Arahan Teknik (Jalan) 14/87
Model Terms of Reference for Detailed Ground Survey and Engineering Design of Roads
7.0m
5.0m
Roads Branch Public Works Department Malaysia Jalan Sultan Salahuddin 50582 Kuala Lumpur
FOR INTERNAL USE ONLY
TOR for Detailed Ground Survey
PREFACE This Arahan Teknik (Jalan) is a model Terms of Reference for the design of a typical new road or improvement of an existing road. It should be modified to cater for any specific requirements or unusual features for the road in question. Appendix A - Terms of Reference for Detailed Ground Survey can also be used on its own for any individual survey assignment. This Arahan Teknik (Jalan) will be reviewed and updated from time to time. In this respect, any comments and feedback from users are welcomed and appreciated.
Cawangan Jalan, Ibu Pejabat JKR, K.L
Page 1
TOR for Detailed Ground Survey
FOR INTERNAL USE ONLY
TERMS OF REFERENCE FOR DETAILED GROUND SURVEY AND ENGINEERING DESIGN 1.0
INTRODUCTION (To be filled by Engineer)
2.0
DESCRIPTION OF WORK (To be filled by Engineer)
3.0
OBJECTIVE (To be filled by Engineer)
4.0
SCOPE OF CONSULTING SERVICES
4.1 General The Consulting Engineers shall undertake all works herein described to achieve the objectives mentioned in Section 2 of this Terms of Reference. In carrying out this work the Consulting Engineer shall cooperate fully with the Government. 4.2 Route Location Where the final alignment of the proposed road or improvement is not yet determined, the Consulting Engineer shall undertake field reconnaissance and preliminary surveys, etc. to determine the best corridor for an alignment and shall propose several alternative routes for the Government's selection. The routes shall be selected according to topographic, geologic, economic and social-political factors and the Consulting Engineer is to liaise closely with the State JKR, the State Town Planner and the Land Office. The Consulting Engineer is to submit his proposals in the form of an Interim Report as detailed in Section 5. 4.3 Engineering Survey 4.3.1 The Consulting Engineer shall propose, coordinate and supervise all field and specialist surveys in accordance with JKR's Standard Terms of Reference (Appendix A) not only for his investigation and analysis but also to enable him to carry out his detailed engineering design. The scope of works for all field surveys are to be
Cawangan Jalan, Ibu Pejabat JKR, K.L
submitted to the Government for approval before any commencement is allowed. 4.3.2 All. field surveys shall be carried out by licensed surveyors, who shall be appointed by the Government. 4.3.3 While the agreement will be between the Government and the surveyor, the Consulting Engineer will act as the Government's agent in the administration of the survey works. The Consulting Engineer is required to provide adequate supervision to ensure that the terms of reference are followed. He will also be required to certify work done for the purposes of payment and to receive the computed works from the licensed surveyor. 4.4
Material Survey And Subsurface Investigation 4.4.1 The Consulting Engineer shall propose, coordinate and supervise sufficient subsurface investigation, sampling and testing togather enough data to permit final detailed design of all structures, slopes, foundations, road pavements etc. The Consulting Engineer shall determine the required scope of subsurface investigation and submit his proposals to the Government for concurrence. (a) The appointment of the soil contrac tor shall generally be done by the Consulting Engineer who shall enter into an agreement with the soil contractor. (b) The Consulting Engineer shall administer the- contract and shall provide adequate supervision to ensure that the works are carried out properly. (c) For works estimated to cost Less than $50,000, the Consulting Engineer can nominate a JKR Registered Soil Contractor for the approval of the Government to carry out the works based on the cur rent JKR Schedule of Rates. (d) For works estimated to cost more than $50,000, tenders shall be called. The Page 2
FOR INTERNAL USE ONLY
Consulting Engineer shall prepare the tender documents which must be vetted and approved by the Government. The Consulting Engineer shall also coordinate the tender exercise and submit his evaluation and recommendation to the Government for endorsement before awarding the tender. The tender procedures shall follow the current practice of JKR. (e) All subsurface investigation works shall be paid as a reimbursable item to the Consulting Engineer who shall then pay the soil contractor. 4.4.2 In conjunction with the subsurface investigation the Consulting Engineer shall also carry out a material survey in the location of the proposed new route or improvement and its vicinity to identify the sources of suitable borrow and construction material. He shall also verify as to their quality, quantity and suitability. 4.4.3 The Consulting Engineer is required to submit a Material Survey and Subsurface Investigation Report as detailed in Section 5.
4.5
Hydrological and Hydrogeological Investigation
The Consulting Engineer shall, where necessary carry out investigations and studies into the existing watersheds, catchment areas and other hydrological data necessary for the design of surface and subsurface drains, bridges, culverts and road finished levels. In the estimation of the flood discharges, waterway requirements and bridge spans, the Consulting Engineer shall liaise closely with the "Jabatan Parit dan Taliair" and obtain their concurrence.
