NASR FULL FIELD DEVELOPMENT PROJECT PACKAGE-2 Jacket, Bridge and Flare Tower Fabrication & Transportation Tra nsportation Project
NASR FULL FIELD DEVELOPMENT DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1 REVISION CONTROL SHEET Rev.
Date
Description
A
09-Jan-17
First issue
B
11-Jan-17
Internal comments incorporated
C
10-Feb-17
Company comments incorporated.
1
17-Apr-17
1. Company comments incorporated. 2. Loadout for BST and FL is re-designed.
Remarks
NASR FULL FIELD DEVELOPMENT DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
CONTENTS 1
INTRODU INTRODUCTION CTION.............................. ................................................. ................................. .................................. ....................................... ..................... .. 4 1.1 目的 PURPOSE PURPOSE .............................. ................................................. ...................................... .................................. .................................. ........................ ..... 4 1.2 定义 DEFINITIO DEFINITION N .............................. ................................................. ................................. .................................. ....................................... ..................... .. 4 1.3 参考文件 REFERENCE DOCUMENT .......................................................................... 4
2
CARGO DESCRIPTION ..................................................................................... 5 2.1 第六船货物列表 CARGO LIST OF 6TH SHIPMENT..................................................... 5 2.2 货物图示 CARGO CARGO SKETCH SKETCH ............................. ................................................ .................................. .................................. .......................... ....... 6
3
FLOW CHART CHART ............................. ................................................ .................................. .................................. ...................................... ................... 10
4
PROCESS DESCRIPTION ............................................................................... 10 4.1 概述 GENERAL GENERAL .............................. ................................................. ...................................... .................................. .................................. ...................... ... 10 4.2 码头布置 ARRANGEMENT ARRANGEMENT AT QUAYSIDE QUAYSIDE .................... .......... .................... ................. ................. .................... ................. ....... 11 4.3 驳船系泊 BARGE MOORING..................................................................................... 11 4.4 监控系统 MONITOR SYSTEM ................................................................................... 12 4.5 装船描述 LOADOUT STATEMENT ............................................................................ 12
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
1
INTRODUCTION
为了向不同语言背景的所有读者传递一致的信息,本文使用汉英双语的形式叙述。凡有矛 盾,应以英文优先。 In order to convey consistent information to all readers, who may possess different language backgrounds, this document is presented in Chinese / English bilingual format. English shall be at the first priority where inconsistency arises. 1.1
目的 PURPOSE 本文件讲述第六船中装船布置、技术要求,用于指导第六船装船操作并保障作业安全。 This procedure provides design guidelines of a loadout system and describes regulatory measures in the loadout operation to ensure a safe loadout of the 6 th shipment.
1.2
定义 DEFINITION
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
AD220-705-G-00371
AD220-705-G-03824
AD220-707-C-38242~38268 AD220-707-C-38281~38296 AD220-714-C-38481~38490 AD220-712-C-38491~38500
NSB30 – Bridges 1 Drawings NSB30 – Bridges 2 Drawings NSBST1 – Deck Drawings NSBST2 – Deck Drawings
AD220-707-C-38521~38530 AD220-709-C-38531~38541
NSBST5 – Deck Drawings NSBST6 – Deck Drawings
AD220-710-C-38601~38635
NSFL2 – Flare and Tower Drawings
Process piping fabrication procedure for carbon steels, stainless steels, alloys Specification for Loadout, Transportation & Installation
1.3.2 胜宝旺文件 CSE DOCUMENT
AD220-705-G-00379 AD220-705-G-00651 AD220-705-G-00657 AD220-705-G-00307
AD220-705-G-00614 AD220-705-G-00632
Master Deliverable Register (CSE) Baseline Survey Procedure (CSE) Distortion Control Procedure (CSE) Tubular Transfer Procedure (CSE) Project Planning procedure (CSE) Vessel Documents for 6th shipment(CSE)
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
There are 7 types’ cargos of 6th shipment for Loadout. The list of 6th shipment is shown on Tab.2.1 below.
表 2.1 第六船货物列表
Loadout Sequence No.
