Advances in the the Use of Drilled Foundations Dan Brown, P.E., Ph.D. President, Dan Brown and Associates, and President, Deep Foundation Institute
Overview !
Why drilled foundations? !
Micropiles
!
Continuous Flight Auger (CFA) Piles and Drilled Displacement (DD) Piles
!
Drilled Shafts (Bored Piles)
Micropiles !
Typically <12” dia
!
Relies on steel for structural capacity
!
Installed with lightweight, versatile drilling equipment
!
Effective in difficult ground conditions World Trade Center, NYC
Advancements in Micropiles !
Standards for design & construction
!
Higher capacity piles
!
Improvements in drilling and more versatile drilling rigs
!
Innovative applications
Micropiles – Design Details !
Casing near surface
!
Center bar(s) through bond zone
AASHTO Design Design Section 10.9
!
FHWA FHW A Micropile Manual, Dec. 2005 2 005
Micropiles – Design Details !
Example Cross-sections
Micropiles in Difficult Ground Conditions !
Karst
!
Till & Boulders
Difficult Site Access
!
!
Restricted Headroom
Drilled Shaft
International Marketplace, Hawaii Micropiles up to 90m deep in soft alluvium
(photo courtesy of Hayward-Baker)
Case History – Foothills Bridge
Foothills Bridge Area of Colluvium Abutment 1 Abutment 2
Foothills Bridge Pier
Residual Soil
Cased zone
Anchor (to rock)
4.6 m (15 ft) uncased bond zone
Weathered Rock
Sound Rock
Foothills Bridge
Foothills – Trestle Foundation
Foothills – Pier Foundations
Rouchleau Mine Crossing, Minnesota
Pier Foundations
52m
Pile Location in Mine Dump Fill
107m
History
Downhole Hammer Drill Crossover Sub-Seal Crossover Sub Port Shock Absorber Hammer Pilot Bit
Drill Head and Casing Ring Bit
Drilling
Final Pile Design Approximate depth 55m
! !
762mm dia steel pipe filled with concrete
!
End bearing on hard rock
!
Design axial resistance = structural capacity of the pile cross section
Note: !
two 600mm dia test piles loaded to 17MN
Continuous Flight Auger Piles
Continuous Flight Auger Piles !
Drill rig capabilities – deeper, larger diameter
!
Control of the drilling process in unstable soils
!
Control of the casting process for quality control / quality assurance
Continuous Flight Auger Piles !
Drill rig capabilities
Continuous Flight Auger Piles Control of the Drilling and Concreting Process
Drilled Displacement Piles
Drilled Displacement Piles !
Reduce or eliminate spoil
!
Requires heavier, more expensive drilling equipment than CFA
!
Increased axial resistance
!
Improve ground
!
Slower than CFA
!
Eliminate risk of subsidence
!
Limited depth of penetration
!
Drill effort related to axial resistance
Kentucky Hospital !
Drilled displacement columns for ground improvement
!
Liquefaction mitigation
!
Bearing capacity for spread footings
Drilled Displacement Piles
Bearing Tests
./(0&1( 2(&0"+1 30(##40(, 53& #
(##
# !(#
) ) , !'# + * ( )! ( ' & !%# % $ # " ! !$# !"#
)*+, ( )*+, ' )*+, &
'##
#
%##
Drilled Shafts (Bored Piles) !
Larger, Deeper Machine Capabilities !
Oscillator/Rotator Machines
!
Reverse Circulation
!
Base Grouting
!
Verification Testing
Oscillator Equipment
Rotator Equipment
Seating Casing into Rock
Considerations Advantages !
!
!
!
Stability of fully cased excavation Minimal vibrations for casing installation Easy removal of spoil & obstructions Avoid or minimize slurry materials
Limitations !
Mobilization cost
!
Equipment support requirements
!
Potential to become stuck for deep shafts
!
Non-level base with hammer-grab excavation
Rotator Construction – Huey P. Long Bridge, New Orleans
Huey Long Bridge Shaft/Cap Connection
Isolation Casing Shaft Cutoff at -11
Completed Foundation
Surface Texture
Restricted Headroom with Rotator Casing Moses Wheeler Bridge, Connecticut Permanent Casing
Obstructions? VE solution to cut through existing piling
Reverse Circulation Top-Drive Drill
Drilling rock socket into schist
Reverse Circulation Drilling Wolf Creek Dam
Deeper Drilled Shafts Case History: Wolf Creek Dam, Kentucky Embankment wall
Secant pile wall
275 ft deep
Wolf Creek Dam Secant Piles
Base Grouting 0
5
O-cell load (MN) 15
10
20
25
30
0
0.0
-1 ) s e h c n i ( -2 e t a l p l l e -3 c O f o t -4 n e m e c a l p -5 s i D
-25.4 ) m m -50.8 ( e t a l P l l -76.2 e c O f o -101.6 t n e m e c a l -127.0 p s i D
T3 (Not Grouted)
-6
-152.4
-7
-177.8 0
500
1,000
1,500 2,000 O-cell load (tons)
2,500
3,000
Load test data from John James Audubon Bridge, Mississippi River, Louisiana
3,500
Widespread Use of Polymer Slurry !
Disposal advantages
!
Improved side resistance
!
Benefits in degradable shales
Widespread Use of Polymer Slurry
Polymer Slurry in Shale at Bond Bridge Sample
River Water Polymer Slurry
Natural Moisture Content (%) 8.3 8.3
Slake Durability Index Type Id(2) (%) II 72.2 II 98.2
Durability Rating Based on Shear Strength Loss Type DR s Intermediate 61.9 Hard, more durable 78.6
Load test: 800 kPa unit side resistance After 4 days exposure
Influence on Axial Resistance f 1.6 s k1.4 , e c1.2 n a 1 t s i s0.8 e R0.6 e d i 0.4 S t i 0.2 n U 0
Polymer Bentonite
0
0.5
1
1.5
2
Axial Displacement, inches
Data from Auburn University National Geotechnical
!
Research Site (Brown, ASCE GT Journal, 2002)
!
Verification Testing !
Integrity Testing
!
Load Testing
!
Verification testing allows performance basis for specification !
Design-build
!
Value engineering
ATC, Mississippi River Bridge, St. Louis O-cells
Cored rock from test shaft excavation