Maintenance of High Speed Lines Report 2010
Auteur : Hugo Goossens ------------------------------------------Company: E-RAILCONSULT ------------------------------------------Document : 1st phase - Report ------------------------------------------Date : September 2010
MAINTENANCE OF HIGH SPEED LINES
REPORT
July 2010
UIC – International Union of Railways – 16 rue Jean Rey – F-75015 Paris – www.uic.org/highspeed
CONTENTS Chapter 1 – Introduction .................................................................................................. 3 1. Preamble ........................................................................................................................ 3 2. Changes in the Railway Sector (…. 2010) ...................................................................... 3 2.1 New technologies ................................................................................................... 3 2.2 New technical requirements .................................................................................... 4 2.2.1 Mixed traffic lines ............................................................................................ 4 2.2.2 Increased design speed .................................................................................. 4 2.2.3 Tilting trains ..................................................................................................... 4 2.2.4 High speed freight ........................................................................................... 4 2.2.5 Normalisation and standardisation .................................................................. 5 2.2.6 Coordinate base reference data 2.2.7 RAMS - Requirements .................................................................................... 5 2.2.8 Contract forms ................................................................................................ 5 2.2.9 Life Cycle Costs (LCC)..................................................................................... 5 2.2.10 Corporate Social Responsibility (CSR) .......................................................... 6 2.2.11 Disposal ....................................................................................................... 6 Chapter 2 - Maintenance needs ........................................................................................ 1. Introduction .................................................................................................................... 2. Maintenance methods ................................................................................................... 3. Levels of maintenance ...................................................................................................
7 7 7 8
Chapter 3 - Maintenance requirements in the “design” phase ...................................... 9 1. Introduction .................................................................................................................... 9 2. Accesses to the infrastructure ........................................................................................ 9 3. Assembly area for switches and crossings .....................................................................11 4. Longitudinal service paths for maintenance staff ...........................................................11 5. Lighting ..........................................................................................................................12 6. Maintenance bases ........................................................................................................12 6.1 Introduction ..............................................................................................................12 6.2. Distances between maintenance bases ..................................................................12 6.3 Functionality of a maintenance base ........................................................................13 6.3.1 Light base ......................................................................................................13 6.3.2 Full base ........................................................................................................13 6.3.3. Emergency depot ..........................................................................................13 7. RAMS data ....................................................................................................................15 7.1 Definition of Availability ............................................................................................15 7.1.1. Analysis of various factors in the life cycle of a railway system ..................... 15 7.2 Factors in determining degree of availability ........................................................... 16 7.2.1 Introduction ................................................................................................... 16 7.2.2. The concept of the infrastructure and the various subsystems ..................... 16 8. Structure and organisation of the operation service ...................................................... 17 9. Structure and organisation of the maintenance service ..................................................17 10. Test devices, wear parts, spare parts ............................................................................17 11. Emergency equipment, traction units .............................................................................18 Chapter 4 - Maintenance requirements during the “construction” phase .....................19 1. Introduction ....................................................................................................................19 2. Collaboration between builders and maintainers ............................................................19 Chapter 5 - Maintenance requirements in the “test and service shadow” phase .........20
Maintenance of High Speed Lines
1/64
1. Introduction ....................................................................................................................20 2. Table of verifications during test and service shadow phase ..........................................20 Chapter 6 - Inspections and tests during operations on the line ...................................21 1. Introduction ......................................................................................................................21 2. Components to be examined during monitoring................................................................21 Chapter 7 - Working windows – Sweep trains..................................................................25 1. Introduction ....................................................................................................................25 2. “Sweep” trains ...............................................................................................................25 3. Working windows ...........................................................................................................25 Chapter 8 - Best practices in maintenance works ...........................................................28 1. Introduction ....................................................................................................................28 2. Integrated maintenance .................................................................................................28 3. Minimum maintenance requirements between finishing the construction and tests and starting operations ..........................................................................................................28 3.1. Prevention against vandalism and burglary of cables, overhead contact wire, etc ...............28 4. Track .............................................................................................................................29 4.1 Rail grinding .............................................................................................................29 4.2 Absolute coordinates ...............................................................................................29 4.3 Flying ballast ............................................................................................................30 4.4 Measures against snow adhering to and dropping from high speed trains.. ..............30 4.5 Wheel scan ..............................................................................................................30 5. Energy ...........................................................................................................................30 5.1 Surveying of the overhead contact wire by thermo-graphic control ...........................30 5.2 Overhead contact system ........................................................................................31 5.3 Control of the pantograph ........................................................................................31 Chapter 9 - Life cycle of subsystems of high speed lines ..............................................32 1. Introduction ..............................................................................................................32 2. Track components ...................................................................................................32 3. Overhead contact lines ............................................................................................33 4. Signalling system .....................................................................................................33 Chapter 10 - Conclusions & Recommendations .............................................................34
Appendices & Abbreviations.............................................................................................35
Maintenance of High Speed Lines
2/64
MAINTENANCE OF HIGH SPEED LINES
CHAPTER 1 1.
Introduction
Preamble
The IUR-UIC published in 1996 the IF-7/96 Report entitled “Maintenance of High Speed Lines”. This technical document, reflecting the experience and knowledge available in Europe at the time it was written, contained general considerations on the maintenance of high speed lines and detail information about the principles concerning the organisation of track supervision and maintenance work. Since then the Railways and Railways environment have changed fundamentally with further internationalisation of High Speed Traffic: -
Reorganisation of the Railways with (partial) privatisation and liberalisation of the Railways in many countries, New techniques introduced for different subsystems and publication of international rules and norms, New types of contract forms to build, operate and maintain Railways requiring longer term commitment.
Due to these various changes and the demand of further internationalisation, the UIC Plenary Committee decided, at its meeting held in Figueras (Spain) on 18 and 19 November 2008, to propose to the General Management of the UIC that a new work group be established to examine: - The experiences acquired over the last decades, - The most recent technologies relating to infrastructure, - The other subsystems with their latest technological developments, - The interfaces between operators (rolling stock) and infrastructure managers (maintenance), - The extended experiences and specificities in other countries outside of Europe.
2.
Changes in the Railway Sector (… 2010)
2.1
New technologies:
New technologies or a generalisation of some new technologies has been seen in Railway Infrastructure over the last decades. Furthermore, contact with Asian Railways increased and the experiences of these countries should be added to those of the European Railways. The updated report will take into account both of these developments.. Significant technological changes include: - Technological changes adapted to increased health and safety requirements, - Changes to meet safety requirements,
Maintenance of High Speed Lines
3/64
-
A generalisation of un-ballasted track on some lines and under certain circumstances, The use of new fastening systems, The introduction in Europe of the new signalling system ERTMS-ETCS supported by the GSM-R communication system, The introduction of new materials (e.g. the catenaries overhead wire; rails), New monitoring systems (e.g. control of switches), New absolute coordinate-based referencing of infrastructure assets for use in net wide support of track maintenance work, New techniques for maintenance machines, The development of new sensors to avoid the non-availability of the infrastructure or to reduce the break down time, Etc.
2.2
New technical requirements:
2.2.1. Mixed traffic lines Most of the high speed lines were, until now, dedicated exclusively to passenger traffic and predominantly to one type of train. With the increase in the number of high speed lines and in congestion on the roads, more and more infrastructure managements extended the use of the infrastructure for different kinds of mixed traffic: - Passenger traffic with use of different type of trains running at the same or different speeds and with the possibility to use push-pull trains on the route, - High speed passenger trains and high speed freight traffic (e.g. post trains), - Passenger and freight traffic with a largely different speed. Mixed traffic could have a significant effect on the maintenance of the infrastructure based on the operating model used.
2.2.2. Increased design speed Railway operators are seeking to reduce travel time; there is an increased demand to increase the maximum speed on the (new) lines. Some new lines are currently designed for speeds up to 350 km/h. These increasing speeds are affecting the survey and the maintenance of the lines.
2.2.3. Tilting trains Some networks have put in operation tilting trains to increase the travel speed in small curves; the introduction of this technology reduces the travel time and increases the capacity often on upgraded lines. Some maintenance requirements relating to tilting trains have to be taken into account.
2.2.4. High speed freight Research relating to the development of high speed freight corridors is ongoing. The concept and the maintenance of these kinds of lines can differ in certain respects. Similarities between HS lines and heavy-haul traffic should be considered.
Maintenance of High Speed Lines
4/64
2.2.5. Normalisation and standardisation Increased normalisation works on high speed lines are ongoing throughout the world. In Europe for example, the European Commission published a series of Technical Specifications for Interoperability in addition to a significant number of European Norms specific to Railway concerns. Comments: i. Implementation of ERTMS is now mandated in the EC for all new projects. ii. There is a tendency for the designers of new high speed lines to “import” a complete system from one country; this limits flexibility in adapting to specific local conditions. iii. There is an increased requirement for “proven” designs (GAME, GAMAB, ALARP)
2.2.6. Coordinate base reference data Its components are: National coordinate reference net, the numeric track net definition, the numeric line net definition and based on track net and line net the numeric work surface definition.
2.2.7. RAMS – Requirements: The performance of a high speed network depends largely on the availability of its lines. This availability becomes even more important when the revenues of the infrastructure owner or/and the operators of the line depend directly on the degree of availability. Therefore, there is an increasing demand on RAMS-studies to prove that the infrastructure being designed will, during its whole life cycle, meet all requirements concerning reliability, availability, maintainability and safety. Compliance with requirements must be provided for during the design and construction phase of a line; follow-up must be conducted during the entire life cycle.
2.2.8. Contract forms: New contract forms are used for financing the construction, operations and maintenance of large infrastructure works. More and more lines are constructed and operated as a concession with contracts with terms up to fifty years. The concessionaire has to (partially) finance the construction costs but also the maintenance and operation costs. At the end of the contract, the infrastructure is transferred back to the owner(s); the requested quality and the residual life cycle of the components are requirements of the contract. The most complete contract form is the DBFMOT (Design – Build – Finance – Maintain – Operate – Transfer).
2.2.9. Life Cycle Costs (LCC): The Life Cycle Costs: the choice between different technologies and the choice of the manufacturing-construction company is more and more based on the total cost during the life cycle rather than on the initial investment costs. The availability and guarantee of delivery of spare parts are important concerns.
