.
Project No. 4. Under the 2004 Revised IRR of P.D. no. 1096 or NBCP, what is the term interchangeably used for an institutional zoning classification? A. Gross instititutional B. General institutional
97.
C. Generic institutional D. Governmental institutional
Project 4. Under the NBCP, what is NOT a principal use permitted for a GI Zoning classification? A. Children’s hospital B. Orphanage
C. Dance School D. Kindergarten School
Page 17
98.
Project 4. Under the NBCP, what is an accessory use permitted for a GI Zoning classification? A. Townhouse B. Residential condominium
99.
Project 4. Under the NBCP, which is the building character of occupancy for a GI Zoning classification? A. Recreational B. Institutional
100.
C. Vocational training center D. home furnishing shop
C. Medium industrial D. Business and mercantile
Project No. 4. Under the NBCP, which is NOT considered a typical lot type? A. Interior lot B. Inside lot
C. Turn court lot D. Corner-through lot
Situation 21 - Project No. 04 101.
Project No. 4. Which of the following is NOT considered an amenity provision for the project? A. Executive Lounge B. Multi-purpose room
102.
Project No. 4. Which of the following is NOT considered a facility provision for the Project? A. Gym B. Daycare center
102.
C. Fire escape stairs D. Elevators
Project No. 4. Which of the following is NOT considered a utility provision for the Project? A. Cistern B. Transformer room
104.
C. Covered Parking D. Multi-purpose room
Project No. 4. Which is NOT considered a service provision for the Project? A. Electrical room B. Main stairs
103.
C. Mini-conference room D. Interdenominational worship room
C. Guard locker and shower D. Sewage treatment plant (STP)
Project No. 4. Which of the following sets of spaces should NOT be situated close to each other? A. B. C. D.
Elevators, service stairs and fire escapes Clinic and common toilets Covered parking slots and fire reserve tanks Guard quarters, locker and shower
Situation 22 - Project No. 04
105.
Project No. 4. Which os the following must be one of the very first architectural activities for the Project? A. Space planning and operations survey. B. Architectural design preparation. C. Architectural plan preparation. D. Space plan preparation.
106.
Project No. 4. Which of the following is the local (or LGU) law that governs the site planning and design of the Project? A. Zoning ordinance. B. Association design standards and guidelines. C. P.D. No. 1096 and IRR. Page 18
D. Comprehensive land and water use plan (CLWUP). 107.
Project no. 4. Which of the following does NOT precede the architectural design activity for the Project? A. Technical specifications. B. Architectural plan
108.
C. Architectural program D. Space plan.
Project No. 4. Under the present practice in the country, which of the following is NOT an architectural design consideration for the Project? A. Compliances with prevailing laws such as R.A. No. 9184, P.D. No. 1096, R.A. No. 9514 and B.P. no. 344 and their IRRs. B. Drainage canal slope and direction. C. Maximum flood level. D. Solar, wind, noise, odor and view orientation.
109.
Project No. 4. Which of the following is NOT regarded as an architectural design consideration for the Project? A. Spatial function and efficiency. B. Vertical and horizontal circulation patterns.
C. Wall hangings D. Aesthetics and landmark quality
Situation 23 - Project No. 04
110.
Project No. 4. Which approx. column dimensions (in meters by meters) may be initially used for the ground floor of the Project if erected on firm soil, and if the structural bay is between 8.5 to 10.0 meters (m)? A. 1.7 x 1.7 B. 1.3 x 1.3
111.
Project No. 4. Which approx. column dimensions (in meters by meters) may be initially used for the fourth (4th) floor of Project if erected on firm soil, if the structural bay is between 8.5 to 10.0 meters (m)? A. 1.2 x 1.2 B. 0.8 x 0.8
112.
C. 0.7 x 0.7 D. 1.9 x 1.9
C. 1.5 x 1.5 D. 0.5 x 0.5
Project No. 4. Assuming a heaviky forested location for the Project Site, what type of roof structure should be introduced? A. RC deck roof B. Low-slope metal roofing on space frame
113.
Project No. 4. Assuming a hillside location for the Project Site, what type of building projections should NOT be introduced? A. 1.2 meter deep balconies B. 2.4 meter deep eaves
114.