Tab.2.1 Cargo list of 6th Shipment Unit NET Qty. Shipping Cargo Item Weight Pcs (T/Pc)
Total Weight (T)
Remark
1
BRIDGE #7(NSBR30-1)
507
1
507
Lifting
2
BRIDGE #8(NSBR30-2)
511
1
511
Lifting
260
1
260
Lifting
BRIDGE SUPPORT #2 - DECK
180
1
180
Lifting
BRIDGE SUPPORT #1 - DECK
150
1
150
Lifting
BRIDGE SUPPORT #6 - DECK
150
1
150
Lifting
BRIDGE SUPPORT #5 - DECK
150
1
150
Lifting
FLARE TOWER #2 - DECK & TOWER
3
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
图 2.2 B30B 八号栈桥 Fig.2.2 Bridge B30B#8
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
图 2.5 五号桥墩台 Fig.2.5 Bridge Support Deck #5
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
3
FLOW CHART
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
码头布置 ARRANGEMENT AT QUAYSIDE
4.2
基于船上布置,结构将按序摆放在码头边,见如下各图。 Based on the arrangement on barge, structures will be arranged accordingly at the quayside. See sketches below. 1 # Y A W D I K S
BRIDGE SUPPORT #2 - DECK
1 # Y A W D I K S
3 # Y A W D I K S
3 # Y A W D I K S
FLARE TOWER #2 DECK & TOWER
BRIDGE SUPPORT
BRIDGE SUPPORT #6 - DECK
BRIDGE SUPPORT #5 - DECK
图 4.1 码头平面布置
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
4.4
监控系统 MONITOR SYSTEM 驳船两侧都须设置测量点以控制驳船倾斜度。测量点布置如下所示: On both sides of the barge, measure points are set in order to monitor incline of the barge. Measure points are shown as below.
MEASURE POINT 4 LOCATIONS
图
测量点分布
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
Lift up the cargo off the supports simultaneously by all the cranes and hold on to verify the crane readings. Adjust the readings until they are closed to the calculated readings. Move the cargo above the barge. The readings of each crane will be closely monitored and kept within the rated capacity.
在货物被放置到驳船上之前继续提升货物高度直至越过所有障碍物。 The cargo needs to be lifted above and clear from all obstructions, prior to lowering down onto the support on barge. 4.5.2
吊机解钩 CRANE DISCONNECTION
货物放置支撑上(如有需要可使用挡板帮助就位 )。解开吊机索具。 After upon landing on the barge (stopper plate can be used to help fit up when necessary), Cargo will be disconnected from the cranes. 4.5.3
固定 FIXING
就位货物须按照图纸要求充分固定。
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
Spreader bar 8m
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
图 5.4 8 号栈桥吊机与索具布置 Fig.5.4 BRIDGE #8 Crane and Rigging Arrangement NOTE: Padeyes us ed during load-out shall be 100% NDT.
5.2
装船顺序及吊机站位 LOADOUT SEQUENCE AND CRANE LAYOUT 第一步:船进港,右舷靠岸侧靠 3#~1#滑道。
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
第三步:调船,左舷靠岸侧靠 3#~1#滑道。 Step 3: Re-arrange vessel and along port side on 3# and 1# skid way.
第四步:BRIDGE #8 装船。 Step 4: BRIDGE #8 Loadout.
1# Crane
2# Crane
3# Crane
4# Crane
FLARE TOWER #2 DECK & TOWER
BRIDGE SUPPORT BRIDGE SUPPORT #2 - DECK #1 - DECK
Loadout For BRIDGE #8
BRIDGE SUPPORT #6 - DECK
BRIDGE #8 (NSBR30-2)
BRIDGE SUPPORT #5 - DECK
BRIDGE #7 (NSBR30-1)
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
5.3
吊机及索具校核 CHECKS FOR CRANES AND RIGGINGS 表 5.1 吊机校核(重量、载荷单位 MT,长度单位 m) Tab.5.1 Crane Check (Load unit MT, Length unit m) 结构 Sructures
吊机 Crane
臂长 Boom
工作半径 配重 极大载荷 能力 利用率 Working Counter Extreme Capacity Utilization Radius Weight Load
1# CC2800-1 SSL 84
38
300
160
106.5
0.67
1# CC2800-1 SSL 96
38
300
158
106.5
0.67
SDB77
22
250
333
309
0.93
1# CC2800-1 SSL 84
28
300
219
165
0.75
BST#1,2,5,6-Deck Flare Tower & Deck #2
Bridge #8
Bridge #7
1# LR1750
2# CC2500
SSL 84
28
230
165
125
0.76
3# CC2500
SSL 72
28
230
176
139
0.79
4# CC2800-1 SSL 96
28
300
189
150
0.79
1# CC2800-1 SSL 84
28
300
219
163
0.74
2# CC2500
SSL 84
28
230
165
122
0.74
3# CC2500
SSL 72
28
230
176
138
0.78
4# CC2800-1 SSL 96
28
300
189
148
0.78
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
5.4
注意 NOTICES 吊装前必须准备好作业许可并获得批准。待吊装结构和临时结构须通过尺寸检查、无损检 测和作业安全分析,其记录与相关机具证书均须齐备,作业许可方可签发。 Work permit shall be prepared and approved before the lifting operation. Structure and temporary structure dimension survey, NDE and Job Safety Analysis (JSA) shall be conducted and all records as well as valid certificate of relevant crane and riggings shall be in place and accepted before the lifting permit is issued.