Maintenance of High Speed Lines
5/64
2.2.10. Corporate Social Responsibility (CSR): The Corporate Social Responsibility of the companies becomes an important factor which must be taken into consideration during the design, construction and operation of the high speed line.
2.2.11. Disposal: The disposal or recycling of materials in case of renewal or upgrading work is an important factor. These various recent developments have an impact on the design of new high speed lines or on the upgrading of lines, but also on the maintenance of these lines during their whole life cycle. These various aspects will be taken into consideration in the development of the document.
Maintenance of High Speed Lines
6/64
CHAPTER 2 1.
MAINTENANCE NEEDS
Introduction
Adequate maintenance procedures must be adopted for each component of the system in order to guarantee very high performance for the high speed railway system during its whole life. These procedures have to be extended to cover also non-specific railway subsystems like surrounding roads, accesses, fences, etc. The people responsible for design, construction (upgrading) and maintenance of a high speed line have to satisfy various requirements concerning reliability, availability, maintainability, safety and security by seeking: - To minimise coincidental defaults by the design of the infrastructure and taking into account the results of the RAMS studies, - To minimise systematic defaults by applying a strong Quality System, - To maximise safety by developing a risk management system, - To maximise the performance of the system by reducing train delays, - To maximise the availability of the system by reducing the number of hours of possession of the line, - Methods to permit rapid recovery from disruption. Preference will be given to incremental/evolutionary improvements rather than revolutionary improvements. These objectives can be reached by effectively managing maintenance and implementing clearly identified procedures: - To guarantee the safety of the system and the reliability and availability of its infrastructure, - To ensure highly adequate maintenance with a brief response time at an optimal cost, - For establishing an extended data base to ensure accurate analyses to assist in the planning and selection of a specific type of maintenance be it on a short, middle or long term basis, - For asset management issues/requirements.
2.
Maintenance methods
The generalised systematic periodic maintenance, which was the general practice a few decades ago, is not currently the best practice (because it is costly, requires track possession and results in the deterioration of the components; in particular in respect of data quality level, old working approaches completely miss the target of 100% completeness and correctness making full automation of the new working methods impossible). This kind of maintenance has progressively been replaced by “Condition-based maintenance” (CMB). With the increased development of the possibilities of control and expertise, periodic maintenance has been further replaced. Curative maintenance has also been further diminished. This curative maintenance has a negative effect on the availability of the infrastructure and the degree of regularity of the line. The maintenance manager has to make a choice between: - Investing in a well-developed diagnostic system and in maximising data quality, and - Limiting supervision with the risk of increasing the non-availability of the line.
Maintenance of High Speed Lines
7/64
Note that the maintainer’s choice is often limited by the supplier delivery and warranty conditions. Maintenance specialists agree that curative maintenance has at least a higher cost than condition-based maintenance. Curative maintenance interventions call upon an appropriate organisation of the maintenance service (availability of specialists, intervention teams out of the normal work schemes, communication means, availability of intervention machines, etc...). More versatile maintenance people means lower costs for curative interventions. It is very important to have a data base on curative interventions. Analysis of this data base can be a real help in transforming the various curative, unplanned interventions in condition- based or preventive maintenance operations (e.g. the catalogue of rail defects published by IUR-UIC can be helpful for the organisation of the inspection of the rails and to plan for preventive maintenance or renewal work).
3.
Levels of maintenance
Certain maintenance norms provide for a classification of the different levels of maintenance. The maintenance manager is required to conduct an analysis (for each subsystem or component of a subsystem) to define the limits and responsibilities at each level of maintenance. A detailed classification is very important in the case of sub-contracting of certain maintenance works to third parties. In accordance with these general principles, we recommend the establishment of 4 maintenance levels: Level 1:
Interventions in situ; no intervention of the supplier is necessary; can be executed without negatively affecting the availability of the infrastructure and the regularity of the operations. Level 2: Intervention of the maintenance team in the maintenance base; maximum availability to guarantee redundancy of parts; interventions require control devices and sometimes special tools. Level 3: Intervention of the supplier; control and repair completed by the technicians of the supplier in its factory; if possible, application of standard exchange of elements Level 4: Heavy replacements and renewal works. Significant impact on the availability of the infrastructure.
Maintenance of High Speed Lines
8/64
CHAPTER 3
1.
MAINTENANCE REQUIREMENTS IN THE “DESIGN” PHASE
Introduction
The requirements for operation and maintenance have to be taken into account early in design phase. Experiences with the operation of high speed lines demonstrate that adaptations of infrastructure a posteriori are more expensive than during the construction of the line. In this chapter, we highlight some measures which must be taken into consideration early in development of the project of a high speed line. They should be completed or adapted based on local needs and circumstances and on specific organisation of the envisaged maintenance.
2.
the the the the
Accesses to the infrastructure
Accesses to the different parts of the line shall be provided; they should be situated close to “significant points”. Optimising these accesses can have a positive effect on the access time of the maintenance staff, the access of rescue services and that of employees of the operating companies. The location of accesses depends largely on the type of substructure (embankment, cutting, atgrade, bridge, and tunnel), the chosen maintenance model, the type of resources/equipment to be used, etc. We have set out below various configurations of possible accesses and have recommended specific features. This list is not exhaustive. Technical specifications or national laws may prescribe other facilities. Connections with other (conventional) lines Railway access to the high speed lines can consist in accesses from: - The conventional network, - The maintenance base(s) along the line, - Maintenance sidings along the line. Distances between two railway accesses to the line will be between 80 and 100 km (this represents, for all practical purposes, 1 hour outward and 1 hour return journey for work trains running up to 100 km/h) Comment: In some countries, the speed of the work trains is limited. The location of the necessary maintenance bases or sidings has to be adapted for each particular case. Road accesses and parking Suggested locations for road accesses - at the maintenance base(s), - at the control and operation post(s),
Maintenance of High Speed Lines
9/64
- at the substation(s) and the auto transformer posts (road must be constructed for heavy loads and with a sufficient clearance), - at the GSM-R piles and specific piles for the rescue services, - at both side viaducts and tunnels, - at emergency exits (in tunnels, walls, etc.), notably safety exits and accesses only for rescue services; the design will depend on the chosen emergency strategy, - to and along the area of preassembling switches and crossings, - along the railway sidings, - about each 4 km, alternating on each side of the track for maintenance staff, - for road/rail vehicles and the necessary platforms for re-railing/derailing. Parking facilities which may be built: - at the maintenance base(s): number of places is based on occupation, - at the control command centre(s), - at the substation(s): minimum of 3 places, - at each end of the viaducts and tunnels: minimum of 3 places, - optionally at the preassembling zone for switches and crossings: 5 trucks with at least two heavy trucks, - at the normal accesses and the emergency exits, - at the technical accesses (for example, for mowing machines). Special attention is necessary to avoid entrance by third parties in the closed-off areas (for example, entrances for the delivery of electrical energy). These accesses shall be built outside of the closed-off area. If it is impossible to build the proposed accesses, parallel routes to the track shall be envisaged to limit the distances for the accesses of the maintenance teams. The dimensions of the access roads shall be based on the carried loads. The slope will be at maximum 5% if the accesses are in road-metal and 8% if they are in an asphalt layer.
Staff accesses Staff accesses are provided at maximum distances of 2 km between 2 access points situated on the same side of the line and if possible, opposite protected track crossings or structures. Prefabricated stairs for crossing the embankments or stairs integrated into the stonework of the structures are necessary.
Identification of the entrances It is recommended to clearly identify the different entrances by an identification board with: - The concerned high speed line, - The position of the entrance, - The name of the street and the name of the village, - The access number, - The telephone number of the nearest maintenance base, - The telephone number of the central control and command post, - The sign “Deadly peril – Zone of high voltage”. Maintenance of High Speed Lines
10/64
It is recommended to have one type of lock for the various entrances. Access of tunnel ends and cut and cover sections. The accesses on the tunnel ends have different functions: - Road access including for emergency vehicles (clearance, weight, height) including rotation possibilities, - If necessary landing area for helicopters, - Parking for maintenance and rescue services (with facilities for easy turning), - Storage zone for materials (lorries, masks, extinguishers, …), - Area for cutting of the catenaries and earthing of the overhead wires, - Lighting of the area (10 Lux). The concept will take into account the risk to cover (e.g. mixed traffic with dangerous freight) and the economic dimension.
3.
Assembly area for switches and crossings
Assembly area for switches and crossings can be envisaged if the methods chosen for building and renewing switches or parts of switches require an assembly area and represent an economic interest (availability, cost). These areas can be envisaged along the same elements in the line (transversal placement of the elements) or along a siding track near the existing elements (longitudinal placement of the elements). In both cases, it is necessary to envisage the necessary clearance for the passage of the preassembled elements: overhead piles, electrical devices, cable ducts, and drainage are to be adapted to permit free passage. The length of the service zone must be at least 2 x 10 m longer as the longest element to be manipulated. Road access is very helpful for delivering the elements. Comment: Switches and crossings are becoming more modular. It is now feasible to also transport preassembled turnouts for high speed (using “split bearers”) on specially designed wagons.
4.
Longitudinal service paths for maintenance staff
The width of the service paths beside high speed lines is stipulated in local legislation. To ensure a safe and accessible walkway for persons working with maintenance equipment (welding groups, lighting groups…, which have generally a wheel-base of 650mm), a minimum width of 800 mm is recommended. The free height should be at least 2.10 m. The service paths are continuous: it is recommended that there be no important level differences and no stairs. In case of important differences in level, ramps must be provided (if necessary with hand rails).
Maintenance of High Speed Lines
11/64
5.
Lighting
Powerful lighting is recommended for: -
Areas outside tunnels and leading into tunnels and cut and cover sections, Track switch areas, The work bases, Specific points.
