Subject
S u bj b j e c t : 1 8 El E l e c t r i c P o w e r S u rv rv e y o f I n d i a . The 18 Electric Power Survey Committee (EPSC) was constituted in Feb.,2011 with the following terms of reference:i) To forecast the year wise electricity demand projection for each State, Union Territory, Region and All India in detail up to the end of 12th Plan i. e. for the years 2012-13 to 2016-17. ii) To project the perspective electricity demand up to the 13th & 14th Five Year Plans i.e. year 2021-22 & 2026-27. A Brain Storming Session & 1st meeting of EPSC was held in August, 2010 to elicit the views/suggestions of Eminent Experts and Members of the EPSC for deciding the details and action plan for taking up 18th EPS. Based on the deliberations, the Committee decided to use Partial End Use Method (PEUM) for conducting the EPS. On account of rapid urbanization, development of SEZs, industrial states and dedicated freight corridors etc. which would have significant impact on the perspective electricity demand in various categories of consumption in 12th Plan and beyond, the committee decided to enlarge the scope of 18th EPS by including EPS of Mega Cities, NCR, Delhi. The Committee also decided that the results of EPS carried out by PEUM method be validated by using econometric model. Accordingly, the 18th report of Electric Power Survey of India is being brought out in four volumes as per details given below:Volume I - All India 18th EPS /Region /State/UT wise Electric Power, Survey of India. Volume II - Electric Power Survey of Mega Cities Volume III - Electric Power Survey of NCR, Delhi Volume IV - 18 ' EPS of India [by econometric model] The 2nd & 3rd meeting of 18th EPSC were held in March, 2011 & June, 2011 respectively to discuss the preliminary forecast of states, revised action plan for completing the studies and consultation with State Utilities/State Electricity Regulatory Commissions and draft report of 18th EPS of India (Volume -1). The Committee in its 3rd meeting accepted the draft report in principle and directed CEA to finalize the same after considering the views/ suggestions of various states. Accordingly, the revised draft report was completed in October, 2011. The details of electricity demand forecast for each state was sent to the concerned states by Email/Speed Post and the draft report has been finalized after incorporating the views/ suggestions of concerned states. The Authority in its meeting held on 19th December, 2011 deliberated the report of 18th EPS (Vol-I) and accorded concurrence for its publication. A brief Note outlining the results of the forecast of 18th EPS (Vol. I) is given in Annex for information of Ministry of Power. N o t e o n 1 8 E l e c t r i c P o w e r S u r v e y o f I n d i a ( V o l .1 .1 ) General Periodic Electric Power Survey (EPS) of the country is conducted by CEA to forecast State/Union Territory-wise/All India Electricity demand on short, medium and long term basis as a foremost planning exercise to base subsequent planning activities. The forecast of electricity demand is an important input for power sector planning to optimally utilize scarce resources. EPS were earlier being conducted annually up to year 1982 (11th Electric Power Survey). Thereafter, five year Plan-wise EPS were undertaken from 12th Electric Power Survey onwards. The 17th EPS, the latest in the series of Electric Power Surveys, was carried out by CEA and its report was published in March, 2007. It covered the forecast of year-wise electricity demand for each State/ UT/ Region/ All India in details up the end of 11th Plan viz. 2011-12 as well as the perspective electricity demand for the terminal years of 12th & 13th Five Year Plan i.e. 2016-17 and 2021-22. 