4.6
Engineering Design
4.6.1 General The Consulting Engineer shall not commence any detail engineering design unless the final alignment of the proposed road or improvement is accepted by the Government. Cawangan Jalan, Ibu Pejabat JKR, K.L
TOR for Detailed Ground Survey
4.6.2 Geometric Design The geometric design shall follow the requirement laid down in Arahan Teknik (Jalan) 8/86 "A Guide To Geometric Design of Roads". 4.6.3 Drainage Design All drainage design shall follow the guidelines and criteria established by JKR as well as standards published by Jabatan Parit dan Saliran. The required return period for design shall be as determined by JKR. 4.6.4 Geotechnical Design The scope of geotechnical design shall include embankment design, slope stability analysis, foundation design for bridges and culverts, design of earth retaining structures,earthworks design and any other necessary geotechnical design. The Consulting Engineer shall pay particular emphasis on areas where the proposed route or improvement traverses through poor subsoil. The Consulting Engineer shall determine the need for any soil improvement and evaluate all possible soil improvement techniques. In cases where special stability problem exists during construction, the Consulting Engineer shall take this into account and make provision for it in his design. All design shall be done to Malaysian Codes of Practice where available or British Codes of Practice. If the Consulting Engineer wishes to design using other International Codes of Practice, prior approval must be obtained from the Government. 4.6.5 Pavement Design All pavements shall be designed in accordance with Arahan Teknik (Jalan) 5/85 - "Manual on Pavement Design". The design life base year as well as the cumulative equivalent standard axles designed for, shall be written on the pavement plan. Rigid pavement design shall follow current Page 3
FOR INTERNAL USE ONLY
JKR Practice. 4.6.6 Bridges i. The structural design for the bridge structures shall follow the latest version of BS 5400 which comprises 10 parts. ii. The bridge loading shall follow that of BS 5400: Part 2. The bridge structures and elements shall be designed to resist the worst traffic loads of: (a) Type HA loading together with a knife edge load of 120KN per notional lane, and (b) 45 Units HB loading guided along the centreline of the carriageway. iii. The longitudinal tractive force shall be as per BS 5400: Part 2 with minimum value of 253 KN and maximum value of 450 KN per loaded length. iv. The parapet shall be designed to the Department of Transport (U.K.) Technical Memorandum No. BE 5: The Design of Highway Parapets. v. Expansion joints in the bridge shall follow the recommendations of BE 3. vi. The design of bridge shall take into account of the debris and log flow, if any, and impact from the vessels plying in the river or impact from road vehicles if applicable. 4.6.7 Culverts i. The structural design for R.C. culverts shall follow the British Standard BS 8110. ii. The loading shall follow that of B.S. 5400: Part 2. The culvert shall be designed to resist the worst traffic load as for the bridge strutures. 4.6.8 Earth Retaining Walls i. The Consulting Engineer shall evaluate all systems of earth retaining structures with respect to technical suitability, cost effectiveness and aesthetic values. A writ ten report shll be submitted to JKR for decision. ii. In calculating lateral pressure full Cawangan Jalan, Ibu Pejabat JKR, K.L
TOR for Detailed Ground Survey account of seepage forces or surcharge loads should be made. iii. Surcharge loads shall include traffic loads and load due to temporary or per manent structures. iv. Traffic loads shall follow that of BS 5400: Part 2 as for bridge structures. v. The structural design shall follow the British Standard BS 8110. 4.6.9 Intersection /Interchange Design The Consulting Engineer shall design all atgrade intersections or interchanges in accordance with the latest JKR guidelines. Where traffic lights are required, the design of the phases and cycle lengths shall also be carried out by the Consulting Engineer. Where a future interchange is required at a present at-grade intersection, the land requirements for the future interchange shall be indicated clearly together with the desired period of staging. 4.6.10 Street Lighting Design The Consulting Engineer shall recommend to the Government any proposals for street lighting and after approval shall carry out the detailed design. Where power is available, street lighting for intersections and bridges should be considered. The Consulting Engineer shall liaise closely with the JKR Electrical Section for all street lighting design. 4.6.11 Traffic Control Devices/ Roadside Furniture Adequate traffic control devices and road side furniture such as directional and traffic signs, lane and pavement markings etc provided in the design shall be in accordance with Arahan Teknik (Jalan) 2A, 2B, 2C, and 2D/85. 4.6.12 Relocation of Services The Consulting Engineer shall make a survey of the existing utility services and liaise closely with the authorities concerned on the proposed future relocation of such services. The Consulting Engineer shall put up detailed plans and proposals for the relocation of these servic-
Page 4
TOR for Detailed Ground Survey
FOR INTERNAL USE ONLY
es if affected by the proposed work.
``Temporary Signs and Work Zones Control".
All official dealings with any service agency shall be done through JKR.
4.6.15 (a) For all other designs not indicated above, the Consulting Engineershall refer to the Government for the design criteria to use. The Consulting Engineer can propose any suitable standards to be used for the Government's approval. (b) The Consulting Engineer shall ensure that adequate provisions are made for access to all adjacent properties affected by the proposed road or improvement as well as for utility services in the design of the bridges.