Rules for lighting in the tunnel (ambient lighting, lighting for maintenance and operational staff and emergency lighting) can be found in the UIC leaflet “Safety in tunnels”, in the technical specifications of Interoperability (“Tunnels”) in the American standards (especially for underground lines and underground stations) and in all applicable national laws and regulations. Lighting installed in switch and crossing areas is helpful during control operations and work operations. The lighting can be installed on separate masts, on the overhead line poles or on mobile masts. The energy can be provided by a separate network (= the most independent solution), by the energy for the overhead contact lines or by an individual energy group. If necessary, in order to increase the lighting and to provide energy for electric tools, fixed sockets can be provided for plugging in lighting or electric devices. Lighting of specific points along the track or at the access points has to be taken into account in the design phase.
6.
Maintenance bases
6.1.
Introduction
The maintenance of a high speed line can be organized in different ways; maintenance of the whole system can be carried out by the owner of the infrastructure or maintenance of some subsystems or the whole system can be sub-contracted by means of a Service Level Agreement with contractors. In both cases, working facilities will be required to park the machines, to store spare parts, and to use toilet facilities. A distinction should be made between: -
Emergency depots for materials, A light maintenance base, A full maintenance base.
Some typical solutions for currently operating maintenance bases are set out in the appendices hereto.
6.2.
Distances between maintenance bases:
The travel time of maintenance staff, from the maintenance base to the place of intervention, shall not exceed one hour (average travel speed on road and track estimated at 65 km/h)*.
Maintenance of High Speed Lines
12/64
Taking into account this restriction, a centrally disposed maintenance base can cover about 150 km of line. In zones with high density of traffic, the distance to cover can be lower. * The distance has to be adapted based on the envisaged working windows and the authorised speed of maintenance equipment
6.3
Functionality of a maintenance base:
6.3.1 Light base: A light base consists in buildings (mess facilities, workshops, tool stores, and toilet facilities), a car park and a storage area for small items. It is equipped with telephone, internet and fax. This type of base can be situated either in a station on a conventional line close to the high speed line (< 5 to 6 km), in a station on the high speed line or on the land of the high speed line, near or combined with a signal box.
6.3.2 Full base: This type of base, with road and rail access, can be situated either in a station on a conventional line open to traffic 24 hours a day in the proximity of the high speed line, at an infrastructure maintenance depot (welding plant, workshop for track, etc.) or on the land of the high speed line. The accessibility of the yard must be guaranteed without the need for any interventions other than those of the signalman in the signal box. It consists of buildings (mess facilities, workshops, tool stores), tracks, a car park and a storage area. The tracks will be 300 m in length, suitable for stabling and forming work trains and for stabling an emergency ballast train. These three tracks are already equipped with lighting. The three tracks are provided with: - An inspection pit for servicing maintenance machines, - A locomotive/machine refuelling station, - A high platform and an end platform for loading and unloading maintenance equipment and spare parts onto the work trains. The full base will also have trackside storage space for the spare parts of the different subsystems. Some of the spare parts are stored in an enclosed area protected by alarms and or camera supervision.
6.3.3. Emergency depot: Some networks (SNCF in France; Infrabel in Belgium) have set up emergency depots that can be installed on a full maintenance base or as an independent single depot to cover the needs for a high speed line up to 500 km. On an area of about 300 m x 20 m served by 3 tracks which are separated by a 5 meter space, it holds: - Telecommunication cables, - Overhead line material for emergency work,
Maintenance of High Speed Lines
13/64
-
A half set of switches with correct orientation, Swing nose crossing centres with correct orientation, Expansion joints, Etc.
Some materials can be stored at wagon height to facilitate the loading on flat wagons.
Maintenance of High Speed Lines
14/64
7.
RAMS data
7.1
Definition of Availability
The availability of a high speed line is an important factor in the life cycle of the line. This availability has an effect, in case of PPP projects, on the revenue of the concessionaire of the infrastructure and often constitutes part of the contract requirements. There is, as of the date hereof, no specific definition for the Degree of availability. Various formulas are used to define this requirement. In some contracts premiums or penalties are foreseen as a function of the availability. To avoid any ambiguity we have set out hereafter the definition employed on an existing concession. Asystem = (A – Bsystem)/A and must be 99.8%, with Asystem = degree of availability of the system A = the arithmetic sum over a year of the running time on the line section, as provided in the time tables, for all trains running in the section during the relevant year Bsystem = the arithmetic sum over a year of the delays caused by defaults in the infrastructure and under the responsibility of the concessionary.
7.1.1 Analysis of various factors in the life cycle of a railway system. Non-availability of an infrastructure can be caused by: -
-
Defaults in the rolling stock under the responsibility of the operators of the system, Scheduled works in the normally scheduled traffic interruption times (day, night and weekend traffic interruptions…); these interruptions are not taken into account in determining the degree of availability, Defaults of one or more critical elements/components in the infrastructure; the delays resulting therefrom must be taken into account, Unforeseen failures, Bad weather or other natural phenomena.
Further analysis of the above demonstrates that various factors must be examined at different times during the life cycle.
T1
T2
T3
T4
T5
T6
T7
T1 =
detection of a default; information obtained by or sent to the control command centre
T2 =
information of staff in charge of repair or maintenance
Maintenance of High Speed Lines
15/64
T3 =
preparation of staff in charge of repair (travel time, availability of spare parts, availability of measuring devices, preparation and travel with respect to the machines). Arriving at the place of intervention.
T4 =
Repair time (depends largely on the MTTR given by the builder)
T5 =
Control and test time after repair; information provided to the control command centre
T6 =
Time to restart the operations
T7 =
End of the consequences of the default; operations in normal mode.
7.2
Factors in determining degree of availability:
7.2.1 Introduction The most important factors affecting the degree of availability are: -
The concept of the infrastructure and its different subsystems, The structure and organisation of the operation services, The structure and organisation of the maintenance services, The means available for intervention and repair.
These various factors are described in more detail below.
7.2.2 The concept of the infrastructure and the various subsystems Prior to and during the design of a high speed line or the upgrading of an existing line, fundamental choices have to be taken between the investment costs and the desired availability. Availability can be increased by: - Design safety margins, - Use of “proven” systems, - Modular design, - An extension of redundant systems; for example: ° Installing three power transformers to feed the overhead line; while two of them operate, the third one permits maintenance or repair works (one of the reasons for this is the long delivery time of such a transformer), ° Doubling some signalling circuits with automatic switch system, ° Placing a spare standard exchange cart into the electrical cubic, ° Double coverage of the GSM-R installation, ° Doubling the central control and command post (J apan, Perpignan-Figueras). -
Maximising the monitoring of the systems and grouping the remote control in one SCADA room; for example by monitoring: ° The switches and crossings, ° The access control, ° Fire detection, ° The condition of the pantograph (made in some st ations),
Maintenance of High Speed Lines
16/64
° °
The wheel impact forces on the rail (especially recommended for lines with mixed traffic), The control of the clearance of freight trains.
-
Choosing components of subsystems with very good RAMS features; for example: ° High MTBF (mean time between failure), ° Low MTTR (mean time to repair), ° High MTBSF (mean time between service failure).
-
Concluding service level agreements with adjacent lines or railway companies to ensure mutual assistance in case of problems; for example: ° Delivering energy in case of system failure, ° Providing the infrastructure manager with a lift ing crane for rolling stock.
8.
Structure and organisation of the operation service
In case of unforeseen default, the reaction time of the operators of the control command room and the content of the given information is very important; they both affect the total duration of the disruption. Two examples of proper organisation are: - Grouping the dispatcher for operations and the technical dispatcher in the same room, - The use of “radio maintenance”, mobile telephones or the GSM-R which permits maintenance staff to follow all communications concerning the operations and to obtain information very quickly in case of disruption.
9.
Structure and organisation of the maintenance service
The structure and the organisation of the maintenance service have a significant effect on the interruption time of the traffic in case of problems. This organisation depends on: - The availability of maintenance staff (duty service; 24 hour maintenance response teams), - Its logistic means (mobile, car, storage and disposal of stock parts, intervention machines, etc.), - The technical assistance contracts of the suppliers, - The contracts with the contractors if proper organisation is not sufficient or fails to provide adequate means of intervention.
10.
Test devices, wear parts, spare parts
Contracts with the suppliers for subsystems should provide for parts of subsystems or elements of subsystems, and the requirements of maintenance in terms of supply. The supplier must deliver the following information: - The definition of the LRU (Line Replaceable Units); these are the smallest units which can be replaced on site. The client’s proposal of LRU can be amended by the client,
Maintenance of High Speed Lines
17/64
-
-
The description of the maintenance tasks which can be allocated to the maintenance service and those which have to be carried out by the supplier, Comment: The supplier may be granted full responsibility of the totality of its deliveries (Service Level Agreement). The information for the RAM study (life span, MTBF, MTTR), The organisation of its services (call number), An offer for the supply of test devices or test banks, The agreement concerning the delivery of wear and spare parts (delivery time and mode, number of years of guaranteed delivery, price level and price review formula… ), The conditions for on-site intervention of specialists of the supplier, The user and maintenance (preventive and corrective) handbook including the frequency of intervention and the limits of use, The proposed program for training staff (operations and maintenance), A copy of all required legal attestations (e.g. in Europe, the “CE” attestations for machinery and for interoperability), The testing check list (cause – symptom – remedy).
This information is necessary for the client to: - Complete the technical examination of the offers using information pertaining to Life Cycle Costs, - Calculate the degree of availability of the different subsystems and use them to determine the availability of the whole system, - Manage wear and spare parts and calculate the risks of an in inventory shortage, - Organise the education and training of operations and maintenance staff.
11
Emergency equipment, traction units
If the owner of the infrastructure does not possess the equipment for intervention in case of emergency (derailment, lack of traction power, etc), a service level agreement must be entered into with one or more operators of the line or with the infrastructure manager of adjacent lines to guarantee an intervention within the shortest possible time.
Maintenance of High Speed Lines
18/64
CHAPTER 4.
1.
MAINTENANCE REQUIREMENTS DURING THE “CONSTRUCTION” PHASE
Introduction
The quality of a high speed line and the degradation of the quality of most of the subsystems depend largely on the initial quality of these subsystems after construction and on the care taken to maintain the initial quality in the period of pre-operation and during the first months of operation. The best way to ensure very high construction quality is to establish an active collaboration between the builders and the maintainers of the system.
2.