1 8 t h E l e c t r i c P ow o w e r S u rv rv e y The 18th Electric Power Survey Committee (EPSC) was constituted in February, 2010 with the following Terms of Reference:i) To forecast the year wise electricity demand projection for each State, Union Territory, Region and All India in detail up to the end of 12th Plan i. e. for the years 2012-13 to 2016-17. ii) To project the perspective electricity demand for the terminal years of 13th & 14th Five Year Plans i.e. year 2021-22 & 2026-27. The work of 18th EPS was taken up by CEA as per guidelines/directions of 18th EPSC. A brainstorming session-cum-1st Meeting of the EPSC was held in August, 2010 to discuss the methodology to be adopted, proformae to be used for conducting EPS and modalities for collection/ compilation of the input data from various State utilities and other concerned organizations/departments. It was also decided that unlike earlier power surveys, the scope of 18th EPS be enlarged to cover EPS of Mega cities on account of rapid urbanization, development of SEZs, industrial file:////server/Prasan/STORIES_2011/December/Dec%203...ts/18th%20Electric%20Power%20Survey%20of%20India.htm (1 of 7)12/30/2011 6:24:52 PM
Subject
estates and dedicated freight corridors which would have significant impact on the perspective electricity demand in various categories of consumption in 12th Plan and beyond. The 2nd Meeting of 18th EPSC was held in March, 2011 wherein Committee discussed the preliminary forecast of 15 Nos. States/UTs and reviewed the action plan for completing studies. The EPSC emphasized on the need for consultation with State utilities and State Electricity Regulatory Commissions (SERCs) to study the pattern of growth of consumption in various categories, programmes of reducing the T&D losses and implementation of steps/measures for improvement of energy efficiency. The EPSC decided that the report of the 18th EPS be prepared in the following four volumes:Volume - I All India 18th EPS /Region /State/UT wise - September, 2011 Volume - II Electric Power Survey of Mega Cities - February, 2012 Volume - III Electric Power Survey of NCR, Delhi - June, 2012 Volume - IV 18th EPS of India [by econometric model] - October, 2012 EPSC in its 3rd meeting held in June, 2011, discussed the draft report of 18th Electric Power Survey (Volume-I). The Committee accepted the draft report in principle and directed to CEA to finalize the same after considering the views/suggestions of State authorities. C o n su l t a t i o n s w i t h S t a t e A u t h o r i t i e s a n d S t a t e E l e c t r i c i t y R e g u l a t o r y C o m m i s s i o n s ( SE RC s ): The preliminary forecast of electricity demand of various states prepared by CEA was discussed in the meetings with State TRANSCOs, State Electricity Boards/Departments as well as SERCs to elicit their views on the growth rate in various categories of electricity consumption, policies/ programmes launched by the respective State Governments to strengthen the infrastructure for transmission and distribution and steps/measures being proposed to be taken for improvement of energy efficiency programme for reduction of Transmission & Distribution Losses, implementation of various programmes for rural electrification and Demand Side Management which would have bearing on the electricity demand in the foreseeable future. The input data including proposal of States/UTs for demand projection were scrutinized and discussed before incorporating in the report EPS. Apart from growth in electricity demand, there would also be marginal reduction due to implementation of various steps/measures for improvement of energy efficiency. The 17th EPS had broadly encompassed the aims and objectives of National Electricity Policy (NEP) [notified in 2005] such as access to electricity by 2012, electricity demand to be fully met by 2012, increase in the per capita availability of electricity to 1000 units by 2012 and reduction of T&D Losses to be in line with international practices by the year 2012. The objectives of NEP are partially fulfilled as T&D Losses in various States/UTs are still very high and the shortages of power continue to be prevailing