The Consulting Engineer's attention is drawn to the financial implication of flagging and inconvenience charges imposed by Keretapi Tanah Melayu Berhad for works affecting any rail way property. The Consulting Engineer shall ascertain from the relevant Service Authorities the existing services along and in the vicinity of any existing bridges or structures and shall allow in his design any necessary deviation, temporary or otherwise, and incorporate necessary safeguards to protect the existing services against damage or destruction during construction. The Consulting Engineer shall also ascertain from the Authorities concerned what new services are required to be installed on any new proposed bridges and make provision for these in the design. 4.6.13 Landscaping and Environmental Protection The Consulting Engineer shall carry out an environmental impact study on the effects of the proposed route or improvement on the environment. The Consulting Engineer's atttention is drawn to the requirements and pro visions of the Environmental Quality Act. The Consulting Engineer shall also design any landscaping or environmental protection works that are needed to preserve and enhance the proposed route or improvement. 4.6.14 Temporary Works or Diversions The Consulting Engineer shall include in his design any temporary works or diversion that are needed during the construction period. All temporary works or diversion designed or proposed should be able to cater for the uninterrupted flow of traffic for the period concerned. All traffic control devices used shall be in accordance with Arahan Teknik (Jalan) 2C/85 Cawangan Jalan, Ibu Pejabat JKR, K.L
4.7
Engineering Plans
4.7.1 General The Consulting Engineer shall prepare contract drawings in sufficient detail suitable for Tendering and Construction. The contract drawings shall include all items such as horizontal and vertical alignment, crosssections, earthwork, details of junctions, culverts, bridges, drainage system, road pavements, erosion and slope protection measures, safety barriers, pavement and lane markings, traffic signals, guardrails, street lighting, fencing, traffic control devices, etc. necessary for the full and effective implementation of the project. The presentation of the engineering drawings shall follow the guidelines as laid down in Arahan Teknik (Jalan) 6/85 -- "Guidelines For Presentation of Engineering Drawings". The originals of all plans shall be submitted to and becomes the property of the Government. 4.7.2 Plan Format All plans shall be prepared on original stable reproducible materials and have title blocks approved by the Government. All dimensions shall be in metric units. All plans whether Preliminary or Final shall be signed by at least a Partner of the Consulting firm and all plans submitted for approval shall also bear the Professional Engineer's Seal of the Partner concerned. Page 5
FOR INTERNAL USE ONLY
4.7.3 Preliminary Plans Preliminary plans shall be submitted from time to time to the Government or as requested for the approval or endorcement of the Government before the final plans are drawn. 4.7.4 Land Acquisition Plans The Consulting Engineer is responsible for preparing land acquisiton plans to enable the Government to acquire the necessary right-ofway. The plans shall be of a scale accepted by the Land Office an must define clearly the limits of the right-of-way required by the project. The land acquisition plan shall include details of Lot Numbers and areas of each individual lot that has to be acquired and coloured appropriately in accordance with the requirement of the Land Office. For this purpose the Consulting Engineer shall collect all the necessary information from the Land Office or Survey Department. The preparation of the land acquisition plans shall follow the guidelines as laid down in Arahan Teknik(Jalan) 7/85 - "Garis Panduan untuk Penyediaan Pelan Pengambilan Balik Tanah bagi projek Jalan Persekutuan". For Federal Projects twenty-six (26) sets and if it is a state project six (6) sets of Right of Way Acquisition Plans shall be submitted by the Consulting Engineer as soon as the final required right of way can be finalised. These plans shall be made available to the Government as the works progress in order to facilitate the prompt acquisition of the necessary right of way.
TOR for Detailed Ground Survey Government. Quantities shall be estimated to a reasonable accuracy consistent with the items concerned. Three sets of the estimate of the works signed by a Partner of the firm based on each item of the Bill of Quantities shall be submitted to the Government under confidential cover. The estimates should be based on realistic current market prices. Estimates of costs for land acquisition and relocation of services shall be prepared separately. 4.9 Prequalification Documents Where necessary and instructed by the Government the Consulting Engineer shall prepare prequalification documents for the purpose of prequalifying suitable contractors for the construction works. The Consulting Engineer is also expected to prepare the evaluation criteria, carry out the evaluation and recommend to the Government the suitable contractors for prequalification. The Government will decide on the final list of prequalified contractors. 4.10 Specifications And Tender Documents 4.10.1 The Consulting Engineer shall prepare complete tender documents based on the Standard Goverment Conditions of Contract, Form of Tender, Bill of Quantities and other documents currently in use for major civil engineering works. Prior consultation with the Government will be necessary before the tender documents are drawn up.
4.8 Bill Of Quantities/Cost Estimate The Consulting Engineer shall submit a preliminary cost estimate to the Government for budgetary purposes immediately after the preliminary design is completed.