Collaboration between builders and maintainers
The best results and the lowest Life Cycle Costs are obtained if: - The requirements of future maintenance are taken into account during the design of the line (see above), - Strict construction and certification standards are taken into account; a quality bonus can be helpful to obtain quality exceeding the required one, - The maintenance staff and technicians-to-be are concerned with the construction and as such co-responsible for the work and tests done, - The results of the tests (and in particular, the dynamic tests at speeds up to the conception speed + 10%) are satisfying. Special attention shall be paid to all interfaces; generally the interfaces cause difficulties during tests and at the time of initial operations. Participation of maintenance staff in construction is the best way of training such staff and prepares them in taking over responsibility with respect to maintenance and repairs in case of disruption. Nevertheless, it is only a preliminary step in the awareness needed to achieve process-driven, computer-supported work.
Maintenance of High Speed Lines
19/64
CHAPTER 5
1.
MAINTENANCE REQUIREMENTS IN THE “TEST AND SERVICE SHADOW” PHASE
Introduction
Before opening the line, a number of tests are to be performed; in this respect, please refer to the requirements of the different specifications for interoperability contained in “Guidelines for homologation of high speed lines” published by the UIC and the specific requirements of the contract. During the test period, and with an increase in speed and in the duration of the shadow service period, specific attention must be given to the geometry of the track and the overhead contact system. Indeed, these tests are done during a period of stabilisation of the construction and its components. Unexpected defaults due to differential settlements or due to the dynamic forces of the high speed test trains may occur. In case of any defaults, measures to repair them must be taken immediately to avoid further degradation of the subsystem. It is strongly recommended that maintenance staff be actively involved in this phase. It is also recommended to conduct the following verifications.
2.
Table of verifications during test and service shadow phase * Frequency
Staff
Infrastructure –
Subsystem
Drainage system and pumping
2 weeks
Senior Technical
Civil works
Barriers and fences
1 week
Technical Assistant
Civil structures and line side
2 weeks
Senior Technical
Geometry of the track
2 weeks
InfrastructureTrack
Energy – Overhead contact system
Type of verification
Comments
Switches and crossings - visual check
2 weeks
- verification of critical dimensions
1 month
Technical assistant Senior technical
Expansion joints
2 weeks
Technical assistant
Surroundings
2 weeks
Technical assistant
Profile of the ballast
2 weeks
Senior technical
Monitoring of the switches and crossings
2 weeks
Senior Technical
Control of the forces in switches and crossings
2 weeks
Senior Technical
Transition zones – slab track/ ballast track
1 month
Technical assistant
Check flying ballast
Geometry of the contact wire
2 weeks
Senior Technical
Lifting of the contact wire
1 month
Senior Technical
Rear cabin of a train
Control command and telecommunication
Recovery of GSM-R
2 weeks
Technical assistant
Or recovery of radio maintenance
Tunnel protection equipment
Control of the fire detection system
1 month
Technical assistant
Control of the ventilation system
1 month
Technical assistant
Control of the sprinklers
1 month
Technical assistant
Control of the water circuit
1 month
Technical assistant
* The final decision relating to the type of verifications to be conducted, the concerned staff and the intervals of verification shall be made by the Railway Authority.
Maintenance of High Speed Lines
20/64
CHAPTER 6. INSPECTIONS AND TESTS DURING OPERATIONS ON THE LINE 1.
Introduction
The frequency of inspection and tests depends on the type of traffic on the line (passenger traffic only or mixed traffic) and on the UIC category of the line. The Railway Authority has jurisdiction to determine these matters.
2.
Components to be examined during monitoring (Non-exhaustive check list of elements to be examined)
Civil works and Surroundings Civil works Codification number
Designation
CV 1
Stability of bridges, viaducts, fly-overs, …
CV 2
Stability of tunnels
CV 3
Stability of earth works (cuttings/embankments)
CV 4
Stability of structures including rock walls
CV 5
Water drainage systems
CV 6
Noise abatement structures (walls, barriers, etc.)
CV 8
Crash barriers
CV 9
Detecting systems for movement of the embankment slopes, rain gauges,
CV 10
Control of weed and undergrowth
Comments
Watch for calcite formation
Surroundings Codification number
Designation
SU 1
Access roads, parking places,
SU2
Fences, access gates
SU 3
Access steps, parapets, etc.
SU 4
Platforms, walls, etc.
SU 5
Trees along the line
Maintenance of High Speed Lines
Comments
Verify distance and height
21/64
Track
Codification number
Designation
Comments
TR1
Track Geometry
If possible, in combination with the OCS geometry
TR2
Ballast - profile of the ballast bed - cleanness of the ballast
Lowered profile for speeds exceeding 250 km/h Avoid fine elements (problem of flying ballast)
TR3*
Slab* concrete structure other elements (mortar …)
TR4
Rails - wear of the rail - internal defects - surface damage - corrugation
TR5
Sleepers and bearers - Concrete structure of the sleeper - Under sleeper mats - Gaps between sleepers and concrete* - Bending of the sleepers and bearers
Thermic and electric rail welds, squats, head checks
Case of slab track Case of wooden sleepers or bearers
TR6
Fastenings
TR7
Expansion joints
TR8
Switches and crossings
TR9
Re-railingplatforms
Rail road vehicles
TR10
Transition zones - slab track – ballast track* - ballast track – earthwork
Special survey during track stabilisation
TR11
Noise abatement devices between rails *
Slab track
TR12
Electric components fixed in the track
Balises, detectors, condensers, axle counters, etc.
Energy Power Supply (PS) Codification number
Designation
Comments
PS1
Transformers
PS2
Return circuit
Continuity
PS3
Protection devices
Protective gratings
PS4
Switches
Maintenance of High Speed Lines
Substations; AT posts
22/64
Overhead Contact System (OCS) Codification number
Designation
OCS1
Feeder
OCS 2
Contact wire
OCS3
Tension equipment
OCS4
Insulators
OCS5
Heating device of the contact wire
Comments
Periodic cleaning operation may be necessary
Earthing Codification number
Designation
EA 1
General Line earthing system
EA 2
Intermittent earthing system
EA 3
Protective earthing of pipe lines, …
EA 4
Earthing devices of the OCS
Comments
EA 5 EA 6 EA 7
Control command and Communication Signalling Codification number
Designation
SI 1
Automatic Train Control System mean system fall back system
SI 2
Electronic interlocking system
SI 3
Signalling power supply system
SI 4
Telemetry system
SI 5
Wayside ATC track circuits
SI 6
Train number processing system
SI 7
Wayside signals
SI 8
Detectors
SI 9
Monitoring systems
SI 10
Switch motorisation
SI 11
Switch heating
Comments
SI 12
Maintenance of High Speed Lines
23/64
Communication System Codification number
Designation
CC 1
Data transmission system
CC 2
Telephone, Automatic telephone system
CC 3
Radio maintenance
CC 4
Public address system
CC 5
Close circuit television
CC 6
Time distribution system
CC 7
Passenger information system
CC 8
SCADA systems
Comments
CC 9
Auxiliary equipment Codification number
Designation
AE 1
Ventilation
AE 2
Rescue doors
AE 3
Pump systems
AE 6
Collectors of dangerous liquids
AE 7
Fire extinguishers
AE 8
Extinguishing circuits in buildings
AE 9
Extinguishing circuits in tunnels
Maintenance of High Speed Lines
Comments
Mixed traffic with dangerous liquids
24/64
CHAPTER 7
1.
WORKING WINDOWS – SWEEP TRAINS –
Introduction
The maintenance of the Infrastructure is important to guarantee that the High Speed System is working properly, remains safe and provides transportation to passengers with a high degree of comfort. In the case of mixed traffic, specific attention must be given to the transportation of dangerous goods. With the increase in train traffic, maintenance services must limit the number and the length of possession times available for maintenance. This chapter provides an overview of the different types of possession time. Some railway infrastructure managers schedule, on a daily basis and before the reopening of the line for commercial traffic, a “sweep” or “pilot” train running at a limited speed. The purpose of such verification procedure is set out below.
2.
“Sweep” train
Objective: -
Confirmation that the line is clear of obstacles and suitable for running at high speed, Confirmation of the absence of undetected defects before opening the line (e.g. due to vandalism), Confirmation of the proper operation of overhead lines and of the control command and communication subsystem, Checking track stability (ballasted track) after carrying out maintenance or renewal operations.
This run is not considered to be essential if the maximum speed on the line does not exceed 220 km/h. To obtain a good overview of the infrastructure, a speed of 160 – 170 km/h is recommended. The function of sweep trains can be attached to the first commercial train; it is recommended to limit the speed of this train.
3.
Working windows
General comments: Provision must be made for different types of possessions in order to enable maintenance operations to be performed. To optimize possession time, it is necessary to think in terms of management of the maintenance of the “infrastructure system” and not in terms of subsystems. We have set out below a table with the practices of different railways and have added some comments obtained in the work group.
Maintenance of High Speed Lines
25/64
Types of possessions Possessions intended for monitoring Possessions intended for making detailed (visual) inspections of some installations situated in the danger area. These inspections are made without machines on the track and do not require the interruption of tension on the overhead wire. A line can be divided into different “possession zones”. Items to inspect: - Defects on the rail and its running surface, - Switches and crossings (general state, signs of wear and rubbing, cracks in the components, etc.), - General state of the disposition of the different contact wires in the zones of switches and crossings. For these inspections, daytime possession is recommended to have good lighting for the inspected zones. Normal regular traffic stoppage is required in the concerned zone. Possession can be introduced at any point in the concerned zone. These daytime inspections should be carried out seven days out of seven. Duration of the traffic stoppage: a minimum of 35 full minutes. Comment: Highly developed automatic monitoring of the switches and crossings can reduce the necessary possession time. - Ballasted track with continuous welded rails (CWR) during periods with hot weather. - Infrastructure likely to be affected during or after abnormal weather conditions (heavy rainfall, cold periods, heavy snow or wind) Possessions intended for light maintenance operations Possessions to permit running repairs shall be carried out in the danger area. These possessions can be in the night time. Possessions are not needed seven days out of seven; four days a week are a minimum. Shut down of the track and power (if needed). Duration: - Minimum of 4 full hours (excluding the time taken up by procedures, including the travel time of the machines) on 1 track, - Minimum of 2 full hours for the second track. Items: - Tamping, grinding, re-profiling, welding, control of the overhead system, cleaning of insulators, etc., - Replacement of elements (expansion joint, rail, sleeper, insulator, contact wire, switch motor, bacon, etc.), - Adjusting works. Must be scheduled 6 weeks prior to start of work.