作业区域应清理并以警戒线包围以防未授权的人员和车辆进入。 Operation area shall be cleared and surrounded with safety tape to stop unauthorized personnel and vehicles from entering.
若吊点处有油漆,钢丝绳与吊点接触的部分应以布料包裹以避免损坏油漆。 When the lifting point is coated, slings parts contacting the lifting point shall be wrapped with cloth to avoid damage to the coat.
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
Meteorological Bureau is in effect for strong wind or heavy fog or rainstorm or thunder.
天气预报需在装船前 3 天内每十二小时更新一次以提前发现任何天气变化,并且因每日举 行天气例会。如发现天气恶劣可能影响装船,则例会可视情况增加。 Weather forecasts will be received every twelve hours, three days prior to and during Loadout in order to discover any weather deterioration as early as possible and daily weather meetings will be held. If Loadout is delayed due to bad weather conditions, meeting may be held more f requently than described above.
表 5.3 装船天气限制 Tab.5.3 Limiting forecast for loadout Limits Wind speed(10 min Mean) Current speed Significant Wave Height
GO
NO GO
<=10 m/s
>10 m/s
-
-
<=0.5 m
>0.5 m
业主吊装计划需在吊装前得到业主批准,并得到完全落实。
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
APPENDIX A:
&
TIDE & WATER DEPTH DATA
船底净空 Under keel clearance 码头面 Quay
装船期最高潮Highest tide in SLW 珠江基准面 Pearl River Datum
平均海面MSL
海图基准/潮高基准 Chart Datum/Tide Datum
装船期最低潮Lowest tide in SLW
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
CSE Water depth data
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1 Tide data
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
APPENDIX B:
MOORING CALCULATION MOORING CALCULATION
A.Design Criteria V10min VC HS RhoSW RhoAir Cdc B.Barge Data LOA B D T C.Wind Profile
= = = = = =
10 0 0.5 1025 1.225 1
m/s m/s m kg/m kg/m
=
100.6 30.5 6.1 4
m m m m
El eva tio n( m) 3s ec 1min 1 0.93 0.79 5 1.15 1.01 10 1.25 1.11 Ch= 20 1.34 1.2 50 1.47 1.33 100 1.56 1.42 Ch 风压高度系数 C h=1+0.137ln(h/10)-0.047ln(t/10) D.Wind Force Coefficients Item Width Height Freeboard 30.5 2.1 BST - DECK 8 11 FT- DECK & TOWER 8 40 Bridge 3.5 5
Wind Speed at EL +10m, 10min Mean Current Speed Significant Wave Height Sea Water Density Air Density Nondimensional Drag Cofficient for Current Overall Length Moulded Breath Moulded Height Loadout Draft 0min 0.69 0.91 1 1.1 1.22 1.32
1 hr 0.6 0.82 0.92 1.01 1.14 1.23
Number Awx 1 64.05 4 352 1 320 2 35
Cs 1 0.5 1.25 1.25
Ch 0.8 0.5 0.92 0.92
0.33534 kN/(m/s)2
∑Cwx=1/2RhoAir∑CsChAwx/1000
Item
Cwx 51.24 88 368 40.25
Width
Height Number Awx
Cs
Ch
Cwy
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
APPENDIX C:
CRANE LOAD CHART
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
APPENDIX D:
ORGANOGRAM COMPANY/CONTRACTOR
CSE Project Manager (Ow Choonyen) Marine Warranty Surveyor CSE Loadout Superintendent (Xu Long)
CSE HSQE Manager(Luo Hao)
CSE Project Engineer(Shi Junfeng)
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
APPENDIX E:
CACULATION FILE
吊点罗氏应力校核 ROARK STRESS CHECK AT LIFTING POINT Roark’s stress and punching shearing shall be checked at lifting points. (As per Roark’s Formulas for Stress and Strain Section 13.7)
max
k
P 2
Ln
t
R t
k
0.02 0.00012( 90)
UC
max F b
其中 Where: P = 绳力 Total reaction R = 圆管半径 Pipe radius t = 圆管厚度 Pipe thickness β= 180 兜绕角度 In degree for this formulation F b
= 按 API 的许用弯曲应力 Allowable bending stress as per Section 3.2 of API RP 2A.