4.10.2 Three (3) Draft copies of the tender documents shall be submitted for the Government's review at least eight weeks before the date scheduled for calling of tenders. Final tender documents shall only be printed after the draft documents have been approved by Government.
After the detailed design is completed, the Consulting Engineer shall prepare a Bill of Quantities for all items of works required for the construction of the project. The Bill of Quantites shall follow the format approved by the
4.10.3 The Consulting Engineer shall also incorporate in the tender documents, the works required to shift the various existing public utility services as well as new services required by the service authorities.
Cawangan Jalan, Ibu Pejabat JKR, K.L
Page 6
TOR for Detailed Ground Survey
FOR INTERNAL USE ONLY
4.10.4 Where standard specifications are available from JKR, the Consulting Engineer shall ensure that they are used. Any specifications used should also be consistent with current JKR standards. 4.10.5 The preparation of the tender documents shall be in 3 volumes, i.e. Volume I - Instruction to Tenderers, Form of Agreement And Condition of Contract, Form of Tender, Form of Acceptance of Tender, Preamble to Bill of Quantities, Bill of Quantities and Schedule of Particulars. Volume II - Work Specifications Volume III - Contract Drawings. The Drawings shall be reduced to A3 print. 4.10.6 The Consulting engineer will be informed of the number of copies he has to furnish to the Government. Payments for this will be as a reimbursable item. 4.11 Evaluation of Tender Where necessary and instructed by the Government the Consulting Engineer may be asked to evaluate the tenders submitted. The Consulting Engineers shall put up his evaluation report and recommendations within two (2) weeks after receipt of the submitted tenders from the Government. 4.12 Post Tendering Services The Consulting Engineer, whenever required by the Government shall also provide the following post tendering service: (a) Make amendments to drawings or redesign any part of the works on the instruction of the Government. Any amendments or redesign carried out because of deficiences or errors in the Consulting Engineer's design shall be at the expense of the Consulting Engineer and will not be reimbursed. (b) Attend site meetings on the instruction of the Government.
Cawangan Jalan, Ibu Pejabat JKR, K.L
5.0
SUBMISSION OF REPORTS AND SCHEDULES
5.1 Interim Report The Interim Report shall be submitted not later than four (4) months after the appointment of the Consulting Engineer. The Interim report shall discuss alternative routes that are possible within the chosen corridor the advantages and disadvantages of each route and cost estimates of land acquisiton, contruction etc. Problems such as pertaining to social,technical and economic aspects should also be highlighted. The Consulting Engineer's recommended route should also be clearly stated. Ten (10) sets of the Interim Report shall be submitted to the Government, who will inform the Consulting Engineer of their decision. The Consulting Engineer may be asked to brief the Government's representative on his report. 5.2
Material Survey and Subsurface Investigation The material survey and subsurface investigation report shall be submitted as soon as the subsurface investigation work are completed. The report shall give a general description of the geology of the area, results of the material survey and details of the sources, quantity and quality of the available materials as well as its relevance to the project. The report should aso highlight the results of the subsurface investigation and give details of the Consulting Engineer's interpretation of those results as well as its implications in geotechnical aspects. Any special soil or foundation treatment that are needed should be discussed and any recommedations proposed must be supported by the relevant geotechnical calculations. 5.3 Bridge Sketch Proposals For all bridges, preliminary sketch proposals are to be submitted to the Government for approval before the final design is carried out. Page 7
TOR for Detailed Ground Survey
FOR INTERNAL USE ONLY
The sketch proposals should contain the Consulting Engineer's hydrological calculations for the discharge and his recommended span arrangements. Alternative arrangements can also be proposed for consideration.
5.4
Progress Reports
The Consulting Engineer shall submit 8 copies of Progress Reports to the JKR Headquarters each month showing the progress of work. The first report is to be handed in 4 weeks after the appointment of the Consulting Engineer. The Report shall be in the format that is approved by the Goverment.
5.5
Implementation Schedule
Within 2 weeks after the appointment of the Consulting Engineer, the Consulting Engineer is to submit his proposed implementation schedule for the overall design of the project. The items should include the following; (a) Route Location and Interim Report (if required only). (b) Components of detailed design such as geometric design of road, pavement design,structural design of bridges, drainage design, road side furniture etc. including soil investigations, ground survey, preparation of draft tender table documents and prequalification documents. (c) Review and approval of drawings and ten der documents. (d) Preparation and submission of final drawings and tender documents. (e) Prequalification period (f) Tender period (g) Evaluation of tenders, and Government approval. The Consulting Engineer shall make every effort to complete their assignments before the dates stipulated in the implementation schedule. 5.6
Final Design Report/Calculation 10 copies each of the final design report and 4 copies of desin calculations shall be submitted on completion of the final design. The design Cawangan Jalan, Ibu Pejabat JKR, K.L
report shall give an overall picture of the Project and Scope of Works involved, the criteria or rationale used for each of the design components and the events and decisions that were made as regards to design changes along the way. T h e design report shall be in a format that is approved by the Government. The design calculations shall be properly bound and set out in the following order i.e. Geometric Design, Drainage, Geotechnical, Structures (Bridge, Culvert, Retaining Walls etc.), Pavement, Streetlighting, Traffic Signal and Junction Design. The design calculations submitted must be complete and be legible enough to be read. Any incomplete or illegible design report or calculations will not be accepted and will be returned to the Consulting Engineer for resubmission.