Maintenance of High Speed Lines
26/64
Possessions intended for heavy maintenance operations (with duration of one or more days). Possessions for carrying out heavy maintenance operations (replacement of a switch, replacement of the overhead wire of a span, etc.) A minimum of 10 full hours. Possible simultaneous work on both tracks for a period of 3 hours. Must be scheduled at least 3 months prior to start of work. Possession time intended for major work and/or long duration Possessions permitting heavy renewal works carried out in danger areas. A minimum of 10 full hours; continuous possession can double or triple the performance. Must be scheduled at least 18 months prior to start of work in collaboration with the adjacent managers of infrastructure. Normal time tables will inevitably be affected. Overview of the possession times in the different networks The tables in Appendix 3 provide data concerning the possession times for various countries.
Maintenance of High Speed Lines
27/64
CHAPTER 8 1.
BEST PRACTICES IN MAINTENANCE WORKS
Introduction
This chapter provides information about best practices with respect to the performance of certain maintenance work on the infrastructure of (high speed) lines.
2.
Integrated maintenance
Traditionally, the maintenance of railway infrastructure is divided up into different subsystems (track, civil structures, substations, overhead contact lines, etc.) with a separate budget, staff and planning system. This kind of organisation leads to a non-optimal use of logistic support and of track possessions. Integration of the maintenance of the various subsystems under the control of one central management team and one central planning unit can have a positive influence on the reliability and the availability of the line. Increased integration can also bring added versatility to maintenance staff.
3.
Minimum maintenance requirements between finishing the construction and tests and starting operations
If, after finishing the construction of the line and before opening the line for operations, there is a period without traffic, a minimum of survey and maintenance works have to be carried out to maintain the installations and to avoid significant costs in preparing once again the line for operations. The works to be carried out depend on the technology chosen for the concerned subsystem and on the requirements of the different suppliers. The following suggestions should be considered:
3.1
Prevention against vandalism and burglary of cables, overhead contact wire, etc.
Regular verification and visits of the line and technical buildings Maintaining tension on the OCS Maintaining monitoring systems protecting against any intrusion with respect to service Maintaining fire detection systems ensuring they are operational Requesting the assistance of the local police for extra patrols (strongly recommended during the first days of school holidays) To avoid corrosion of the running surface of the rails, some traffic must run over the line (in general, a passage of some axles each 72 hours is a minimum); when it is not possible, the rail surface has to be blanked before traffic may operate. To avoid functioning failures in the switches, they have to be moved every three days. To control the functionality of the circuit-breakers, they have to be switched every month.
Maintenance of High Speed Lines
28/64
It is recommended to carry out a verification, on foot or in a motorcar running at low speed, every two weeks to inspect the line equipment, the water drainage of the platform and the surroundings of the line. It is recommended to schedule (three years after initial operations) a yearly weed killing operation for the track and the surroundings. Control of the substations, the AT-posts, the rooms with transformers and with batteries to be carried out each month. Control of the pump stations to be carried out every 2 months or after violent rainfall. During line visits, verification (each 500 m) of the GSM-R functionality. Defaults or missing elements must be repaired/replaced as soon as possible. Before opening the line for regular service, a verification of the geometry of the track and the overhead contact wire at a reduced speed (maximum 120 km/h) is mandatory. During these runs, the functionality of the entire system shall be examined.
4.
Track
4.1
Rail grinding
Several years ago, track specialists determined that, for ballast track, combining lining, levelling and tamping of the track with grinding results in a lower degradation ratio of the geometry of the track. About ten years ago, preventive grinding of the rail heads before opening the line was introduced. The aim of this operation is to: - Provide a homogeneous railhead profile along the long welded rails, - Eliminate rail surface defaults on the railhead caused by the construction of the line and the test runs, - Prevent the decarbonisation of the surface of the railhead (~ 0.3 mm) causing micro cracks and, over a longer period, rail defects. Recent research on the phenomena of squats and head checks (especially in rails of higher steel grade) has determined another advantage of grinding. SNCF and Infrabel have found that “light grinding” (about 0.1 mm) on a regular basis (once a year on lines with high traffic density) could avoid the formation of these modern defects. Test programs are ongoing to confirm the results. An additional advantage of such “light grinding” is the resulting low noise and vibration level due to the contact of the wheel and rail. This “light grinding” can also be applied on slab track.
4.2
Absolute coordinates
If, for ballast track, the levelling and lining is permanently carried out on a relative work base, a shift of the track coordinates occurs and the dynamic forces on the track increases.
Maintenance of High Speed Lines
29/64
To overcome this negative loop, works must be done periodically on absolute coordinates to restore the original position of the track and to lower the rate of degradation.
4.3
Flying ballast
The interaction between rolling stock and the track can cause an elevation of ballast stones and damage the rails or the rolling stock. A good ballast profile (the upper surface of the ballast must be about 4 cm lower than the upper face of the sleepers) and avoiding ballast stones on the surface of the sleepers or bearers help to overcome these kind of defects. If the described measures are not sufficient for some types of rolling stock, a temporary or permanent speed reduction shall be applied.
4.4
Measures against snow adhering to and dropping from high speed trains
Snow dropping from high speed trains can have negative effects: - Dispersion of ballast by the impact of falling ice lumps, - Damage to places along railway tracks, glass breakage in vehicles, and damage to ground equipment. By combining vehicle side measures and ground side measures, the amount of snow adhesion can be minimised. Measures can be taken against these problems: - Expansion of ballast screen installations, - Protection of ground equipment, - Snow removals (by hand, by hot water jet device), - On-train measures (electric heaters, air conditioners).
4.5
Wheel scan
Wheel scan is a real time wheel inspection system positioned beside the track. The wheel set diagnosis system is generally speaking a modular design and can check (depending upon the modules fitted) the following features of the wheel: flats and ovality, diameter, profile, flange thickness, cracks. Some systems are capable of measuring the angle of attack of the wheel sets of rolling stock travelling at speeds up to 30 km/h. The scanned wheel can be compared to a pre-defined reference profile. It can be a help to survey rolling stock and in particular the rolling stock on high speed lines with mixed traffic.
5.
Energy
5.1
Surveying of the overhead contact wire by thermo-graphic control
SNCF introduced, after tests in 2001, infrared thermo-graphic cameras to conduct their inspection work. The purpose of this kind of inspection is to obtain a clear and consistent picture of the heating pattern of the catenaries. The camera was mounted on a wagon and inspected the overhead contact wire with speeds up to 120 km/h.
Maintenance of High Speed Lines
30/64
Definition of appropriate severity criteria for the heat development of catenaries is ongoing.
5.2
Overhead contact system
UIC published in 2004 Leaflet 791-1 RI entitled “Maintenance guidelines for overhead contact lines”. This technical leaflet contains a list of inspection and surveys of the OCS based on the classification of the railway lines. Appendix 4 provides an overview of the practices on high speed lines (results from responses of various networks in addition to recently received answers from some managers of high speed lines). One of the conclusions of this overview is that there are significant differences in the frequency of inspection. As aforementioned, type and density of traffic, system design, chosen materials, and environment can have an effect on fixed periodicity. Specialists of overhead contact lines must decide if a more detailed discussion can lead to a certain optimisation.
5.3
Control of the pantograph
Some infrastructure managers installed, in some end or intermediary stations, optical devices for controlling the pantographs of the rolling stock. Various high definition colour video survey cameras are installed on piles and check the various pantographs of the high speed trains at low speed.
Maintenance of High Speed Lines
31/64
CHAPTER 9
1.
LIFE CYCLE OF SUBSYSTEMS OF HIGH SPEED LINES
Introduction
Due to increasing performance demands from governments and train operating companies, infrastructure management must optimise the reliability and the availability of high speed lines. Reliability and availability have an impact on the Life Cycle Costs of the infrastructure and indirectly on the costs and revenues of transport operations. Even during the development, construction and operation phases, choices must be made on the design, the maintenance programs and – in the long term - the renewal programs. These choices have an effect on the Life Cycle Costs of the system and the various subsystems in achieving an optimal trade-off between investment and maintenance. This chapter provides information about some relevant components of the railway system and comments on the origin of such information.
2.
Track components
Rails: On high speed lines, the life cycle of rails is not determined by vertical and/or lateral wear of the rail but rather by the number and frequency of rail defects and the related repair costs (direct costs and operational costs). Operational costs (due to non-availability of the track or due to delays) are dependent on the organisation of the maintenance service and also on the operating rules concerning traffic on defective rails (total interruption, reduced speed…). The following data can be used as a first approach for high speed tracks dedicated to passenger traffic. Rails Grade 700: 400 - 500 Mio Ton Rails Grade 900: 600 -700 Mio Ton Bainitic Rails (on test): expectation of 1000 - 1100 Mio Ton Freight traffic, mixed passenger traffic at different speeds, sand erosion, etc. can reduce the life cycle of the rails or certain parts of the track (e.g. the lower rail in curves); no data are available for these types of high speed track. Switches:
No specific data available
Sleepers for ballast track or for non embedded slab track Wooden sleepers: not of general use on high speed lines (expected life cycle of 25 years) Concrete sleepers:
40 years
Slab track:
60 years
Fastenings:
40 years
Ballast:
35 years (depending on its initial quality, the type of traffic, the number of tamping cycles, etc.)
Maintenance of High Speed Lines
32/64
3.
Overhead contact lines
Overhead Contact Wire The quality of the contact between pantograph and the overhead contact wire depends on: - The quality of the concept of the pantograph and the quality of maintenance of the pantograph, - The quality of the overhead contact wire; factors influencing this quality are: The chemical composition of the contact wire (Cu, CuAg, CuMg), The concept of the overhead contact system, The tension on the overhead contact wire, The initial quality of the construction work, The quality of the maintenance, The quality of the pantographs running over the line. The life cycle of the overhead contact line depends on the aforementioned parameters; the composition of the overhead contact line is the predominant parameter. Recent studies on the Belgium high speed lines comparing CuAg and CuMg contact lines show that concerning the limits of wear, the life cycle of a CuMg wire is about 4 times the life cycle of a CuAg contact wire. Overhead contact system piles and portals: For the overhead contact system piles and portals, the concept, the chosen material and the modes of protection are very different. In addition to these differences, the weather conditions, atmospheric air and pollution make that it is very difficult to predict its life time. 40 years is a forecasted mean value.