C. Steel deck roof D. Steep gable roof
C. 2.4 meter deep canopy D. 0.3 meter deep sun-breakers
Project No. 4. Assuming a hilltop location for the Project Site, what type of building projections should be introduces to protect the building? A. 3.6 meter deep cantilevered canopy C. 0.6 meter deep eaves B. 1.2 meter deep balconies D. Windbreakers and sun-breakers
Page 19
Situation 24 - Project No. 04
115.
Project No. 4. In terms of acoustics, which material is NOT good for use as cladding, wall or partition for very crowded, low-ceilinged and noisy spaces? A. Wood or wood substitutes B. Texture-painted masonry
116.
C. Metal with textured surface D. Smooth glass
Project No. 4. Under the NBCP, what are the maximum riser and tread dimensions (in meters) of a stairway? A. 0.15 and 0.3 B. 0.2 and 0.28
117.
Project No. 4. Under the NBCP, what is the maximum width (in meters) of an exit door leaf? A. 1.2 B. 2.1
118.
C. 1.5 D. 1.8
Project No. 4. How many whole units of 0.61 meter (m) x 1.22 m acoustical ceiling boards are required for a conference room with clear measurements of 4.0 m (width parallel to hallway and cladding) x 6.1 m (depth)? Please note that there are 6 light troffers also measuring 0.61m x 1.22m for the room and its line of lighting is perpendicular to the cladding. A. 26 B. 22
119.
C. 0.17 and 0.27 D. 0.2 and 0.25
C. 24 D. 28
Project No. 4. How much tee runner angle section (in linear meters) is required for the same 4.0m x 6.1m conference room? A. 19.2 B. 21.2
C. 20.2 D. 22.2
Situation 25 - Project No. 5
120.
Project No. 5. Under the 2004 Revised IRR of P.D. no. 1096 or NBCP, what shall be the maximum allowable percentage of site occupancy (PSO) for the Project (if without firewall)? A. 80% of TLA B. 90% of TLA
121.
Project No. 5. Under the NBCP, what is the prescribed minimum front setback (in meters) for the Project Site? A. 6 B. 5
122.
C. 8 D. 3
Project No. 5. Under the NBCP, what is the prescribed minimum side setback (in meters) for the Project Site? A. 6 B. 5
123.
C. 70% of TLA D. 75% of TLA
C. 3 D. 8
Project No. 5. Under the NBCP, what is the prescribed minimum rear setback (in meters) for the Project Site? A. 8 B. 6
C. 3 D. 5
Page 20
124.
Project No. 5. Under the NBCP, what should be the maximum dimensions and footprint for the proposed building, assuming only one (1) structure is erected? A. 64m x 109m = 6,796 sqm C. 67m x 115m = 7,705 sqm B. 70m x 112m = 7,840 sqm D. 65m x 107m = 6,955 sqm
Situation 26 - Project No. 5
125.
Project No. 5. What is the approximate lot depth (in meters) of the Project Site? A. 115 B. 135
127.
Project No. 5. At a four percent (4.0%) slope, what is the difference in elevation (in meters) between the front and rear portions of the Project Site? A. 5.0 B. 3.5
128.
C. 2 D. 6
Project No. 5. Which is a basic part of the road right-of-way (RROW) and immediately outside the Project Site? A. Curb B. Front Yard
130.
C. 6.5 D. 8.0
Project No. 5. What is the maximum number of adult persons who can walk side by side on the 2.4 meter wide sidewalk fronting the Project Site? A. 4 B. 8
129.
C. 145 D. 125
C. Canopy D. Perimeter
Project No. 5. Where on the Project Site is the best location for the loading dock? A. North yard B. South yard
C. West yard D. East yard
Situation 27 – PROJECT NO. 5
131.
Project No. 5. Which of the following is NOT considered an amenity provision for the Project? A. executive lounge B. worker’s union office
132.
Project No. 5. Which of the following is NOT considered a service provision for the Project? A. Gym for all staff B. Business center for clients
133.
C. gameroom for workers D. video conference room
C. Concessionaire-operated cafeteria D. Gameroom for workers
Project No. 5. Which of the following is NOT considered a service provision for the Project? A. Workshop and carpentry room B. Mail room
134.