in the country. During the 11th Plan, Ministry of Power have introduced various programmes for improvement of energy efficiency and impetus has been given on measures for utilities based demand side management with the objectives of reducing generation capacity, augmentation and strengthening of T&D System. The National Mission on Enhanced Energy Efficiency (NMEEE) was initiated in 2008 under the Nation Action Plan on Climate Change (NACC) with the objective of enhanced energy efficiency by putting in place new initiatives. Perform, Achieve and Trade (PAT) mechanism launched for implementation of NMEEE is a market based mechanism to enhance cost effectiveness for improvement in energy efficiency in nine identified different types of energy intense industries. The main aspects taken into consideration for electricity demand forecasting for 18th EPS are policies/programmes launched by Government of India and states during 11th Plan which would impact on the electricity demand in. domestic, commercial and industrial categories of consumption. The state authorities in their programmes submitted to CEA have worked out projections after considering the effects of implementation of such policies/programmes. Methodology Partial End Use methodology (PEUM), a combination of time series analysis and End Use Method is a proven method for demand forecasting and has been used for earlier EPS by CEA. In line with directions of EPSC, PEUM has been used to forecast electricity demand for 18th EPS. The time series method has been used to derive growth indicators giving higher weightage to recent trend so as to incorporate benefits of energy conservation initiatives and new technologies. The input data for period 2003-04 to 2009-10 was scrutinized for EPS. The year-wise and Statewise/UT-wise electricity energy requirement has been worked out up to end of 13th Plan (2021-22) on the basis of data for year 2009-10 which is taken as base year after adding one time shortages to electrical energy available. The 18th EPS has conducted short/medium term forecast for next 10 years viz. 12th Plan and 13th Plan period so as to facilitate the states/ file:////server/Prasan/STORIES_2011/December/Dec%203...ts/18th%20Electric%20Power%20Survey%20of%20India.htm (2 of 7)12/30/2011 6:24:52 PM
Subject
utilities to achieve their programme for growth of demand, T&D losses reduction, augmenting of T&D system. The forecast covers demand for various categories of consumption viz. Domestic, Commercial, Public Lighting, Public Water Works, Irrigation, Industrial (LT, HT less than 1 MW each, HT 1 MW and above each), Railway Traction & Bulk Non-Industrial HT Supply. The long term projections cover the made forecast for terminal years of 14th Plan and 15th Plan period. O v e rv i e w o f P r o j e c t i o n s o f 1 8 t h E P S According to 18th EPS the All India energy requirements in 2016-17 is assessed to be 1354.58 BU as against forecast of 1392.06 BU as per 17th EPS. The peak power demand in 2016-17 is assessed to be 199540 MW as against 218209 MW estimated as per 17th EPS. The State-wise/UTwise/region-wise and All India details of short-term projections' of energy requirements by end of 12th Plan (2016-17) and 13th Plan (2021-22) and the long-term projections of energy requirements by end of 14th Plan (2026-27) and 15th Plan (2031-32) are given in Annex-I The short-term peak load demand projections by end of 12th Plan (2016-17) & 13th Plan (2021-22) and the long-term projections of peak load by end of 14th Plan (2026-27) and 15th Plan (2031-32) are given in Annex-II. Table 1.1 indicates, Region wise short-term forecast of energy requirements of peak load for the end of 12th Plan (2016-17) and 13th Plan (202122)as well as for long term forecast for terminal years of 14th Plan (2026-27) and 15th Plan (2031-32). Table 1.1 R e g i o n w i s e s u m m a r y o f p r o j e c t i o n s f o r En e r g y R e q u i r e m e n t s ( M U ) a n d P e a k L o a d (M W ) Year / Region/ All India