6.0
SPECIFICATION FOR MATERIALS AND WORKMANSHIP
All materials and workmanship shall be specified to comply with Malaysian Standards and Code of Practise. Where these are not available, then British Standards or its equivalent may be adopted instead. If departure from the Malaysian or British Standards or Codes of Practice is considered desirable, prior consultation with JKR is necessary.Materials of Malaysian origin are to be specified throughout in preference to imported materials and the use of proprietory names is to be avoided in the Specification. Where this is unavoidable or where materials of foreign manufacture have to be specified, the prior approval of the Government has to be obtained.
7.0
INFORMATION TO BE PROVIDED BY THE GOVERNMENT
7.1 Notwithstanding Clause 10 of the Memorandum of Agreement, the Government shall provide the Consulting Engineer with the following: (a) (To be filled as appropriate) Page 8
FOR INTERNAL USE ONLY
(b) (To be filled as appropriate) 7.2 All relevant Arahan Teknik (Jalan) listed can be purchased from Cawangan Bekalan dan Kontrek, Kementerian Kerja Raya (Tingkat 3) Jalan Mahameru, 50580 Kuala Lumpur.
8.0
PROJECT CO-ORDINATOR
The Government reserves the right to assign a project co-ordinator for close monitoring during the design period.
9.0
LIAISON WITH OTHER AGENCIES
In case the Consulting Engineer requires the cooperation of Government Departments and Agencies, the Government shall provide liaison and shall assist the Consulting Engineer to gather information required for the completion of the project.
10.0 GOVERNMENT INDEMNITY The Consulting Engineer shall be responsible for any damage to life and property that may arise out of their works and they shall. take all necessary insurance cover to indemnify the Government from any claims for compensation that may arise through their negligence.
11.0 REMUNERATION PROCEDURES 11.1 All reimbursable items especially out of pocket expenses shall be claimed on a monthly basis. Any reimbursable claims which are outstanding after three (3) months shall not be entertained at all.
12.0 AGREEMENT The Consulting Engineer shall prepare ten (10) sets of agreement for signing not later than three (3) months after the date of the Letter of Appointment.
Cawangan Jalan, Ibu Pejabat JKR, K.L
TOR for Detailed Ground Survey
APPENDIX A TERMS OF REFERENCE FOR DETAILED GROUND SURVEY TERMS OF REFERENCE FOR DETAILED GROUND SURVEY FOR ROAD DESIGN OF (NAME OF PROJECT)
1.0 OBJECTIVE The purpose of the detailed ground survey is to provide all the necessary data and information required for undertaking the engineering design for Name of Project and also for the necessary land acquisition.
2.0 EXTENT OF WORKS 2.1 Survey Length The details of the extent of the works to be surveyed is given in the attached plan No:_______ The total length to be surveyed is about __ km. 2.2 Survey Width A minimum of a._______ metre width band of the proposed road alignment corridor is to be fully located and surveyed. The corridor width is to be appropriately increased where relevant to cover existing road reserves and also major details like rivers, railway line, lot boundaries, interchange site, new alignment routes and or as decided by the Government. The exact location of the alignment of the corridor is subject to changes on site by the Government.
3.0 SCOPE OF SERVICES 3.1 General The scope of survey services to be provided by the Surveyor shall be as listed hereinunder and as detailed in subsequent paragraphs: (a) Prior discussion with relevant authorities such as JKR, Police and Land office before the physical commencement of work on site. (b) Study all relevant information and maps
Page 9
FOR INTERNAL USE ONLY
(c) (d) (e) (f) (g)
(h) (i)
provided and obtain additional data if necessary for the proper execution of the works. Field survey and picking up details. Consultation with the Engineer and Setting Out. Levelling and establishment of Temporary Bench Marks (TBM). Preparation of plans and data suitable for the road design. Preparation of land acquisition plans in accordance to JKR guidelines as contained in Arahan Teknik No. 7/85 (Garis Panduan Untuk Penyediaan Pelan Pengambilan Balik Tanah Bagi Projek Jalan Persekutuan). Pegging of centre line and cross-sectioning. Pegging of right-of-way (if required).