4.
Signalling system
Over the last three decades, the signalling systems have changed fundamentally. The classic line side signalling system disappeared over time and was replaced systematically by on board CAB signalling. Different levels of CAB signalling were developed over the last few years (e.g. in Europe, the ERTMS-ETCS system (level 1 and 2) is becoming commonplace); new developments are forthcoming (e.g. in Europe, level 3 of the ERTMS-ETCS system). Due to rapid advances in the development of electronic devices, the maximum life cycle of electronic components in signalling systems is now 15 years.
Maintenance of High Speed Lines
33/64
CHAPTER 10 CONCLUSIONS & RECOMMENDATIONS CONCLUSIONS 1. Railways have changed considerably over the last decades; these changes occurred on different levels: technology, organisation, goals, etc. 2. High speed lines appeared in different continents; new high speed lines are under construction or planned; most of the lines are dedicated to passenger traffic but some high speed lines are equipped for mixed traffic. 3. Maintenance of high speed lines is an important issue; it must start with the conception of the line. RAMS and Life Cycle Costs have to been taken into account during the design phase of the project and followed up during the whole life cycle of the line. 4. Although the control parameters for maintenance purposes are very similar in each country, the frequency of inspection can be very different. The origin of these differences is the speed, the type of traffic, the UIC class of the line, the chosen technologies, etc. Another factor is the fact that the regulations for high speed lines, in numerous countries, were implemented by transposing the national regulations for the conventional network. 5. In many countries, maintenance organisation is switching from time-based to condition-based maintenance. Monitoring is a very important issue to control the different parameters of the subsystems. New research and developments are forthcoming. 6. The life cycle of many components of the infrastructure of high speed lines increased. For some new developments, more time is required to confirm the expectations.
RECOMMENDATIONS 1. Exchanges of Return of Experiences on a regular basis. 2. An effort to stabilise the technology of some subsystems as the interfaces are becoming more and more difficult to manage. 3. Common research for the development of a RAMS databank to assist in choosing components and in the management of spare parts.
Maintenance of High Speed Lines
34/64
APPENDICES
Maintenance of High Speed Lines
35/64
Maintenance of High Speed Lines
36/64
Appendix 1 Abbreviations ADIF
Administrador de Infraestructures (Spain)
ALARP
As Low As Reasonably PracticableAT-posts Auto transformer posts
“CE”
CE mark
CBM
Condition Based Maintenance
CSR
Corporate Social Responsibility
CWR
Continuous Welded Rails
DB
Deutsche Bahn
DBFMOT
Design Build Finance Maintain Operate Transfer
ERTMS
European Rail Traffic Management System
ETCS
European Traffic Control System
GAME
Globalement au Moins Equivalent
GAMAB
Globalement au moins aussi bon
GSM-R
Global System for Mobile Communications - Railway
HSL
High Speed Line
UIC
Union Internationale des Chemins de Fer
JR EAST
Japanese Railways East
KORAIL
Korean Railways
LCC
Life Cycle Cost
LRU
Line Replaceable Unit
MDT
Mean Down Time
MTBF
Mean Time between Failure
MTBSF
Mean Time between Service Failure
MTTR
Mean Time to Repair
MTTRS
Mean Time to Restore Service
Maintenance of High Speed Lines
37/64
OCS
Overhead Contact System
PPP
Public Private Partnership
RAMS
Reliability, Availability Maintainability, Safety
RENFE
Red National de Ferrocarrilis Españoles (Spain)
RFF
Réseau Ferrée Français
RFI
Rete Ferroviara Italiana (Italy)
SNCF
Société National des Chemins de Fer Français
THSRC
Taiwan High Speed Rail Corporation
TSI
Technical Specification of Interoperability
Maintenance of High Speed Lines
38/64
Appendix 2 Example of tables of inspection frequencies on high speed lines
Maintenance of High Speed Lines
39/64
Maintenance of High Speed Lines
40/64
Appendix 2 A: Inspection and verification: Table used during the period of speed increase and during the first weeks of operation TYPE OF SURVEILLANCE Inspection of turns on running track
Inspection of transition zones between - types of track - types of OCL system - types of signalling systems Inspection of turns in zones of switches and crossings
Specific inspection of turns on slab track
OBJECT OF INSPECTION
INTERVALS
Running track and line side in cab (front or rear)
1 week
OCL in cab
1 week
Running track and line side on foot
2 weeks
OCL on foot
2 weeks
Inspection in cab
1 week
Inspection on foot 2 weeks
Visual safety check (except for safety critical dimensions)
1 week
Verification of safety critical dimensions
2 weeks
Detailed verification
1 month
Inspection on foot to control cracks in the concrete of the slab
2 weeks
Appendix 2 B: Inspection and verification: Table used in normal operation mode TYPE OF SURVEILLANCE Inspection of turns
Recordings of - Track - OCL system
OBJECT OF INSPECTION
INTERVALS UIC 1 and 2
UIC 3 and 4
UIC 5 and 6
Running track and OCL on foot
2 months
2 months
2 months
Running track in front or rear cabin
2 weeks
2 weeks
3 weeks
Switches and crossings
5 weeks
5 weeks
6 weeks
OCL in front or rear cabin
6 months
6 months
8 months
Line sides
5 weeks
5 weeks
5 weeks
2 months 3 months 1 week
3 months 4 months 2 weeks
4 months 6 months 3 weeks
6 months 1 year
6 months 2 years
8 months 3 years
Track level and alignment faults, including long waves: - conventional recording car ° ballasted track ° slab track - vertical and lateral accelerations (axle boxes and body) Geometry of the OCL Wear on the contact wire Ultrasonic testing
Switches and crossings
See details in table 2C
Corrugation testing*
1 year
2 years
3 years
Recording of the ballast profile
1 year
1 year
1 year
Visual safety check (except for safety critical dimensions)
See details in table 2D
Verification of safety critical dimensions Detailed verification
* As of the date hereof, no significant corrugation has been found on high speed lines.
Maintenance of High Speed Lines
41/64
Appendix 2 C: Ultrasonic inspections of rails, switches and crossings
Ultrasonic control with heavy equipment
UIC Category 1& 2
3&4
5&6
Before commencement of operations
once
once
Cumulative load carried <200 million tons
Once per year
Once per year
Once per year
Cumulative load carried > 200 million tons and <400 million tons
Twice per year
Once per year
Once per year
Cumulative load carried >= 400 million tons
3 times per year
Twice per year
Once per year
Once
If during the operations unexpected defects in rails and welds occur, the frequency of the ultrasonic control must be adapted. In some cases, a verification with light apparatus of the suspected zones may suffice.
Appendix 2 D: Detailed verifications of switches and crossings UIC Category Type of verification 1&2
3&4
5&6
Age of the switch Detailed verification
Visual safety check
Verification of safety critical dimensions
< 3 years
Once in the period
Once in the period
Once in the period
> 3 years < =6 years
Once in the period
Once in the period
> 6 years
Twice in the period 1 year
1 year
1 year
< 6 years
1 year
1 year
1 year
> 6 years
6 months
1 year
1 year
< 6 years
3 months
6 months
1 year
> 6 years
2 months
4 months
6 months
Maintenance of High Speed Lines
42/64
Appendix 3 Data on high speed lines in the world
Maintenance of High Speed Lines
43/64
Maintenance of High Speed Lines
44/64
Country Italy Line
Milan-Bologna
Bologna-Florence
Turin - Milan
Rome - Naples
200 km
100 km
120 km
220 km
Comments
Topics Length of the line (km) Total km of line - Double track % - Single track % Maximum Speed (km/h) - Design - Operational
100 0
100 0
100 0
100 0
300 km/h 300 km/h
300 km/h 300 km/h
300 km/h 300 km/h
300 km/h 300 km/h
Daily service (trains/day)
90
104
16
80
39% 1% 60%
5% 90% 5%
80% 1% 19%
40% 30% 20%
100%
100%
100%
100%
P No freight at the moment
P No freight at the moment
P No freight at the moment
P No freight at the moment
100% 0% 0% 48 tg 0,022 + 20 tg 0,074 + 20 tg 0,040
100% 0% 0% 24 tg 0,022 + 10 tg 0,074 + 10 tg 0,040
100% 0% 0% 24 tg 0,022 + 10 tg 0,074 + 10 tg 0,040
100% 0% 0% 48 tg 0,022 + 20 tg 0,074 + 20 tg 0,040
4 2
2 2
2 2
5 3
120 MVA
120 MVA
120 MVA
120 MVA
2x25 kV c.a. – 50 Hz 3 kV c.c.
2x25 kV c.a. – 50 Hz 3 kV c.c.
2x25 kV c.a. – 50 Hz 3 kV c.c.
2x25 kV c.a. – 50 Hz 3 kV c.c.