C. Security office D. Overhead water tank
Project No. 5. Which of the following is NOT considered a utility provision for the Project? A. Cistern B. Generator room
C. Covered parking D. Sewage treatment plant (STP)
Page 21
135.
Project No. 5. Which of the following sets of spaces should NOT be stuated close to each other? A. B. C. D.
Security staff quarters, locker and shower Solid waste holding area and sewage treatment plant Elevators, service stairs and fire escapes Covered parking slots, driveways, ramps etc.
Situation 28 – Project No. 5
136.
Project No. 5. Which is NOT generally considered a Green Architecture concern? A. B. C. D.
137.
Building energy consumption Rainwater harvesting, if applicable Lowering the building carbon footprint Relocation of informal settlers on the Project Site, if any
Project No. 5. In terms of construction material production, which of the following flooring materials is considered to have the lowest carbon footprint? A. Vigan tiles B. Mariwasa tiles
138.
Project No. 5. In terms of production, transportation and installation, which of the following ceiling materials is considered to have the highest embodied energy? A. Recycled cardboard egg crate B. Polycarbonate sheet
139.
C. Cement bonded board (CBB) D. Gypsum board
Project No. 5. If the executive offices on the 5th floor are to be air-conditioned, what shall be the minimum distance (in meters) between the finished floor line (FFL ) and the finished ceiling line (FCL), as provided for under the NBCP? A. 2.40 B. 3.00
140.
C. High-pressure laminate flooring D. Baguio stone
C. 2.70 D. 2.10
Project No. 5. If the staff offices at the 4 th floor are NOT to be air-conditioned, what shall be the minimum distance (in meters) between the FFl and the FCL, as provided for under the NBCP? A. 3.00 B. 2.10
C. 2.40 D. 2.70
Situation 29 - Project No. 5
141.
Project No. 5. What is the nominal thickness (in meters) of an exterior CHB wall, excluding plaster? A. 0.10 B. 0.20
142.
Project No. 5. What is the nominal thickness (in meters) of an interior CHB wall, excluding plaster? A. 0.25 B. 0.10
143.
C. 0.25 D. 0.15
C. 0.15 D. 0.20
Project No. 5. Assuming a near coastal location for the Project Site, what type of roof structure should be introduced? A. Metal roofing on space frame B. RC deck roof
C. Composible deck roof D. Steel deck roof Page 22
144.
Project No. 5. Assuming a lakeside location for the Project Site, what type of building projections should NOT be introduced? A. 3.0 meter deep eaves B. 1.5 meter deep balconies
145.
C. 0.3 meter deep sun-breakers D. 1.8 meter deep canopy
Project No. 5. Assuming a hilltop location for the Projec t Site, what type of building projections should be introduced to protect the building? A. 0.9 meter deep balconies B. Windbreakers and sun-breakers
C. 1.2 meter deep canopy D. 0.6 meter deep eaves
Situation 30 – Project No. 05
146.
Project No. 5. Which of the following is a good lighting device for a watercolor painting on the wall of the waiting area of the president’s office? A. CFL B. High-heat halogen lamps
147.
Project No. 5. Which of the following is a good task lighting color (i.e. the shade of the emitted artificial light), for drawing, reading and writing purposed? A. Warm white B. Cool white
148.
C. Daylight D. Yellow
Project No. 5. Which of the following is a good lighting technique for emphasizing a curved ceiling, if introduced at the lobby? A. B. C. D.
150.
C. Yellow D. Daylight
Project No. 5. Which of the following is a good general lighting color (i.e. the shade of the emitted artificial light), for work areas? A. Warm white B. Cool white
149.
C. Low-wattage track light D. High-output spot lamp
Use of pendant lighting Indirect lighting at the base of the curved ceiling Direct lighting of the curved ceiling using spotlights Down-lighting from the ceiling using halogen lamps
Project No. 5. Which of the following is a good lighting device for a general production area with the ceiling consisting of the soffit of a suspended slab? A. B. C. D.
Troffer lighting (fluorescent lamps with soffit-mounted light boxes and diffusers) Industrial lighting (suspended fluorescent lamps with reflectors) Pendant lighting (suspended CFLs with housing) Pendant lighting (suspended incandescent lamps)
Page 23