3.2 Field Survey and Setting Out 3.2.1 General The Surveyor shall perform all field survey work necessary to locate accurately the locations and dimensions of the following features within the proposed corridor for survey of::(a) Existing roads, tracks and paths. (b) Existing structures above and below the ground level indicating whether temporary, semi-permanent or permanent and whether dwelling, industrial or other use, type of construction and any other relevant particulars. (c) Existing drains including their type of construction. (d) Existing watermains, LLN and Telecom overhead lines and underground cables, Teleco0m manholes, fire hydrants, pylons etc. (e) Existing rivers, water courses and their discharge directions. (f) Existing vegetation, their types and swamps. (g) Boundaries of individual lots and their lot numbers and the baseline from which reference can be made, preferably to tie up with existing boundary stones. Cawangan Jalan, Ibu Pejabat JKR, K.L
TOR for Detailed Ground Survey (h) Highest known flood levels. 3.2.2 Consultation with Client before Setting Out Before setting out, proposals for the detailed survey should be submitted to the Government before the work is being carried out. The Surveyor has to consult and follow the Government's instructions either verbally on site or in plans on the locations of all intersection points, circular or spiral curves and the characteristics of the curves. If instructed by the Government, the Surveyor shall submit field survey plans showing the details as specified in Clause 3.2.1 to the limit so as to enable the Government to make the decisions in choosing the best alignment of the road. The Surveyor shall make any minor adjustment on the setting out of the road alignment when requested by the Government provided such request is made before all the plans are submitted. 3.2.3 Setting and Pegging Out of Road Alignment The Surveyor has to set out and peg the centreline of the proposed road alignment and the right-of-way limit where appropriate, including tangent points, intersection points and horizontal curves, essentially in two (2) stages as follows: Stage 1 - Preliminary setting out based initially on drawings supplied as stated in Section 2.1 - and modified appropriately to suit site conditions and/or as directed by the Government. Stage II - Final setting out. and pegging of the centre-line on the field based on Completion of final. design from the earlier surveyed data. The Surveyor shall provide at least one senior survey technician and other supporting staff to pick up the line to set out, giving bearings and distances. The Surveyor when requested by the Government shall provide all the assistance and necessary information regarding the survey and show the Government's representative on the ground the whole setting out whenever required to do so.
Page 10
FOR INTERNAL USE ONLY
TOR for Detailed Ground Survey
The Surveyor shall erect permanent intersection points (IPs) using 50mm diameter G.I. pipes embedded in concrete and protruding 300mm above the ground and tied to at least 2 reference pegs or marks outside of the construction limits and shall be numbered in accordance to the plans given by the Government. Such ties shall be of 12 mm diameter G.I. pipes embedded in concrete projecting not less than 300mm above ground level and painted red. The Surveyor shall also peg-out the centre-line of the road accurately and mark at every 25 metres interval using 50mm x 50mm x 450mm hardwood peg painted red.At least 150mm of the peg must be above the ground. There shall be a joint inspection and handing over of all IPs, TPs and TBMs to the Government's representative after pegging out or setting out have been completed.
3.3.2 Cross-Section and Longitudinal Profile of the Proposed Roads Cross-section shall be taken along the centre line of the proposed road at an interval of 25 metres and up to the corridor width. For the longitudinal profile along the proposed route centre line, levels shall be taken at every 25 metres intervals. However, in rolling and hilly terrain where the ground level changes abruptly, closer intervals for the cross-section and profile section will be required. Additional crosssection or wider cross-section may be necessary in order to delineate special features or when indicated in the plan. The Surveyor shall include levels of abruptly changing natural ground. Wherever possible, the Surveyor shall give the highest known flood levels to enable the designer to decide the formation level of the proposed road.
For setting out of the center- line on existing roads, steel rod pins or spikes must be used. These spikes shall be permanent in nature.
3.3.3 Levelling to Establish Temporary Bench Marks The Surveyor shall establish temporary bench marks at approximately 1 km intervals and relate it to Survey Department Datum (Ordinance Datum). Reduced levels of these temporary bench marks shall be clearly and legibly inscribed on the marks and referenced for identification for the subsequent construction stage. The location of all bench marks must be clearly described and indicated on the plans to be submitted. All these TBMs shall be located well away from the construction limits. All levelling shall be done in sections of approximately I km in length. The closing error for each section shall not exceed 16 mm and the equipment used must be capable of executing the works to this degree of accuracy. The maximum error in spot levels shall not both exceed ± 0.02 _/K metres where K is the horizontal distance in kilometres from the nearest Permanent Bench Mark.
The Surveyor shall determine the rectangular coordinates of all junctions and intersection points so marked, and the bearings of all straight sections of the routes relative to the State Grid. Azimuths shall be checked by solar observations at suitable intervals and the survey traverses shall be tied up to any near-by trigonometrical points or cadestral survey marks. The maximum closing error of the traverse shall be 1 : 4000.
3.3 Levelling 3.3.1 Strip Survey with 2m contour The Surveyor shall carry out a strip survey with the specified contours together with the details of the strip. The width of the strip is as indicated in section 2.2. The Surveyor shall carry out all field work necessary to accurately determine, the contours at the specified intervals and detailed physical features of the terrain. Sufficient control height points and spot heights shall be taken to ensure accuracy of the contour lines.
