PROCEDURE TO PERFORM PRESSURE TEST OF PIPINGFull description
METHOF STATTEMENT OF PIPING HYDROTEST ,explain the construction procedures and methodology for the pressure testing of pipeworkFull description
Paccar Truck Fuel Test
pressure vesselFull description
Description complète
ParticleFull description
Lecture Notes for Topic 9
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004) SATIP No.
SAUDI ARAMCO TYPICAL INSPECTION PLA Hydrostatic Testing of Pipelines Pipelines
SATIP-A-004-03
PROJECT TITLE:
ITEM NO. 1.0 1.0
PROJECT PHASE & Ac ti vi ty Co de
APPROVED DATE
WBS/BI/JO/NO.
TASK / ACTIVITY
QUALITY PROCEDURE
QUALITY RECORD
DISCIPLINE:
MECHANICAL
25-May-05 CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY ASSIGNMENTS CNTRCTR
SAUDI ARAMCO
REMARKS
DOCU DOCUME MENT NT REVI REVIEW EW
1.1
Hydrostatic testing Procedure
SAIC-A-2001
RH1
RH1
1.2
Revi Review ew of Test Test Pack Packag age e Prep Prepar arat atio ion n
SAIC SAIC-A -A-2 -200 003 3
RH1
R2
1.3
Lay-Up Procedure
SAIC-A-2007
RH1
RH1
Verification of water chemistry and corrosion inhibitor
SAIC-A-2008
SATR-A-2014
RH1
R1
SAIC-L-2139 SATR-A-2007
H1
H1
In conjunction with Pipeline SATIP-L-450-03, SATIP-L-450-04.
SAIC-A-2017 SATR-A-2008
H1
W1
In conjunction with Pipeline SATIP-L-450-03, SATIP-L-450-04.
H1
W1
Forms SATR-A-2003 shall be used for 24-hr recorded hydrostatic test, Ie; underground piping or piping whose joints are covered before pressure testing.
W1
S
2.0
MATERIAL RECEIVING
2.1 3.0
A PP PPL IC ICA TI TION
3.1
Pre-Test Punchlisting-PIPELINES
3.2
Cleaning/Flushing (Scraping) prior to hydrotest
SAIC-L-2139 SAIC-A-2017
SATR-A-2002 SATR-A-2003 SATR-A-2004 SATR-A-2005 SATR-A-2006 SATR-A-2001 (for test Manifold)
3.3
Test Preparation & Verification of Testing equipment (including safety requirements)
3.4
Filling & Pressurization a. Strength Test Pressure Pressure b. Tightness Test Pressure
SAIC-A-2013
3.5
Visual Inspection at Test Pressure
SAIC-A-2015
SATR-A-2001
H1
H1
3.6
Pneumatic Testing of Reinforcing pads/sleeves covering pressure containing Welds and Weld+ End Couplings
SAIC-A-2016
SAIC-A-2016 SATR-A-2001
W1
W1
4.0
* See Note 1 (General Notes)
POST- TEST
SAIC-A-2009
Form SATR-A-2001 is a modified version or merging of Forms SA-2642ENG & SA-2642-1
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004) SATIP No.
SAUDI ARAMCO TYPICAL INSPECTION PLA Hydrostatic Testing of Pipelines
SATIP-A-004-03
PROJECT TITLE:
ITEM NO.
APPROVED DATE
WBS/BI/JO/NO.
PROJECT PHASE & Ac ti vi ty Co de
TASK / ACTIVITY
QUALITY PROCEDURE
4.1
De-Pressurization & Water Disposal
SAIC-A-2017
4.2
Lay-up
SATR-A-2009
QUALITY RECORD
SATR-A-2009
DISCIPLINE:
25-May-05
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY ASSIGNMENTS CNTRCTR
SAUDI ARAMCO
W1
S
H1
W1
REMARKS
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004) SATIP No.
SAUDI ARAMCO TYPICAL INSPECTION PLA Hydrostatic Testing of Pipelines
SATIP-A-004-03
PROJECT TITLE:
ITEM NO.
APPROVED DATE
WBS/BI/JO/NO.
PROJECT PHASE & Ac ti vi ty Co de
QUALITY PROCEDURE
TASK / ACTIVITY
QUALITY RECORD
DISCIPLINE:
25-May-05
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY ASSIGNMENTS CNTRCTR
REMARKS
SAUDI ARAMCO
GENERAL NOTES
1
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.
2
Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
3
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present.
4
Hold: attendance.
5
If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in