20 1 6 -1 7
2 0 2 1 -2 2
2 0 2 6 -2 7
2 0 3 1 -3 2
Northern
Energy Requirement (MUs) 422498
Peak Load (MW) 60934
Energy Requirement (MUs) 59400
Peak Load (MW) 86461
Energy Requirement (MUs) 840670
Peak Load (MW) 121979
Energy Requirement (MUs) 1135543
Peak Load (MW) 164236
Western
394188
62015
539310
86054
757318
120620
1028974
163222
Southern Eastern North-Eastern
357826 163790 16154
57221 24303 2966
510786 236952 23244
82199 35928 4056
727913 349412 33952
118764 53053 6169
1017526 480046 46921
165336 72874 8450
A l l In d i a
13 5 4 8 7 4
199540 1904861
283470 2710058
4 0 0 7 05 3 7 1 0 0 8 3
5 4 1 8 23
The year-wise forecast of energy requirement during 12l Plan period is given below in Table 1.2. Table 1.2 E n e r g y Re q u i r e m e n t ( M U s ) Region/All I n d ia Northern Region
2 0 11 -1 2 2 0 1 2 -1 3 2 01 3 -1 4 271301 297350 324206
2 0 1 4-1 5 353738
2 0 1 5 -16 386382
2 0 1 6 -1 7 422498
Western Region Southern Region
271453 242729
291608 260865
313465 280709
337289 301823
362901 324033
394188 357826
Eastern Region
106086
119893
129725
140637
151668
163790
North-Eastern Region
10706
11624
12621
13703
14878
16154
A l l In d i a
9 2 79 3 1 9 9 9 3 7 8 1 07 6 3 2 7 1 1 5 92 0 1 1 2 4 8 4 56 1 3 5 4 8 7 4
T r a n s m i s s i o n & D i s t r i b u t i o n ( T& D ) L o s s e s : According to 18th EPS, the All India Transmission & Distribution Losses for the base year 2009-10 are 25.36%. Based on the of consultations with State utilities/SERCs regarding their strategy and the steps being taken to reduce the T&D losses, it is expected that the All India T&D losses could be reduced to 18.90% by the end of 12th Plan which could further be brought down to 15.39% by the end of 13th Plan. The states which have performed well are expected to reduce the T&D Losses to around 15% by the end of 12th Plan whereas the poorly performing states which have yet to implement the upgradation of infrastructure for T&D system may be in a position to reduce losses to around 15%> by the end of 13th Plan. The region wise information regarding expected T&D Losses by the end of 12th & 13th Plans are given below in Table 1.4. Table 1.4 R e g i o n -w i s e T & D L o s s e s (% ) Re g i o n /A l l In d i a
2 0 16 -1 7 2 0 2 1 -2 2
file:////server/Prasan/STORIES_2011/December/Dec%203...ts/18th%20Electric%20Power%20Survey%20of%20India.htm (3 of 7)12/30/2011 6:24:52 PM
Subject
Northern Region Western Region
20.13 19.12
16.12 14.91
Southern Region Eastern Region
16.78 19.36
15.44 14.22
North-Eastern Region
22.71
18.65
A l l In d i a
1 8 .9 0
1 5 .3 9
E n e r g y r e q u i r e m e n t s d u r i n g 1 2 P l a n a n d 1 3 Pl a n p e r i o d : The forecast of All India Energy Consumption, Energy Requirements, T&D Losses and for 2011-12 and terminal years of 12th 13th & 14th Plans as per 18th EPS are given in Table 1.5 below: Table 1.5
Energy Consumption (MUs) Energy Requirement (MUs) T&D Losses (MUs) & (%)
2 0 11 -1 2 2 0 16 -1 7 2 0 21 -2 2 694304 1098995 1611809
904012
1354874 1904861
209708
255879
293052
(23.20)
(18.90)
(15.38)
The year-wise all India category-wise forecast of energy consumption, energy requirements, peak load T&D losses and load factor for 12th & 13th Plan period is given in Annex-Ill. P a t t e r n o f U t i l i za t i o n o f e l e c t r i c i t y The study of the pattern of utilization of electricity for 2009-10 indicates that the major part of consumption viz 35.34% is for the industrial category followed by 25.07% in domestic category whereas in the irrigation category the utilization is 21.02% and in commercial category the utilization is 10.16% and the remaining 8.40% is on account of consumption in other categories. The results of 18th EPS indicate that by the end of 12th Plan, the trends is likely to marginally change and increase in the pattern utilization in domestic and commercial categories is anticipated whereas marginal decrease in the consumption in the irrigation category is expected. The summary of the All India pattern of utilization in the major categories of consumption is given below in Table 1.7: Table 1.7 A H I n d i a C a t e g o r y w i s e P a t t e r n o f U t i l i za t i o n ( % ) Ca te go ry Domestic Commercial