Copper 1x150 mmq (c.a. system) 2x150 mmq (c.c. system)
Copper 1x150 mmq (c.a. system) 2x150 mmq (c.c. system)
Copper 1x150 mmq (c.a. system) 2x150 mmq (c.c. system) 2000 daN
2000 daN
2000 daN
Copper (2 experimental regulations in coppersilver) 1x150 mmq (c.a. system) 2x150 mmq (c.c. system) 2000 daN
Copper 1x120 mmq (c.a. system) 2x120 mmq (c.c. system)
Copper 1x120 mmq (c.a. system) 2x120 mmq (c.c. system)
1500 daN
1500 daN
Structure type: - % bridges and viaducts - % tunnels - % earthwork Subgrade - Classic % - Bituminous % - Concrete % Traffic - Passengers (P) - Mixed (M) Type of track - Ballast track % - Slab track % - Embedded rail % Number of switches Substations - Number of substations - Number of AT- stations - Installed power Overhead contact system - Voltage and frequency
- Type of contact wire: - Material - Section (mm²)
- Tension (daN)
- Type of carrying cable - material - section (mm²)
- tension (daN)
Copper 1x120 mmq (c.a. system) 2x120 mmq (c.c. system)
Specify the maximum speed of freight traffic
Copper 1x120 mmq (c.a. system) 2x120 mmq (c.c. system)
1500 daN 1500 daN
Control command -Signalling system
ERTMS/ETCS L2 No lateral signalling (only in STM-L0 ambient)
ERTMS/ETCS L2 No lateral signalling (only in STM-L0 ambient)
ERTMS/ETCS L2 No lateral signalling (only in STM-L0 ambient)
ERTMS/ETCS L2 No lateral signalling (only in STM-L0 ambient)
Track-train communication for the position reports + GSM-R
Track-train communication for the position reports + GSM-R
Track-train communication for the position reports + GSM-R
Track-train communication for the position reports + GSM-R
4 50 RFI is moving from time-based maintenance to condition-based maintenance in terms of defect detection by
3 30 RFI is moving from time-based maintenance to condition-based maintenance in terms of defect detection by
3 40 RFI is moving from time-based maintenance to condition-based maintenance in terms of defect detection by
4 55 RFI is moving from time-based maintenance to condition-based maintenance in terms of defect detection by
- telecommunication system
Maintenance Bases - Number - Average coverage (km) Maintenance approach
Maintenance of High Speed Lines
Specify : timebased or condition-based Also specify changes planned in the
45/64
Sweep train
Daily possession time - During day - Overnight .1 track .2 tracks
mobile diagnostic means No
mobile diagnostic means No
mobile diagnostic means No
mobile diagnostic means No
No
No
No
No
2 tracks
2 tracks
2 tracks
2 tracks
near future Indicate yes or no. Also specify the max. speed On HSL, track possession is only during the night. The lines are typically not in operation from 00:00 to 5:30 for both tracks. There is no difference between working days and weekend. In case of interruption of only one track (e.g. failure), the other one operates at 150 km/h by Radio Block Center logic.
Number of staff/km single track Details : - Management - Track and civil works - Energy and Ocs - Control command - Others
Works done by contractors
10 30 persons for 400 km of track and all civil works 47 persons for 4 substations, 11 Parallel Sites, 400 km of OCL and 200 km of HVL line 38 persons for 400 km of track (200 km of line - double track)
10 15 persons for 180 km of track and all civil works 20 persons for 2 substations, 5 Parallel Sites, 180 km of OCL and 100 km of HVL line 20 persons for 180 km of track (90 km of line double track)
10 20 persons for 240 km of track and all civil works 20 persons for 2 substations, 5 Parallel Sites, 240 km of OCL and 120 km of HVL line 20 persons for 240 km of track (120 km of line - double track)
10 30 persons for 440 km of track and all civil works 40 persons for 5 substations, 11 Parallel Sites, 440 km of OCL and 240 km of HVL line 40 persons for 440 km of track (220 km of line - double track)
Assistance during warranty period (2 years)
Assistance during warranty period (2 years)
Assistance during warranty period (2 years)
Assistance during warranty period (2 years)
2nd level operations
2nd level operations
2nd level operations
2nd level operations
The Rome – Florence line (operational speed of 250 km/h) is configured as a traditional line (3 kV dc as feeding system, automatic block with codified currents as signalling system).
Maintenance of High Speed Lines
46/64
Country: Spain Line Madrid - Sevilla
Cordoba - Malaga
Madrid - Barcelona
Madrid – Valladolid
471 km
155 km
620 km
180 km
100 % 0%
100 % 0%
100 % 0%
100 % 0%
300 km/h 300 km/h
350 km/h 300 km/h
350 km/h 300 km/h
350 km/h 300 km/h
100 % 0% 0%
100 % 0% 0%
100 % 0% 0%
Only Passengers
Only Passengers
Only Passengers
Only Passengers
100 % 0% 0%
100 % 0% 0%
100 % 0% 0%
60 % 40 % 0%
12 Substations 0 AT
3 Substations 11 AT
500 MVA
360 MVA
25 kV, 50 Hz
25 kV, 50 Hz
25 kV, 50 Hz
25 kV, 50 Hz
Cu, Ag AC 120 mm 1500
Cu, Mg AC 150 3000
Cu, Mg AC 150 3000
Cu, Mg AC 120 2700
Bz II 70 70 mm 1500
Cu 95 95 mm 1500
Cu 95 95 mm 1500
Bz II 120 120 mm 2100
LZB GSM-R
LZB y ERTMS GSM-R
ERTMS GSM-R
ERTMS GSM-R
3 Bases 150 km
1 Base 155 km
4 Bases 150 km
1 Base 180 km
Maintenance approach
Time & Conditions
Time & Conditions
Time & Conditions
Time & Conditions
Sweep train
Yes 200 km/h
Yes 200 km/h
Yes 200 km/h
Yes 200 km/h
-0 h during day 4 h overnight 2 tracks
-0 h during day 4 h overnight 2 tracks
-0 h during day 4 h overnight 2 tracks
-0 h during day 4 h overnight 2 tracks
Topics Length of the line (km) Total km of line - double track % - single track % Maximum Speed (km/h) - design - operational
Comments
Daily service (trains/day) Structure type: - % bridges and viaducts - % tunnels - % earthwork Subgrade - Classic % - Bituminous % - Concrete % Traffic - Passengers (P) - Mixed (M) Type of track - Ballast track % - Slab track % - Embedded rail %
100 % 0% 0%
Specify maximum speed of freight traffic
Number of switches Substations - Number of substations - Number of AT- stations - Installed power Overhead contact system - Voltage and frequency - Type of contact wire: . Material . Section (mm²) . Tension (daN) - Type of carrying cable . Material . Section (mm²) . Tension (daN) Control command: - Signalling system - Telecommunication system Maintenance Bases - Number - Average coverage (km)
Daily possession time - During day - Overnight . 1 track . 2 tracks Number of staff/km single track Details:
Maintenance of High Speed Lines
Specify : timebased or condition-based Also specify changes planned in the near future Indicate yes or no. Also specify the max. speed
47/64
- Management - Track and civil works - Energy and Ocs - Control command - Others
- 0,072 - 0,33 - 0,046
- 0,072 - 0,33 - 0,046
Yes
Yes
Works done by contractors
Maintenance of High Speed Lines
- 0,072 - 0,33 - 0,046
Yes
- 0,072 - 0,33 - 0,046
Yes
48/64
Taiwan High Speed Rail Corporation Line Topics Length of the line (km)
345km
Comments
Total km of line - Double track % - Single track % Maximum Speed (km/h) - Design - Operational
- Double track: 100% - Single track: 0% Maximum Speed (km/h) - Design: 350km/h - Operational: 300km/h
Daily service (trains/day)
123 trains/day (weekday)/146 trains/day (weekends)
Structure type: - % bridges and viaducts - % tunnels - % earthwork Subgrade - Classic % - Bituminous % - Concrete % Traffic - Passengers (P) - Mixed (M)
Structure type: - 72.5% bridges and viaducts - 18.3% tunnels - 9.2% earthwork NA
Type of track - Ballast track % - Slab track %
- Embedded rail %
Type of track - Ballast track 1.2% - Slab track (Including Japanese slab, J-slab: 80.9 % and Rheda track: 14 %) LVT (Low Vibration Track): 3.6% - Embedded rail 0.3%
Number of switches
146
Substations - Number of substations - Number of AT- stations - Installed power Overhead contact system - Voltage and frequency - Type of contact wire: - Material - Section (mm²) - Tension (daN) - Type of carrying cable . Material . Section (mm²) - Tension (daN) Control command - Signalling system
- Telecommunication system
Maintenance Bases - Number - Average coverage (km) Maintenance approach
- Passengers (P)
Specify maximum speed of freight traffic
Number of sub stations: 7 Substations in Mainline and 2 Substations in Depot. Number of AT-stations: 4 ATs in each Substation. Installed power: Each Main Transformer capacity is 80MVA. - Voltage and frequency: 25kV/60Hz - Contact wire composition: Copper and Tin - Contact wire cross-section (mm2): 170mm2. - Tension: 1960 daN - Type of carrying cable: Material is unknown.
Signalling system - Type of CAB signalling system: ATC Cab signalling system - Lateral signalling: No lateral signalling - Fall back system: Fall back wayside indicator (FWI) Telecommunication system -Track-train communication: TETRA Radio system -GSM-R -other - Number: 5 - Average coverage (km): 69km -Time-based maintenance: According to O&M Manual – performance of PM works. -Condition-based maintenance: Currently being examined in each subsystem.
Maintenance of High Speed Lines
Specify : timebased or conditionbased Also specify
49/64
Sweep train
Yes, 170km/h by 700T trainset
Daily possession time - During day - Overnight 1 track 2 tracks Number of staff/km single track Details: - Management - Track and civil works - Energy and Ocs - Control command - Others
During day: 0630~2400 at revenue time Overnight: 1 track: 4.5 hours: 0030~0500
Works done by contractors
changes planned in the near future Indicate yes or no. Also specify the max. speed
- Management: Each department has 3 sections - Civil works and buildings - Track: 0.26 staff/km. - Energy and OCS: Energy: 0.116 staff/km, OCS: 0.223 staff/km. - Control command: Signalling: 0.243 staff/km, Communication: 0.171 staff/km - Other Tamping, Rail grinding, Hi-rail type UT test, Wayside E&M system & equipment building etc.