Cawangan Jalan, Ibu Pejabat JKR, K.L
3.3.4 Surveys at Bridges and Culvert Sites The Surveyor shall survey all streams, rivers and water-courses crossing the line of the routes. These include all watercourses whether there is water or no water flow at the time of surveying. The survey shall extend to the following disPage 11
TOR for Detailed Ground Survey
FOR INTERNAL USE ONLY
tances on either side of the route centre-lines. (distances measured along the channels). Rivers exceeding 15m width .... 150m Streams less than 15m width .... 30m The locations of channel edges and other significant features shall be recorded and levels shall be taken along the bank slopes and channel inverts at intervals of 3m. A minimum of 3 cross-sections showing all significant changes of level are required at both sides of the channel. The crosssections, one of which shall be taken along the route-line shall extend to a distance not less than 30m from the bank tops on either side of the stream. The Surveyor shall record the maximum flood level at each river crossing. Existing water surface at suitable points shall be taken along the channel. Each reading shall be taken at intervals not exceeding one hour. The Surveyor shall indicate on the Plan and Longitudinal Profile the chainage and reduced level of the lowest point of all depressions along the route including direction of flow.
3.4
Details of Junctions to Existing Roads
The Surveyor shall survey all junctions to enable the designer to design the junction properly. Cross-sections shall be of 25 metres intervals with a corridor width of 40m and shall be taken for a distance not less than 150 metres up and down the proposed intersection of the road or as required by Government.
3.5
Demarcation of Road Rightof-Way (R.O.W.)
The Surveyor shall demarcate the road right-ofway (R.O.W.) if so required by the Government. In the case of new alignment the R.O.W. shall be demarcated using G.I. pipes 50mm diameter embedded in concrete of dimension 250mm x 250mm x 450mm. The pipe shall be 1.20 m in length of which 0.80 m shall protrude above ground level. The pipes shall also be painted according to the colour code as provided for in clause 3.8. These pipes shall be placed at intervals of every 100 m.
Cawangan Jalan, Ibu Pejabat JKR, K.L
3.6
Booking for Survey
The Surveyor shall do all workings in proper books, adequately in good style and according to best. practice. All field books shall be done in ink. Unsatisfactory works and errors shall be struck off and there shall be no superimposed writing or erasure. The field books must be kept properly. On completion of the survey works, all field books shall be properly labelled, certified and submitted to the Government and will remain the property of the Government.
3.7
Reference Markers
To ensure accuracy, reference markers shall be placed at least 25m away from the mark (i.e. IP's or TBM's). There shall be at least 2 reference markers and the base of the triangle which they form with the apex should be at least 15m apart.
3.8
Colour Codes For Pegs
All pegs should be colour-coded with paint on site to indicate their purpose. A consistent colour code as specified below must be retained throughout the survey. PEG COLOUR CODE PEG FUNCTION Centre Line pegs for all line Off-met pegs from centre line Right of Way (ROW)
COLOUR Red White (Specified Design)
4.O PREPARATION AND SUBMISSION 0F PLANS AND DATA 4.1 The Surveyor shall provide the Government with two sets of prints together with one set of tracings for all drawings prepared, The Surveyor shall also provide a set of prints and survey data listed under clause 4.l(b) and 4.3 prior to the submission of the completed drawings. The drawings required are as follows: (a) Location Plan Location plan of the proposed roads to a suitable scale such that the area under study can be put into a single standard Al size sheet. The chainage of the alignment shall be indicated for ease of reference to the detail plans.
Page 12
FOR INTERNAL USE ONLY
(b) Plan showing the Plan View And Longitudinal Profile The plan view and the longitudinal profile should be shown in the same plan and shall be as follows:(i) Top Section of Plan-Plan View These shall show the route centre-line, tangent points, intersection points (with rectangular coordinates at road junctions), intersection angles, bearings of all the straights, chainages of tangent points and centre-line markers, levels of Temporary Bench Marks, contours of corridor surveyed, streams, rivers, positions of proposed culverts (if determined already) and other features, crop and vegetation detail to a scale of 1: 1000. All base stations such as boundary stones, survey department Bench Marks, trigonometrical stations shall also be clearly stated and indicated on the drawings. (ii) Bottom Section of Plan-Longitudinal Profile These shall show the longitudinal profile of the route centre-line, cross-section of the rivers, positions of culverts, highest known flood level (if any), swamps and their water level and other features needed for design considerations. Scale: Horizontal (1 : 1000) Vertical (1 : 100) (c) Plans for Bridge and Culvert Sites These shall show features and levels as detailed in Clause 3.3.4 above and are to be of suitable scale for Al size drawings. (d) Cross-Sections Drawings of all the cross-sections along the centre line of the proposed road, shall be plotted in consecutive order, to a scale of 1:100 both horizontal and vertical. The drawings shall show details of ground levels and distances from the centreline of the proposed road. (e) Plans for Preliminary Design A set of prints listed under Clause 4.1(b) Cawangan Jalan, Ibu Pejabat JKR, K.L
TOR for Detailed Ground Survey shall be submitted together with the survey data listed under Clause 4.2.These prints can be made from the same negatives used for drawings listed under Clause 4.1(b) and may exclude contours of corridor surveyed and other features such as crops and vegetation details. All horizontal intersection points should be clearly numbered on these prints. A layout plan with horizontal. intersection points, bearings and distances between IPs shall be included. (f) Land Acquisition Plans The Surveyor shall compile and prepare base plans for property and land acquisition purposes from the Survey Department cadastral sheets and latest revenue sheets from the Land Office and other Government land scheme agencies where relevant to the same scale. This drawing shall show: (i) lot boundaries within the surveyed corridor (ii) lot numbers (iii) lot areas computed based on coordiates. (Determination of areas by measurement is not acceptable). (iv) land use indicating type of cultivation. (v) types of buildings indicating permanent or semi-permanent - usage of the building whether commercial, industrial, religious, communal, schools etc. (vi) size of all buildings shall be plotted to scale and correct shape. (vii) show clearly whether the affected buildings are within the construction limits or within the R.O.W. (viii) pay special attention to burial grounds if any fall within the survey corridor. (ix) other relevant details such as dimensions of the lots, coordinates of the boundary of the lots etc. The drawing of this base plan does not include the preparation of the final land acquisition plan nor the computation of the area to be acquired.