2 00 9-1 0 2 01 1-12 2 01 6-1 7 2 02 1-22 25.07 25.15 26.38 26.44 10.16 10.22 10.60 11.52
Irrigation Industries
21.02 35.34
20.47 35.31
18.96 35.79
17.86 36.35
Others
8.41
8.84
8.02
7.23
B r e a k -u p o f R u r a l a n d U r b a n E le c t r i c i t y c o n s u m p t i o n :During the consultation with the State utilities most of the states indicated that separate feeders for meeting the rural & urban load requirements are not being provided. The information on the consumption in urban and rural areas have been submitted by a few states. Based on the available data and the details of consumption in respect of domestic, commercial categories, the pattern of utilization in rural and urban areas has been worked out. For this purpose the consumption in agriculture/irrigation is treated to be rural category. The Region wise anticipated break-up of Urban (domestic, commercial) consumption and Rural consumption (domestic, commercial & rural) by the end of 12 Plan (2016-17) is indicated in Table 1.8. Table 1.8
file:////server/Prasan/STORIES_2011/December/Dec%203...ts/18th%20Electric%20Power%20Survey%20of%20India.htm (4 of 7)12/30/2011 6:24:52 PM
Subject
Re g i o n /A l l In d i a Northern Region Western Region
Urban (% ) 44.55 31.23
Rural (%) 55.45 68.77
Southern Region Eastern Region
40.91 61.64
59.09 38.36
North-Eastern Region
60.87
39.13
A l l In d i a
4 1 .2 4
5 8 .7 6
According to the EPS results on All India basis, the rural electricity consumption is likely to marginally decline from 60.89% in 2009-10 to 58.76% by the end of 12th Plan 2016-17. Annex ure - I 1 8 t h E l e c t r i c P ow e r S u rv e y L o n g T e r m F o r e c a s t o f E l e c t r i c a l E n er g y R e q ui r e m e n t a t P o w e r S t a t i o n B u s B a r s i n M U s ( U t i l i t i e s O n l y) St a t e /U t s Delhi
2 0 1 1 -1 2 2 0 1 6-1 7 27142 37529
2 0 2 1 -22 52930
2 0 2 6 -2 7 73827
2 0 3 1 -3 2 99649
Haryana
36575
56681
78586
110915
150083
Himachal Pradesh Jammu & Kashmir
8535 12504
10901 16298
14514 21884
19198 31110
25096 43075
Punjab
46300
69410
86941
108835
136243
Rajasthan Uttar Pradesh Uttrakhand
49859 78984 9722
77907 138854 12751
110483 209046 16774
161741 308887 22438
226014 420829 29733
Chandigarh
1681
2165
2842
3719
4821
N o r t h e r n Re g i o n Goa
2 7 1 3 0 1 4 2 2 49 8 3391 4853
5 9 4 0 00 6837
840670 9442
1135543 12617
Gujarat Chhattisgarh
74229 16304
108704 24222
153582 34106
218610 46979
301160 62620
Madhya Pradesh Maharashtra
49878 120856
77953 169353
107060 225606
155489 310654
213539 417826
D. & N. Haveli Daman & Diu
4682 2114
6286 2817
8413 3706
11164 4980
14676 6536
We s t e r n Re g i o n Andhra Pradesh Karnataka
2 7 1 4 5 3 3 9 4 18 8 85358 129767 53523 78637
5 3 9 3 10 191912 108012
757318 284776 147941
1028974 412903 200736
Kerala Tamil Nadu
19867 82335
26584 119251
34691 171718
46049 244703
61125 337491
Pudducherry
2828
3586
4452
4444
5271
So u t h e r n Re g i o n Bihar Jharkhand
2 4 3 9 1 2 3 5 7 82 6 15015 29447 19905 27691
5 1 0 7 86 52975 37482
727913 91733 51512
1017526 131219 69475
Orissa
25004
35772
42566
54565
70154
West Bengal Sikkim
45774 389
70352 528
103283 645
150704 898
207948 1250
Ea s t e r n Re g i on Assam Manipur
1 0 6 0 8 6 1 6 3 79 0 6081 8947 615 1241
2 3 6 9 52 12699 2219
349412 18107 3881
480046 25224 5416
Meghalaya
1817
2243
3029
4206
5651
Nagaiand Tripura
620 930
834 1402
1163 2026
1728 2892
2373 3921
Arunachal Pradesh Mizoram
435 455
552 936
721 1388
1085 2053
1489 2847
North Eastern Region
10953
1 6 1 54
23244
33952
46921
file:////server/Prasan/STORIES_2011/December/Dec%203...ts/18th%20Electric%20Power%20Survey%20of%20India.htm (5 of 7)12/30/2011 6:24:52 PM
Subject
Andman & Nicobar Lakshadweep