Maintenance of High Speed Lines
50/64
France (not confirmed by RFF) Line
Paris- Lyon
Topics
Length of the line (km) Total km of line - Double track % - Single track % Maximum Speed (km/h) - Design speed - Operation speed
LGV Atlantique
LGV Nord
LGV Méditéranée
LGV Est
300 300
300 300
320 320
320 320
389 100%
260 300
Daily service (trains/day) Structure type: - % bridges and viaducts - % tunnels - % earthwork Subgrade: - Classic % - Bituminous % - Concrete % Traffic: - Passengers (P) - Mixed (M) Type of track: - Ballast track % - Slab track % - Embedded rail % Number of switches
7 3 90 100%
100%
85 0 15
P
P
P
P
P
100
100
100
100
100
119
89
176
Substations: - Number of substations - Number of AT- stations - Installed power Overhead contact system - Voltage and frequency - Type of contact wire
- Type of carrying cable
Control command - Signalling system
- Telecommunication system Maintenance Bases - Number - Average coverage (km) Maintenance approach
Sweep train Daily possession time - During day - Overnight . 1 track . 2 tracks Number of staff/km single track Details: - Management - Track and civil works - Energy and Ocs - Control command - Others
Test areas
3
2x60 MVA 2x25 kV 50 Hz Cu 150mm² 2000 daN
2X25 kV 50 Hz
2X25kV 50 Hz
TVM 430
TVM 430
2x25 kV 50 Hz CuAg/CuMg 2000daN/3000 daN
Cu 120mm² 1250 kg TVM 300
(1)TVM 430 (2) TBL1/2 (3+4) ERTMS / ETCS ½ GSM-R
7 78 Actual: Timebased Future: Conditionbased No
GSM-R
3 70 km Timebased/ Condition-based
Yes
Yes
No 5h30
Maintenance of High Speed Lines
51/64
RFI
Line
China
The Netherlands
Korea
UK
Topics Length of the line (km) Total km of line - Double track % - Single track %
200 100
Maximum Speed (km/h)
212 100 300
Daily service (trains/day)
330
74
Structure type: - % bridges and viaducts - % tunnels - % earthwork Subgrade - Classic % - Bituminous % - Concrete % Traffic - Passengers - Mixed Type of track - Ballast track % - Slab track % - Embedded rail %
39 1 60
7 3 90
100
85 0 15
P
P
P
100
100
100
4 2
3
Number of switches Substations - Number of substations - Number of AT- stations - Installed power Overhead contact system: - Voltage and frequency - Type of contact wire - Type of carrying cable
2x60 MVA 2x25 kV 50 Hz Cu 150mm² 2000 daN
2,25 kV 50 Hz CuAg/CuMg 2000daN/3000 daN
Cu 120mm² 1250 kg Control command - Signalling system
- Telecommunication system Maintenance Bases - Number - Average coverage (km) Maintenance approach
ERTMS/ETCS 2
GSM-R 4 50 Actual: time-based Future: condition-based
Sweep train Daily possession time - During day - Overnight . 1 track . 2 tracks Number of staff/km single track Details : - Management - Track and civil works - Energy and Ocs - Control command - Others
Maintenance of High Speed Lines
No
GSM-R
GSM-R
3 70 km Time-based/ Condition-based Yes
Yes
No 5h30 3.4 10 30 47
47
52/64
Belgium - Infrabel Line Topics
Length of the line (km) Total km of line - Double track % - Single track % Maximum Speed (km/h) - Design - Operation
L1 French border - Brussels
L2 Leuven - Bierset
L3 Chênée German border
L4 Antwerp Dutch border
71
65
36
38
100%
100%
100%
100%
320 300
300 300
260 260
300 300
6% 1% 93%
3% 1% 96%
85% 15% 0%
16% 7% 77%
100% 0 0
98% 0 2%
0 0 100%
100% 0 0
P
P*
P
P**
100 0 0
100 0 0
100 0 0
100 0 0
1 7 2x60 MVA
1 7 2x60MVA
1 3 2x40MVA
1 4 2x40MVA
2x25 kV 50 Hz CuAg 150mm² * 2000 daN
2x25kV 50 Hz CuMg 150mm² 3000 daN
2x25 kV 50Hz CuAg 150 mm² 2200 daN
2x25 kV 50 Hz CuMg 150 mm² 3000 daN
Bz 65 mm² 1370 kg
Bz 94 mm2 1960 kg
Bz 65 mm² 1370 kg
Bz 65 mm² 1370 kg
TVM 430
TBL 1/2
ERTMS/ETCS ½
ERTMS ETCS½
GSM-R
GSM-R GSM-R
GSM-R
2 65
Common base with L2
Common base with L2
idem
idem
Time-based/ Conditionbased
Comments
Daily service (trains/day) Structure type: - % bridges and viaducts - % tunnels - % earthwork Subgrade - Classic % - Bituminous % - Concrete % Traffic - Passengers - Mixed
Type of track - Ballast track % - Slab track % - Embedded rail %
P* : HS trains and IC-trains (200km/h)-ICE3 ( 250km/h) P** : HS trains and IC trains (160 km/h)
Number of switches Substations - Number of substations - Number of AT- stations - Installed power Overhead contact system - Voltage and frequency - Type of contact wire
* Test section of CuMg 150mm²
- Type of carrying cable
Control command - Signalling system
- Telecommunication system Maintenance Bases - Number - Average coverage (km) Maintenance approach
1 72 Time-based inspections / Conditionbased maintenance
Sweep train
Yes
Yes
Yes
Yes
Daily possession time - During day - Overnight
1h
40 min
40 min
40 min
Maintenance of High Speed Lines
ERTMS Version 2.3.0
Daily
53/64
. 1 track . 2 tracks Number of staff/km single track Details : - Management - Track and civil works - Energy and Ocs - Control command Others Works done by contractors
6h00 4h00
1/40km 1/8km 1/14km 1/20km 1/50 Grinding and ultra-sonic testing of rails Weed control Maintenance of slopes and hydraulic systems Measuring cars (partly)
Maintenance of High Speed Lines
6h00 4h00
1/40km 1/10km 1/14km 1/18km 1/50 Idem L1
6h00 4h00
1/40km 1/10km 1/12km 1/20km 1/50 Idem L1 + ERTMS 1/2
6h00 4h00
1/40km 1/8km 1/16km 1/20km 1/50 Idem L1 + ERTMS 1/2
One management staff for the whole HS network
Subcontractor can be the conventional network (tamping, measuring of the geometry of track and OCS, …) or a private contractor
54/64
Japan (not confirmed by JR East) Line Topics
Comments
Length of the line (km)
Total km of line - double track % - single track % Maximum Speed (km/h) - design - operation Daily service (trains/day) Structure type: - % bridges and viaducts - % tunnels - % earthwork Subgrade - classic % - bituminous % - concrete % Traffic - Passengers - Mixed Type of track - Ballast track % - Slab track % - Embedded rail % Number of switches Substations - number of substations - number of AT- stations - installed power Overhead contact system - voltage and frequency - type of contact wire
- type of carrying cable Control command - signalling system
- telecommunication system Maintenance Bases - Number - Average coverage (km) Maintenance approach Sweep train Daily possession time - during day - overnight 1 track 2 tracks Number of staff/km single track Details : - Management - Track and civil works - Energy and Ocs - Control command - Others Works done by contractors
Maintenance of High Speed Lines
55/64
Maintenance of High Speed Lines
56/64
Appendix 4 Overview of the maintenance activities periodicity of the Overhead Contact System
Maintenance of High Speed Lines
57/64
Maintenance of High Speed Lines
58/64
MAINTENANCE ACTIVITIES PERIODICITY OCS* Scheduled activities Network
Frequency ADIF **
DB 6M
- by trolley
6M
- by train M a i n O b s e r v a t i o n s
Inspections / Controls
- on foot
INFRABEL
JR-EAST
2M 1Y
KORAIL
RFI**
SNCF
THSRC**
4M
3/6 M
-
1M
4/6 W
1D
2M
1W
Cantilevers
1Y
1W
3Y
Insulators
1Y
1W
1Y
Insulators with severe pollution
6M
1W
Section insulators
6M
1W
6M
Gauges
1Y
1W
-
Electric clearances
1Y
2Y
1W
6M
(Automatic) tensioners
1Y
6M
Switches
6M
1W
3/4 Y
6M
2M
4M
3/4 Y
6M
Overhead crossings
2M
1W
1/2 Y
6M
Diodes or welded valves
1Y
1Y
-
Overvoltage discharges
1Y
1Y
-
Switch disconnectors
1Y
1Y
1Y
Transformers
1Y
1Y
2Y
Maintenance of High Speed Lines
4M
1/2 Y
59/64
6M
- examinations
4Y
Parameters
Verification Checks Measures
- recording runs
Geometrical
1Y
2W
-
6M
-
Height (gradient and sag) Stagger Wear
6M
2Y
1Y
2W
1Y
6M
6M 6M
6M 4Y
1Y 1Y
2W 2W
1Y 1Y
6M 6M
Mechanical
Contact Forces
6M
6M
1Y
2W
1Y
-
Electrical
Voltage Current Number of arcs
Particular Measurements
Geometry over points and crossings Earth resistance
S h e d u l e d
- hard-time maintenance
6M
1Y
4M
Cleaning insulators Lubrification contact wire
2W 2W 2W
-
2W
6M
5Y
2/3 Y
-
1Y
4/6 Y
6M
M a i n t .
1Y
-
NO Lubrification by graphite pantographs
6M
(Automatic) tensioning devices
4M
1Y
6M
Disconnectors
4M
1Y
-
Section insulators,air gaps
4M
1Y
1Y
OCL in switches
4M
1Y
-
Maintenance of High Speed Lines
60/64
* Basic information was obtained from the UIC document; every infrastructure manager has been requested to verify and adapt the basic information. ** Data confirmed in June 2010 From these tables, we can conclude that there are no standards concerning periodicity for maintenance activities on the Overhead Contact System. An exceedingly large number of parameters (line speed, density of traffic, concept of the OCS, materials…, interfaces with the pantograph, climatic and environmental conditions) are influencing the decision-makers with respect to the maintenance of the OCS. Nevertheless, the table may be helpful in establishing an initial maintenance program for a new or upgraded line and for self-criticism purposes with respect to the applied program.
# # # END # # #
Maintenance of High Speed Lines
61/64
Maintenance of High Speed Lines
62/64
INTERNATIONAL UNION OF RAILWAYS (UIC) 16 rue Jean Rey - F-75015 PARIS Tel: +33 (0)1 44 49 20 20 Fax: +33 (0)1 44 49 20 29 PASSENGER DEPARTMENT - HIGH SPEED ACTIVITY Copyright deposit: November 2010 ISBN 978 2 7461 1900 0 www.uic.org
Published by UIC - November 2010 Printed on recycled paper using vegetable-based inks