Page 13
FOR INTERNAL USE ONLY
4.2
Survey data for Preliminary Design The Surveyor shall provide the Government with one set of survey data prior to the submission of the complete survey plan. These data shall be presented as follows: (i) Natural Ground Surface Natural ground surface data neatly presented to the format required. (ii) Horizontal Intersection Points (I.P.) The following data shall be recorded and neatly tabulated. (a) Name or number of the road (b) I.P numbers (c) Distance to the next I.P (d) Azimuth in deg-min-sec. The I.P number shall coincide with those on the plans listed under Clause 4.1 (b). 4.3
Format of the Plans and Drawings All formats of plans submitted including the title block shall conform to JKR Guidelines as contained in Arahan Teknik (Jalan) 6/85 (Guidelines For Presentation of Engineering Drawings). All drawings shall be to Al size unless otherwise specified. All legends and symbols used in the plans shall be those. currently used by the JKR and approval must be obtained for any departure from accepted practice. 4.4
Date of submission of Plans and Data (a) Survey plans and data for preliminary design Plans and data listed under _____ and _____ are to be prepared and submitted to the Government within 2 weeks after completion of the relevant field works and prior to the preparation of other plans. (b) Complete survey plans All survey plans are to be prepared and submitted to the Government within 4 weeks after completion of the relevant field works. Cawangan Jalan, Ibu Pejabat JKR, K.L
TOR for Detailed Ground Survey However, all services to be performed under the Terms of Reference shall be completed within ____months of the date of appointment. The surveyor is to submit his time schedule showing each item of work and the time required to the Government for approval.
5.0 FIELD BOOKS All field books must be properly kept and shall record truthfully all the survey work carried out. The Government's representative may check the field books now and then to ensure that a high standard of work is maintained. He may request the Surveyor to carry out some spot checks if he has reasonable doubt on the accuracy of the survey work. The Surveyor shall comply with such requests unless he can prove to the Government's representative's satisfaction that such checks are unnecessary. On completion of survey work, all field books shall be properly labelled and submitted to JKR and shall remain the property of the Government.
6.0 SURVEY STAFF ETC. The Surveyor shall provide such staff, instruments and equipment, tools, materials, tentage, transport, etc, and will ensure the completion of the work to the standards and within the time schedules specified. All technical staff employed by the Surveyor for the execution of the works shall be suitably qualified and experienced in route location work. Party leaders shall possess the minimum qualification of technician surveyor. A professionally qualified surveyor shall be provided to take charge of the survey parties and provide day-to day liaison with the Government's representative.
7.0 GOVERNMENT INDEMNITY The Surveyor shall be responsible for any damage to life and property that may arise out of his work and he shall take out all necessary insurance cover to indemnify the Government from any claims of compensation that may arise out of his work.
Page 14
FOR INTERNAL USE ONLY
TOR for Detailed Ground Survey
8.0 REMUNERATION The fees payable to the Surveyor firm shall follow the approved Treasury's rates of payment (Jadual Kadar Bayaran untuk Ukur Tanah Bagi Tujuan Kejuruteraan - Part I) The Surveyor's fees for the rendering of services mentioned under the Scope of Work and elsewhere in the Terms of Reference, shall be deemed to cover all materials, services, wages, allowances, investigations, field surveys, equipment, transport, computations, preparation of plans, overheads, profits and other fees and expenses as stated in the Memorandum of Agreement between Government and consulting Surveyor for Professional Services.
9.0 AGREEMENT The Surveyor will be required to enter into an Agreement with the Ketua Pengarah Kerja Raya, Malaysia and such Agreement shall be signed by both parties before the commencement of work.
Cawangan Jalan, Ibu Pejabat JKR, K.L
Page 15