267 41
366 52
505 65
709 84
963 110
A l l In d i a
9 0 4 0 1 2 1 3 5 48 7 4 1 9 0 4 86 1 2 7 1 0 0 5 8 3 7 1 0 0 8 3
Annex ure - II 1 8 t h E l e c t r i c P ow e r S u rv e y L o n g T e r m F o r e c a s t o f P e a k E l e c t r i c L o a d a t P o w e r S t a t i o n B u s B a r s i n M W (U t i l i t i e s Only) St a t e /U t s Delhi Haryana
2 0 1 1 -1 2 2 0 1 6-1 7 2 0 2 1 -2 2 2 0 26 -2 7 2 0 3 1 -3 2 4770 6398 9024 12681 17246 6376 10273 14244 20103 27202
Himachal Pradesh Jammu & Kashmir
1335 1802
1900 2687
2589 4217
3424 5996
4476 8302
Punjab
8363
12342
14552
18352
23144
Rajasthan Uttar Pradesh
8097 12021
13886 23081
19692 36061
28828 53690
40284 73708
Uttrakhand Chandigarh
1656 336
2189 426
2901 559
3911 732
5222 948
Nort hern Region Goa
37265 530
6 0 9 34 815
86461 1192
1 2 19 7 9 1 6 4 2 3 6 1658 2216
Gujarat Chhattisgarh
11556 3155
19091 4687
26973 6599
38691 9090
53301 12116
Madhya Pradesh Maharashtra
8897 18398
13904 28645
18802 39622
27519 54982
38088 74528
D. & N. Haveli
640
944
1297
1733
2294
Daman & Diu
308
441
605
818
1082
We s t e r n Re g i o n Andhra Pradesh Karnataka
39351 14122 8545
6 2 0 15 22445 13010
86054 33194 18403
1 2 06 2 0 1 6 3 2 2 2 51601 74818 25396 34720
Kerala Tamil Nadu
3489 12271
4669 20816
6093 29975
8150 43044
10903 59827
Pudducherry
497
630
782
787
940
So u t h e r n Re g i o n Bihar Jharkhand
36175 2226 3201
5 7 2 21 5018 4616
82199 9306 6341
1 1 87 6 4 1 6 5 3 3 6 16239 23411 8780 11930
Orissa
3964
5672
6749
8712
11280
West Bengal Sikkim
7454 106
11793 144
17703 176
26027 245
36187 341
Ea s t e r n Re g i on Assam Manipur
15122 1257 171
2 4 3 03 1817 346
35928 2534 497
5 3 05 3 3613 869
72874 5033 1212
Meghalaya
361
445
596
828
1112
Nagaland
130
185
271
403
554
Tripura Arunachal Pradesh
239 88
340 135
472 177
674 266
913 365
Mizoram
160
285
352
521
723
North Eastern Region Andaman & Nicobar Lakshadweep
2021
2966
4056
6 1 69
8450
51 7
67 11
89 18
125 23
172 30
A l l In d i a
1 2 4 9 9 5 1 9 9 54 0 2 8 3 4 7 0 4 0 07 0 5 5 4 1 8 2 3
Annex ure - III All India
file:////server/Prasan/STORIES_2011/December/Dec%203...ts/18th%20Electric%20Power%20Survey%20of%20India.htm (6 of 7)12/30/2011 6:24:52 PM
Subject
18T H ELECTRIC POWER SURVEY FORECAST ENERGY CONSUMPTI ON ,ENERGY REQUIREMENT AND PEAK LOAD CATEGORY WISE & YEAR WISE SUMMERY OF FORECAST Energy Consumption in MUs Consumption Categories Domestic
2 01 1-1 2 2 01 2-1 3 2 01 3-1 4 2 01 4-1 5 2 01 5-1 6 2 01 6-1 7 2 01 7-1 8 2 01 8-1 9 2 01 9-2 0 2 02 0-2 1 2 02 1-2 2 174634
193571
214189
237347
262202
289924
315335
339762
366224
394939
426148
Commercial & Misc.
70929
78308
86494
95497
105472
116535
128099
140506
154153
169173
185722
Public lighting Public Water Works
6971 17532
7492 18927
8054 20436
8661 22064
9315 23829
10021 25742
10675 27651
11315 29592
11995 31677
12718 33918
13488 36329
Irrigation
142152
154010
166425
179784
194559
210611
225044
239194
254338
270524
287926
Industries LT Industries HT Railway traction
47339 197852 14374
52722 219607 15339
57977 240057 16437
63721 262437 17489
70010 286699 18635
76898 316408 19832
84096 339228 21055
91626 367341 22353
99714 397991 23714
108480 431358 25232
117984 467835 26810
Bulk Supply Total (Energy Consumption)
22521 694304
24288 764263
26154 836224
28247 915249
30523 33024 35759 38754 42027 45622 49566 1001244 1098995 1186942 1280444 1381833 1491963 1611809
T&D losses -ML)
209708
220480
229347
238357
246836
T&D Losses in % Energy Requirement - Ml
23.20 904012
22.39 984743
21.52 20.66 19.78 18.89 18.20 17.50 16.80 16.09 15.38 1065571 1153606 1248081 1354874 1450982 1552008 1660783 1778109 1904861
Annual Load Factor - % Peak Load - MW
81.28 126959
80.48 139682
79.85 152329
79.21 166260
78.29 181988
255879
77.51 199540
264040
77.37 214093
file:////server/Prasan/STORIES_2011/December/Dec%203...ts/18th%20Electric%20Power%20Survey%20of%20India.htm (7 of 7)12/30/2011 6:24:52 PM
271564
77.21 229465
278950
77.05 246068
286145
76.87 264041
293052
76.71 283470