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
APPENDIX F: 时间 Date
Day 1-2
Day 3
Day 4 Day 5-7
LOADOUT SCHEDULE 工作描述 Description 船舶侧靠(包括系泊及搭设岸边与船舶之间的通道) Vessel along side - mooring and install ladder excess to vessel. 打开船上人孔(每个人孔安排 2 名工人) Opening of manholes - 2 fitters at each manhole 测爆检查、划线 Marking on vessel、Gas free inspection 沿船舷安装临时护栏 Install temporary safety fenders along the edge of vessel 吊装就位结构支撑、叉车及焊接设备等 Lifting of main structure supports into location, forklift, welding sets etc onto vessel 组对及点焊货物支撑 Fit up and tack weld cargo support onto vessel 吊装货物前邀请官方检验 Invite government official for inspection before lifting cargos 吊装并安装固定好 BRIDGE #7(NSBR30-1) Lift, install and seafasten BRIDGE #7(NSBR30-1) 调船 Re-arrangement of barge 吊装并安装固定好 BRIDGE #8(NSBR30-2) Lift, install and seafasten BRIDGE #7(NSBR30-2) 吊装并安装固定好 BRIDGE SUPPORT #1,2,5,6 and FLARE TOWER #2 - DECK & TOWER Lift, install and seafasten BRIDGE SUPPORT #1,2,5,6 and FLARE TOWER #2 - DECK & TOWER
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
APPENDIX G: FENDER INFORMATION
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
APPENDIX H: GO-NO GO CHECK LIST
NASR FULL FIELD DEVELOPMENT PROJECT Package 2 Loadout Procedure For 6th Shipment AD220-705-G-00356 Rev.1
Comment Resolution Sheet
Project Name:
NASR FULL FIELD DEVELOPMENT PROJECT EPC WORKS FOR PACKAGE-2 JACKET, BRIDGE AND FLARE TOWER FABRICATION & TRANSPORTATION PROJECT Rev. No: C AD220-705-G-00356 Rev. No: C AD220-705-G-00356
CSE Document No.: HHI Document No: Doc Class
Approval Code 1 APPROVED (A)
APPROVED WITH COMMENTS (AC)
REJECTED (RR)
2
REVIEWED (R)
REVIEWED WITH COMMENTS (RC)
REJECTED (RR)
3
FOR INFORMATION
REVISE AND RESUBMIT (RS)
REJECTED (RR)
S/ N
Section reference
1
General
3
4
Approval Code 3
1
Document Title: Transmittal reference number: Received date: All Comments incorporated:
2
Approval Code 2
AD220-705-G00355 section5.2 AD220-705-G00355 section5.3 AD220-705-G00355 section5.4
Loadout Procedure For 6th Shipment(CSE) NASR-ADMA-HHI-T-16093
Yes
No If no please specify below Company Comments
For other comments, please refer to comments marked on Doc No. AD220-705-G-00355 Rec C and incorporate as applicable Add " Sea fastening welding shall be completed prior to move the vessel to next location" Add " This table will be updated and to be submitted to Company prior to Load out for approval if there is any change" All such NDT records to be sent offshore for reference. This comment is applicable for all loadouts/shipments
Subcontractor Response Noted and incorporated.
As per MWS requirement, Sea fastening welding shall be completed 25% prior to move the vessel to next location. Noted and added in section5.3. Noted and incorporated.
Noted and revised.
Company Response